Earned Value: Valerie Colber, MBA, PMP, SCPM
Earned Value: Valerie Colber, MBA, PMP, SCPM
Earned Value
Valerie Colber, MBA, PMP, SCPM
Not for duplication nor distribution 2
Where did Earned Value Management come from?
In 1967 the Department of Defense (DoD)
established the Cost/Schedule Control
Systems Criteria (C/SCSC) to standardize
contractor requirements for reporting cost
and schedule performance on major
contracts.
A basic tenet of C/SCSC is the concept of
Earned Value Management.
Not for duplication nor distribution 3
What is Earned Value Management (EVM)?
EVM is an incremental methodology for measuring project
performance by determining cost and schedule performance of a
project by comparing "planned" work with "accomplished" work in
terms of the dollar value assigned to the work, and determining the
need to recommend corrective actions.
EVM results from an earned value analysis to indicate potential
deviation of the project from cost and schedule baselines.
Earned value is a Management Tool
Provides a snapshot of project performance at a point in time.
Compares where the project is now with: (1) previous work
accomplished and (2) where the project was planned to be.
Serves as an early warning system to detect deficient or
endangered progress.
EVM is a significant tool in the Project Manager's "toolbox" for
gaining valuable insight into project performance and is the tool that
integrates technical, cost, schedule and risk management. In
addition, EVM provides valuable quantifiable performance metrics
for forecasting at-completion cost and schedule for their project.
Not for duplication nor distribution 4
Why use Earned Value Management (EVM)?
When you manage project performance by just comparing planned to actual
results, you could easily be on time but overspend according to your plan.
Using EVM is a better method because it integrates cost, time and the work
done (scope) and can be used to forecast future performance and project
completion dates and costs.
Earned value analysis results should be a major part of project reporting.
EVM is the basis for course correction and will lead to new forecasted
completion costs, change requests and other items that will need to be
communicated.
EVM provides an accurate picture of contract status and supports mutual
goals of contractor and customer.
The major objectives of applying earned value to a contract are to
encourage contractors to use effective internal technical, cost and schedule
management control systems, and to permit the customer to rely on timely
data produced by those systems, for better management insight to bring
project in on schedule and cost.
This data is in turn used for determining product-oriented contract status,
and projecting future performance based on trends to date.
Not for duplication nor distribution 5
Why use Earned Value Management?
EVM allows better and more effective management decision making to
minimize adverse impacts to the project.
Earned value provides an objective measurement of how much work has
been accomplished on a project.
EVM ensures a clear definition of work prior to beginning that work
EVM presents a logical plan for accomplishing the work
EVM provides early and accurate identification of trends and potential
problems, and serves as a key element of a project's risk management
process.
To measure progress, there must be a standard against which the
movement may be compared. EVM establishes that standard as the
Performance Measurement Baseline and measures progress against that
baseline.
Unless you are tracking earned value, you really have no idea what is going
on with your project!
Not for duplication nor distribution 6
Key questions that Earned Value Management answers
We analyze past performance
PAST PRESENT FUTURE
1. Did we get what we wanted for what we spent?
2. At the end of the project, is it likely that the cost will be less
than or equal to the original estimate?
The Two Key Questions
Not for duplication nor distribution 7
What do we measure progress against?
Performance measurement baseline
budget is spread over . . .
time, to accomplish the scope of
work against which progress can be
measured
Earned Value is a key concept
how much progress did I make against my
original plan?
expressed in dollars or hours
Not for duplication nor distribution 8
Ways of earning value
Should be a quantitative and discrete
whenever possible
Discrete = tangible end product
e.g. delivery of a specification, vendor parts
contract awarded, foundation completed
Should be integrated with success criteria
or technical measures
e.g., successful completion of clean-up, a specific
test, reliability growth curve
Not for duplication nor distribution 9
The Work Breakdown Structure (WBS) and Earned Value
The WBS has been an integral part of the earned value concept.
The WBS is a graphic portrayal of the project, exploding it in a level-by-level fashion,
down to the degree of detail needed for effective planning and control. It must
include all deliverable end items, and include the major functional activities that must
be performed.
A project consists of the sum total of all the elements of the WBS. Conversely, an
element that is not contained in the WBS is not a part of the project. Any work that
cannot be identified in the WBS requires authorization to proceed, either as a
recognized omission or as an approved change order.
The lowest levels of the WBS are significant because each defines a discrete element
of work or task to be performed against which resources can be assigned and cost
and schedule measured.
