Method Statement Excavation Works

Download as doc, pdf, or txt
Download as doc, pdf, or txt
You are on page 1of 24

MS NO.

METHOD STATEMENT Revision No. A

EXCAVATION WORKS Page 1 of 25

1.0 PURPOSE:

This method statement provides guidance to prevent injury to persons


engaged in excavation works on the RAS LAFFAN C IWPP/QATAR site.
2.0 SCOPE:
Planning, preparation conduct and Method of excavation work.
3.0 PLANNING AND PREPARATION:

3.1 CONSULTATION

The principal contractor, the contractor doing the work, employers,


employees and their representatives will consult with each and
determine the provision of all safeguards. The consultation process will
be used during the planning and preparation stages to determine safe
systems of work based on the assessment of the risks. Structural or
geotechnical engineers will be involved in the consultation process when
appropriate.
The consultation process will at least cover the following:
(a) Nature and condition of the ground or working environment.
(b)Nature of the work and other activities that may affect safety
(c) Static and dynamic loads near excavation
(d)Interaction with other trades
(e) Workplace access
(f) Management of surrounding vehicular traffic and ground vibration
(g) Work force safety

(h)Type of equipment used for excavation


(i) The provision of appropriate amenities, which will depend on the type
of work space.
(j) Compliance with all RLC/ HSE regulations

3.2 PLANNING
MS NO.
METHOD STATEMENT Revision No. A

EXCAVATION WORKS Page 2 of 25

Planning and preparation will be the first essential step in ensuring that
work is done safely. Planning and preparation will involve
consultation with all relevant persons engaged in the work and will
include hazard identification, risk assessment and risk control processes.
Where appropriate, the advice of a geotechnical engineer will be sought
before starting excavation work. The principal contractor and the
contractor in their capacity as employers will:
1. Provide such information, instruction, training and supervision as may
be necessary to ensure the health and safety of his employees; and
2. Provide or maintain means of access to and egress from the work place
safe and without risks.

3.3 PLANNING BY PRINCIPAL CONTRACTOR

The principal contractor will plan for the work to be done safely. The principal
contractor will ensure that a site specific occupational health and safety
management plan is prepared and documented for each place of work where
excavation is to be carried out, before the excavation work commences. This
plan will be developed in consultations undertaken with the contractor/s and
their employees or representatives. The plan will include a documented work
method statement, provided by the contractor, describing how the work is to
be done safely. The health and safety management plan will be monitored to
ensure that work is carried out according to that plan and that the plan is
effective. The plan will be maintained and up to date during the course of the
excavation works. Before excavation work starts, the principal contractor in
consultation with the contractor doing the work will at least consider:

(a) An assessment of the risks involved in carrying out the work.


(b) the most appropriate method to prevent any risk of injury.
(c) An assessment of the ground conditions and working environment
(d) Providing suitable and safe access to and from the work place including the
work area.
(e) The area of the excavation work will be clearly defined by barricades and
warning signs.
(f) Where necessary the exact location of the work will be clearly marked.
(g) The identification and marking of the location of any above ground,
underground or overhead services
(h) That the work does not affect the structural integrity of adjoining buildings
or structures, roads, footpaths.
(i) Electrical safety, including the location of underground and aboveground
service cables and nearby overhead power lines and providing systems of work
which comply with RLC & RLC/HSE regulations.
(j) That all persons carrying out the work will receive appropriate supervision,
training and instruction.
(k) Security of excavation during work and when left unattended.
MS NO.
METHOD STATEMENT Revision No. A

EXCAVATION WORKS Page 3 of 25

(l) Establishment of emergency and rescue procedures in the event of an


emergency.

3.4 PLANNING BY THE CONTRACTOR

The contractor doing the work has an obligation under RLC/HSE regulations to
provide and maintain a workplace that is safe and without risks to health for
their employees in relation to those matters over which he has control.

In addition to consultation with the principal contractor in the overall job


planning, the contractor will at least consider:
(a) An assessment of the risks in carrying out the work.
(b) The most appropriate methods of preventing the risk of injury.
(c) Providing a documented safe work method statement describing how the
work will be done safely. This safe work method statement will take into
account an assessment of the risk involved in carrying out the work.
(d) Providing suitable and safe access to and from the work area at all times.
(e) Preventing persons entering a work area where there is a risk of injury.
(f) An assessment of manual handling tasks which could cause back strains and
other injuries and providing systems of work which comply with the provisions
of RLC/HSE regulations.
(g) That the location of overhead and underground services, i.e. electricity and
telecommunication cables, are identified and clearly marked.
(h) Electrical safety, including the location of underground electrical service
cables and nearby overhead power lines and providing systems of work which
comply with RLC/HSE regulations
(i) The use of personal protective equipment (PPE) Eg: Safety footwear, eye,
coveralls, high visibility jackets, hearing protection, safety helmets, gum boots,
gloves, disposable clothing etc.
(j) That all persons carrying out the work are provided with appropriate training
and instruction.
(k) That supervision is provided by a competent person.
(l) Establishment of emergency and rescue procedures in the event of an
emergency.

