Dynamics of Primary and Secondary Chilled Water Systems

Download as pdf or txt
Download as pdf or txt
You are on page 1of 13
At a glance
Powered by AI
The paper aims to analyze the dynamics of variable flow chilled water systems and investigate the effects of restricting flow in the bypass line and adding thermal storage. It also discusses load degradation in chilled water systems over time.

The purpose of the paper is to bring additional understanding to the dynamics of variable flow chilled water systems and illustrate the reasons for the improvement after installing a check valve in the bypass line based on a computer simulation.

In the balanced system, the effects of essentially zero flow in the bypass line at peak cooling load are analyzed. The temperatures and flows for a system meeting a 15,150 ton load with seven chillers running are presented.

DYNAMICS OF PRIMARY/SECONDARY

CHILLED WATER SYSTEMS

By Kirby P. Nelson, P.E.


Paul Mueller Company Springfield, Missouri

Abstract

he purpose of this paper is to bring some additional understanding to the dynamics of variable flow chilled
water systems. The literature has had several articles in recent months on this subject with some
disagreement regarding a check valve in the bypass line. Reference (1) gave an example of a very positive
result after the installation of a check valve. This paper will show a similar result and try to illustrate the reasons
for the improvement. The Reference (1) article also presents information on load degradation as a chilled water
system ages and, therefore, requires colder supply water and greater flow. This paper will present a study of the
dynamics of a new and aged primary/secondary system based on a computer simulation which includes the
characteristics of a specific chiller and the laws of thermodynamics.
We will analyze the effects of restricting flow in the bypass line and also look at the dynamics of adding thermal
storage to the system.

BALANCED SYSTEM
We define the balanced system to be essentially zero flow in the bypass line at peak cooling load. We will assume
the load is designed for a delta temperature of 16F and a peak design load of 15,150 tons. The primary pumps
provide constant flow through the chiller with variable flow to the load. Our selected chiller is a 2,165-ton unit at
peak conditions. Therefore, seven chillers will meet the peak load. Figure 1 illustrates the temperatures and flows
at this near-balanced condition. Note that there is a small negative flow in the bypass line of 305 gpm due to the
difficulty of exactly matching a chiller system to the load. Table 1, Column 1 shows the same data for this
balanced condition. (See References 2 and 3 for additional discussion.)
The chiller is modeled as providing about 2,165 tons for a chiller entering temperature of 60F and
1,700 tons for an inlet temperature of about 48.5F.

Figure 1 - Balanced System

Nomenclature
Load in Tons
Delta T

= Tls - Tlr (F)

Fce

= Required flow entering chillers (gpm)

Tls

= Temperature load supply (F)

Tce

= Temperature entering chillers (F)

Fls

= Flowload supply (gpm)

Tcl

= Temperature leaving chillers (F)

Tlr

= Temperature load return (F)

Tpl

= Temperature after bypass (F)

Fb

= Flow in bypass (gpm)

Chillers On = Number Running

Tb

= Temperature of bypass flow (F)

% Load Assumes Chillers Share Load Equally

BALANCED PLUS ONE CHILLER


If the project was built with eight chillers, then its probably safe to assume that the plant operator would turn on
the eighth chiller as the load approached 15,150 tons. Table 1, Column 2 illustrates the effect which is increased
flow to the chillers from 23,020 to 26,320 gpm, which must be accommodated by negative flow in the bypass line if
constant flow through the chiller is maintained. The resulting lower temperature into the chillers results in a little
less chiller efficiency, and therefore the total capacity on line is 2,164 tons x 8 x .89 = 15,408 tons operating at
15,150 tons to meet the 15,150-ton load. In other words, seven chillers would meet the load, but once the eighth
chiller is turned on and flow through that eighth chiller occurs, then seven chillers cannot meet the load.