These lowest level activities or tasks in the WBS, when assigned a schedule and
cost, together with required resources (people and material) and the individual
responsible for its accomplishment, define a work package, which can be rolled up to
a control account via a process called cost aggregation.
The control account is a critical point for performance measurement to occur, for this
is where the integration of scope, schedule, and resources will take place and where
the project will measure its performance throughout the duration of the project.
Definition of the work package is critical to effective Earned Value Management and
the use of earned value in risk management.
Perhaps most critical to the use of earned value in risk management is the tenet that
work packages either be limited in size to be accomplishable in a relatively short
period of time, or that they include discrete milestones against which work
performance can be measured.
Not for duplication nor distribution 10
Cost Budgeting
A budget is merely a compilation of the individual costs estimates.
Activity costs are rolled up to work package costs.
Work package costs are rolled up to control account costs.
Control account costs are rolled up to project costs.
Contingency reserve is for the risks remaining after risk response
planning.
The cost baseline is made up of the contingency reserve plus
project costs.
Management reserve is any extra amount of funds to be set aside to
cover unforeseen risks or changes to the project.
The cost budget will include the management reserve and the cost
baseline.
Not for duplication nor distribution 11
How does Earned Value work?
Work is planned, budgeted and scheduled in time-phased increments
utilizing a Work Breakdown Structure (WBS) to define activities and to
assign costs to those activities.
As work is accomplished, value is "earned" on the same basis it was
planned.
Comparison of this earned value with the planned value for a specific time
period provides an indication of activity progress- if more value is planned
than is earned for a specified period, then the project is in danger of not
meeting its required schedule, unless action is taken to recapture the
unaccomplished work.
Similarly, comparison of the earned value for a task or group of tasks with
the "actual" costs required to accomplish the same activities provides an
indication of task cost performance- if actual costs are greater than planned
costs for the accomplished activities, then the project is experiencing a cost
overrun situation.
Therefore, EVM requires that the projects scope be fully defined, and then
a bottoms-up baseline plan be put in place that integrates the scope with
the authorized resources, all set within a specific time frame for
performance with detailed measurement taken against the project plan, and
a periodic forecast of the final expected results based on the actual
performance results.
Not for duplication nor distribution 12
Earned value and your project
Plan the Work
Work the Plan
External
Changes
Collect Results
Define the Work
Analyze
Deviations
Take
Corrective Action
Take
Corrective Action
Measure
Performance
Change Control
Not for duplication nor distribution 13
Earned Value Terminology
How much over or under budget
do we expect to be at the end of
the project?
Variance at
Completion
VAC
From this point on, how much
MORE do we expect it to cost to
finish the project?
Estimate to Complete ETC
What do we currently expect the
TOTAL project to cost?
Estimate at
Completion
EAC
How much did we BUDGET for
the TOTAL project effort?
Budget at completion BAC
What is the actual cost incurred
for the work accomplished?
Actual Cost AC
What is the estimated value of
the work actually accomplished?
Earned Value EV
What is the estimated value of
the work planned to be done?
Planned Value PV
Interpretation
(as of today)
Term Acronym
Not for duplication nor distribution 14
Earned Value formulas
How much over or under budget
will we be at the end of the
project?
BAC EAC Variance at Completion
(VAC)
How much more will the project
cost?
EAC AC Estimate to Complete (ETC)
We are (only) progressing at ___
percent of the rate originally
planned.
EV / PV Schedule Performance Index
(SPI)
We are getting $____ worth of
work out of every $1 spent.
Funds are or are not being used
efficiently.
EV / AC Cost Performance Index
(CPI)
NEGATIVE is behind schedule,
POSTIVE is ahead of schedule.
EV PV Schedule Variance (SV)
NEGATIVE is over budget,
POSITIVE is under budget.
EV - AC Cost Variance (CV)
Interpretation
(as of today)
Formula Name
Not for duplication nor distribution 15
Earned Value Formulas
As of now, how much do we
expect the total project to cost?
Used if no variances from the
BAC have occurred or you will
continue at the same rate of
spending.
Actual plus a new estimate for
remaining work. Used when
original estimate was
fundamentally flawed.
Actual to date plus remaining
budget. Used when current
variances are thought to be
atypical of the future. AC plus
the remaining value of work to
perform.
Actual to date plus remaining
budget modified by performance.
Used when current variances are
thought to be typical of the future.
BAC / CPI
AC + ETC
AC + (BAC - EV)
AC + (BAC - EV) / CPI
Estimate At Completion
(EAC)
Note: there are many ways
to calculate EAC, depending
on the assumptions made.