3.5 HAZARD IDENTIFICATION, RISK ASSESSMENT AND CONTROL

A hazard identification risk assessment and control process will be carried out
by the contractor in consultation with the principal contractor to determine if
persons are at risk. Safe systems of work will then be put into place to control
the risk. The identification of the hazards associated with excavation work, the
risk assessment and the risk control measures will be documented.
The process of hazard identification, risk assessment and control is made up of
the following steps:

1. Identify the hazards.


MS NO.
METHOD STATEMENT Revision No. A

EXCAVATION WORKS Page 4 of 25

2. Assess the risk(s) arising from the hazards.


3. Use appropriate control measures to eliminate or reduce the risk(s).
4. Monitor and review the control measures to ensure continual safety.

After identifying the hazards involved in carrying out the work the principal
contractor in consultation with the contractor will assess the health and safety
risks and determine what type of safeguards or systems of work will be
implemented to ensure the health and safety of all persons on site. This will
always include eliminating exposure of persons to the hazard.

3.6 HIERARCHY OF CONTROL MEASURES

The following hierarchy of control measures is listed in terms of levels.


selecting the highest level possible to develop each control measure.

Level 1: Eliminate the hazard:


• For example, choose different Excavation method.

Level 2: Minimize the risk by:


• substituting the system of work or plant (with something safer).
• modifying the system of work or plant (to make it safer).
• isolating the hazard (eg. introduce a restrictive work area).
• introducing engineering control (eg. dust control).

Level 3: Other controls:


• adopting administrative controls such as hazard warning signs and specific
training and work instructions.
• using personal protective equipment (eg. eye, respiratory and hearing
protection).

The control measures at Level 1 (eliminate the hazard) give the best results
and will be adopted. The measures at Levels 2 (minimize the risk) and 3 (other
controls) are less effective and they require more frequent reviews of the
hazards and systems of work. In some situations a combination of control
measures may need to be used.
The control measures recommended by the contractor will be considered by
the principal contractor as part of the health and safety management plan. Any
new control measures will be evaluated to ensure that they are effective and
safe and that new hazards are not created (directly or indirectly) by them.

3.7 PREPARATION

When preparing for the commencement of work the principal contractor and
the contractor doing the work will ensure that the workplace is safe based on
the health and safety management plan. They will also check to ensure that all
MS NO.
METHOD STATEMENT Revision No. A

EXCAVATION WORKS Page 5 of 25

controls identified by the risk assessment have been put in place and that no
new hazards exist.

Preparation will also at least include:

(a) an assessment of climatic/environmental conditions.


(b) access to and from the workplace.
(c) specific instructions for employees.
(d) that plant and equipment is suitable for the intended use and inspected by
a third party before use and is properly maintained.
(f) personal protective equipment.
(g) that the location of underground, above ground and overhead services are
identified and clearly marked.
(h) emergency and rescue procedures in the event of an accident, injury or
other emergency, including the means of protect any other persons in the
vicinity.

3.8 EMERGENCY AND RESCUE PROCEDURES

The contractor will ensure that, in the event of an emergency, adequate


arrangements have been made to ensure the safety of workers and other
persons on site. The emergency may result from an accident or injury, landslip
or other potentially dangerous occurrence. Natural disaster including electrical
storms, floods,plant or machinary fire etc may also present hazards to the
working operations.

The contractor will plan for such matters and ensure that appropriate control
measures are in place. The risk assessment will take into account the following
factors:
(a) nature of hazard and possible emergencies;
(b) size and location of place of work;
(c) number and mobility of persons at the workplace; and
(d) location of nearest emergency services.

Control measures may include:

(a) development and communication of a warning system.


(b) development and communication of safe and rapid evacuation procedures,
including injured persons.
(c) having trained personnel to oversee evacuation and rescue procedures until
emergency authorities arrive.
(d) appropriate medical treatment and evacuation of injured persons.
(e) shutting down of work, including plant and electrical equipment.
(f) provision of firefighting equipment at appropriate locations.
MS NO.
METHOD STATEMENT Revision No. A

EXCAVATION WORKS Page 6 of 25

(g) display of evacuation procedures in appropriate location(s)

4. WORK SYSTEMS AND CONTROL MEASURES

The principal contractor and contractor have an obligation under RLC/HSE


regulations to provide and maintain a workplace that is safe and without risks
to health for their employees in relation to those matters over which they have
control. Control measures to prevent persons being injured during excavation
work will be provided and maintained as part of a safe system of work.

The system of work and control measures selected will be determined by


individual job factors identified in the
consultation and risk assessment process. The following hazards are commonly
associated with excavation work and will be considered by the risk assessment
process:

(a) the fall or dislodgement of earth and rock


(b) the instability of the excavation or any adjoining structure
(c) the inrush or seepage of water
(d) unplanned contact with utility services eg, electricity
(e) the placement of excavated material
(f) falls into excavations
(g) the movement and positioning of heavy plant and equipment affecting the
excavation
(h) ground vibration affecting the stability of the excavation
(i) vehicle movement
(j) excessive noise from the operation of machinery and plant
(k) manual handling injuries
(l) changes to excavation conditions.

