GRE Lined Carbon Steel

Download as pdf or txt
Download as pdf or txt
You are on page 1of 11

SAUDI ARAMCO JOURNAL OF TECHNOLOGY FALL 2013

Experience with Fiberglass (GRE) Lined Carbon


Steel Tubulars for Corrosion Protection for Oil
Production Applications


Authors: Dr. Qamar J. Sharif, Dr. Omar J. Esmail, Gokulnath Radhakrishnan, John A. Simpson and Martin R. Bremner

ABSTRACT

Saudi Aramco experienced serious corrosion problems
in an oil production tubing in one offshore field
attributed to the presence of carbon dioxide (CO
2
),
hydrogen sulfide (H
2
S) and varying levels of water cut.
In early 2002, the company installed, on a trial test
basis, glass reinforced epoxy (GRE), commonly known
as fiberglass, lined carbon steel tubing in three wells.
The fiberglass lining was installed to provide a corrosion
barrier to protect the steel tubing from internal corrosion.
As for the technology, the fiberglass lining or sleeve is
carried out joint by joint by inserting a solid fiberglass
tube into the low cost carbon steel tubing and cement is
pumped into the narrow annulus between the fiberglass
liner and the carbon steel tubing. The connection area is
protected by the combination of end flares and a
corrosion barrier ring.
The company examined various methods to evalu-
ate the performance of the fiberglass lined tubing, with-
out having to pull out the tubing from the well as these
wells are oil producers. After review of the evaluation
options, it was decided to run a multifinger caliper to
evaluate the condition of the fiberglass lining and check
for any internal corrosion in the steel tubing. The log
showed the fiberglass lining to be in good condition with
no damage, indicating that the steel tubing was
protected from corrosion. The other two wells had no
tubing leaks, indicating the GRE lining is providing
corrosion protection.
Based on successful trial test results, the company
adopted the technology to protect tubing strings
deployed in corrosive environments in oil producers,
water injectors and water supply wells.
Field experience has shown that the use of fiber-
glass lined tubing is a low life cycle cost solution
compared to other options. There has been no workover
in these wells since installation. Today, fiberglass lined
tubing is applied in Saudi Aramco in high water cut oil
producers, water injectors and combined water source
and injection wells.
This article shares the history of corrosion,
challenges and lessons learned during the imple-
mentation of the solution, various performance assess-
ment methods evaluated and the results and inter-
pretation of the caliper log.


INTRODUCTION

Five oil producers were worked over during 2001-2002.
These offshore wells had been completed with carbon
steel J55 tubing with API connections. The failures of
tubing were attributed to corrosion related problems.
These wells were based offshore and the wellbore fluids
had combinations of various levels of carbon dioxide
(CO
2
), hydrogen sulfide (H
2
S) and with water cuts
ranging from zero to a maximum of 10%. The corrosion
was so severe that four out of the five oil wells required
multiple milling/fishing runs to retrieve the tubing string,
resulting in high workover costs. Figure 1 shows the
condition of the tubing pulled out from one of the wells in
the subject field.
Three wells were selected for the trial test of glass
reinforced epoxy (GRE) lined tubing to evaluate the
effectiveness of the fiberglass lining in protecting the
steel tubing from corrosion. The flow rates of the wells
ranged from 2,000 to 6,000 barrels of oil per day (bopd).
The CO
2
and H
2
S levels were about 1% and 2%, re-
spectively. The static bottom-hole temperature (SBHT)
was 220 F. With water-wet conditions in the presence of
CO
2
, the corrosion potential of the wells was high for low
alloy carbon steel exposed to the low pH well fluids. But
the co-existence of CO
2
and H
2
S brings in a certain level
of unpredictability to the expected corrosion rates and
the corrosion mechanisms.
Bijan et al.
1
, presents an extensive discourse on the
effects of CO
2
and H
2
S coexisting in the production
stream with water. The prevalence of H
2
S can either


Fig. 1. Corroded tubing pulled out from one of the wells in the
subject field.

