JKR Malaysia - Street Lighting Requirment

Download as pdf or txt
Download as pdf or txt
You are on page 1of 54

L-S20 (August 1999)

SPECIFICATION FOR ROAD LIGHTING INSTALLATION


ITEM CONTENTS GENERAL ROAD LIGHTING LUMINARIES General Conformity With Standards Construction And Components
General The Optical System Lamp Lampholder And Associated Supports And Brackets Electrical Control Gear Internal Wiring, Terminal Block And Earthing Terminal

PAGE 1 1 1 1 2 2 3 4 4 5 6 7 7 8 8

1.0
2.0 2.1 2.2 2.3 2.3.1 2.3.2 2.3.3 2.3.4 2.3.5 2.3.6 3.0 4.0 5.0 6.0

PHOTOMETRIC DATA SAMPLE OF LUMINAIRES SCHEDULE AND TECHNICAL INFORMATION ON LUMINAIRES PROJECTS BASED ON THE 'TURNKEY', 'DESIGN AND BUILD' OR 'BUILD-OPERATE-TRANSFER' (B.O.T) APPROACH OUTDOOR WEATHERPROOF FEEDER PILLARS General Fabrication Factory Inspection

7.0 7.1 7.2 7.3

8 8 8 9

SPECIFICATION FOR ROAD LIGHTING INSTALLATION

Hak Cipta :1999 Cawangan Elektrik JKR Malaysia


i/iv

L-S20 (August 1999)

ITEM 7.4 7.5 7.6 7.7 7.8 7.9 7.10 8.0 8.1 8.2 8.3 8.3.1 8.3.2 8.3.3 8.4 8.4.1 8.4.2 8.4.3 8.5 8.5.1 8.5.2 8.5.3 8.6 8.7 Foundation Earthing Switching Circuit Contactors

CONTENTS

PAGE 9 10 10 10 10 10 11 11 11 11 11 11 12 12 13 13 13 14 15 15 16 16 16 16

By-Pass Switch And Selector Switch Miniature Circuit Breakers Termination COLUMNS AND BRACKETS General Design Loading Fabrication
Hot Dip Galvanised Steel Columns Pre-stressed Spun Concrete Columns Fibreglass Reinforced Columns

Material
Hot Dip Galvanised Steel Columns Pre-stressed Spun Concrete Columns Fibreglass Reinforced Columns Protection Against Corrosion Hop Dip Galvanised Steel Columns Pre-stressed Spun Concrete Columns Fibreglass Reinforced Columns

Bracket Arms Spigots

SPECIFICATION FOR ROAD LIGHTING INSTALLATION

Hak Cipta :1999 Cawangan Elektrik JKR Malaysia


ii/iv

L-S20 (August 1999)

ITEM 8.8 8.9 8.10 8.11 8.12 8.12.1 8.12.2 8.12.3 8.13 8.13.1 8.13.2 8.13.3 8.14 8.15 8.16 9.0 10.0 11.0 12.0 13.0 14.0

CONTENTS Doors, Door Openings And Opening For Wiring To Decorative Signs/Lights Baseboard Earthing Terminal Service Slots Flange And Anti-Sink Base Plate
Hot Dip Galvanised Steel Columns Pre-stressed Concrete Columns Fibreglass Reinforced Columns

PAGE 16 17 17 17 17 17 17 17 18 18 19 20 21 21 21 22 22 23 23 24 25

Factory Testing Of The Columns


Hot Dip Galvanised Steel Columns Pre-stressed Concrete Columns Fibreglass Reinforced Columns

Terminal Block Cable Terminations And Internal Wiring Erection Of Columns CABLES AND DUCTS SHOP DRAWINGS CONSTRUCTION REQUIREMENTS TESTING AND TEST CERTIFICATES SERVICE AND MAINTENANCE AS-INSTALLED DRAWINGS, MANUALS AND TOOLS

SPECIFICATION FOR ROAD LIGHTING INSTALLATION

Hak Cipta :1999 Cawangan Elektrik JKR Malaysia


iii/iv

L-S20 (August 1999)

ITEM Appendix A-1 Appendix A-2 Appendix A-3 Appendix A-4 Appendix B Appendix C Appendix D Appendix D1-1 Appendix D1-2 Appendix D1-3 Appendix D1-4 Appendix D2-1 Appendix D2-2 Appendix E Appendix F Appendix G

CONTENTS Schedule Of Luminaire (400W HPSV/SON) Schedule Of Luminaire (250W HPSV/SON) Schedule Of Luminaire (150W HPSV/SON) Schedule Of Luminaire (100W HPSV/SON) Schedule Of Technical Data - HPSV Lamps Schedule Of Technical Data - Control Gear (Ballast, Ignitor and Capacitor) Submission Of Computer Plots Description Of The Layout Illuminance On The 'Grid A' (Typical For 3 Lane Road) Illuminance On The 'Grid A' (Observer's Position: X= - 60.0m Y= Lw/2 H=1.5m) Longitudinal Uniformity For Each Lane Tabulated Summary Of Lighting Level Calculation / Data (Luminance) For Road Lighting Installation Tabulated Summary Of Lighting Level Calculation / Data (Illuminance) For Road Lighting Installation Technical Schedule Of Columns And Bracket Arms Voltage Drop Calculation For The Road Lighting Installation Service And Maintenance For The Road Lighting System

PAGE 27 29 31 33 35 36 38 39 40 41 42 43 44 45 47 48

SPECIFICATION FOR ROAD LIGHTING INSTALLATION

Hak Cipta :1999 Cawangan Elektrik JKR Malaysia


iv/iv

L-S20 (August 1999)

SPECIFICATION FOR ROAD LIGHTING INSTALLATION


1.0 1.1 GENERAL This section of the Specification describes and specifies requirements for the supply, delivery, storage, assembly, installation, erection, testing, commissioning, handing over in approved working order and maintenance during the Defects Liability Period of the Road Lighting Installation in accordance with the Specification, Notes, Bill of Quantities (B.Q.), Conditions of Contract and Drawings. The Road Lighting Installation shall include all luminaires, fittings, brackets, spigots, other supporting devices, columns, feeder pillars, bases, cables, switchgears and all necessary ancillary equipment, foundations, ducting and all other necessary equipment for a complete road lighting system in accordance with the details shown on the Drawings, Bill of Quantities.(B.Q.), Notes, Appendices and as specified herein. ROAD LIGHTING LUMINAIRES General The luminaire shall be complete with integral control gears as a unit and shall be designed for both side entry and post top mounting and suitable for use with 100W/150W/250W/400W High Pressure Sodium Vapour (HPSV or SON) Tubular Lamp and on a supply voltage of 240 Volt, +5%, -10%, 50 Hz. 2.2 Conformity With Standards The luminaire and its associated electrical components shall comply with and be tested to the following IEC Standards together with all current amendments. ITEM Luminaire Lamp Lampholder Ballast Ignitor Capacitor Others IEC 60662 IEC 60598 Part 1 IEC 60922 & IEC 60923 IEC 60926 & IEC 60927 IEC 61048/61049 Relevant IEC Standards STANDARD IEC 60598 Parts 1 & 2

1.2

2.0 2.1

SPECIFICATION FOR ROAD LIGHTING INSTALLATION

Hak Cipta :1999 Cawangan Elektrik JKR Malaysia


1/49

L-S20 (August 1999)

2.3 2.3.1

Construction And Components General i. The luminaire shall be so designed and constructed that it is capable of providing the service for which it is intended. Sound engineering principles shall be adopted throughout and the luminaire shall be designed to enable ease of maintenance and replacement of lamp, control gear, reflector and lampholder without the use of special tools. The main supporting structure of the luminaire shall be constructed from die-cast aluminium alloy material such that no undue deterioration in its safety, performance or appearance during normal life when operating in all climatic conditions prevailing in a tropical country such as heavy rains, high winds, high humidity and hot day-time temperatures. It shall be robustly constructed to withstand vibration in normal use. The luminaire shall be designed so that condensation shall not fall on any operating part which may fail or deteriorate as a result. All luminaires shall be new, totally enclosed and protected against contact with live or moving parts inside the enclosure. The following Index of protection (IP) are required:-

ii.

iii. iv.