4.1 PREVENTION OF COLLAPSE OR FAILURE OF TRENCHES AND OPEN


EXCAVATIONS

A risk assessment will be conducted to determine which controls will be


implemented to prevent persons being injured by collapse or failure of all or
part of a trench or open excavation. It will consider at least the following:

(a) the depth of the excavation;


(b) the nature of the strata - sand, clay, shale, floaters, etc including their likely
behavior upon exposure to the elements;
(c) fractures or faults in rock.
(d) the presence of moisture or water;
(e) the possibility of exposure to wet weather and water from other sources;
(f) any load close to the edge or in the zone of influence of the excavation;
(g) vibration;
(h) the exposure time;
MS NO.
METHOD STATEMENT Revision No. A

EXCAVATION WORKS Page 7 of 25

(i) any previous disturbance of the ground, eg previous excavations; and


(j) adjoining buildings or structures

Removal of soil from an excavation causes unbalanced soil stresses which


reduce the capacity of the excavation to support itself. There may be additional
geotechnical engineering issues that will be considered. Accordingly where the
risk assessment identifies the risk of an unstable condition, the following
measures will be considered before starting excavation work:

(a) seeking advice from appropriately qualified engineers,


(b) carrying out a geotechnical analysis,
(c) engaging a competent person to supervise the progress of the excavation
work.

Shoring systems, benching and battering are engineering issues that involve
both structural design and soil mechanics. The use of adequate shoring,
benching and battering is essential to control the risk of a collapse or failure of
a trench or open excavation.

4.2 DESIGN OF ENGINEERING CONTROLS

Design specifications for engineering controls such as shoring support


structures, benching or battering will be prepared by an appropriately qualified
person in accordance with relevant standards and codes. In developing
specifications, at least the following factors will be considered:
(a) the size and strength of the component members of the shoring
(b) existing and changing ground conditions
(c) the loads and types of ground or soil conditions to be shored
(d) static loads near excavation, eg. spoil pile, buildings and structures
(e) dynamic loads near excavation, eg. traffic and excavation equipment
(f) ground vibration, eg. heavy traffic, mobile plant, and pile driving.
(g) difficulties or risks that other services may pose ie overhead power lines,
existing or proposed underground services
(h) working environment such as exposure to dust, noise, water,
(i) that systems of work are in accordance with any requirements of the
RLC/HSE regulations
(j) location of utility services
(k) safety during installation and removal.

4.3 SHORING

Where necessary, all trenches and excavations will be adequately shored or


supported to prevent a fall or dislodgement of earth, rock or other material
forming the side of or adjacent to, any excavation work from burying, trapping
or striking a person that is in the excavation. Where such a risk also exists for
those installing supports, other appropriate control measures will be in place to
MS NO.
METHOD STATEMENT Revision No. A

EXCAVATION WORKS Page 8 of 25

ensure the safety of persons entering the excavation. A shoring system will not
be required if, having regard to the nature and slope of the side of the
excavation and other relevant circumstances there is no reasonable likelihood
that earth, rocks other material will fall or dislodge from a height of more
than1.5m and bury, trap or strike a person that is in the excavation. The risk
assessment process will be used to identify unstable conditions and the risks
involved. Shoring the face of an excavation will proceed as the work of
excavation progresses. Where a mechanical digger is used, the risk
assessment will be used to determine whether any part of the trench may be
left unsupported. Shoring may include any suitable system of temporary
supports
and sheeting material used to maintain the stability of the sides of an
excavation. The installation and removal of shoring will take place from outside
an excavation.

4.3.1 REMOVAL OF SHORING SUPPORTS

When removing shoring, the support system will be extracted / dismantled in


the reverse order of its installation. Persons performing the work in the
excavation will not work outside the protection of the ground support system.

4.4 BENCHING AND BATTERING EXCAVATION WALLS

Both benching and battering of excavation walls are methods of work which
may be used to minimize the risk of the soil or rock slipping onto the
excavation.

If battering is implemented, it will commence from the bottom of the


excavation. When benching or battering the walls of an excavation, an angle of
repose of 45 degrees will not be exceeded unless certified in writing by a
geotechnical engineer.

4.5 INSPECTION OF SUPPORT SYSTEMS

Where risks or hazards that create a risk to health and safety of those carrying
out the work are identified, they will be controlled prior to any further work
being carried out. This may require further advice from geotechnical and
design engineers to review the adequacy of the control measures in place. The
risk assessment will be reviewed at all terms during the excavation works.