SAUDI ARAMCO JOURNAL OF TECHNOLOGY FALL 2013

increase CO
2
corrosion by acting as a promoter of
anodic dissolution through sulfide adsorption and
affecting the pH or decrease sweet corrosion through the
formation of a protective sulfide scale. The exact inter-
action of H
2
S on the anodic dissolution reactions in the
presence of CO
2
is not fully understood. Both CO
2
and
H
2
S gases lower the solution pH and potentially increase
the corrosion rate. With a CO
2
and H
2
S ratio of less than
1:5 (1% and 2%, respectively), the corrosion is domi-
nated by H
2
S with FeS as the main corrosion product
2
.
The in-situ pH is also a key parameter governing
corrosion in wet hydrocarbon production conditions
affecting the formation and retaining a protective layer.
Apart from the CO
2
and H
2
S ratio, corrosion is depend-
ent on multiple yet interacting factors such as tem-
perature, fluid chemistry (water chemistry, pH, organic
acids, water cut, oil wetability, phase ratios, etc.), the
hydrocarbon phase, flow characteristics and fluid
velocity, including corrosion products, scales, wax and
asphaltene and steel chemistry
1
.
While the investigations were in process to identify
the causes of the corrosion in the tubing, the company
decided to trial test the GRE lined tubing. A total of
17,873 ft of 3, J55, 9.3 ppf, external upset end (EUE)
tubing was lined with a GRE lining at Saudi Aramcos
pipe yard. Well-2, (callipered in 2008) was completed
with 237 joints of GRE lined tubing and 288 ft of 4
J55, 11.6 ppf, new Vallourec and Mannesmann (VAM),
internally plastic coated (IPC) tubing at the top of the
completion string.

GRE LINED TUBING

The technology of lining the tubing with GRE has been
used by the industry as a method for corrosion pro-
tection of downhole tubing. Over 30,000 wells have been
installed in water handling, oil and gas producing and
gas injection and disposal wells. GRE lining acts as a
barrier between the corrosive fluids and the base metal.
Fiberglass reinforced plastic (FRP) or GRE pipe is a
composite material formed from thermosetting epoxy
resins with continuous fiberglass filament reinforce-
ments. The GRE liner tube is manufactured in a filament
winding process, which applies continuous lengths of
fiberglass filaments that are wetted with epoxy to a steel
mandrel in helical angles. The epoxy resin is heat cured
at temperatures above the recommended operating
ranges for the product. The resulting GRE pipe exhibits
high strength combined with excellent chemical
resistance. GRE or fiberglass pipe is used extensively
in the oil, gas and chemical industry for low-pressure oil
and gas transmission, salt water disposal, chemical
piping system, etc. It is resistant to corrosion and prone
to other deterioration generally caused by crude oil and
other common oil field chemicals.
The GRE lining is a joint-by-joint process carried out
on a pumping rack with specialized pumping equipment
and qualified personnel. The corrosion protection barrier
is achieved by inserting a rigid GRE lined tube into the
steel pipe and filling the annular space with a special

mortar/cement. The cement is a closely regulated
mixture of oil well cement and oil well cement additives
mixed with water to a controlled slurry viscosity. The
purpose of the cement is to support the GRE lined tube
in the steel tubing and not to provide a pressure seal
between the two tubes. After the GRE liner is placed
inside the pipe, mortar is pumped through special end
fittings into the annulus. The mortar slurry is pumped
under pressure from the lower end of the tubing. The
other end of the tubing is raised to ensure a complete
filling of the annulus with no possible air bubbles. The
pressure is raised to affect a squeeze and cause partial
dehydration of the mortar.
The liner is centralized at each end by the threaded
fixtures used for injection of the mortar. More impor-
tantly, the end fixtures centralize the liner to the thread
profile, providing for improved joint to joint centerline
alignment within the couplings, an important consid-
eration in wireline or other through tubing interventions.
There are no centralizers along the length of the joint,
but this is not important since the outside diameter of the
GRE liner is slightly larger than the drift diameter of the
pipe, providing little room for deviation. Any deviation
from concentricity in the body area of the pipe is minimal
and unimportant.
On both ends of the tubing, the GRE liner is
protected by a precisely molded fiberglass flange,
commonly as the flare. A specially designed reinforced
elastomeric corrosion barrier ring (CBR) is compressed
in the coupling by the opposing flares. For API con-
nections, the CBR is an oil resistant nitrile rubber ring
with spring steel wire reinforcements, which hold the ring
in place during pressure cycles. For premium or
proprietary threaded connections, a glass reinforced
PTFE CBR is installed, which is designed exclusively for
the system with specifications from the premium thread
manufacturing companies. Figure 2 presents details of
the API lining system.


Fig. 2. GRE lining inside API connection.

COMPLETION CONSIDERATIONS

Tubing details from top to bottom after the workover are:

4 J55, 11.6 ppf, new VAM, IPC tubing to 288
ft.
Subsurface safety valve.

Reference band
Corrosion Barrier Ring
Flare
Liner
Grout
SAUDI ARAMCO JOURNAL OF TECHNOLOGY FALL 2013