LOAD DEGRADATION - 8 CHILLERS


Reference 1 presents a typical degradation of the load which results in a required supply temperature of 37.8F
versus 44F when the system was new, and a T of 14.8F versus 16F, when the system was new. The first law of
thermodynamics requires an increase in flow for this decrease in T. Table 1, Column 3 illustrates that our eight
chiller system can only meet a 14,000-ton load under these conditions; therefore, an additional chiller would have
been added as the system aged in order to meet a 15,150-ton load.

LOAD DEGRADATION - 9 CHILLERS


Nine chillers at 96% load would meet the aged conditions of the system. Table 1, Column 4 illustrates the flow and
temperature conditions. Note that, in all cases shown above, the temperature of water leaving the chillers is the
supply temperature to the load because flow in the bypass line is negative, i.e. the chillers require more flow than
the load. This negative flow in the bypass means that the temperature entering the chillers (Tce) is less than the
temperature returning from the load (Tlr), resulting in decreased capacity of the chillers.
A shut-off valve in the bypass will be considered next.

BYPASS VALVE
A valve to stop the negative flow in the bypass line (Fb = 0) will improve the efficiency of the chillers as illustrated
by Table 1, Column 5. Forcing all flow through the chillers increases the temperature entering the chillers from
50.08F to 52.62F which results in increased chiller capacity; and therefore, chiller loading is decreased from 96%
(Column 4) to 92% (Column 5). For this system at these conditions, stopping negative flow in the bypass improved
plant performance, i.e. the chillers are unloaded about 4%. References 1, 4, 5, 6 and 7 are recommended reading
on this subject.

EXCESS FLOW
A condition to consider is that plant operators may have a tendency to pump more flow to the load than required.
If this condition exists, the result is a decrease in load delta temperature and decreased negative flow or positive
flow in the bypass line. Column 6 of Table 1 assumes about 35% over pumping which results in 3,445 gpm of
positive flow in the bypass line and a T of 11.0F. The nine chillers are 99% loaded and must supply 36.5F water
to mix with the 48.78F bypass water to provide the required 37.78F supply to the load as shown by Table 1,
Column 6. Note that for this condition, if the plant operators increased flow a little more, the load could not be met
and reducing flow would reduce the load on the chillers and improve plant performance. A shut-off valve in the
bypass line will force all excess flow to the chillers and improve performance just as it did in Column 5 of Table 1
for negative flow in the bypass line. We must, of course, be sure that the flow to the chillers does not exceed the
manufacturers requirement, nor reduce the flow below the chiller manufacturers requirement.

SHUT-OFF VALVE WITH EXCESS FLOW


Lets assume a shut-off valve which eliminates the 3,445 gpm positive flow in the bypass and forces all flow to the
nine chillers operating at 99% capacity. Column 7 illustrates that the load supply temperature (Tls and Tpl) reduced
from 37.78F to 37.07F which means that the chillers can be unloaded; i.e., the shut-off valve improves
performance of this system. Unloading the chillers will raise the load supply temperature to the desired 37.8F.
Column 8 illustrates unloading the chillers from 99% to 97% to provide the required 37.82F supply to the load; i.e.
the shut-off valve improved performance by a 2% unloading of the chillers. Over pumping still exists in our
Column 8 system; and it will be difficult for the plant operators to determine how much over pumping is occurring
without a good simulation of the total system including the load. Because we have set up the problem, we know
that the system required flow (Fls) is 24,568 gpm, as shown by Columns 4 and 5. The plant typically would like to
minimize pumping and provide as high a value of temperature supply as possible. Defining this optimum operation
without a dynamic model of the existing system may be difficult, if not impossible.
The Column 5 System of Table 1 illustrates the optimum operation of the system requiring 92% loading of nine
chillers. This is accomplished by eliminating excess flow to the load and eliminating flow in the bypass line.