The following conditions will be considered or monitored:


(a) shoring becoming unstable
(b) shoring components not secure or failing
(c) angle of batter remains sufficient to prevent collapse
(d) premature removal of shoring
MS NO.
METHOD STATEMENT Revision No. A

EXCAVATION WORKS Page 9 of 25

(e) workers in excavations venturing outside the confines of shoring, benching


or battering
(f) cracks appearing near the edge of an excavation
(g) excavated and other material being placed within the zone of influence of
the excavation (h) machinery operating within the zone of influence of
excavations causing weight and vibration influences
(i) surface soil falling into the excavation
(j) water seeping into excavations from its side walls or base
(k) changes to soil and/or weather conditions
(l) extra loading
(m)surface water or run-off entering the excavations or accumulating on
surface near the excavation
(n) inclined bedding planes “dipping” into the excavation
(o) heaving or swelling of the ground at the bottom of the trench
(p) subsidence alongside the excavations
(q) unsafe access or egress
(r) exposure of contaminated ground
(s) undercutting of the excavation

4.6 SECURITY OF EXCAVATIONS

A risk assessment will be conducted in order to determine which controls will


be implemented to ensure the security of excavation both during work and
when left unattended.

The control measures implemented will be appropriate and effective for the
hazards and risks of the situation. Consideration will be given to factors such as
how long the excavation will be open, and who may gain access to the
excavation. The following control measures will be considered:

(a) isolating the hazardous area, such as by the use of perimeter fencing,
barricades, screens, barriers, handrails and/or covers, which are capable of
preventing access or preventing the fall of a person
(b) removal or lowering ladders on work site
(c) immobilization of plant to prevent unauthorized use
(d) compliance with relevant RLC/HSE requirements.
(e) hazard warning lights, signs, markers or flags
(f) site security measures, including fencing or use of safety observer(s)
(g) night lighting.
MS NO.
METHOD STATEMENT Revision No. A

EXCAVATION WORKS Page 10 of 25

Signs will be erected around the site showing the name and contact telephone
number (including after hours emergency number) of the principal
contractor/contractor/RLC emergency numbers.

4.6.1 FALL PREVENTION

A safe system of work and appropriate control measures will be provided


wherever persons are exposed to a risk of falling during excavation work. It is a
RLC/HSE requirement to effectively fence all excavations and holes more than
1.2m deep. It will also be noted that all platforms, open sides of stairways and
stairway landings will be fenced.

In addition to the security measures listed above, the following measures to


prevent falls will be considered:

(a) use of intermediate platforms for deep excavation


(b) provision of a safe means of movement between different levels of the
excavation
(c) provision of an adequate fall arrest system
(d) backfilling as work progresses Control measures will be properly installed
and maintained until the work
is completed or until there is no longer any risk of persons falling into the
excavation.

4.6.2 PREVENTION OF DROWNING

Where, during excavation work, and excavation is likely to collect or retain


water so as to create a hazard to persons in the vicinity, the excavation will be
covered or fenced off.

Control measures will be provided where there is a risk of a person drowning as


a result of a fall into water or other liquid, eg slurry. The following measures
will be considered:
(a) provision of positive means of fall protection such as fencing, handrails and
safety harness
(b) provision of an observer.

4.7 UNDERGROUND SERVICES

Before starting the work, the location of any underground services (eg.
electricity, telecommunication cables, etc) will be identified. Wherever service
plans are available they will be obtained by the principal contractor and also
provided to the contractor and operator carrying out the excavation work. The
MS NO.
METHOD STATEMENT Revision No. A

EXCAVATION WORKS Page 11 of 25

contractor will allow for inaccuracies and the possibility of other unknown or
hidden services.

Further, the principal contractor will arrange for these services to be clearly
marked according to the available plans and on site checks prior to
commencement of work. Services will be exposed at sufficient intervals to
positively identify their location and/or lie. The following are ways of checking
for underground services:

(a) using remote location devices


(b) hand digging, using hand tools with non-conductive handles.

All persons whose work may be affected by an underground service will be


advised of the location of every underground service.

Appropriate control measures will be implemented after consultation with


relevant service providers. These measures may include the protection,
support or removal of services to ensure safety of workers.

4.8 EXCAVATIONS ADJACENT TO BUILDINGS OR STRUCTURES

The contractor will ensure that excavation work which is likely to reduce the
security or stability of any part of any building or structure will not be
commenced or continued unless adequate steps are taken before and during
the progress of the work to prevent danger to any person from collapse of the
building or structure or a part of a building or structure.

In assessing the risk, measures such as the following will be considered before
starting excavation work:

(a) seeking advice from appropriately qualified engineers


(b) undertaking a geotechnical analysis
(c) engaging a competent person to supervise the progress of the excavation
work
(d) underpinning of structures
(e) construction of effective retaining walls
(f) minimizing ground disturbance and vibration by taking into account the
location of machinery, the sequence of work, the impact, severity and scale of
excavation
(g) backfilling as work progresses
(h) evacuation of affected areas.