IP 55 or higher for the optical compartment of the luminaires. IP 43 or higher for the main luminaire housing and control gear compartment.

Full details of the IP system can be referred to in IEC 60529. v. vi. vii. Access to the interior of the luminaire shall be from the top. Bottom access is not acceptable. Material used for the construction of the luminaire shall be recyclable. Glass/Fibre glass reinforced polyester (GRP/FRP) material is not acceptable. Hinges and clips of the top housing cover if used, shall be robust and made of stainless steel and simple to operate and shall not be liable to accidental detachment during installation or maintenance.

viii. The top cover or luminaire canopy giving access to the interior of the luminaire shall in the closed position, be firmly attached to the fixed position of the luminaire. In the open position, it shall be attached in such a way that there is no likelihood of it becoming accidentally detached and thereby damaging any part of the luminaire or the bracket or the column. ix. Attachment of the luminaire to its bracket arm shall be by means of clamps or jam bolts and designed to accommodate spigot sizes as shown in the table. A minimum of 2 (two) locking bolts / jam screws shall be provided. The minimum depth of penetration of the bracket arm shall be as shown in the table. The mounting arrangement and attachment of the luminaire shall be such as to withstand a

x.

SPECIFICATION FOR ROAD LIGHTING INSTALLATION

Hak Cipta :1999 Cawangan Elektrik JKR Malaysia


2/49

L-S20 (August 1999)

windspeed of 150 km per hour on the projected surface of the assembly without due deflection.

Rating of Lamp 100 Watt 150 Watt 250 Watt 400 Watt xi.

Diameter of Bracket (mm.) 50 50 50 50

Diameter for Side Entry (mm.) 40 - 60 40 - 60 40 - 60 40 - 60

Min.Depth of Penetration (mm.) 100 100 100 110

All parts which carry the weight of the luminaire and internal accessories shall be provided with suitable locking devices to prevent the dislodgment of any part of the luminaire by vibration either in service or during maintenance.

2.3.2

The Optical System i. The design of the optical system shall incorporate a one piece full bowl reflector and shall be replaceable as a unit, independent of the canopy. The reflector shall be made of at least 99.85% pure aluminium with a minimum thickness of 1 mm., be electrically brightened, anodised and chemically treated to give high reflectance. The optical compartment shall be tested and certified to IP 55 or higher. The luminaire shall incorporate provisions to enable adjustments to shift the main light distribution towards the axis of the road to suit different road widths. Such adjustments shall be simple and positive and shall be firmly retained in clearly identified positions. Photometric data shall be supplied for the particular distribution recommended in a given installation. These data may be supplied in computer diskettes together with software in the CIE format. The bowl shall be designed and constructed such that when in the closed position, it will be firmly held. The bowl shall be easily detached from the canopy without having to use any tool and at the same time will not be detached when in the opened position during maintenance. If an IP66 rating is specified for the optical compartment, the bowl shall be designed, constructed and totally sealed to the reflector to form a single removable optical unit. The bowl shall be made of glass or acrylic material. Where acrylic material is used, it shall be stabilised against deformation, deterioration or discolouration due to the lamp and/or solar radiation. The bowl shall be clear or prismatic. In the case of prismatic bowls, the fluted surface shall form the inner surface to facilitate cleaning.

ii. iii.

iv.

v.

vi.

SPECIFICATION FOR ROAD LIGHTING INSTALLATION

Hak Cipta :1999 Cawangan Elektrik JKR Malaysia


3/49

L-S20 (August 1999)

vii.

The gasket shall be a one piece tropicalised weather resistant type made of suitable soft resilient material that will not cause crazing of the bowl. The gasket shall form an integral part of the bowl such that any bowl change will necessitate a change of the gasket.

2.3.3

Lamp i. ii. iii. The lamp to be accommodated in the luminaire shall be 100/150/250/400 watt tubular clear type High Pressure Sodium Vapour (HPSV) lamp. The lamp shall comply with the requirements of IEC 60662 together with all current amendments. The minimum lumen output specifications of the lamp shall be as follows:Lamp Lamp Cap Type E 40 E 40 E40 E40 Colour Corrected Temperature C.C.T 2000 K - 2100 K 2000 K - 2100 K 2000 K - 2100 K 2000 K - 2100 K Lumen Output (Lm) Initial, at 100 hrs. 9500 14500 28000 48000 After 2000 hrs. 9200 13500 26500 46000

100 Watt 150 Watt 250 Watt 400 Watt

iv. The lamp shall not take longer than 4 minutes after the initial switch on to attain 80% of its guaranteed lumen output at the rated voltage 240 Volts, +5%, -10% and frequency 50 Hertz. The re-ignition period after an interruption of the supply shall not be longer than 1 minute to attain 80% of its lumen output. v. The average luminous flux of the lamp shall not depreciate more than 10% of initial value after 10,000 switched operating hours. vi. The average mortality rate for the 100/150/250/400 watt HPSV lamp shall not be greater than 10% at 12,000 switched operating hours. 2.3.4 Lampholder And Associated Supports And Brackets i. ii. The lampholder shall be made of non-metallic, heat resistant material and be rigidly fixed onto the optical compartment. The lampholder shall be an E40 type for the 100/150/250/400 watt HPSV lamp. The lampholder shall be complete with an appropriate brake system to prevent loosening of the lamp.

SPECIFICATION FOR ROAD LIGHTING INSTALLATION

Hak Cipta :1999 Cawangan Elektrik JKR Malaysia


4/49

L-S20 (August 1999)

iii. iv.

The lampholder together with its supports and brackets shall withstand normal usage throughout the life of the luminaire. A lamp fully inserted shall be rigidly held with its axis substantially concident with that of the lampholder under the normal conditions of wind, vibration and mechanical shock. The E40 lampholder shall be rated for 4.5kV pulse.

v. 2.3.5

Electrical Control Gear A. General i. ii. iii. The luminaire shall be furnished complete with integral electrical control gear comprising of inductive ballast, capacitor and ignitor. The electrical control gear shall be mounted on a suitable module unit and shall be easily removable and replaceable as a unit without the use of any special tools. Electrical connection and disconnection of the electrical control gear unit from the luminaire shall be through a plug and socket type connection/terminal block such that incoming supply cables need not be removed when removing the electrical control gear module.