API Connections Standard Unlined Completion Lined Tubing
Size, inch Tubing
ID
Drift X Nipple
Profile
XN Nipple
No-Go ID
Tubing
ID
Flare ID
(Lowest)
Drift X Nipple
Profile
XN Nipple
No-Go ID
2 6.5 ppf 2.441 2.347 2.313 2.205 2.251 2.195 1.945 1.875 1.791
3 9.3 ppf 2.992 2.867 2.813 2.666 2.750 2.670 2.420 2.313 2.250
4 11.6 ppf 4.000 3.875 3.813 3.725 3.691 3.600 3.350 2.813 2.666
4 11.6 ppf 4.000 3.875 3.813 3.725 3.691 3.600 3.350 3.313 3.135
4 12.6 ppf (Opt) 3.958 3.833 3.813 3.725 3.691 3.600 3.350
2.813
3.313
2.666
3.135
5 17 and 20 ppf
(R Nipple Opt)
4.892 4.767 4.562 4.455 4.520 4.400 4.150 4.125 3.912
5 17 and 20 ppf
(X Nipple Opt)
4.892 4.767 4.562 4.455 4.520 4.400 4.150 3.813 3.725
7 23 ppf
(R Nipple)
6.366 6.241 5.963 5.770 6.091 5.976 5.726 5.625 5.500
7 26 ppf
(R Nipple)
6.276 6.151 5.963 5.770 5.900 5.785 5.535 5.250 5.018
7 29 ppf
(R Nipple)
6.184 6.059 5.963 5.770 5.800 5.685 5.435 5.250 5.018
7 32 ppf
(R Nipple)
6.094 5.969 5.963 5.770 5.800 5.685 5.435 5.250 5.018

Table 1. API completions: Reference table for dimensional changes while applying GRE lining

Depth, Pressure
Corrosive
Fluids H
2
S/CO
2

Low High

Low

Quadrant 1:
Low alloy carbon steel
API connections
Quadrant 2:
Low alloy carbon steel
Premium connections

High

Quadrant 3:
Corrosion resistant alloy
Premium connections
Quadrant 4:
Corrosion resistant alloy
Premium connections

Table 2. Basic connection and material selection matrix

Depth, Pressure
Corrosive
Fluids H
2
S/CO
2

Low High

Low

Quadrant 1:
Low alloy carbon steel
API connections
Quadrant 2:
Low alloy carbon steel
Premium connections

High

Quadrant 3:
GRE lined tubing
API connections
Quadrant 4:
GRE lined tubing options
Premium connections

Table 3. Reflecting the option GRE lined tubing brings in (Quadrant 3)

Crossover 4 new VAM x 3 9.3 ppf EUE at
around 310 ft.
3 9.3 ppf J 55 GRE lined tubing (2 internal
diameter (ID)) to 7,835 ft.
9 packer.
Crossover 3 J55, 9.3 ppf EUE x 2 J55, 6.5
ppf EUE.
2 nipple (2.313 ID) at 7,888 ft.


For a standard 3 API unlined completion, the
nipple profile sizes would be 2.813, whereas with a
GRE lining, the ID of 3 tubing is reduced to 2. This
requires the nipple profiles to be re-sized to 2.313.
Table 1 provides the dimensional changes and re-
profiling requirements for the commonly applied tubing
sizes for reference purposes.



SAUDI ARAMCO JOURNAL OF TECHNOLOGY FALL 2013

MATERIAL AND CONNECTION
CONSIDERATIONS

Completion accessories in a GRE lined completion
should follow the same metallurgy as the GRE lined
carbon steel tubing. The GRE lined completion provides
the cost savings, while the accessories that cannot be
lined are installed in the CRA suitable for the process
conditions
3
.
Generally, the material and connection selection
for production wells can be compartmentalized based on
the mechanical demands (pressure, depth, onshore vs.
offshore) and the corrosive nature of the well fluids, as
presented in Table 2. Quadrants 1 and 2, with little or no
corrosion impact would rightfully adopt low alloy carbon
steel solutions with a corrosion management program.
Quadrants 3 and 4 are worthwhile applications for GRE
lined tubing.
Specific attention is required to Quadrant 3 one
would notice that to address the corrosion issue by going
for CRA material for the tubing in a mechanically not so
demanding condition, the connections need to be in
premium as CRA tubing is rarely delivered in API
connections. The same application can be served by a
GRE lined API completion resulting in more than 50%
cost savings on the completion. The GRE lining takes
care of the corrosion issues and the API connections
serve the mechanical need of these wells. For Quadrant
3, Table 2 can be revised to reflect the above concept as
shown in Table 3.