The contractor will also ensure the stability of vehicular access which might be
affected by the work.
MS NO.
METHOD STATEMENT Revision No. A

EXCAVATION WORKS Page 12 of 25

4.9 PROTECTION AGAINST RISING, IRRUPTIONOR INRUSH OF WATER


OR MATERIAL

The contractor will ensure that where there is risk from rising water or from an
eruption of water or material, the means to enable every person to reach a
position of safety will be provided.

If a risk assessment reveals a risk of rising, irruption or inrush of water or


material, appropriate control measures will be provided. These may include the
following:

(a) provision of exploratory or warning holes where water flows at a reduced


rate to warn of danger
(b) provision of sumps
(c) lowering the water table (eg use of spear pumps)
(d) increasing exit points eg increasing the number of exit ladders
(e) provision of pumps

4.10 MATERIALS AND LOADS ABOVE AND NEAR EXCAVATIONS

To reduce the risk of excavation collapse, excavated or other loose material


will be effectively stored or retained away from the excavation. Excavated
material will be placed outside the zone of influence.

Alternatively the support system will be designed to accommodate such


additional load including ground water pressures, saturated soil conditions and
saturated materials.

Mechanical plant, vehicles, storage of materials or any heavy loads will be


prevented from approaching within or encroaching on the zone of influence of
the excavation unless the support system has been specifically designed for
such loads.

Where the risk assessment has identified a risk of collapse as a result of loads
or materials above or near the excavation, shoring will be in place before any
person enters the excavated area.

The following measures will also be considered before starting excavation


work:
(a) controlling access to exclude persons from hazardous areas, eg relocating
means of access
(b) moving and storing loads outside the zone of influence of the excavation
(c) provision of wheel stoppers to limit movement of mobile equipment
adjacent to the excavation
(d) reducing the number of trench shields stored near excavation by pulling
along trench shields and backfilling as the excavation progresses
MS NO.
METHOD STATEMENT Revision No. A

EXCAVATION WORKS Page 13 of 25

(e) securing all loose materials in place. When working on a slope, a risk
assessment will be conducted to determine the safest side of the excavation to
dump soil and excavated material. This will often be on the lower side of the
slope to reduce the risk of wall collapse or material falling into the excavation.
Site factors will be considered.

4.11 PROTECTION FROM FALLING OBJECTS

The risk assessment will be used to determine appropriate control measures to


protect persons from accidental falls of objects including tools, plant and other
construction materials.

As far as practicable, loads will not be suspended or travel over a person. The
following control measures will be considered:
(a) fences
(b) hand rails and toe boards
(c) overhead protection
(d) enclosed walkways
(e) safety helmets and other adequate means of protection
(f) provision of safe means of lowering and raising plant, materials, spoil, etc
(g) use of lanyards to secure loose tools
(h) loads will be lifted/suspended within the safe working limits of the
machinery load used.

4.12 ELECTRICAL HAZARDS

Specific control measures will be implemented when work is done in the


vicinity of power lines whether they are overhead or underground.

A power line or electrical conductor will always be assumed to be energized or


‘live’, including when a communication cable or wire is encountered.

4.12.1 UNDERGROUND ELECTRICAL HAZARDS

A safe system of work will be devised to address electrical hazards associated


with underground services as the following:
(a) de-energizing and isolating the cables and obtaining documentary evidence
of the continuing isolation of the power supply before proceeding with the work
(b) a system of lock out and lock out tags
(c) use of electronic surveillance prior to excavation to determine location of
services.
(d) hand digging using tools with non conductive handles
(e) wearing rubber boots and insulating gloves
MS NO.
METHOD STATEMENT Revision No. A

EXCAVATION WORKS Page 14 of 25

4.12.2 OVERHEAD POWER LINES

When cranes, excavators, earthmoving machines or similar appliances are


operated near
overhead power lines the following provisions will be observed:
(a) A thorough examination of the approaches and surroundings of the site will
be carried out before taking an appliance to the site or setting it up.

4.13 MANUAL HANDLING

Manual Handling requires engineers and supervisors to design equipment,


tasks and work environments so that manual handling risks are eliminated or
reduced as far as reasonably practicable.

The contractor will assess and control the risks involved in carrying out manual
handling tasks. This will be done in consultation with employees who are
required to carry out the work.

The contractor will control risks by:


(a) designing or re-designing the manual handling task to eliminate or control
the risk factor. Where re-design is not practicable, the employer will:
• provide mechanical aids and/or personal protective equipment. Using
powered mechanical equipment to lift and move materials may control manual
handling risks. Lifting equipment will include cranes, forklifts.
(b) providing appropriate training to employees in safe handling techniques.
This training will also include the prevention of manual handling injuries by an
approach based on a hazard identification, risk assessment and control through
job and task design. Employees will receive appropriate training in methods of
manual handling involving team lifting procedures, correct use of the
mechanical aids and PPE.
(c) weights that are manually handled will be minimized. Furthermore persons
will not be required to lift, lower or carry loads above 25kg, unless mechanical
assistance and/or team lifting arrangements are provided to lower the risk of
injury.
(d) where manual handling involves repetitive bending, twisting, over-reaching,
work overhead or where persons have pre existing injuries, these loads will be
further decreased. Often used items such as tools, etc, will be stored at waist
level. Where possible, most commonly used items will be stored between thigh
and chest height.
(e) the rotation of work duties will be considered in consultation with
employees so that employees are not
subjected to the same task for the whole shift.
(g) ensuring that work areas and passageways are kept clean and clear of
debris. Slippery floors and surfaces and trip hazards will be controlled.

