Compaction Test by Core Cutter (Is: 2720, Part 29)

This document summarizes a compaction test by core cutter conducted on a highway rehabilitation project in Andhra Pradesh, India. The test was performed on a core sample taken from the road section between km 221.340 to 270.340 on NH-9. Bulk density and compaction percentage were calculated for the core sample based on its weight in air and water. The compaction achieved was compared to the minimum required compaction of 98% specified by MORTH for such projects.
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
271 views

Compaction Test by Core Cutter (Is: 2720, Part 29)

This document summarizes a compaction test by core cutter conducted on a highway rehabilitation project in Andhra Pradesh, India. The test was performed on a core sample taken from the road section between km 221.340 to 270.340 on NH-9. Bulk density and compaction percentage were calculated for the core sample based on its weight in air and water. The compaction achieved was compared to the minimum required compaction of 98% specified by MORTH for such projects.
Copyright
© © All Rights Reserved
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 2

Client: National Highways Authority of India.

Consultant:Feedback Infra Pvt Ltd


Concessionaire: Swarna Tollway Pvt.Ltd. Contractor : IJM(INDIA)Infrastructure Ltd.
Location :- Date of Sampled:-
Description :- Date of tested:-
Layer no.
Marshall Density : g/cc
S.No
1 2 3 4 5 6 7 8 9
1
2 Offset From Center ( mts)
3
Thicness In ( mm )
3
Wt. Of Sample in air (gms)
4
Wt. Of Sample in Water (gms)
5
Wt. Of SSD Sample in air (gms)
6
Volume Of Sample (cc)
7
Bulk Density (g/cc)
8
Compaction (%)
Remarks : As per MORTH, specified required compaction > 98 %
Checked By:
Contractor's Representative Concessionaire's Representative
Name : Name : Name :
Date: Date: Date:
I/C's Representative
Project : Localized Rehabilitation,Overlay and Associated works in portion between km.221.340 to 270.340 Vijayawada-Ibrahimpatnam-Nandigama
NH-9 Section in the state of Andhra Pradesh
COMPACTION TEST BY CORE CUTTER (IS : 2720 , PART 29)
Chainage
Submitted By: Witnessed By :
Contractor : IJM(INDIA)Infrastructure Ltd.
Marshall Density : g/cc
10
Project : Localized Rehabilitation,Overlay and Associated works in portion between km.221.340 to 270.340 Vijayawada-Ibrahimpatnam-Nandigama
NH-9 Section in the state of Andhra Pradesh
COMPACTION TEST BY CORE CUTTER (IS : 2720 , PART 29)