TRANSITION BETWEEN LINED TUBING
AND UNLINED ACCESSORIES

The transition between the GRE lined tubing and unlined
accessories is achieved by the combination of an
adapter ring (AR) and CBR. The AR is used to crossover
from unlined accessories to lined tubing with an API
EUE 8 round/long thread and coupling (LTC)/short
thread and coupling (STC) or buttress thread and
coupling (BTC) threads.
When making up a joint of GRE lined EUE tubing to
an unlined accessory, such as a packer, on/off tool, gas
lift mandrel, hanger, etc., the most important consid-
eration is that a CBR must be compressed against the
GRE lined tubing joint to protect the lined joint and the
connection area from corrosion
4
.
There are two possible combinations to connect the
GRE lined tubing connection with the unlined tubing or
completion components. Option 1, to make up a GRE
lined tubing pin, mating into an unlined accessory
coupling or box, or option 2, to make up an unlined pin
mating into a GRE lined tubing box or coupling. When a
GRE lined tubing pin mates into an unlined accessory
box/coupling, a CBR and possibly an AR must be placed
into the unlined accessory box.
Figure 3 presents the illustration of the step change
in the ID when GRE lined tubing is made up to an
unlined box of an accessory. Figure 4 is the schematic

and the actual photo of the AR. The AR is a nitrile
butadiene rubber beveled ring designed to help provide
a shoulder with an ID consistent with the CBR ID. This
provides full support for the compressed CBR. The AR
should be used with a CBR in the case where the
shoulder in the unlined box may not provide a full mating
surface for the CBR. The AR design may vary de-
pending on the configuration inside the box. The smaller
beveled end of the AR should be placed into the box
first, the thicker end of the AR supports the CBR. The
CBR is always compressed against the mating GRE
lined tubing pin end flare.


Fig. 3. Illustration of step change in ID when making up a lined
pin to an unlined box of an accessory.


Fig. 4. AR for API completions (also referred as a packer AR).

For an unlined pin end to be made into a GRE lined
tubing box, a CBR will be installed in the GRE lined
tubing box as usual. Because the unlined pin ID is not
consistent with the CBR ID, a half or sh CBR
(different heights of the ring) needs to be installed in the
box with an AR on top of the CBR to mate against the
unlined pin. The unlined pin end must contact against
the AR and CBR to protect the GRE lined tubing
connection. It is recommended that the manufacturer
authorized service technician is on location when GRE
lined tubing is run in a well. Figure 5 shows the cross-
over configuration from GRE lined tubing to unlined
completion accessories for a new VAM connection. A
profile is cut in the base of the box connection to seat
the CBR, referred to as the Duoline accessory box
profile.



SAUDI ARAMCO JOURNAL OF TECHNOLOGY FALL 2013




Fig. 5. Crossovers configuration to connect GRE lined tubing to unlined accessories in API and premium connection (ABC is a generic
name given to represent a premium connection) completed wells.

INTERVENTION HISTORY

During the evaluation period of the GRE lined tubing
performance, from June 2002 to December 2008, the three
wells were subjected to various types of well interventions
such as wireline SBHP/T surveys and cased hole logs
without any incidents. The intervention history of Well-2 is
summarized in Table 4. No material interference has been
encountered and there were no issues with the driftability.

DISCUSSIONS ON THE PERFORMANCE OF
GRE LINED TUBING

Industry evaluation criteria for plastic reinforced steel are to
look for failures within the first 6 to 12 months. If the plastic
had to fail because of any incompatibility issues from
chemicals and water, it shall fail within the first year. The
three wells installed with the GRE lining had passed about 7
years of service with no evidences of corrosion or annulus


pressure buildup and no driftability issues. The failure mode
for GRE lined tubing is breakage of the fiberglass liner into
pieces rather than wall thickness losses and if any failures
had to occur, pieces of the GRE liner would have shown up
in the choke. No such events were recorded in any of the
three trial wells. The wells were acidized after completion in
2002 followed by multiple wireline runs and drifting to
ensure that the well is free of any obstructions. The
production rates were consistent with the expectations of
the Operations teams.
The company had plans to run the trial test for more
than 5 years to qualify the technology. The goal was to have
a long-term evaluation to arrive at a more realistic life cycle
cost estimate and compare it with alternate solutions. After
successful qualification of the product for an extended
period of time, it is relatively easy to prove and make a
business case for the implementation of the GRE lined
tubing as an alternative to other corrosion barrier solutions.
The company plans to go for a large scale implementation,
therefore a longer and more definitive evaluation was

DESCRIPTION ID MATERIAL
Tubing hanger 3 1/2" x 11" Box down - NU/EUE 2.992" CRA
Adapter ring 2.992"x 2.750" GRE
3-1/2" 9.3# EUE Pup - Pin Up x Pin Down. 2.750" L 80 + GRE
Duoline 20 lined 3-1/2" 9.3# joints 2.750" L 80 + GRE
Adapter ring 2.750" x 2.992" GRE
Expansion joint EUE Box x Pin 2.992" CRA
DESCRIPTION ID MATERIAL
Tubing hanger 3 1/2" x 11"; ABC Box down 2.990" CRA
ABC Pin x Crossover accessory Box for ABC down 2.990"x 2.75" CRA
Duoline 20 lined ABC Pup joint 3 1/2 9.2 ppf Pin x Pin 2.750" L80 + GRE
Duoline 20 lined Tubing joints 3 1/2 9.2 ppf ABC Box xPin 2.750" L 80 + GRE
Crossover accessory Box for ABC x ABC Pin 2.750" CRA
Expansion joint ABC Box x Pin 2.750" CRA
PREMIUM GRE LINED
COMPLETION
API GRE LINED
COMPLETION
SAUDI ARAMCO JOURNAL OF TECHNOLOGY FALL 2013