OPTIMUM OPERATION
We suggest that the procedure for defining optimum operation of an existing system consists of first defining the
dynamic characteristics of the plant equipment, and then by observing the dynamic characteristics of the real
system, incorporate these characteristics into a system computer model. This procedure will define the
characteristics of the load which will typically be the source of making major improvements to the efficient

operation of the system. As changes are made on the load side, the computer simulation would be updated; and
therefore always provide the plant operators direction on how to optimally control the plant.
Simply stated, we are suggesting that without a computer simulation of the existing system that is updated as the
system changes, optimum operation of the plant is not achievable for reasons including the tendency of plant
operations to pump excess flow and to turn on more chillers than required.
For the purpose of this paper, lets assume that the plant operation as defined by Column 8, could be returned to
the conditions of Column 4, wherein the flow and supply temperature to the load are optimized to the load we
have assumed without a shut-off valve in the bypass line. (See References 8, 9, 10, 11, and 12.)

THERMAL STORAGE - AGED SYSTEM


Thermal storage is a part of many chilled water systems; and therefore the dynamics of this feature will be
considered in our modeled system, see Table 1, Column 9.
Figure 2 illustrates that the peak load of 15,150 tons for an aged system can be met with seven chillers and a 6,200
ton-hour storage tank and a 306-ton ice slurry generator versus nine chillers of Column 4, i.e. a 306-ton ice slurry
generator and a storage tank replaces two 2,164-ton chillers.
Column 1 is for a balanced system and requires seven chillers. The degradation in load, as defined by Column 4,
resulted in the need for two additional chillers. One conclusion is to be drawn from System Column 1 and System
Column 9 is that thermal storage could have been the original plan for meeting the load as it degraded; i.e.
replacing the need for two additional chillers. (See References 13, 14, 15, 16, and 17.)

FIGURE 2

Figure 3 illustrates the 24-hour operation of the system. The seven chillers can meet the cooling load for all but
four hours; therefore, ice melting occurs during four hours for a total melt of 7,144 tons. The 306-ton ice slurry
generator makes ice all 24 hours, with storage peaking the 14th hour at about 6,200 ton-hours. The storage tank is
essentially depleted the 18th hour and begins to build up on the 19th hour. (See References 18, 19, 20, and 21.)

LOAD DYNAMICS
This paper illustrates the positive effects offered by thermal storage, especially in a system that has experienced
decreased delta temperature. However, it must be remembered that fixing the load is also an alternative. Reference
3 presents some basic concepts and Reference 22 is a case history of a successful effort to fix the load along with
decreasing the supply temperature to the load. Also, References 23, 24 and 25 present an alternative approach to
thermal storage.

FIGURE 3

THERMAL STORAGE - AGED SYSTEM - WITH SHUT-OFF VALVE


The Column 10 system with thermal storage and a by-pass shut-off valve is equivalent to the Column 5 System with
a shut-off valve and no thermal storage. A by-pass shut-off valve slightly reduces the peak thermal storage
requirement from 2,159 tons to 2,016 tons because the Column 9 system conditions include 1,538 gpm of bypass
flow which gives a temperature going to the thermal storage tank of 39.91F, versus 39.77F with a shut-off valve
installed. The size of the ice slurry generator can be reduced from 306 tons to 288 tons. The 24-hour ice melt is
reduced from 7,144 tons to 6,794 tons and storage is reduced from 6,200 ton-hours to 5,900 ton-hours, all
improvements provided by the bypass shut-off valve. Figure 4 illustrates the 24-hour operation of the system.

Figure 4

NEW SYSTEM - THERMAL STORAGE - SIX CHILLERS


Column 11 illustrates the conditions of a new system with thermal storage versus Column 1 or 2 of Table 1. Six
chillers can meet the load with 2,117-tons of peak thermal storage cooling. For 24-hour operation, the required
tank storage would be 6,200 ton-hours, and a 306-ton ice slurry generator could provide this daily requirement.
The thermal storage is used for four hours for a total of 6,975 tons over the 24-hour period.
Figure 5 illustrates the 24-hour operation of the system. A 306-ton ice generator and 6,200 ton-hour storage tank
replaces one or two 2,164 chillers depending if the new design was installed with seven or eight chillers. Note that
this system has flow of 2,985 gpm in the bypass. Lets assume the new system was built with six chillers and
thermal storage and see how it performs when aged.