B. Ballast i. The ballast shall be solidly filled with polyester compound and enclosed in a sheet steel or die cast aluminium container or vacuum impregnated with polyester resin of not less than thermal class H (180 C in accordance with IEC 60085). The ballast shall be reactor type and comply fully with IEC 60922 - Ballast for Discharge Lamps : General and Safety Requirements and IEC 60923 - Ballast for discharge lamps (excluding tubular fluorescent lamps) - Performance Requirements. The rated voltage of the ballast shall be 240 Volt, 50 Hz (Nominal) and shall be suitable for operation on a 240 Volt, +5%, -10%, 50 Hz supply system. All terminals shall be of screw connector type. The lamp current crest factor of the ballast shall not exceed 1.8 for 6% voltage variations. At normal operating temperature, the maximum ballast losses, as per IEC 60923 shall not exceed 16 Watt for the 100 Watt HPSV lamp, 18 watts for the 150 watt HPSV lamp, 27 watts for the 250 watt HPSV lamp and 39 watts for the 400 watt HPSV lamp. The rated maximum operating temperature of the ballast winding (tw) shall not be less than 130 C whereas the maximum winding temperature rise (t) shall not be more than 70 C.

ii.

iii.

iv.

v.

C. Ignitor
SPECIFICATION FOR ROAD LIGHTING INSTALLATION

Hak Cipta :1999 Cawangan Elektrik JKR Malaysia


5/49

L-S20 (August 1999)

i. ii. iii. iv.

The ignitor shall be solid state, fully electronic, timed, superimposed multiple-pulse type which does not require the use of tapped ballast to ignite the HPSV lamp. The ignitor shall be fully encapsulated and totally sealed against the ingress of moisture. The ignitor shall have a casing temperature rating of not less than 90 C. The case of the unit shall carry a label showing the connections and listing the operating voltage and the precautions to take during its removal. The ignitor shall be mounted with nut and lock washer. The ignitor shall comply with and be tested to IEC 60926 and IEC 60927 together with all current amendments.

v.

D. Capacitor i. ii. The capacitors shall comply with and be tested to IEC 61048/61049. The capacitors shall have a minimum voltage rating of 250 Volt and a casing temperature rating not less than 85 C and shall be of sufficient capacity to raise the power factor of the circuit to not less than 0.85 lagging. The capacitors shall be housed in extruded aluminium or thermoplastic cannisters and mounted with nut and lock washer. Capacitors shall not be fused but incorporate a safety discharge resistor.

iii. 2.3.6

Internal Wiring, Terminal Block And Earthing Terminal A. Internal Wiring i. The luminaire shall be completely pre-wired, requiring only the connection of the electrical power supply cables to the terminal and the earth continuity conductor to the earthing terminal.

ii. The control gear looping cables shall be non-hygroscopic heat resistant copper-core flexible cable, with a temperature rating of not less than 105 C and marked on the insulation and securely clipped. The minimum size of the cable shall not be less than 1 sq. mm. iii. PTFE insulation or the equivalent, rated to a minimum of 250 C shall be used for leads to the lampholder. B Terminal Block i. A readily accessible barriered terminal block with the live and neutral connections clearly and indelibly marked for the connection of incoming supply cables shall be provided as close as possible to the point of entry of the supply cables. The terminal block shall be made of non-inflammable material.

SPECIFICATION FOR ROAD LIGHTING INSTALLATION

Hak Cipta :1999 Cawangan Elektrik JKR Malaysia


6/49

L-S20 (August 1999)

ii. A means of clamping the electrical supply cables shall be provided in the luminaire to relieve the terminations of strain where they are connected to the terminals. The cable clamp arrangement shall not damage the insulation of the cables. C i. Earthing Terminal A separate terminal for the connection of an earth continuity conductor, clearly and indelibly marked shall be provided.

ii. All exposed metal parts and other parts accessible when the luminaire is opened for maintenance and liable to become live in the event of an insulation fault shall be permanently and reliably connected to this earthing terminal.

3.0

PHOTOMETRIC DATA The following Photometric Data relevant to each luminaire type shall be provided together with the Tender submission. i) ii) iii) iv) v) Isolux Diagram Utilization Factor Curves Polar Curves of the folowing C-Planes : 0/180; 90/270; maximum intensity plane. Downward Light Output Ratio. Downward and Upward Flux Fractions

Tender documents without the appropriate Photometric Data will be disqualified.

4.0 4.1

SAMPLE OF LUMINAIRES Tenderers may be required to submit a sample each of the various luminaires offered after the closing date of the tender submission. Such luminaires submitted shall be furnished complete with control gear, lamp, wiring, etc. as per the tenderers offer in the tender document together with supply cable and a 13 Ampere plug, ready for test. The name and address of the tenderer shall be affixed onto the samples of the luminaire. Delivery of the SAMPLES shall be within a period of ONE WEEK immediately following the request from JKR. Tenderers who fail to submit the SAMPLES of the luminaires within this stipulated period shall be disqualified. Tenderers shall arrange to collect back the samples on notification. SCHEDULE AND TECHNICAL INFORMATION ON LUMINAIRES.

4.2 4.3 4.4 4.5 5.0

SPECIFICATION FOR ROAD LIGHTING INSTALLATION

Hak Cipta :1999 Cawangan Elektrik JKR Malaysia


7/49

L-S20 (August 1999)

5.1 5.2

Tenderers are required to furnish the comprehensive information and technical particulars as stipulated in the APPENDICES A, B, C and D. The information required in each Appendix shall be completed fully and correctly and all technical data entered therein shall be substantiated with relevant pamphlets and test certificates from the manufacturers or the recognized testing authorities. Failure to fulfil the above said requirements shall result in the disqualification of the tender.

5.3

6.0

PROJECTS BASED ON THE 'TURNKEY', 'DESIGN AND BUILD' OR 'BUILDOPERATE-TRANSFER' (B.O.T.) APPROACH. In the case of 'Turnkey' or Design and Build or Build-Operate-Transfer (B.O.T.) type projects, the Road Lighting System shall be designed in accordance with the recommendations set forth in the CIE 115 - 1995 Recommendations For The Lighting Of Roads For Motor And Pedestrian Traffic. The Tenderer shall obtain the consent of JKR for the classifications of Description of Road, Conflict Areas and Lighting Class from JKR for the whole road system prior to designing the layout of the Road Lighting System. This Specification applies to such projects.

6.1

6.2

7.0 7.1

OUTDOOR WEATHERPROOF FEEDER PILLARS General The Feeder Pillars shall be supplied completely assembled with control gear and all internal electrical and mechanical interconnections and structural parts for voltages up to and including 1000 volts A.C. It shall comply with and be tested to the requirements of IEC 60439 - 1 and IEC 60439 - 5.

7.2

Fabrication The Electrical Contractor shall submit design drawings showing the plan, elevations, sections, layout and construction details of the feeder-pillar for the approval of the S.Os Representative prior to fabrication. The plinth, foundation work, ducting, etc. shall be included in the design drawing. The feeder-pillar housing shall comprise of a drip canopy with sufficient overhang, rigid welded channelled steel framework as specified in the Drawings and/or Bill of Quantities and/or Notes. Anti-corrosive treatment shall be applied to the pillar and it shall be painted . A non perishable resilient gasket shall be provided all around the edge of the feeder door. On the front and rear sides of the feeder-pillar, the following sign and lettering of 90 mm height shall be stencilled in red paint:

SPECIFICATION FOR ROAD LIGHTING INSTALLATION

Hak Cipta :1999 Cawangan Elektrik JKR Malaysia


8/49

L-S20 (August 1999)

