Construction Planning and Management Multiple Choice Questions
This document contains a list of 4 multiple choice questions and their answers related to construction planning and management. The questions cover topics like which project types PERT is useful for, characteristics of CPM networks, weaknesses of bar charts, and dependencies between activities in a network diagram. A link is provided at the end to access additional construction planning and management practice questions.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
75%(12)75% found this document useful (12 votes)
12K views2 pages
Construction Planning and Management Multiple Choice Questions
This document contains a list of 4 multiple choice questions and their answers related to construction planning and management. The questions cover topics like which project types PERT is useful for, characteristics of CPM networks, weaknesses of bar charts, and dependencies between activities in a network diagram. A link is provided at the end to access additional construction planning and management practice questions.
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 2
99 TOP Construction Planning and Management - Civil
Engineering Multiple choice Questions and Answers
pdf Latest Construction Planning and Management Questions and Answers 1. PERT technique of network analysis is mainly useful for a) small projects b) large and complex projects c) research and development projects d) deterministic activities Ans: c
2. Select the correct statement. a) Activity arrows in a CPM network are drawn to scale b) The tail of an arrow represents the finish of an activity c) Arrow bead represents the start of an activity d) none of the above Ans: d
3. Which of the following is a weakness of bar chart ? a) interdependencies of activities b) project progress c) uncertainties d) all of the above Ans: d
4. In the network shown in Fig. 7.1, activity 4-5 can be started only when
a) activity 3-4 is completed b) activity 2-4 is completed c) activity 2-3 is completed d) activity 2-4 and 2>-A both are com-pleted Ans: d More Construction Planning and Management Multiple choice Questions: Click Below Link http://engineeringmcqs.blogspot.in/2014/08/99-top-construction- planning-and.html
Construction Planning and Management Multiple Choice Questions and Answers For Freshers and Experienced PDF Download Free - Preparation For Engineering