4.14 ACCESS
MS NO.
METHOD STATEMENT Revision No. A

EXCAVATION WORKS Page 15 of 25

An assessment of access requirements will take into account the number of


persons using them and any tools and equipment that they may be required to
carry to and from the work site.

Control measures may include:


(a) proper storage of materials and plant
(b) keeping work areas and passageways clear and free of obstructions
(c) removal of rubbish, including construction waste and excess excavated
material
(d) use of handrails
(e) traffic and plant controls
(f) safety fences and warning signs.

4.14.1 LIGHTING

Adequate lighting (natural or artificial) will be provided to ensure the work


areas and access ways are well lit. Adequate local lighting will be provided for
detailed work, for dangerous processes and where machinery is being
operated. When artificial lighting is used, including lighting for night work, the
contractor will ensure it does not create excessive glare or shadows.

4.14.2 RAMPS

When access ramps are provided they will not exceed 1:2.7 (20 degrees).
Ramps steeper than 1:8 (7 degrees) will be cleared, grated or have surfaces
which allow adequate foot grip. Where such ramps form part of an excavation,
a risk assessment will be conducted to determine the maximum safe soil height
above the ramp before some sort of soil support (eg trench shield) is provided.
Ramps will be designed and constructed to effectively withstand any
anticipated load that they may be required to support during use.

4.14.3 LADDERS

when ladders are used for access the contractor will provide the following:
(a) the ladder will be secured at both top and bottom against displacement.
Ladders will have non-slip feet and whenever practicable will be set up at an
angle of 1:4 (75degrees).
(b) a safe and adequately sized landing place when stepping off the ladder will
be provided.
(c) the stiles of the ladder will extend at least one meter above the landing
place.
(d) metal or wire reinforced ladders will not be used where there is a risk of
contact with electrical conductor wires(power lines) or of electric shock. Non-
conducting ladders will be used or a clearance of at least 4metres from
conductors will be maintained.
MS NO.
METHOD STATEMENT Revision No. A

EXCAVATION WORKS Page 16 of 25

4.14.4 SCAFFOLDING

Scaffolding will be used to provide workers with a safe temporary work


platform. It will be planned, erected, inspected and tagged by competent
persons and will be regularly inspected to ensure there are no risks to safety
and will comply with the requirements of RLC/HSE regulations.
.

4.14.5 FIXED PLATFORMS, WALKWAYS, STAIRWAYS AND LADDERS

Fixed platforms, walkways, stairways and ladders will comply with the
requirements of RLC/HSE regulations

4.15 WORKS NEAR TRAFFIC OR MOVING PLANT


.
Planning and preparation will also include the development of a vehicle
movement procedure for each worksite. Vehicle movement procedures will
identify the preferred travel paths for vehicles associated with a work site
entering, leaving or crossing the through traffic stream. A vehicle movement
procedure will include persons, moving equipment, plant and vehicle traffic in
the work area and also identify travel paths for trucks at key points on routes
remote from the work site, such as places to turn around, accesses, ramps and
side roads. A vehicle movement procedure will be a documented procedure, a
diagram, combined with or superimposed on a Traffic Control Plan, or may be
verbal information and instructions specific to the particular construction
workplace or site. The risk management process will be used to determine
which is the most appropriate.

A risk assessment will be conducted to determine what type of safeguards or


systems of work that be implemented on the site and will include eliminating
exposure of persons to moving plant. Vehicle movement procedures will be
developed based on the risk assessment and will be developed each time the
conditions on the site change in a way that may affect the health and safety of
persons. The risk assessment will consider at least the following:
(a) isolating vehicles and plant used in or around the site and work area from
persons on the site or work area, eg. vehicles or persons may be guided around
or past the work area.
(b) securing the area where moving plant is being used eg. fencing, barriers,
barricades, temporary warning or control signs or a combination.
(c) planning the direction that the plant moves so that the visibility of operators
is not restricted. This will also include an assessment of the visibility of plant
and traffic from all areas of the work site.
(d) the use of spotters/safety observers to control traffic movement
(e) implementing safe working distances
MS NO.
METHOD STATEMENT Revision No. A

EXCAVATION WORKS Page 17 of 25

(f) the use of audible reversing alarms and/or other technologies or other safe
work practices. Note: reversing
alarms may cause confusion where multiple plant is using the same area and
other systems of work may be required.
(g) minimizing the number of moving plant working at one time. Where
multiple plant is being operated around the work site a competent person will
be used to direct the plant:
• when operating in close proximity to each other;
• when reversing;
• where persons are on the ground; and
• in other situations as indicated by the risk assessment.
(i) where construction vehicles or plant enter or leave the work area by public
roads, systems of control and notices will be placed at all entrances and exits
to the work area to protect and warn all persons approaching or in the vicinity
(j) where plant is being operated near persons, near underground or above
ground services (any other workers, soils technicians, surveyors, visitors etc)
(k) designated delivery and turning areas. The movement of delivery vehicles
on construction sites frequently
presents a hazard particularly when reversing, loading and unloading.

