Method Statement Excavation Works
Method Statement Excavation Works
Method Statement Excavation Works
1.0 PURPOSE:
3.1 CONSULTATION
3.2 PLANNING
MS NO.
METHOD STATEMENT Revision No. A
Planning and preparation will be the first essential step in ensuring that
work is done safely. Planning and preparation will involve
consultation with all relevant persons engaged in the work and will
include hazard identification, risk assessment and risk control processes.
Where appropriate, the advice of a geotechnical engineer will be sought
before starting excavation work. The principal contractor and the
contractor in their capacity as employers will:
1. Provide such information, instruction, training and supervision as may
be necessary to ensure the health and safety of his employees; and
2. Provide or maintain means of access to and egress from the work place
safe and without risks.
The principal contractor will plan for the work to be done safely. The principal
contractor will ensure that a site specific occupational health and safety
management plan is prepared and documented for each place of work where
excavation is to be carried out, before the excavation work commences. This
plan will be developed in consultations undertaken with the contractor/s and
their employees or representatives. The plan will include a documented work
method statement, provided by the contractor, describing how the work is to
be done safely. The health and safety management plan will be monitored to
ensure that work is carried out according to that plan and that the plan is
effective. The plan will be maintained and up to date during the course of the
excavation works. Before excavation work starts, the principal contractor in
consultation with the contractor doing the work will at least consider:
The contractor doing the work has an obligation under RLC/HSE regulations to
provide and maintain a workplace that is safe and without risks to health for
their employees in relation to those matters over which he has control.
A hazard identification risk assessment and control process will be carried out
by the contractor in consultation with the principal contractor to determine if
persons are at risk. Safe systems of work will then be put into place to control
the risk. The identification of the hazards associated with excavation work, the
risk assessment and the risk control measures will be documented.
The process of hazard identification, risk assessment and control is made up of
the following steps:
After identifying the hazards involved in carrying out the work the principal
contractor in consultation with the contractor will assess the health and safety
risks and determine what type of safeguards or systems of work will be
implemented to ensure the health and safety of all persons on site. This will
always include eliminating exposure of persons to the hazard.
The control measures at Level 1 (eliminate the hazard) give the best results
and will be adopted. The measures at Levels 2 (minimize the risk) and 3 (other
controls) are less effective and they require more frequent reviews of the
hazards and systems of work. In some situations a combination of control
measures may need to be used.
The control measures recommended by the contractor will be considered by
the principal contractor as part of the health and safety management plan. Any
new control measures will be evaluated to ensure that they are effective and
safe and that new hazards are not created (directly or indirectly) by them.
3.7 PREPARATION
When preparing for the commencement of work the principal contractor and
the contractor doing the work will ensure that the workplace is safe based on
the health and safety management plan. They will also check to ensure that all
MS NO.
METHOD STATEMENT Revision No. A
controls identified by the risk assessment have been put in place and that no
new hazards exist.
The contractor will plan for such matters and ensure that appropriate control
measures are in place. The risk assessment will take into account the following
factors:
(a) nature of hazard and possible emergencies;
(b) size and location of place of work;
(c) number and mobility of persons at the workplace; and
(d) location of nearest emergency services.
Shoring systems, benching and battering are engineering issues that involve
both structural design and soil mechanics. The use of adequate shoring,
benching and battering is essential to control the risk of a collapse or failure of
a trench or open excavation.
4.3 SHORING
ensure the safety of persons entering the excavation. A shoring system will not
be required if, having regard to the nature and slope of the side of the
excavation and other relevant circumstances there is no reasonable likelihood
that earth, rocks other material will fall or dislodge from a height of more
than1.5m and bury, trap or strike a person that is in the excavation. The risk
assessment process will be used to identify unstable conditions and the risks
involved. Shoring the face of an excavation will proceed as the work of
excavation progresses. Where a mechanical digger is used, the risk
assessment will be used to determine whether any part of the trench may be
left unsupported. Shoring may include any suitable system of temporary
supports
and sheeting material used to maintain the stability of the sides of an
excavation. The installation and removal of shoring will take place from outside
an excavation.
Both benching and battering of excavation walls are methods of work which
may be used to minimize the risk of the soil or rock slipping onto the
excavation.
Where risks or hazards that create a risk to health and safety of those carrying
out the work are identified, they will be controlled prior to any further work
being carried out. This may require further advice from geotechnical and
design engineers to review the adequacy of the control measures in place. The
risk assessment will be reviewed at all terms during the excavation works.