FIGURE 5

AGED SYSTEM - THERMAL STORAGE AND SIX CHILLERS


Aging of the new system with six chillers and thermal storage increases the thermal storage load as shown by
Column 12 of Table 1. Note that the equivalent system without thermal storage is represented by Column 4 which
consists of 9 chillers.
Twenty-four hour operation requires seven hours of ice melting for a total of 15,543 tons. A storage tank capacity
of about 12,400 ton-hours would be required and a 670-ton ice slurry generator would replace 3 x 2,164 = 6, 492
tons of chiller capacity. Figure 6 illustrates the 24-hour operation.

FIGURE 6

AGED SYSTEM - THERMAL STORAGE AND FIVE CHILLERS


Reducing the number of chillers from six to five for the aged system further increases the thermal storage load as
shown by Column 13 of Table 1 to be 5,871 tons.
Figure 7 illustrates 24-hour operation showing 13 hours of ice melting for a total of 32,897 tons. A storage tank
capacity of about 19,100 ton-hours would be required and a 1,400-ton ice slurry generator would replace 4 x 2,164
= 8,656 tons of chiller capacity.

FIGURE 7

The following table illustrates the 13 conditions we have considered. The author suggests making copies of Figures
1 and 2 and writing in the values of Table 1 for each condition for ease of studying the dynamics of this assumed
system.

Table 1

Load

Balanced

Balanced
+ One

15,150

15,150

Load
Load
Degradation Degradation
-8 Chillers -9 Chillers
14,000

15,150

Shut-Off
Valve
15,150

Excess
Excess
Flow with
Flow
Shut-Off w/Shut-Off
Valve
Valve

Excess
Flow
15,150

15,150

15,150

Thermal
Storage
Thermal
Thermal
Thermal
Thermal
Aged
Storage
Storage
Storage
Storage
System
New
-6 Chillers -5 Chillers
Aged
w/Shut-Off
System
Aged
Aged
System
Valve
6 Chillers
System
System
15,150

15,150

15,150

15,150

15,150

Delta T

16.0

16.0

14.8

14.8

14.8

11.0

11.0

11.0

14.8

14.8

16.0

14.8

14.8

Tls

44.03

44.03

37.36

37.80

37.82

37.78

37.07

37.82

37.80

37.80

44.00

37.80

37.80

Tlr

60.03

60.03

52.16

52.60

52.62

48.78

48.07

48.82

52.60

52.60

60.00

52.60

52.60

Fls

22,725

22,725

22,703

24,568

24,568

33,055

33,055

33,055

24,568

24,568

22,725

24,568

24,568

Fb

-305

-3595

-3617

-5042

3445

1538

2985

4828

8118

Tb

44.03

44.03

37.36

37.80

48.78

52.60

60.00

52.60

52.60

Fce

23,030

26,320

26,320

29,610

24,568

29,610

33,055

33,055

23,030

24,568

19,740

19,740

16,450

Tce

59.81

57.84

50.12

50.08

52.62

48.78

48.07

48.82

52.6

52.6

60

52.6

52.6

Tcl

44.03

44.03

37.37

37.8

37.82

36.5

37.07

37.82

39.06

39.77

44.15

39.06

39.06

Tpl

44.03

44.03

37.37

37.8

37.82

37.78

37.07

37.82

39.91

39.77

46.24

41.72

43.53

Chillers On

% Load

100

89

100

96

92

99

99

97

100

100

100

100

100

Peak Ice
Tons

2159

2016

2117

4015

5871

24-hr
Ice Melt

7144

6794

6975

15,543

32,897

Tank
Storage
Ton-Hours

6200

5900

6200

12,400

19,100

Ice Slurry

306

288

306

670

1400

Column

10

11

12

13

SUMMARY
The paper makes three points:
Point One:

A shut-off valve in the bypass line can improve system performance, but the amount of
improvement is a function of the characteristics of the system and how it is being operated.

