The document lists key project management terms and their definitions. It also provides formulas for calculating common project management metrics like SPI, CPI, SV, CV, EAC, ETC and expected value. Float and discounting formulas are also included.
The document lists key project management terms and their definitions. It also provides formulas for calculating common project management metrics like SPI, CPI, SV, CV, EAC, ETC and expected value. Float and discounting formulas are also included.
The document lists key project management terms and their definitions. It also provides formulas for calculating common project management metrics like SPI, CPI, SV, CV, EAC, ETC and expected value. Float and discounting formulas are also included.
The document lists key project management terms and their definitions. It also provides formulas for calculating common project management metrics like SPI, CPI, SV, CV, EAC, ETC and expected value. Float and discounting formulas are also included.
Download as XLSX, PDF, TXT or read online from Scribd
Download as xlsx, pdf, or txt
You are on page 1of 12
Keywords
Net Present Value (NPV)
Internal Rate of Return (IRR) The Payback Period The Life Cycle Cost The Benefit to Cost Ratio (BCR) Critical Path Rough Order of Magnitude (ROM) Estimate Variance Keywords Schedule Performance Index (SPI) Cost Performance Index (CPI) Schedule Variance (SV) Cost Variance (CV) Estimate to Complete (ETC) when original estimates are flawed Estimate to Complete (ETC) when variances are typical Cost Variance (CV) Estimate at Completion (EAC) Estimate to Complete (ETC) when variances are atypical Estimate to Complete (ETC) when variances are atypical Number of Communication Channels Expected Value (EV) or PERT Estimation To-Complete Performance Index (TCPI) based on the BAC To-Complete Performance Index (TCPI) based on the EAC Total Float (or) Total Slack Net Present Value (NPV) Internal Rate of Return (IRR) The Payback Period The Life Cycle Cost The Benefit to Cost Ratio (BCR) Critical Path Rough Order of Magnitude (ROM) Estimate Variance Total Float (or) Total Slack Formulas A) SPI = EV/PV EV = Earned Value PV = Planned Value [PMBOK Guide - Fourth Edition - Page 183] B) < 1 Project is behind schedule = 1 Project is on schedule > 1 Project is ahead of schedule [PMBOK Guide - Fourth Edition - Page 183] A) CPI = EV/AC EV = Earned Value AC = Actual Cost [PMBOK Guide - Fourth Edition - Page 183] B) < 1 Over budget = 1 On budget > 1 Under budget [PMBOK Guide - Fourth Edition - Page 183] A) SV = EV - PV EV = Earned Value PV = Planned Value [PMBOK Guide - Fourth Edition - Page 182] B) Negative Behind schedule Zero On schedule Positive Ahead of schedule [PMBOK Guide - Fourth Edition - Page 182] A) CV = EV - AC EV = Earned Value AC = Actual Cost [PMBOK Guide - Fourth Edition - Page 182] B) Negative Over budget Zero On budget Positive Under budget [PMBOK Guide - Fourth Edition - Page 182] EAC = (BAC/CPI) BAC = Budget at completion CPI = Cost performance index [PMBOK Guide - Fourth Edition - Page 184] ETC = (EAC - AC) EAC = Estimate at completion AC = Actual cost [PMBOK Guide - Fourth Edition - Page 184, 185] ETC = (BAC - EV)/CPI BAC = Budget at completion EV = Earned value CPI = Cost performance index [PMBOK Guide - Fourth Edition - Page 184, 185] ETC = BAC - EV BAC = Budget at completion EV = Earned value [PMBOK Guide - Fourth Edition - Page 184, 185] N(N-1)/2 Where N = Number of project team members (O+4M+P)/6 O= Optimistic estimate M= Most Likely estimate P= Pessimistic estimate [PMBOK Guide - Fourth Edition - Page 253] TCPI = (BAC - EV) / (BAC - AC) BAC = Budget at completion AC = Actual cost EV = Earned value [PMBOK Guide - Fourth Edition - Page 185] TCPI = (BAC - EV) / (EAC - AC) BAC = Budget at completion AC = Actual cost EV = Earned value EAC = Estimate at completion [PMBOK Guide - Fourth Edition - Page 185] LS-ES (or) LF-EF LS = Late start ES = Early start LF = Late finish EF = Early finish (P-O)/6 P = Pessimistic estimate O = Optimistic estimate PV = FV/(1 + r/100)n N = Number of years r = Discount rate The higher the better The higher the better The lower the better The lower the better The higher the better Path with longest duration Estimated value + or - 50% [PMBOK Guide -Fourth Edition - Page 168] (Standard Deviation) * (Standard Deviation)
Phase 4 - Project Management Financial Assessments Value in Using PERT, Risk Matrices, and Earned Value Management Memo Joseph M. Rivard Professor: Dr. Gonzalez PM620-1003B-01 September 10, 2010