Not for duplication nor distribution 16
Earned Value in action
EAC
Today
PV
AC
BAC
ETC
Not for duplication nor distribution 17
Earned Value Analysis example
You have a project to build a new fence. The fence is four sided. Each side is
to take one day to build and is budgeted for $1,000 per side. The sides are
planned to be completed one after the other. Today is the end of day three.
Not yet
started
PS---------PF Side 4
50% done,
spent $600
PSS----PF Side 3
Complete,
spent $1,200
------F S-----------PF Side 2
Complete,
spent $1,000
S------------F Side 1
Status End
of Day 3
Day 4 Day 3 Day 2 Day 1 Activity
Key S = Actual Start, F = Actual Finish, PS = Planned Start, and PF = Planned Finish
Not for duplication nor distribution 18
Earned Value analysis example interpretation
We currently expect to be
$479 over budget when the
project is completed.
-479
4,000 4,479
VAC
We need to spend $1,679 to
finish the project.
1,679
4,479 2,800
ETC
We currently estimate that the
total project will cost $4,479.
4,479
4,000 / .893
EAC
We are only progressing at
83 percent of the rate
planned.
.833
2,500 / 3,000
SPI
We are behind schedule.
-500
2,500 3,000
SV
We are only getting 89 cents
out of every dollar we put into
the project.
.893
2,500 / 2,800
CPI
We are over budget by $300.
-300
2,500 2,800
CV
Our project budget is $4,000.
4,000
1,000 + 1,000 + 1,000 +
1,000
BAC
We have actually spent
$2,800.
2,800
1,000 + 1,200 + 600
AC
We have actually completed
$2,500 worth of work.
2,500
complete, complete, half
done or 1,000 + 1,000 + 500
EV
We should have done $3,000
worth of work.
3,000
1,000 + 1,000 +1,000
PV
Interpretation of
answer
Answer Calculation What is?
Not for duplication nor distribution 19
Using performance measurements for decision making
Behind Schedule
- How critical is schedule?
- Can I afford to work overtime to recover?
- Can I do tasks concurrently?
- Are there technical innovations which could speed up the
process?
- Am I gold plating instead of just meeting requirements?
- Should I do a schedule risk assessment to project impact to
program?
Over Cost
- Can I reschedule tasks? (Time phasing)
- Is there a less costly facility I can use?
- Are there tasks which can be deleted?
- Should the element be added to my risk management profile?
Not for duplication nor distribution 20
Earned Value Analysis techniques
Sort on significant variances
eliminate almost complete, just starting, etc.
Graph and analyze trends
Look at comparative data
e.g. cumulative performance vs. projected performance
Examine written analysis by contractor
does it answer why?
adequacy of corrective action plans
Analysis of schedule trends, critical path
Analysis of Estimate At Completion (EAC) realism
what are the drivers?
what can we do about them?
what are the drivers?
what can we do about them?
Not for duplication nor distribution 21
Cost variance chart
Not for duplication nor distribution 22
Schedule variance chart
Not for duplication nor distribution 23
What is a significant variance?
% variance (e.g., >10%)
$ variance (e.g., >$50,000 at the control
account level)
critical path element
risk/complexity
impact to other elements
Top 10, Top 20, etc.
contractor defined
Not for duplication nor distribution 24
EVM Performance Reporting
Not for duplication nor distribution 25
Earned value analysis reporting
X-Axis
Y
-
A
x
i
s
Under
Budget
Ahead of
schedule
Behind
schedule
Over
budget
-5 -10 (-)
Variance %
5 10 (+)
(-)
Variance %
-5
-10
5
10
(+)
A
B
D
C
Cost and schedule performance chart.
Graphing the cost and schedule variance of Projects A, B, C, and D quickly identifies which needs
the most immediate attention. Earned value reporting uses cost data to give more accurate cost and
schedule reports. It does this by combining cost and schedule status to provide a complete picutre
of the project. Project cost can also be graphed versus time.
0% Cost or
schedule
variance =
On Schedule
On Budget
Not for duplication nor distribution 26
References
A Guide to the Project Management Body of Knowledge, 3
rd
Edition, by PMI
PMP Exam Prep, 5
th
Edition, by Rita Mulcahy.
Use of Earned Value Management to Mitigate Software Development Risk, by Paul
E. Young.
Using Earned Value Management For Better Contract Administration, by U.S.A
Government Department of Energy.
Earned Value Management, by James R. Chapman.
Earned Value Management, by U.S.A. Government NASA
Earned Value Project Management, 2
nd
Edition, by Quentin W. Fleming and Joel M.
Koppelman