BAHAYA VOLTAN ELEKTRIK 415 V Side panels and front and back doors shall be fabricated from 12 swg sheet steel as specified in the Drawings. The feeder pillar shall rest on an angle iron base where suitable holes have been prepared to accomodate foundation bolts and to secure the feeder-pillar onto the concrete foundation. The door of the feeder pillar shall be rigidly reinforced bonded and hinged internally to the main frame to prevent unauthorised access. The feeder pillar shall be of lockable type as approved by the S.Os Representative. The feeder-pillar shall be self-ventilated and weatherproof, and such ventilation openings shall be protected by wire mesh to prevent the entry of vermins, rodents and birds. A suitable size wire mesh glass window shall be provided to facilitate reading of the kWH meter. A pocket of suitable size for housing A4 size documents shall be fitted onto the inside of feeder-pillar as specified in the Drawings. The hinged door must be earthed using copper braid as shown in the Drawings. If a stainless steel feeder pillar is specified, all material including framework, panels, bolts and nuts used in the manufacture shall be totally stainless steel. The side panels and front and back doors shall be fabricated from 14 SWG stainless steel. No additional anti-corrosion and paint treatment are required unless otherwise stated. 7.3 Factory Inspection The Electrical Contractor shall make arrangements for a joint inspection and to witness the electrical tests at the factory prior to transportation to the site of the feeder pillars. All costs incurred shall be deemed to be included in the tender price. Test certificates shall be issued upon completion of all tests. 7.4 Foundation The site for the foundation of the feeder-pillar shall be excavated and filled where required, compacted and levelled before the reinforced concrete base is constructed to a minimum of 300 mm. (or otherwise specified ) above the finished ground level and 700 mm. below the finished ground level. Cable entry ducts shall also be provided as specified in the Drawings. 7.5 Earthing

SPECIFICATION FOR ROAD LIGHTING INSTALLATION

Hak Cipta :1999 Cawangan Elektrik JKR Malaysia


9/49

L-S20 (August 1999)

The earthing system for the feeder-pillar shall comply with the requirements of MS IEC 60364, BS 7671:1992 (formerly known as the IEE Wiring Regulations), JKR, JBEG and in accordance with the Drawings. Each feeder-pillar shall be effectively earthed by using 16mm. diameter copper jacketed steel core rods, 25mm x 3mm copper tape and heavy duty inspection chamber with removable cover, etc. 7.6 Switching Circuit The time switch supplied for the control of the luminaires etc, shall be of the synchronous/step motor wound handset dial, plug-in type. It shall incorporate a 24 hours spring reserve. The time switch shall be suitably rated and operational on 220/240 V, 50 Hz supply. 7.7 Contactors The contactor supplied shall comply to IEC 60947-4 with uninterrupted ratings, mechanical duty class 2 and utilisation category of minimum AC3. The contactor coils shall be fully tropicalised and wound for continuous operation for 240/415 V, 50 Hz supply. The contacts of the contactor shall be rated for the breaking capacity on the connected load. 7.8 By-pass Switch and Selector Switch A single and three phase by-pass switch as applicable shall be connected in parallel with the contactor for use in the event of the failure of the contactor. This by-pass switch shall be manufactured to B.S. 5419 and shall be capable of breaking the load connected without undue wear or damage. A four position selector switch shall be provided to select the mode of operation and shall be appropriately labelled. 7.9 Miniature Circuit Breakers. Unless otherwise indicated in the Drawings and/or Bill of Quantities, miniature circuit breakers (MCBs) shall have breaking capacity not less than 6 kA (rms) and of B-type with Class 3 energy limiting characteristics. They shall comply with IEC 60898, fully tropicalised and suitable for use on a 240/415 V, 50Hz A.C. system and in an ambient temperature of 40oC. They shall be quick-make, quick-break and trip free type complete with de-ion arc interrupters. The tripping elements shall be of thermal magnetic type with inverse time delay overcurrent and instantaneous short circuit characteristics. The response to overload shall be independent of variations on ambient temperature. They shall be manually operated by means of toggle type handle having visual indication of whether the breaker is opened, closed or tripped. Multiple breakers shall be provided with a common trip mechanism for simultaneous operation of all the poles. 7.10 Termination

SPECIFICATION FOR ROAD LIGHTING INSTALLATION

Hak Cipta :1999 Cawangan Elektrik JKR Malaysia


10/49

L-S20 (August 1999)

All cables terminated into the various components including incoming and outgoing cables must be terminated through compression glands and heat shrinkable sleeves. 8.0 8.1 COLUMNS AND BRACKETS. General Unless otherwise specified, all columns and brackets shall be tapered octagonal or tapered round type, made up of hot dip galvanised steel interchangeable sections or pre-stressed spun concrete columns or fibreglass reinforced material to comply in all respects to the Drawings, Bill of Quantities and Notes. They shall be manufactured to comply with the relevant sections of the latest edition of B.S. 5649 (EN 40) or ANSI C-136.20 and ASTM D4923-89, or other approved international standards. The base plate, if any, (for planted type columns), brackets arms and spigots shall be manufactured as separate units suitable for mounting or fixing onto the columns. The data for the columns and brackets shall be provided in Appendix E. 8.2 Design loading The columns shall be designed to withstand loading comprising of: i. ii. iii. 8.3 8.3.1 Loads of wind speed up to 35m/sec. The loads due to the weight of the column and accessories, luminaires and associated control gear, the bracket arms and spigots. Other applied loads

Fabrication Hot Dip Galvanised Steel Columns Each column section shall be mechanically formed and longitudinally welded by continuous automatic gas shielded electric arc process (M.I.G. Process) or continuous automatic electric resistance welding, to B.S. 5135:1984. The sections shall be constructed so as to overlap each other by a minimum of 1.5 times the diameter of the immediate lower section (external across face dimension) and to be easily assembled on site by using simple tools without employing welding. The manufacturer shall provide a mark on the finished column sections indicating the minimum overlapping position of 1.5 times the external across-face dimension.

8.3.2

Pre-stressed Spun Concrete Columns i. Pre-stressed Concrete wires and reinforcement Pre-stressed Concrete (PC) wires, Non Tension (NT) wires and Spiral wires shall be cut to correctly coincide with the shapes and dimensions specified in the Drawings. The PC

SPECIFICATION FOR ROAD LIGHTING INSTALLATION

Hak Cipta :1999 Cawangan Elektrik JKR Malaysia


11/49

L-S20 (August 1999)

wires and reinforcement wires shall be arranged so that they are uniformly distributed in the cross-section of the concrete column. All steel reinforcement shall have a concrete cover of not less than 9mm. Pre-stressed concrete columns shall also comply to BS 607 : Part 2 1970. ii. Moulding Moulds used shall be sufficiently rigid in order to withstand the pre-stressing forces. The PC wires shall be tensioned in advance, before the compaction process. iii. Concrete The quality of the concrete and the curing process used shall be such that the compressive strength of the concrete at 28 days in age is greater than 49.0 N/mm2 in accordance with the tests stipulated in JIS A 1132 and JIS A 1108. 8.3.3 Fibreglass Reinforced Columns i. Type 1. Each column section shall be mechanically formed by a centrifugation process. Textile glass fabrics shall be used as reinforcement with the majority of fibre. Fibre only shall be used to stabilize the fabric for extraordinary longitudinal alignment for main reinforcement of the tension direction. On one side of the fabric a chopped strand mat shall be provided to shear strength required in case of impact, compression or torsion. The column section shall be produced and cured in a one-way operation, including the resin and colour pigmentation process. ii. Type 2. The columns shall be made from continuous E-glass roving, encapsulated in a high temperature cured, corrosion resistant, epoxy resin matrix. The glass shall be wound under tension, and at required angles to provide suitable axial and transversal mechanical properties. The columns shall be cured by a process which allows the epoxy resin to migrate to the surface of the column giving it an exceptionally smooth and uniform finish. The glass content shall be approximately 65% by weight. 8.4 8.4.1 Material Hot Dip Galvanised Steel Columns. The column and accessories shall be fabricated from the following materials : COMPONENT Column and Door MATERIAL Steel to BS EN 10025 Grade Fe 510C or BS EN 10025 Fe 430C or BS 1387:1985 or JIS G3452:1978
SPECIFICATION FOR ROAD LIGHTING INSTALLATION