The control measures implemented will be appropriate and effective for the
hazards and risks of the situation. Consideration will be given to factors such as
how long the excavation will be open, and who may gain access to the
excavation. The following control measures will be considered:
(a) isolating the hazardous area, such as by the use of perimeter fencing,
barricades, screens, barriers, handrails and/or covers, which are capable of
preventing access or preventing the fall of a person
(b) removal or lowering ladders on work site
(c) immobilization of plant to prevent unauthorized use
(d) compliance with relevant RLC/HSE requirements.
(e) hazard warning lights, signs, markers or flags
(f) site security measures, including fencing or use of safety observer(s)
(g) night lighting.
MS NO.
METHOD STATEMENT Revision No. A
Signs will be erected around the site showing the name and contact telephone
number (including after hours emergency number) of the principal
contractor/contractor/RLC emergency numbers.
Before starting the work, the location of any underground services (eg.
electricity, telecommunication cables, etc) will be identified. Wherever service
plans are available they will be obtained by the principal contractor and also
provided to the contractor and operator carrying out the excavation work. The
MS NO.
METHOD STATEMENT Revision No. A
contractor will allow for inaccuracies and the possibility of other unknown or
hidden services.
Further, the principal contractor will arrange for these services to be clearly
marked according to the available plans and on site checks prior to
commencement of work. Services will be exposed at sufficient intervals to
positively identify their location and/or lie. The following are ways of checking
for underground services:
The contractor will ensure that excavation work which is likely to reduce the
security or stability of any part of any building or structure will not be
commenced or continued unless adequate steps are taken before and during
the progress of the work to prevent danger to any person from collapse of the
building or structure or a part of a building or structure.
In assessing the risk, measures such as the following will be considered before
starting excavation work:
The contractor will also ensure the stability of vehicular access which might be
affected by the work.
MS NO.
METHOD STATEMENT Revision No. A
The contractor will ensure that where there is risk from rising water or from an
eruption of water or material, the means to enable every person to reach a
position of safety will be provided.
Where the risk assessment has identified a risk of collapse as a result of loads
or materials above or near the excavation, shoring will be in place before any
person enters the excavated area.
(e) securing all loose materials in place. When working on a slope, a risk
assessment will be conducted to determine the safest side of the excavation to
dump soil and excavated material. This will often be on the lower side of the
slope to reduce the risk of wall collapse or material falling into the excavation.
Site factors will be considered.
As far as practicable, loads will not be suspended or travel over a person. The
following control measures will be considered:
(a) fences
(b) hand rails and toe boards
(c) overhead protection
(d) enclosed walkways
(e) safety helmets and other adequate means of protection
(f) provision of safe means of lowering and raising plant, materials, spoil, etc
(g) use of lanyards to secure loose tools
(h) loads will be lifted/suspended within the safe working limits of the
machinery load used.
The contractor will assess and control the risks involved in carrying out manual
handling tasks. This will be done in consultation with employees who are
required to carry out the work.
4.14 ACCESS
MS NO.
METHOD STATEMENT Revision No. A
4.14.1 LIGHTING
4.14.2 RAMPS
When access ramps are provided they will not exceed 1:2.7 (20 degrees).
Ramps steeper than 1:8 (7 degrees) will be cleared, grated or have surfaces
which allow adequate foot grip. Where such ramps form part of an excavation,
a risk assessment will be conducted to determine the maximum safe soil height
above the ramp before some sort of soil support (eg trench shield) is provided.
Ramps will be designed and constructed to effectively withstand any
anticipated load that they may be required to support during use.
4.14.3 LADDERS
when ladders are used for access the contractor will provide the following:
(a) the ladder will be secured at both top and bottom against displacement.
Ladders will have non-slip feet and whenever practicable will be set up at an
angle of 1:4 (75degrees).
(b) a safe and adequately sized landing place when stepping off the ladder will
be provided.
(c) the stiles of the ladder will extend at least one meter above the landing
place.
(d) metal or wire reinforced ladders will not be used where there is a risk of
contact with electrical conductor wires(power lines) or of electric shock. Non-
conducting ladders will be used or a clearance of at least 4metres from
conductors will be maintained.
MS NO.
METHOD STATEMENT Revision No. A
4.14.4 SCAFFOLDING
Fixed platforms, walkways, stairways and ladders will comply with the
requirements of RLC/HSE regulations
(f) the use of audible reversing alarms and/or other technologies or other safe
work practices. Note: reversing
alarms may cause confusion where multiple plant is using the same area and
other systems of work may be required.
(g) minimizing the number of moving plant working at one time. Where
multiple plant is being operated around the work site a competent person will
be used to direct the plant:
• when operating in close proximity to each other;
• when reversing;
• where persons are on the ground; and
• in other situations as indicated by the risk assessment.
