This document is a past examination paper for the course Construction Law from Universiti Sains Malaysia. It consists of 5 questions related to construction law. The first question asks students to discuss the reasons for and procedures of extending time periods for contractors according to JKR 203A and PAM standards. The second question asks about the meaning and scope of worker safety at construction sites. The third questions asks students to discuss the unique legal relationship between contractors and subcontractors. The fourth question asks students to discuss arbitration as an alternative means of dispute resolution in the construction industry. The fifth question asks students to discuss why professional project members need to be registered with professional bodies and explain wrongful torts committed by them.
This document is a past examination paper for the course Construction Law from Universiti Sains Malaysia. It consists of 5 questions related to construction law. The first question asks students to discuss the reasons for and procedures of extending time periods for contractors according to JKR 203A and PAM standards. The second question asks about the meaning and scope of worker safety at construction sites. The third questions asks students to discuss the unique legal relationship between contractors and subcontractors. The fourth question asks students to discuss arbitration as an alternative means of dispute resolution in the construction industry. The fifth question asks students to discuss why professional project members need to be registered with professional bodies and explain wrongful torts committed by them.
This document is a past examination paper for the course Construction Law from Universiti Sains Malaysia. It consists of 5 questions related to construction law. The first question asks students to discuss the reasons for and procedures of extending time periods for contractors according to JKR 203A and PAM standards. The second question asks about the meaning and scope of worker safety at construction sites. The third questions asks students to discuss the unique legal relationship between contractors and subcontractors. The fourth question asks students to discuss arbitration as an alternative means of dispute resolution in the construction industry. The fifth question asks students to discuss why professional project members need to be registered with professional bodies and explain wrongful torts committed by them.
This document is a past examination paper for the course Construction Law from Universiti Sains Malaysia. It consists of 5 questions related to construction law. The first question asks students to discuss the reasons for and procedures of extending time periods for contractors according to JKR 203A and PAM standards. The second question asks about the meaning and scope of worker safety at construction sites. The third questions asks students to discuss the unique legal relationship between contractors and subcontractors. The fourth question asks students to discuss arbitration as an alternative means of dispute resolution in the construction industry. The fifth question asks students to discuss why professional project members need to be registered with professional bodies and explain wrongful torts committed by them.
Academic Session 200812009 April/May 2009 RMK 354 - Construction Law I Undang-Undang Binaan I Duration: 3 hours [Masa: 3 jam] Please check that this examination paper consists of THREE pages of printed material before you begin the examination, Sila pastikan bahawa kertas peperiksaan ini mengandungi TIGA muka surat yang tercetak sebelum anda memulakan peperiksaan ini. Students are allowed to answer all questions either in English OR in Bahasa Malaysia only. Pelajar dibenarkan menjawab semua soalan dalam Bahasa lnggeis ATAU Bahasa Malaysia sahaja. Answer FOUR questions only. Jawab EMPAT soalan sahaja. L}L "'2t- 1. IRMK 3541 -2- Extension of time is the extending of time for the construction period given to the contractor because the construction work cannot be completed before or on the date of completion of work. lt is given as of right and not as of priviledge to the contractor. Discuss the reasons for it being given and the procedure as provided by JKR 203A and PAM. Lanjutan masa merupakan suatu tempoh memaniangkan masa pembinaan yang mana diberikan kepada pihak kontraktor kerana tidak dapat menyiapkan keria-keria pembinaan sebelum atau pada tarikh penyiapan kerja. lanya menjadi suatu hak dan bukan suatu keistimewaan kepada kontraktor. Bincangkan sebab-sebab laniutan masa diberi dan aturcara tanjutan masa sepertimana yang diperuntukan di dalam borang JKR 203A dan PAM. (25 markslmarkah) What is meant by 'safety of Workers at the Work Site' and what is its scope? Apakah yang dimaksudkan 'Keselamatan Pekeria di Tapak Bina' dan apakah skopnya? (25 markslmarkah) 3. The legal concept of relationship between the contractor and subcontractor is unique. Discuss. Konsep hubungan undang-undang di antara kontraktor dan subkontraktor adalah unik. Bincangkan. (25 markslmarkah) 4. Arbitration is an alternative means of dispute resolution in the Construction Industry. Discuss. Timbangtara adalah antara altemative penyelesaian pertikaian didalam tndustri Pembinaan. Bincangkan- (25 markslmatuah) 2. 122 ...31- IRMK 3541 5. Professional project members need to exist in a project. Discuss why they need to be registered with professional bodies and explain the wrongful tort committed by them. Ahli-ahli profesional projek perlu wujud di dalam proiek. Bincangkan sebab mereka perlu mendaftar dengan badan profesional dan terangkan kesalahan-kesalahan tort yang melibatkan ahli profesional. (25 markslmarkah) -oooOooo- -3- 723