Hak Cipta :1999 Cawangan Elektrik JKR Malaysia


12/49

L-S20 (August 1999)

Bracket Spigot

Arm

and Steel to BS EN 10025 Fe 430C or BS 1387:1985 or JIS G3452:1978 Steel to BS EN 10025 Fe 360A Steel to BS EN 10025 Fe 360A

Base Flange Base Plate

8.4.2

Pre-stressed Spun Concrete Columns The column and accessories shall be manufactured/fabricated from the following materials. COMPONENT Column MATERIAL 1) Concrete grade 50 (50 N/mm2) 2) P.C Wire shall conform to JIS G 3536 3) N.T Wire & reinforcement bar shall conform to JIS G 3532 4) Spiral wire shall conform to JIS G 3532 Door & Spigot Bracket Arm Base Plate Steel to BS EN 10025 Grade Fe 510C or BS EN 10025 Fe 430C or BS 1387 : 1985 or JIS G 3452 : 1978 Steel to BS EN 10025 Fe 430C or BS 1387 : 1985 or JIS G 3452 : 1978 Steel to BS EN 10025 Fe 360A

8.4.3

Fibreglass Reinforced Columns i. Type 1 The column and accessories shall be fabricated from the following materials : COMPONENT Column and Door Bracket Arm and Spigot MATERIAL Fibreglass mat and thermoplastic polyester resin combination Bracket arm -seamless steel with polyurethane coating.

SPECIFICATION FOR ROAD LIGHTING INSTALLATION

Hak Cipta :1999 Cawangan Elektrik JKR Malaysia


13/49

L-S20 (August 1999)

Spigot - galvanised steel Base Flange Pigmentation Of Colour: The colour pigmentatation of the columns shall be guaranteed for at least 15 years of use. Electrical Properties: The columns shall comply with the following electrical properties: Surface resistivity Resistivity Creep resistance Dielectric strength Insulation class DIN 53482 DIN 53482 DIN53480 DIN53481 II 1013 1015 KA3c about 30 kV/mm Galvanised steel

VDE 0303 VDE0303

The flame retardancy properties shall be similar to that of the type 2 composite columns. Mechanical Properties: The columns shall comply with the following mechanical properties: Tensile strength Flex elongation Flexural strength Flex E-modulus Impact strength Heat distortion temperature DIN 53455 DIN 53455 DIN 53452 DIN 53452 DIN 53453 DIN 53458 2.500 kp/cm2 7.5% 1.700 kp/cm2 70.000 kp/cm2 50 kp/cm2 above maximum of standard.

ii.

Type 2. The column and accessories shall be facricated from the following materials: COMPONENT Column and Door MATERIAL E-glass roving and epoxy resin matrix. The door may also be fabricated from aluminium or galvanised steel. Bracket arm - Same material as column or galvanised steel. Spigot/tenon - aluminium Base Flange Galvanised steel

Bracket Arm and Spigot

SPECIFICATION FOR ROAD LIGHTING INSTALLATION

Hak Cipta :1999 Cawangan Elektrik JKR Malaysia


14/49

L-S20 (August 1999)

Flame Resistance: Columns shall not contain chlorine halogen gases or other toxic materials in excess of trace levels which shall always be within the safe OSHA limits. When the column material is subjected to 3 consecutive 60 second flame applications, it shall self extinguish within 5 seconds after the last flame application. Flame resistance shall be in accordance with ASTMD635. The fibreglass reinforced material shall be non-conductive. 8.5 8.5.1 Protection Against Corrosion Hot Dip Galvanised Steel Columns Individual sections of the column, base-plate, door, spigots and bracket arms shall be protected against corrosion by hot dip galvanising, internally and externally in accordance with B.S. 729:1971 or ASTM Standard A123. All welding work shall be done before galvanising. The treatment prior to galvanising shall include degreasing, rinsing, pickling, further rinsing and fluxing. The minimum average weight of the zinc coating shall be 460 g/m2 for any individual test area. The galvanised column and spigots/bracket arms shall be of prime finish and of good uniformity, i.e. free from injurious defects, such as blister, flux or any uncoated spot. The planted section of the column shall be factory-coated with bitumen using the hot dipping process conforming to AASHTO M 190.

8.5.2

Pre-stressed Spun Concrete Columns All exposed metal parts of the concrete columns shall be treated and protected against corrosion.

8.5.3

Fibreglass Reinforced Columns Fibreglass reinforced columns shall not erode, rot or corrode and shall not deteriorate in the Malaysian tropical climate coupled with high sunshine and heavy rainfall, together with other severe evironmental conditions of salt-laden air, acid rain, acid soil and marshy soil and shall be finished in a UV-resistant surface. A range of colour finish shall be available for the columns, with no colour fading over time. Unless otherwise specified, the finish of the column shall be smooth.

8.6

Bracket Arms

SPECIFICATION FOR ROAD LIGHTING INSTALLATION

Hak Cipta :1999 Cawangan Elektrik JKR Malaysia


15/49

L-S20 (August 1999)

Bracket arms shall be of suitable outreach as indicated in the Drawings and/or the B.Q. Unless otherwise indicated in the Drawings and/or B.Q. the bracket arms shall be arranged to give a 5 degree uplift. A spigot of approved material and of appropriate dimensions for the luminaire shall be welded or suitably attached at the base of the bracket arms. In the case of a steel bracket arm, after welding and related work, the bracket arm shall be treated as per clause 8.5 before being hot-dip galvanised. 8.7 Spigots Steel spigots or spigots made of other approved material shall be supplied and installed as indicated in the Drawings and/or B.Q. and treated as per clause 8.5 in the case of steel. 8.8 Doors, Door Openings and Opening for Wiring to Decorative Signs/Lights A hingged weather-proof flush-type or overlapping door, hingged on the upper side with provision to hold the fully opened (180 from the closed position) hingged door in place, shall be provided complete with an anti-vandal locking device over the door opening of each column as shown in the relevant Drawings. The door openings shall have internal reinforcement to compensate for the loss of stiffness of the column caused by forming the door openings. In addition, an opening of 16 mm. diameter complete with rubber plug shall be provided on the column at a height of 5.6 m above the finished ground level for wiring to decorative lighting/signs. The opening shall be located on the same side of the column as the door opening.

8.9

Baseboard A piece of galvanised perforated steel baseboard shall be included in the base compartment for cable termination of the control gear assembly. The baseboard shall have suitable dimensions as indicated in the Drawings and securely fixed in position inside the column.

8.10

Earthing Terminal Columns shall be provided with a corrosion-resistant earthing terminal having substantial contact surface for the attachment of an earthing lead. The terminal shall be provided close to the door opening inside the columns. Where a bolt is used, it shall be at least 6 mm. in diameter and 20mm. in length and provided with two suitable washers and nuts. Unless otherwise specified , the bolt, nuts and washers shall be made of stainless steel.

8.11

Service Slots For the planted type column, the service slot shall be on the same side and vertically below the service door.