Point Two:

This paper suggests that a dynamic math model simulation of a system, verified by existing plant
operational data, is the first and necessary step in improving operational performance or
modifying an existing system for increased capacity. (See References 26, 27, 28, 29 and 30.)

Point Three:

We have shown that thermal storage can offer some significant system characteristics for new or
modified systems. For the system of this study, we have shown the following:

10

Table 2
Tons Chilling
Required
Aged System

Chilling Tons
Not Purchased
with Thermal Storage

Required
Ice Generating
Capacity Tons

Ratio Ice Capacity


to Chilling Tons
Not Purchased

Required Tank
Thermal Storage
Ton-Hours

System without
Thermal Storage
9 Chillers

19,476

System with
Thermal Storage
and
7 Chillers
6 Chillers
5 Chillers

15,148
12,294
10,820

4328
6492
8656

306
670
1400

.07
.10
.16

6200
12,400
19,100

For the systems studied here, unless the cost of space for a storage tank is very high, the five-chiller system with
thermal storage should have an attractive return on investment and the six-chiller and seven-chiller systems will
have an even more attractive return on investment.

CONCLUSION
Simulating the dynamics of physical systems by applying the laws of physics and thermodynamics is a well
established procedure in the design of military products which the author participated in until the mid-1970s. The
oil embargo in the fourth quarter of 1973 presented the challenge of simulating energy systems, including buildings
and its contents, for the purpose of defining energy waste and systems to eliminate that waste. A fundamental rule
of system simulation is that the simulation must give the same results, within reasonable accuracy, as the real
system.
This paper presents a simulation based on the first law of thermodynamics. Other features provided by a computer
simulation of a central chilled water system include:
The system energy use and KW demand
Chiller dynamics of various type chillers
Pumping dynamics
Load dynamics
The purpose of a computer simulation of a physical system is to understand the dynamics of the system so that
correct decisions about the system can be made. A computer simulation is not required to understand many HVAC
systems; however, the author suggests that a primary/secondary chilled water system is sufficiently complex to
require a simulation for purposes of operating, changing and expanding the system. Reference 31 is an example of
the approach.

References
(1)

Controlling Chillers In Variable Flow Systems


Gil Avery, P.E., ASHRAE Journal, February 1998

(2)

Hydronic Heating and Cooling System Design


ASHRAE Systems and Equipment Handbook, 1996, Pages 12.12

(3)

A Fundamental Perspective on Chilled Water Systems


William J. Coad, P.E., HPAC Heating/Piping/Air Conditioning, August 1998

11

(4)

A Check Valve in the Chiller Bypass Line?


Wayne Kirsner, P.E., Heating/Piping/Air Conditioning, January 1998
System Analysis Versus Quick Fixes for Existing Chilled Water Systems
James B. (Burt) Rishel, P.E., HPAC Heating/Piping/Air Conditioning, January 1998

(5)

Applying Variable Volume Pumping


Kenneth R. Luther, HPAC Heating/Piping/Air Conditioning, October 1998

(6)

Variable FlowA Control Engineers Perspective


Harris Bynum and Ed Merwin, ASHRAE Journal, January 1999

(7)

Variable Volume Pumping Fundamentals


Kenneth R. Luther, HPAC Heating/Piping/Air Conditioning, August 1998

(8)

Designing for 42F Chilled Water Supply TemperatureDoes It Save Energy?