Date Remarks
May 2002 Workover: Recompleted the well with permanent downhole monitoring system (PDHMS) and
GRE lined 3.5 EUE tubing. Acidized the well with 8,500 gallons of 20% HCl acid. The PDHMS
was tested with surface readout successfully.
June 2002 Placed the well on production after workover.
Sep 2002 Trap test, water cut: 0%.
Nov 2004 Annuli survey was conducted and showed zero psig.
Feb 2005 Trap test, water cut: 0%.
Apr 2005 Flow meter survey. Drifted the tubing to TD.
Aug 2006 Well went wet. Wireline work.
Oct 2006 Jack up separator tests.
Mar 2007 Trap test.
April 2007 Wireline work. Drift the well to TD. Increased water cut.
July 2007 Trap test.
Dec 2008 Drifted the well. Shut in the well and run log: MIT/PMIT logs for corrosion evaluation of the tubing.

Table 4. Summary of intervention history for Well #2

necessary. The company also saw the opportunity for the
potential application of the product as a cost-effective
alternative to chrome tubing. Notwithstanding the above
observations, which were interpreted as inferences, the
company decided to go further to do a detailed intrusive
investigation on the GRE liner integrity inside the tubing.

EVALUATION OF THE GRE LINER
INTEGRITY

The company considered three options to assess the
condition of the GRE lining inside the tubing.

1. Run a downhole video camera.
2. Run a caliper log.
3. Pull out and inspect the tubing.

The downhole camera requires the presence of a clear fluid
in the tubing string to provide pictures. It was consid-ered to
displace the tubing with clear water/brine, but it was ruled
out because of multiple reasons, such as the need for
unnecessarily killing the producing well and loss of
production. The possibility of pulling out the tubing for
investigation was also ruled out because of costly workover
and loss of production. It was against common sense to
lose revenue from a producing well just for tubing
evaluation.
The company decided to log the well using a caliper
Multifinger Imaging Tool (MIT), but getting the 1
11
/
16
outer
diameter (OD) 24 finger MIT tool was a challenge in itself.
There are not very many small tools available and there
needs to be enough business volume for the logging
companies to bring the tool in Saudi Arabia. The company
tried to line up a few more jobs to justify the import of the
tool in the country and the reason for delays in evaluation.
About 2 years were lost because of delays in the
commissioning of the caliper log into the well. Multiple
attempts were made from 2007 until the end of 2008 to
carry out the caliper log in Well-2, and finally it was run in
December 2008.
In the meantime, the service provider of the GRE lining





services continue to make the case with Saudi Aramco by
presenting GRE lined tubing evaluation data from another
regional oil company. Trials were carried out on the surface
with tools from two service companies. Service Company 1
applied a 2 40 finger Sondex tool with a production roller
centralizer. The oil company machine shop cut longitudinal
sections of the tubing to allow close examination of the GRE
lining, which showed no adverse effect on the lining
material; in fact there were no evident marks on the ID of
the GRE liner at all.
Service Company 2 applied a similar 2 40 finger
Sondex caliper tool with a motorized centralizer. Marks and
scratches were observed on the surface of the GRE liner;
however, they were not significant enough to affect the
performance of the liner. The marks were not caused by the
caliper finger itself but by the motorized centralizing system
deployed with the caliper tool.
Based on the data from the above two trials, the
recommendation was made to use non-motorized pro-
duction roller centralizers whenever caliper runs are
conducted on the GRE lining system. Pictures of lined
tubing and corrosion barrier rings taken after the caliper
runs are presented in Fig. 6.
The caliper log gives more meaningful results if the well
has a base log. The well under consideration did not have a
caliper log run at the time of installation but given that the
well had been in service for about 7 years and the GRE
lined tubing had a fixed ID of 2 with a maximum ovality of
0.01, the caliper log was expected to highlight it in any
case, all changes in the ID of the GRE liner. It was also
taken into consideration that after about 7 years, if the GRE
lined tubing had maintained its wall thickness and smooth-
ness the results could be compared with IPC tubing
installed in the same well.