SPECIFICATION FOR ROAD LIGHTING INSTALLATION

Hak Cipta :1999 Cawangan Elektrik JKR Malaysia


16/49

L-S20 (August 1999)

For the flange mounted type of column, the cable entry shall be through the flange plate having a hole of suitable diameter as shown in the Drawings and a suitable duct for cable entry shall also be provided at the concrete base. 8.12 Flange and Anti-sink Base Plate

8.12.1 Hot Dip Galvanised Steel Columns For the flange mounted type of column, a flange plate of substantial thickness as shown in the Drawings shall be welded onto the column. As for the planted type column, a detachable antisink base plate shall be supplied. The anti-sink plate, bolt, and nut etc. shall be hot-dip galvanised after manufacture and treated as in clause 8.5. 8.12.2 Pre-stressed Concrete Columns For concrete columns, a flange plate shall be assembled and cast together with concrete during the manufacturing process. 8.12.3 Fibreglass Reinforced Columns i. Type 1. For the flange mounted type column, a flange plate with a rod adapted to the column shall be assembled. The base plate/concrete shell, bolt, and nut etc. shall be hot dip galvanised steel assembled on concrete foundation as per Drawings.

Prefabricated foundation shall be constructed to the column manufacturer's recommendations. ii. Type 2. In the case of the flange-mounted column, a hot-dipped galvanised steel base plate of thickness and dimensions as shown in the Drawings shall be welded to the attachment collar. The attachment collar shall be bonded and mechanically secured to the inside of the column. All required anchor bolts, nuts and washers shall be galvanised steel type and supplied by the column manufacturer. In the case of the planted column, the base of the column shall be enlarged via two integral anti-rotation bosses, located 180 from each other and appropriately centred above the column butt. These bosses shall be large enough to effectively prevent rotation and pull-out of the column and shall be formed by the column manufacturer. 8.12.4 Where the concrete base for the flange mounted columns are included in the Electrical Contractors work, the bolts and nuts for mounting the flanged mounted columns shall be supplied by the column manufacturer.

SPECIFICATION FOR ROAD LIGHTING INSTALLATION

Hak Cipta :1999 Cawangan Elektrik JKR Malaysia


17/49

L-S20 (August 1999)

8.13

Factory Testing of the Columns A sample of all types of columns and bracket arms shall be tested at the factory of manufacture in the presence of the S.O's Representatives. The tests shall comprise of :

8.13.1 Hot Dip Galvanised Steel Columns a) b) Dimensional and Weight Measurements of column and bracket. Temporary Deflection Test : The column is to be mounted horizontally and rigidly supported for the distance equivalent to the planting depth from the base, and loaded, as a cantilever at a point from the top of the column (excluding the bracket arm). The temporary deflection measured at the point of application of load shall not exceed 150 mm. and the load to cause 150 mm. deflection at the top of the column (excluding the bracket arm) shall not be less than the folowing figures: COLUMN MOUNTING HEIGHT (m) Load to cause 150 mm deflection at top of column (excluding bracket arm) (N) 6 1340 7 1120 8 1230 9 800 10 700 11 550 12 480

The deflection test shall be carried out with the column placed in the two weakest positions. c) Galvanising Test : The columns and brackets shall be subjected to the galvanising thickness test as laid down in BS 729:1971. d) Bitumen Test : The bitumen coating on the column base shall be subjected to thickness test. e) Material Test : Steel material used for the manufacturing of columns and brackets shall be subjected to test for compliancee with BS EN 10025 (Grade 43C or Grade 50C). The supplier shall state the test method and the reference standards together with the tender. The test method and the reference standards shall be subject to the approval of the S.O.'s Representative. f) Welding Test : The welded portions of the columns and brackets shall be subjected to the welding test as stipulated in the British Standard B.S. 5135 or equivalent Standard approved by the S.O.s Representative.
SPECIFICATION FOR ROAD LIGHTING INSTALLATION

Hak Cipta :1999 Cawangan Elektrik JKR Malaysia


18/49

L-S20 (August 1999)

The minimum percentage penetration for the longitudinal seam weld shall be 60%. g) Mechanical Property Test : A small piece of steel plate of adequate size shall be cut off from the base of the sample column for this test. The tensile strength and yield of the sheet metal shall be measured. The test results shall comply with the limits specified in BS EN 10025 for Grade 510C and 430C steel as follows : Fe 510C Tensile Strength (N/mm2) Yield Strength (Min. N/mm2) 8.13.2 Pre-stressed Concrete Columns i. Bending Strength Test This test shall be carried out in accordance with JIS A 5309. When the design load of 1.5kN is applied, cracks exceeding 0.25 mm in width shall not appear. When the design load is removed there shall be no cracks exceeding 0.05mm in width. ii. Breaking Test This test shall be carried out in accordance to JIS A 5309. The load is applied to the column in one of the two loading directions until the column is broken. The breaking load shall be more than twice the design load. iii. Inspection a) Quantity of Column to be Inspected Inspection of the appearance, shape and dimensions shall be performed on all columns. Inspection of the concrete cover shall be performed on the column that was subjected to the breaking test. The bending strength test shall be conducted on three column sampled from a batch of 1000 columns or part thereof. The breaking test shall be performed on one of three columns used in the bending strength test. b) Determination of Acceptability All columns shall comply to the specification with respect to appearance, shape and dimensions.
SPECIFICATION FOR ROAD LIGHTING INSTALLATION

Fe430C 430 to 580 275

490 to 640 355

Hak Cipta :1999 Cawangan Elektrik JKR Malaysia


19/49

L-S20 (August 1999)

When all the three columns subjected to the bending strength test comply with the specification, then all the columns in the batch shall be accepted. When one column does not conform with the specification during the bending strength test, the test shall be repeated one or two sampled columns. When both columns conform to the specification, all columns in the batch shall be accepted except for the initially rejected column. When test column does not comply to the specification, the test shall be repeated with two more sampled columns. When both columns conform, all the columns in the batch shall be accepted except for the initially rejected column. 8.13.3 Fibreglass Reinforced Columns Fibreglass Reinforced Columns shall be tested to the relevant sections of the applicable BS, VDE, DIN, ANSI/AASHTO as the case requires, to ensure compliance with the mechanical properties, strength, stiffness, flame retardancy, accepted deflection tolerances and breaking point loading including testing under full wind loading condition. 8.13.4 All test and measuring equipment shall be provided by the column manufacturer and all such test and measuring equipment shall be certified to have been calibrated by an accredited laboratory for testing and calibration. Proof of validity of the calibration shall be submitted to the S.Os Representative for approval prior to making arrangements for the factory testing. 8.13.5 A verified Test Report for the tests on the columns shall be submitted by the manufacturer. 8.13.6 All expenses incurred for the tests shall be borne by the Electrical Contractor and shall be deemed to have been included in the Contract Price. 8.14 Terminal Block The terminal block shall be of a type manufactured for use in road lighting installation. They shall have facilities for double fusing loop-in loop-out terminals. The cut-out bases shall have a supply cable contact block rating of at least 50A and shall be capable of accepting circular cable cores up to 25 mm2 copper 2 core or 4 core as required. The cut-out shall be provided with adequate shrouding to prevent cross phasing with live metal parts. 8.15 Cable Terminations and Internal Wiring An appropriate type of earthing clamp shall be provided to bond the armouring of the cables which shall be effectively earthed. Cable glands c/w hot-dipped galvanised mild steel L-bracket shall be used for all armoured cable termination. The cables, including the earthing cable, from the road lighting cut-outs to the luminaires shall not be less than 2.5 mm2 pvc. They shall be bundled together with cable ties and terminated with lugs.
SPECIFICATION FOR ROAD LIGHTING INSTALLATION

Hak Cipta :1999 Cawangan Elektrik JKR Malaysia


20/49

L-S20 (August 1999)

8.16

Erection of Columns Columns shall be installed in accordance with the manufacturer's recommendation and as per Drawings. The Electrical Contractor shall peg out the positions of the columns for the approval of the S.Os Representative before planting the columns or before the construction of the concrete bases in the case of flange mounted columns. The columns shall be erected such that the service doors shall face the opposite side to the oncoming traffic except at parapets of bridges and retaining walls. At such locations the orientation of the service doors shall be determined by the S.Os Representative. After erecting the column, the backfill shall be compacted by means of a suitable ramming equipment and the uprightness of the columns shall be verified with the use of a plumb line or equivalent device.