(i) where construction vehicles or plant enter or leave the work area by public
roads, systems of control and notices will be placed at all entrances and exits
to the work area to protect and warn all persons approaching or in the vicinity
(j) where plant is being operated near persons, near underground or above
ground services (any other workers, soils technicians, surveyors, visitors etc)
(k) designated delivery and turning areas. The movement of delivery vehicles
on construction sites frequently
presents a hazard particularly when reversing, loading and unloading.
4.16 NOISE
Noise management provisions will be carried out by the contractor doing the
work and will ensure noise levels from machinery or equipment being used do
not become a risk to hearing or health.
The contractor will also ensure compliance with RLC Environmental Protection
requirements in relation to noise.
MS NO.
METHOD STATEMENT Revision No. A
The contractor will also ensure that exposure to nonhazardous substances such
as nuisance dust is at a level not greater than that established by safe
exposure standards. In dry conditions, frequent watering, where practicable, or
other similar methods will be used to reduce nuisance dust that will not exceed
20mg/m3.
Hydrogen Sulfide
Carbon dioxide
These may be encountered when carrying out work such as excavations for
foundations, in addition to trenches.
Where the risk assessment indicates the possibility of air contamination, the
work will be examined by competent persons using appropriate detecting
equipment and will include air testing for:
(a) oxygen deficiency
(b) airborne contaminants
All plant such as excavators, tractors, etc used for lifting will have their safe
working loads displayed and maintained. If the function or condition of plant
represents an immediate risk to health and safety, operation will cease and the
plant will be withdrawn from use until a risk assessment and appropriate
control measures are implemented.
MS NO.
METHOD STATEMENT Revision No. A
The contractor will ensure the plant repairs will be carried out by a competent
person and in accordance with the designer’s or manufacturer’s requirements.
The contractor will keep logbooks and inspection check sheets containing a full
service and repairs history of the equipment.
The training provided and the instruction given will at least include:
MS NO.
METHOD STATEMENT Revision No. A
(a) induction training which complies with Construction Safety & RLC/HSE
regulation
(b) the work method to be used for the excavation or
associated work and the manual handling procedures for the work to be carried
out, including control measures
based on the risk assessment to prevent injury.
(c) the correct use, care and storage in accordance with the manufacturer’s
recommendations where appropriate, of:
• personal protective equipment; and
• tools and equipment to be used.
(d) the use of plant and associated equipment, including electrical safety and
hazardous substances.
(e) procedures to be adopted in the event of accident, injury or other
emergency, including evacuation.
The use of PPE to control hazards and risks is the least effective measure and is
lowest on the hierarchy of control measures. Control measures will be selected
from the highest level possible and be adopted where practicable. The
measures at the lower levels are less effective and they require more frequent
reviews of the hazards and systems of work. They will only be used when other
control
measures are impracticable or when, after implementing other controls, a
residual risk remains.
Before commencing any work, the principal contractor and or contractors will
identify any conditions likely to affect the health and safety of persons. If other
means of control are not practical, the provision and use of appropriate PPE
that complies with the relevant RLC/HSE regulations will be arranged.
Employees will be trained till they are competent in the proper selection, use
and maintenance of the PPE. There will be sufficient supervision and
monitoring conducted to ensure compliance.
The use of safety helmets may prevent or lessen a head injury from falling
objects or a person hitting their head against something. Where there is a
likelihood of persons being injured by falling objects and overhead protection is
not provided, persons will be provided with and will use an appropriate safety
helmet. Appropriate safety helmets will also be provided and used where a
person may strike their hand against a fixed or protruding object or where
there is a risk of accidental head contact with electrical hazards.
MS NO.
METHOD STATEMENT Revision No. A
All persons on excavation sites will wear head protection that conforms to
Occupational protective helmets.
Eye protection complying with RLC/HSE regulations will also be provided, where
there is a risk of eye injury. Selection, use and management systems will
comply with RLC/HSE regulations
Persons working near traffic, mobile plant or equipment under operator control,
will be provided with and use high visibility garments. Other clothing not
covered by the high visibility garment will be light colored and all garments will
be selected for best contrast with the surrounding background.
Where there is a risk of hand injury hand protection that complies with RLC/HSE
regulations will be provided and used.
While the obligation for each person is different, all persons will ensure that the
way they carry out their work will not interfere with the health and safety of the
other persons who are present at the workplace. All work practices must
comply with RLC/HSE regulations.
CONTRACTOR’S RESPONSIBILITIES
The contractor has an obligation to take reasonable care for the health and
safety of the other persons in the place of work and to cooperate with their
MS NO.
METHOD STATEMENT Revision No. A
employer in the interests of health, safety and welfare. Employees will use
appropriate protective equipment for the work being performed.