EXPERIENCE WITH MIT CALIPER LOG

In December 2008, a 24 finger caliper log was run in Well-2
to check the condition of the tubing after about 7 years of
service. The caliper tool allows three dimensional imaging
and the calculation of rates of corrosion or scale deposition


SAUDI ARAMCO JOURNAL OF TECHNOLOGY FALL 2013



Box end after trial 4 Box end after trial 5

CB ring after trial 7 CB ring after trial 8

Pin after trial 6 Cleaned pin after trial 9

Fig. 6. Pictures showing condition of GRE lined tubing and
CBR after multiple caliper runs.

by collecting continuous signals from 24 spring loaded,
hardened tip fingers, which push against the ID of the tubing
with low force and provide an independent reading on the
movement of each finger corresponding to the irregularities
in the ID or the wall thickness. Data from each finger is
recorded and plotted independently.
The log recorded the interval from surface to tailpipe. At
the time of the log, the wellhead temperature was 89 F, log
speed was up to 1,000 ft/hr; the logging cable tension was
recorded up to 5,000 lbf through the system, which is again
a test of the endurance of the GRE lined tubing to typical
loads encountered during slick line runs. A detailed analysis
of the MIT caliper log indicated that the fiberglass was in
good condition with no internal pitting.

CALIPER LOG INTERPRETATION

The liner is not guaranteed to be a perfect circle. During the
cement pumping process in the narrow annulus between
carbon steel tubing and the GRE liner, there is a possibility
of ovality of up to 0.01 in the ID of the GRE lined tubing.
The caliper readings across the lined tubing do not
exhibit any abrupt changes but exhibit wavy patterns, which
represent the flowing diameter change and not missing or
broken parts of the liner. The increase in the ID is an
indication of the eroded or missing liner while the decrease
in the ID is an indication of a scale or corrosion by product

buildup. The caliper readings showed that there was neither
wall loss nor scale/deposits buildup. The spikes in the
caliper readings at about every 31 ft are the reading from
the caliper fingers passing over the CBR and the flares
installed at each connection. The consistent shape of the
spikes shows that all CBRs and flares are intact after about
7 years of service with frequent interventions carried out in
the well.
The caliper readings from the 4 IPC tubing in the
upper section of the well can be compared with the readings
from the 3 GRE lined tubing in Fig. 7. The caliper
readings smoothened immediately after passing from the
4 IPC tubing to the 3 GRE lined tubing. There was a
reduced disturbance on the caliper fingers providing clear
evidence that the smooth surface of the GRE liner still
remained intact. It is worth noting that the variation in the
average, minimum and maximum radii readings is a lot less
in the GRE liner compared to the IPC tubing.


Fig. 7. Caliper readings across the crossover between 4 IPC
and 3 GRE lined tubing.

Figure 8 is a snapshot of the interpreted caliper/
corrosion monitoring log. The metal loss graph shows that
the first 288 ft of the 4 IPC tubing is in the red zone.
Figure 9 is a zoomed out image of the same caliper log to
present the comparison between the 3 GRE lined tubing
section, green color, (lowest or no wall loss) and the 4
IPC tubing. The data between 550 ft and 650 ft is not
available as the tool was reported to have a failure. The
GRE lined 3 tubing below the crossover shows no
evidence of wall corrosion or erosion loss. Figure 10 shows
the 24 finger MIT Sondex tool that was run for the
evaluation.

LESSONS LEARNED

1. The GRE lined API 8 round EUE tubing exhibited a
greater resistance to corrosion than the premium IPC
tubing over the 7 years of continuous service in
production.

SAUDI ARAMCO JOURNAL OF TECHNOLOGY FALL 2013


Fig. 8. 24 finger caliper, corrosion monitoring log across 4 IPC
tubing and GRE lined 3 tubing.

2. Caliper results showed that majority of the tubing
remained intact with no wall losses and scale buildup as
direct benefits of being inert to corrosive fluids and
being smoother compared to carbon steel.
3. Repetitive interventions over the 7 year period and the
satisfactory status of the tubing showed that the GRE
lined tubing is tolerant to wireline intervention without
compromising its integrity.
4. We could establish that 20% hydrochloric (HCl) acid
pumped through the GRE tubing did not cause any
appreciable damage to the ID and it is acceptable to
bullhead 20% HCl acid through the GRE lined tubing.
5. It is advisable to run non-motorized production roller
centralizers whenever caliper runs are conducted on
the GRE lining system.
6. GRE lined API connection tubing can be a cost-
effective alternative to CRA tubing with premium
connections in low mechanical demand (lower depth
and pressures, but with high corrosion potential) wells.

Benefits/Features of GRE Lined Tubulars

1. Extended well life and avoidance of frequent
workover operations because of corrosion related
problems.
2. Continuity of production/injection operations.








































Fig. 9. CML (zoomed out).

3. Positive business impact with less frequency of
workover jobs and improved allocation of rigs and
resources.
4. The connection area is better protected with GRE
lined tubing compared to IPC tubing.
5. Within the allowed temperature limits, the application
of this product in sour gas wells as an alternative to
expensive chrome alloys that can offer substantial
savings in completion costs.