9.0

CABLES AND DUCTS Road lighting cables and their installation shall be in compliance with the latest JKR Specification for Low Voltage Underground Cable, and to any additional notes mentioned in the Drawings and Notes to Tenderers. Ducts for road crossing, etc. shall be laid in accordance with the Drawings, B.Q. and appropriate sections of the Specification. Cables in the central median shall be laid close to the columns and as far away as possible from the edge of the pavement. The minimum distance from the edge of the pavement shall be 1 metre or as directed by the S.Os Representative. Cables along the road shoulders shall be laid as far away as possible from the usable shoulder width or as directed by the S.Os Representative. Data for voltage drop calculations for all the road lighting circuits shall be give in the format of Appendix F - Voltage Drop Calculation For The Road Lighting Installation, together with the detailed calculations.

10.0

SHOP DRAWINGS Two sets of prints of shop drawings for construction and/or installation shall be submitted to the S.O.s Representative for approval. The Electrical Contractor shall prepare and submit shop drawings for the whole work or parts of the work at least two weeks before the work begins. If the shop drawings submitted are not acceptable by the S.O.s Representative, the Electrical Contractor shall amend and re-submit the shop drawings within two weeks from the date of return of the shop drawings. No work including fabrication of the feeder pillars shall be carried out without the shop drawings being approved by the S.O.s Representative. The shop drawings shall include and show the following:

SPECIFICATION FOR ROAD LIGHTING INSTALLATION

Hak Cipta :1999 Cawangan Elektrik JKR Malaysia


21/49

L-S20 (August 1999)

The dimensioned general arrangements, layouts and positions of columns and luminaires, feeder pillars, and all others necessary for the complete road lighting installation as specified in the Drawings and/or Bill of Quantities; Circuits and switching arrangements including schematic line diagrams of the installation; The dimensioned general arrangements and layouts of the equipment and the schematic line diagram of the feeder pillars; Cable routes for all cables laid underground, in ducts and trenches; The dimensioned general arrangements and layout of earthing system including routes for earthing conductors and positions of earth electrodes. The cost of all these shop drawings, whether or not provided in the Bill of Quantities, is deemed to be included in the Contract. 11.0 CONSTRUCTION REQUIREMENTS Adequate warning signs including flashing lights, luminous signs and flagmen shall be provided for the safety of the road user and general public. The general arrangement and location of temporary warning signs shall be in strict accordance with ARAHAN TEKNIK (JALAN) 2C/85 and amendments, published by Cawangan Jalan, Ibu Pejabat JKR Malaysia, Kuala Lumpur. All workers on the site shall be appropriately dressed with luminous jackets and the work area adequately cordoned. No night work shall be permitted without the prior approval of the S.Os Representative. All warning signs shall conform to standard JKR requirements. Adequate illuminated, flashing and luminous warning signs shall be provided during the night time. The maximum trenching distance and working area for the day shall be determined after prior consultation with the S.Os Representative. The mobile trenching method shall be employed as far as is practicable and all excavations, installation of ducting/sand/cabling/bricks/accessories, backfilling, compacting and cleaning up shall be executed in one coordinated operation to expeditiously complete the work and therefore minimise inconvenience and danger to the public. The carriageway and road shoulder area including all work area shall be cleared of all debris and cleaned after each days work All excess excavated material and construction material shall be removed from the site and no such material shall be permitted to be left by the road side without the consent of the S.Os Representative. 12.0 TESTING AND TEST CERTIFICATES On completion of the installation work on site and before the Certificate of Practical Completion is issued, the Electrical Contractor shall at his own expense, arrange for all necessary tests to be carried out on the installation by competent person as part of the tests required of him for the whole installation under this contract. The tests to be carried out shall be as prescribed in the Electricity Regulations 1994, B.S. 7671: 1992 including all amendments (formerly known as the IEE Wiring Regulations), IEC 60364 and other tests deemed necessary by the S.O.'s Representative.
SPECIFICATION FOR ROAD LIGHTING INSTALLATION

Hak Cipta :1999 Cawangan Elektrik JKR Malaysia


22/49

L-S20 (August 1999)

In the event the installation fails any of these tests, the Electrical Contractor shall, at his own expense, take such measures as are necessary to remedy the defects and the installation shall not be considered as completed until it complies with the requirements of all such tests. The tests to be carried out by the Electrical Contractor shall consist of the following tests (where applicable) :a) Continuity of final circuit conductors. b) Continuity of protective conductors including main and supplementary equipotential bonding. c) Insulation resistance. d) e) f) g) h) i) j) k) l) m) Insulation of site-built assemblies. Protection by electrical separation. Protection by barriers or enclosures provided during erection. Insulation of non-conducting floors and walls. Polarity. Earth fault loop impedance. Earth electrode resistance. Fuctional testing of all types of switches and switchgear. Alignment and uprightness of the columns and the tilting angle of the bracket arms. Luminance and illuminance readings in accordance with the computer plots.

Two sets of Supervision and Completion Certificate and Test Certificate including copies of all the test results and drawings as prescribed in the Electricity Regulations 1994 shall be submitted to the S.O.s Representative within two weeks after the completion of the testing. The aforesaid Certificates shall be properly bound in hard cover and titled. 13.O SERVICE AND MAINTENANCE During the Defects Liability Period, the Electrical Contractor shall be responsible for the service and maintenance for the complete installation. All works shall be carried out by competent person. All labour, tranport, equipment, materials, tools and parts necessary to service the installation and/or rectify the defect due to manufacturing/installation faults shall be supplied/executed at the Electrical Contractors cost. The Electrical Contractor shall provide a three-monthly report in the manner of Appendix G. The service and maintenance to be performed and defects to be rectified and made good shall include but not limited to the following :a) Replacing or making good all luminaires, lamps, ballasts, capacitors, ignitors, control gears, switches, socket outlets, isolators, mcb, mccb, fuses, time switches, contactors, relays, meters, etc. b) Replacing all consumable items that do not meet the manufacturers guaranteed or declared lifespan. c) Straightening columns and replacing missing doors, covers and locking devices.
SPECIFICATION FOR ROAD LIGHTING INSTALLATION

Hak Cipta :1999 Cawangan Elektrik JKR Malaysia


23/49

L-S20 (August 1999)

d) Replacing and making good all loose/damaged cable terminations, damaged cables, mechanical support linkages, earth electrode chambers and covers, etc. e) Making good damage to roads, buildings, drains, cables, pipes, concrete areas, paved areas, turfed areas, etc. which was his responsibility to make good but which had not been properly rectified. f) All other works deemed necessary by the S.O.s Representative.