Procedures will be implemented to warn all persons affected by the potential


hazard. These procedures will include:
• the requirement for truck drivers to report to a suitably signposted area on
the site;
• the requirement for a designated worker to act as an observer to ensure all
persons are clear of the reversing
vehicle; and
• a system of communication and warning to persons near delivery point.

All personnel on site will wear high visibility garments.

4.16 NOISE

Noise management provisions will be carried out by the contractor doing the
work and will ensure noise levels from machinery or equipment being used do
not become a risk to hearing or health.

An appropriately qualified person will conduct a noise assessment to determine


the level of noise that employees are exposed to. Where the noise is in excess
of the noise exposure limits, engineering controls will be implemented. Where
this cannot be achieved or work cannot be organized to minimize exposure,
appropriate hearing protection equipment, hearing protectors, will be provided
to all persons in the vicinity of the noise.

The contractor will also ensure compliance with RLC Environmental Protection
requirements in relation to noise.
MS NO.
METHOD STATEMENT Revision No. A

EXCAVATION WORKS Page 18 of 25

The contractors will ensure that all necessary prevention or protection


measures are taken to ensure the health and safety of persons who may be
exposed to excavated material.

Where there is a risk of inhalation of harmful airborne substances such as silica


dust or contact with harmful soil contaminants, the contractor will ensure a
safe system of work.

The risk assessment process will be used to determine the engineering


controls, work practices and site, atmospheric monitoring required.

Appropriate assessment of the exposure levels will be undertaken before


selecting the control measures.

The assessments will consider:


(a) any persons on site, including other contractors or persons working on the
site;
(b) persons conducting the assessment and site remediation, including
subcontract workers;
(c) visitors to the site (for example, couriers); and
(d) site neighbors (as appropriate).

The contractor will also ensure that exposure to nonhazardous substances such
as nuisance dust is at a level not greater than that established by safe
exposure standards. In dry conditions, frequent watering, where practicable, or
other similar methods will be used to reduce nuisance dust that will not exceed
20mg/m3.

TABLE 1: GASES COMMONLY FOUND IN EXCAVATIONS AND


TRENCHES

Gases or fumes found Type of


ground

Carbon dioxide, hydrogen sulfide Filled and made


ground

TABLE 2: TOXIC, FLAMMABLE AND ASPHYXIATE GASES


MS NO.
METHOD STATEMENT Revision No. A

EXCAVATION WORKS Page 19 of 25

Gas Toxic Flammable


Asphyxiate

Hydrogen Sulfide

Carbon dioxide

Employers will implement a suitable system of work so as to ensure a safe


repairable atmosphere and effective ventilation and will protect persons
against the effects of insufficient oxygen.

These may be encountered when carrying out work such as excavations for
foundations, in addition to trenches.

Where the risk assessment indicates the possibility of air contamination, the
work will be examined by competent persons using appropriate detecting
equipment and will include air testing for:
(a) oxygen deficiency
(b) airborne contaminants

5. INSPECTION AND MAINTENANCE OF PLANT AND EQUIPMENT

A risk assessment will be conducted before operating plant to identify any


hazards that may arise and the control measures to be implemented. The risk
assessment will consider at least the following:
(a) that appropriate guards, including roll-over protective devices (ROPS) are
fitted
(b) that the safe working load is displayed
(c) record of testing, maintenance, servicing and repair
(d) the general mechanical/electrical condition of plant, especially any wear or
damage that may affect safe operation
(e) specific controls to prevent entanglement or workers being trapped
between moving parts.

All plant such as excavators, tractors, etc used for lifting will have their safe
working loads displayed and maintained. If the function or condition of plant
represents an immediate risk to health and safety, operation will cease and the
plant will be withdrawn from use until a risk assessment and appropriate
control measures are implemented.
MS NO.
METHOD STATEMENT Revision No. A

EXCAVATION WORKS Page 20 of 25

5.1 ROUTINE INSPECTION

Regular planned inspection and adequate maintenance will be carried out to


ensure safe operation of all plant used on excavation work, whether leased,
hired or owned. Both mechanical and electrical testing will be done. The
following checks will also be carried out:
(a) Daily checks: general condition and maintenance of the plant will be
checked daily by the person doing the excavation work.
(b) Regular checks: the plant will be inspected by a competent person on a
regular basis, or at least every two weeks.