Operational Considerations and Limitation of GRE
Lined Technology

1. Reduction in the ID of the tubing and restrictions to
run production logging tools. With GRE lined tubing
the sizes of X-nipples need to be stepped down.
2. Hydrofluoric acid (commonly known as mud acid)
cannot be pumped through the GRE lined tubing. It
is recommended to use coiled tubing to spot the
acid, if required.

SAUDI ARAMCO JOURNAL OF TECHNOLOGY FALL 2013



Fig. 10. 1
11
/16 OD 24 finger MIT tool.

3. The key limitation of this nonmetallic GRE lining
technology is the maximum temperature limit of 130
C (266 F).
4. GRE lined tubing does not protect the tubing against
scale formation from BaSO
4
and SrSO
4
, however,
there are successful case studies in the prevention
of CaSO
4
and CaCO
3
and Fe
2
CO
3
scales, paraffin
and asphaltene deposition.
5. GRE lining is not steel but it has better mechanical
wear and resistance properties than plastic or epoxy
coatings. The wireline operations require simple
procedures and precautionary measures to get
prolonged life.

FUTURE OUTLOOK

The product has been adopted for use in oil producers,
power water injectors and water source wells. At the time of
writing this article, more than 50 wells have been installed
with GRE lining between 2008 and 2013. This excludes the
three wells where the GRE lined flush joint tubing was
installed with an electrical submersed pump in 2002; none
of these wells have reported any failures.
Further product development is in progress by the
manufacturers to develop a high temperature (up to 350 F)
product capable of handling sour gas conditions
Potential applications exist within Saudi Aramco to
apply the product in flow lines and in sour gas
production/injection wells (subject to further evaluation).

ACKNOWLEDGMENTS

The authors wish to thank Saudi Aramco management
for permission to publish this article. The authors also
express their gratitude to the Drilling Technical
Department and the Northern Area Production
Department for their support in implementation and
evaluation of the technology.

REFERENCES

1. Kermani, B., Martin, J.W. and Esaklul, K.A.:
Materials Design Strategy: Effects of H
2
S/CO
2

Corrosion on Material Selection, paper 06121,
presented at the Corrosion NACE Exposition, San
Diego, California, March 12-16, 2006.

2. Radhakrishnan, G., Bremner, M. and Simpson, J.:
Downhole Completion Considerations while
Applying GRE Lining Barriers to Downhole Tubing
for Corrosion Protection, paper 10126, presented at
the 13
th
Middle East Corrosion Conference and
Exhibition, Bahrain, February 14-17, 2010.

3. Pots, B.F.M., Kapusta, S.D., John, R.C., Simon
Thomas, M.J.J., Rippon, I.J., Whitman, T.S., et al.:
Improvements on de Waard-Milliams Corrosion
Prediction and Applications to Corrosion
Management, paper 02235, presented at NACE
Annual Corrosion Conference, Denver, Colorado,
April 7-11, 2002.

4. Duoline Technologies Inc.: Best Practices for
Duoline Tubular Goods, Rev. 16, July 2007.
















SAUDI ARAMCO JOURNAL OF TECHNOLOGY FALL 2013

BIOGRAPHIES

Dr. Qamar J. Sharif is a Petroleum
Engineering Specialist with Saudi
Aramcos Drilling and Workover
(D&WO) Department. He has more
than 30 years of diversified experience
in the oil and gas industry, including
academics. Qamar joined Saudi
Aramco in 2005, working in the Drilling
Engineering Department. During this period, his
responsibilities included conducting trial tests for the
application of new technologies and services in drilling
operations, such as drilling with casing. Qamar has also
conducted failure investigations of downhole tools and
performed root causes analysis, making
recommendations to establish new procedures to
prevent reoccurrence, along with other technical and
commercial studies, including analyzing drilling
operations and making recommendations for
performance improvement.
In 2012 he moved to the D&WO Training and
Competency Development Division and developed a
stuck pipe prevention course, specific to Saudi Aramcos
needs and has been teaching the course.
Qamar has worked in drilling, workover and
completion operations, research, business planning,
operations management, technology development and
implementation and competencies development.
His expertise is in the development of novel ideas
and transforming them into robust and practical
solutions. One example includes the development of
innovative Multistring (Quad) Steam Injection Well
Design for Aera Energy, Bakersfield, CA, which included
a novel concept for a thermal packer and a ninefold
increase in the length of oriented perforation per run.
Qamar has contributed to the professional
development of individuals in the oil and gas industry as
an instructor and a mentor, and currently teaches
undergraduate and graduate courses in the Petroleum
Engineering Department at King Fahd University of
Petroleum and Minerals (KFUPM), Dhahran. He served
as Curriculum Advisor for Well Construction,
representing Saudi Aramco with PetroSkills.
Previously, Qamar worked with Shell International
Exploration and Production for about 9 years at the
Bellaire Technology Center, Houston, TX. He worked on
multi-string steam injection well design in Bakersfield,
CA, the development of expandable tubular technology
for Enventure from initial surface tests to the first
downhole application for the BAHA deep-water project in
the Gulf of Mexico, and dual string completions in
Nigeria. Qamar also worked with Shell Deepwater
Services as senior drilling engineer.
He started his career on a steam-powered rig in
1980 with Pakistan Oilfields Ltd. and worked in
drilling/workover operations for about 10 years, which
included about 7 years on jack-up rigs, offshore Abu
Dhabi with the National Drilling Company, working as
assistant driller, driller and tool pusher.
Qamar received his B.S. degree in Mining
Engineering from the University of Engineering and
Technology, Lahore, Pakistan, and his M.S. and Ph.D.
degrees, both in Petroleum Engineering, from Texas
A&M University, College Station, TX.
He is a member of the Society of Petroleum
Engineers (SPE) and is the author of more than 10
papers.
Qamar is the recipient of the Shell President Award
for premier performance for 1997.