Wayne Kirsner, P.E., ASHRAE Journal, January 1998

(9)

Optimizing Chilled Water Plants


David W. Kelly and Tumin Chan, HPAC, Heating/Piping/Air Conditioning, January 1999

(10) Applications of Optimal Control to Chilled Water Systems Without Storage


J. E. Braun, S. A. Klein, J. W. Mitchell, and W. A. Beckman, ASHRAE Publication #CH-89-6-6
(11) Methodologies for Optimal Control of Chilled Water Systems Without Storage
J. E. Braun, S. A. Klein, W. A. Beckman, and J. W. Mitchell, ASHRAE Publication #CH-89-6-5 (RP-539)
(12) Performance and Control Characteristics of a Large Cooling System
J. E. Braun, J. W. Mitchell, S. A. Klein, and W. A. Beckman, ASHRAE Publication NY 87-22-4(RP-409)
(13) Thermal Storage: A Reversible Process
Robert M. Lumpkin, HPAC Heating/Piping/Air Conditioning, January 1998
(14) Achieving Energy Conservation with Ice-Based Thermal Storage
T. W. Brady, ASHRAE Publication 94-32-1, ASHRAE Transactions: Symposia.
(15) A Comparison of Chiller-Priority, Storage-Priority, and Optimal Control of an Ice-Storage
System
J. E. Braun, ASHRAE Publication AN-92-8-1, ASHRAE Transactions: Symposia.
(16) 34 System Water Temperature Designs Save First Cost and Operating Cost
William D. McCloskey
11th Annual IDEA College/University Conference, Redondo Beach, CA, February 1998
(17) Model of an Ice-on-Pipe Brine Thermal Storage Component
Brian Vick, Douglas J. Nelson and Xianhui Yu
ASHRAE Publication 3936 (RP-699) ASHRAE Transactions: Research
(18) Ice Crystal Slurry TES System Using The Orbital Rod Evaporator
Sam P. Gladis, Michael J. Marciniak, Joseph B. OHanlon and Brad Yundt
1996 International Sustainable TES Conference, Minneapolis, MN, August 1996
(19) Ice Slurry Generator
Kirby P. Nelson, IDEA Conference, San Antonio, TX, June 1998
(20) Optimizing District Cooling Performance Utilizing Ice Slurry
Kirby P. Nelson, IDEA Conference, Williamsburg, VA, October 1998
(21) University Ice Slurry System
John Dunlap, Jerry Pippin and Kirby P. Nelson, IDEA Conference, New Orleans, LA., February 1999

12

(22) A Case History of Increasing Delta T at Arizona Health Sciences Center


Henry Johnstone and William Nelson, IDEA Conference, October 1994
(23) Rethinking Chiller Plant Design
Milton Meckler, HPAC Heating/Piping/Air Conditioning, January 1998
(24) Peak Shaving Using Natural Gas Engine-Driven Chillers
Roger L. Arnold, Jr.,and William P. Bahnfleth, HPAC Heating/Piping/Air Conditioning, September 1998
(25) Gas-Fired Chiller-Heaters as a Central Plan Alternative for Small Office Buildings
Roger M. Thies and William P. Bahnfleth, HPAC Heating/Piping/Air Conditioning, January 1998
(26) Near-Optimal Control of Cooling Towers for Chilled-Water Systems
J. E. Braun and G. T. Diderrich, ASHRAE Publication SL-90-13-3
(27) Effectiveness Models for Cooling Towers and Cooling Coils
J. E. Braun, S. A. Klein, and J. W. Mitchell, ASHRAE Publication 3270.
(28) Models for Variable-Speed Centrifugal Chillers
J. E. Braun, J. W. Mitchell, and S. A. Klein, ASHRAE Publication NY 87-22-2 (RP-409).
(29) Predicting Central Plant HVAC Equipment Performance Using Neural Networks - Laboratory
System Test Results
Darrell D. Massie, Peter S. Curtiss and Jan F. Kreider, ASHRAE Publication SF-98-22-4 (4112).
(30) Optimizing System Control with Load Prediction by Neural Networks for an Ice Storage
System
Minoru Kawashima, Charles E. Dorgan, and John W. Mitchell, ASHRAE Publication AT-96-21-4.
(31) Modifications Can Optimize Existing Cooling System Capacity
Steve M. Tredinnick, District Energy, IDEA, Volume 84, Number 2, Fourth Quarter 1998

13

You might also like