5.2 REPAIRS AND MAINTENANCE

The contractor will ensure the plant repairs will be carried out by a competent
person and in accordance with the designer’s or manufacturer’s requirements.

5.3 REPORTING DEFECTS

Any defects to equipment will be reported immediately to the person


responsible for maintaining such plant.
Where a defect is likely to pose an immediate risk to health and safety the
equipment or plant will not be used until the defect is rectified.

5.4 LOG BOOKS AND INSPECTION CHECK SHEETS

The contractor will keep logbooks and inspection check sheets containing a full
service and repairs history of the equipment.

6. TRAINING AND INSTRUCTION

Under RLC/HSE regulations employers will provide training, instruction,


information and supervision, as may be necessary, to ensure the health and
safety at work of their employees. This will be provided by a competent person.
All persons involved in any excavation or associated work will:
• be trained to follow systems of work and work practices that enable them to
perform their work in a manner that is safe and without risks to health, and;
• hold appropriate certificates of competencies where required, particularly in
the operation and use of load shifting equipment. Only persons who have
received training and instruction will carry out the work.

The training provided and the instruction given will at least include:
MS NO.
METHOD STATEMENT Revision No. A

EXCAVATION WORKS Page 21 of 25

(a) induction training which complies with Construction Safety & RLC/HSE
regulation
(b) the work method to be used for the excavation or
associated work and the manual handling procedures for the work to be carried
out, including control measures
based on the risk assessment to prevent injury.
(c) the correct use, care and storage in accordance with the manufacturer’s
recommendations where appropriate, of:
• personal protective equipment; and
• tools and equipment to be used.
(d) the use of plant and associated equipment, including electrical safety and
hazardous substances.
(e) procedures to be adopted in the event of accident, injury or other
emergency, including evacuation.

7. PERSONAL PROTECTIVE EQUIPMENT(PPE)

The use of PPE to control hazards and risks is the least effective measure and is
lowest on the hierarchy of control measures. Control measures will be selected
from the highest level possible and be adopted where practicable. The
measures at the lower levels are less effective and they require more frequent
reviews of the hazards and systems of work. They will only be used when other
control
measures are impracticable or when, after implementing other controls, a
residual risk remains.

7.1 PROVISION OF PPE

Before commencing any work, the principal contractor and or contractors will
identify any conditions likely to affect the health and safety of persons. If other
means of control are not practical, the provision and use of appropriate PPE
that complies with the relevant RLC/HSE regulations will be arranged.
Employees will be trained till they are competent in the proper selection, use
and maintenance of the PPE. There will be sufficient supervision and
monitoring conducted to ensure compliance.

7.1.1 SAFETY HELMETS

The use of safety helmets may prevent or lessen a head injury from falling
objects or a person hitting their head against something. Where there is a
likelihood of persons being injured by falling objects and overhead protection is
not provided, persons will be provided with and will use an appropriate safety
helmet. Appropriate safety helmets will also be provided and used where a
person may strike their hand against a fixed or protruding object or where
there is a risk of accidental head contact with electrical hazards.
MS NO.
METHOD STATEMENT Revision No. A

EXCAVATION WORKS Page 22 of 25

All persons on excavation sites will wear head protection that conforms to
Occupational protective helmets.

7.1.2 EYE PROTECTION

Eye protection complying with RLC/HSE regulations will also be provided, where
there is a risk of eye injury. Selection, use and management systems will
comply with RLC/HSE regulations

7.1.3 PERSONAL HEARING PROTECTION

A noise assessment will be conducted to determine the level of noise that


employees are exposed to. Where the noise is in excess of the noise exposure
limits, engineering controls will be implemented.

7.1.4 HIGH VISIBILITY GARMENTS/SAFETY REFLECTIVE VESTS

Persons working near traffic, mobile plant or equipment under operator control,
will be provided with and use high visibility garments. Other clothing not
covered by the high visibility garment will be light colored and all garments will
be selected for best contrast with the surrounding background.

7.1.5 SAFETY GLOVES

Where there is a risk of hand injury hand protection that complies with RLC/HSE
regulations will be provided and used.

7.2 MAINTENANCE AND USE OF PPE

The contractor will provide such information, instruction, training and


supervision as may be necessary to ensure that PPE are used and maintained
as intended. All PPE used by persons during excavation work will be regularly
inspected and replaced as necessary.

8. OCCUPATIONAL HEALTH AND SAFETY

While the obligation for each person is different, all persons will ensure that the
way they carry out their work will not interfere with the health and safety of the
other persons who are present at the workplace. All work practices must
comply with RLC/HSE regulations.

CONTRACTOR’S RESPONSIBILITIES

The contractor has an obligation to take reasonable care for the health and
safety of the other persons in the place of work and to cooperate with their
MS NO.
METHOD STATEMENT Revision No. A

EXCAVATION WORKS Page 23 of 25

employer in the interests of health, safety and welfare. Employees will use
appropriate protective equipment for the work being performed.

You might also like