Dr. Omar J. Esmail retired from Saudi
Aramco after working for the company
for more than 38 years. He worked in
the areas of reservoir, production,
workover and drilling engineering and
held various supervisory and
managerial positions in both of these
departments prior to retiring in 2011.
In 2009 Omar joined the Upstream
Professional Development Career (UPDC) as a subject
matter expert where he wrote drilling engineering
courses for training young Saudi Aramco drilling
engineers. He continues to teach drilling engineering
courses in the UPDC as a Consultant.
He received his B.S. degree in Chemical
Engineering and his M.S. degree in Petroleum
Engineering, both from Louisiana State University, Baton
Rouge, LA, and then received his Ph.D. degree in
Petroleum Engineering from the University of Texas at
Austin, Austin, TX.






























SAUDI ARAMCO JOURNAL OF TECHNOLOGY FALL 2013


Gokul Radhakrishnan is a Process
Engineer by training with 20 years of
work experience in various upstream
domains, such as control systems,
surface facilities, multiphase flow
metering, Oil Country Tubular Goods
(OCTG) material selection and
nonmetallics. He works for MaxTube
Limited as Regional Manager Middle East and North
Africa and Southeast Asia promoting his companys
fiberglass (GRE) lining services for downhole tubing for
corrosion protection. Gokuls expertise involves making
recommendations to his customers when to use
nonmetallics based on technical suitability and
commercial attractiveness, along with helping to modify
completions to suit the GRE lining. He has been actively
involved in the testing of the GRE liners for Saudi
Aramco for sweet and sour gas production applications.
Gokul is an active member of the Society of
Petroleum Engineers (SPE) and the National
Association of Corrosion Engineers (NACE) and has
coauthored several papers on multiphase metering and
GRE lined completions for production and injection
applications.
He received his B.Eng. degree (with honors) in
chemical Engineering from Birla Institute of Technology
and Science, Pilani, Rajasthan, India, and his Post-
Graduate Diploma in International Trade, from the Indian
Institute of Foreign Trade, Mehruli, New Delhi, India.


John Simpson is the General Manager
of MaxTube, which provides fiberglass
(GRE) lined completions for corrosion
protection in oil/gas producers and
water injection well systems. He has
over 25 years of experience in
upstream oil and gas commercial
operations, with extensive experience
in drilling and completion operations as well as pressure
control and drill through equipment. John has been a
resident in the Middle East since 1997 and has wide
exposure to drilling and completion practices throughout
the Arabian Gulf, Middle East and North Africa and
Asian oil fields. He has also been actively involved in the
testing of the GRE liners for Saudi Aramco for sweet and
sour gas production applications.
John has coauthored several papers for both the
National Association of Corrosion Engineers (NACE)
and Society of Petroleum Engineers (SPE) on GRE lined
completions.
He received his B.S. degree in Chemistry from the
University of Aberdeen, Aberdeen, Scotland, U.K.







Martin Bremner has been the
Operations Director of MaxTube since
2006 and also previously served as
Technical Sales Support Manager,
Quality Manager and Operations
Manager. He has been with MaxTube
since 2002. Martin has a background in
Oil Country Tubular Goods (OCTG)
inspection and quality assurance.
He has coauthored several papers for both the
National Association of Corrosion Engineers (NACE)
and Society of Petroleum Engineers (SPE) on GRE lined
completions and has been involved in the design and
delivery of GRE lining systems for a wide range of
premium OCTG connections.
Martin received his MBA degree in Oil and Gas
Management from the Robert Gordons University
School of Business, Aberdeen, Scotland, U.K.

You might also like