All works shall be carried out as soon as the Electrical Contractor is informed by the S.O.s Representative or the owner and shall be completed within a reasonable time except under emergency situation as stipulated in the Supplementary Conditions for Electrical Work. If the Electrical Contractor fails to comply with the above requirements, the S.O.s Representative reserves the right to engage a third party to carry out the work, in which case, the Electrical Contractor shall be responsible for all the expenses incurred. 14.0 AS-INSTALLED DRAWINGS, MANUALS AND TOOLS Within three calendar months after the practical completion of the project, one set of true to scale negative (110/115 gm./sq.m. ISO A0 or A1 size) and four sets of prints for each of the following drawings shall be submitted :a) b) c) d) Site plan Schematic Wiring Diagrams and Control Circuit Drawings Road Lighting Layout Plans Layout plan of cable routes and earthing points, with reference to easily recognisable landmarks, buildings and structures.

These drawings shall be properly stencilled and shall have at the lower right corner the Electrical Contractor's name and address, date of commissioning, scale, drawing number (the drawing number shall be obtained from the S.O.'s Representative), title and the following particulars:JABATAN KERJA RAYA MALAYSIA CAWANGAN ELEKTRIK CONTRACT NO: TENDER NO : If the drawings submitted are not acceptable to the S.O.s Representative, the Electrical Contractor shall amend and resubmit the drawings within two weeks from the date of notification by the S.O.s Representative. If required and specified elsewhere, in addition to the aforesaid negatives and prints, the asinstalled drawings shall be stored in electronic media or any other media as specified. The
SPECIFICATION FOR ROAD LIGHTING INSTALLATION

Hak Cipta :1999 Cawangan Elektrik JKR Malaysia


24/49

L-S20 (August 1999)

electronic media shall be floppy disks and/or CD as specified which can be readily retrieved by computer. The software programme shall be AutoCAD of a release specified or of the latest release. Two sets or copies of the as-installed drawings in the format required, appropriately titled and stored in container or casing, shall be submitted.

In addition, four sets of the following manuals/brochures and documents, suitably bound, shall be submitted to the S.Os Representative: a) b) c) d) c) d) Installation manual Operation manual Service and Maintenance Manual Parts List Product data and catalogues Product Test Certificates

Each of the above sets of prints together with the manuals shall be in a stiff cover ring file. In addition, a set of A4 size schematic drawings shall be laminated and placed inside the pockets of the Feeder Pillars.

Special tools required for the operation, service and maintenance of the feeder pillars and switchgear, columns and other equipment shall also be provided.
The cost of all these prints, manuals and tools shall be deemed to be included in the Contract Price.

SPECIFICATION FOR ROAD LIGHTING INSTALLATION

Hak Cipta :1999 Cawangan Elektrik JKR Malaysia


25/49

L-S20 (August 1999)

APPENDIX A-1 SCHEDULE OF LUMINAIRE (400W HPSV/SON)

ITEM A
1 2 3 4

DESCRIPTION MAKE
Manufacturer Country of manufacture Brand of Luminaire Model of Luminaire

DATA/MATERIAL

B
5 6 7 8 9 10 11

MATERIAL
Lamp Compartment Control Gear Compartment Sealing Gasket Reflector Cover Bowl Lampholder Bowl Retainer Catch

C
12 13 14 15

PHOTOMETRY
Standard Position Facilities for Directional Light Control Optical Compartment (Degree of Protection) Control Gear Compartment (Degree of Protection)

...cont. pg. 28/49


SPECIFICATION FOR ROAD LIGHTING INSTALLATION

Hak Cipta :1999 Cawangan Elektrik JKR Malaysia


26/49

L-S20 (August 1999)

APPENDIX A-1 SCHEDULE OF LUMINAIRE (400W HPSV/SON)

ITEM
16 17 18 19 20

DESCRIPTION
Relevant Standard of Conformity Total Light Output Ratio - TLOR Downward Light Output Ratio-DLOR Direction of maximum intensity measured from the downward vertical (Cd/1000 lm) Maximum intensity at 80 from the downward vertical (Cd/1000 lumen) Maximum intensity at 88 from the downward vertical (Cd/1000 lumen) Maximum intensity above the horizontal (Cd/1000 lumen) Relevant pamphlets to substantiate the above mentioned data and test certificates to be enclosed

DATA/MATERIAL

21 22 23

.. T/t, Nama & Cop Pengilang

T/t, Nama & Cop Kontraktor Elektrik

APPENDIX A-2
SPECIFICATION FOR ROAD LIGHTING INSTALLATION

Hak Cipta :1999 Cawangan Elektrik JKR Malaysia


27/49

L-S20 (August 1999)

SCHEDULE OF LUMINAIRE (250W HPSV/SON)

ITEM A
1 2 3 4

DESCRIPTION MAKE
Manufacturer Country of manufacture Brand of Luminaire Model of Luminaire

DATA/MATERIAL

B
5 6 7 8 9 10 11

MATERIAL
Lamp Compartment Control Gear Compartment Sealing Gasket Reflector Cover Bowl Lampholder Bowl Retainer Catch

C
12 13 14 15

PHOTOMETRY
Standard Position Facilities for Directional Light Control Optical Compartment (Degree of Protection) Control Gear Compartment (Degree of Protection) ...cont. pg. 30/49

APPENDIX A-2
SPECIFICATION FOR ROAD LIGHTING INSTALLATION

Hak Cipta :1999 Cawangan Elektrik JKR Malaysia


28/49

L-S20 (August 1999)

SCHEDULE OF LUMINAIRE (250W HPSV/SON)

ITEM
16 17 18 19

DESCRIPTION
Relevant Standard of Conformity Total Light Output Ratio - TLOR Downward Light Output Ratio-DLOR Direction of maximum intensity measured from the downward vertical (Cd/1000 lm) Maximum intensity at 80 from the downward vertical (Cd/1000 lumen) Maximum intensity at 88 from the downward vertical (Cd/1000 lumen) Maximum intensity above the horizontal (Cd/1000 lumen) Relevant pamphlets to substantiate the above mentioned data and test certificates to be enclosed

DATA/MATERIAL

20

21

22

23

.. T/t, Nama & Cop Pengilang

T/t, Nama & Cop Kontraktor Elektrik

SPECIFICATION FOR ROAD LIGHTING INSTALLATION

Hak Cipta :1999 Cawangan Elektrik JKR Malaysia


29/49

L-S20 (August 1999)

APPENDIX A-3 SCHEDULE OF LUMINAIRE (150W HPSV/SON)

ITEM A
1 2 3 4

DESCRIPTION MAKE
Manufacturer Country of manufacture Brand of Luminaire Model of Luminaire

DATA/MATERIAL

B
5 6 7 8 9 10 11

MATERIAL
Lamp Compartment Control Gear Compartment Sealing Gasket Reflector Cover Bowl Lampholder Bowl Retainer Catch

C
12 13 14

PHOTOMETRY
Standard Position Facilities for Directional Light Control Optical Compartment (Degree of Protection)

...cont. pg. 32/49


SPECIFICATION FOR ROAD LIGHTING INSTALLATION

Hak Cipta :1999 Cawangan Elektrik JKR Malaysia


30/49

L-S20 (August 1999)

APPENDIX A-3 SCHEDULE OF LUMINAIRE (150W HPSV/SON)

ITEM
15 16 17 18 19

DESCRIPTION
Control Gear Compartment (Degree of Protection) Relevant Standard of Conformity Total Light Output Ratio - TLOR Downward Light Output Ratio-DLOR Direction of maximum intensity measured from the downward vertical (Cd/1000 lm) Maximum intensity at 80 from the downward vertical (Cd/1000 lumen) Maximum intensity at 88 from the downward vertical (Cd/1000 lumen) Maximum intensity above the horizontal (Cd/1000 lumen) Relevant pamphlets to substantiate the above mentioned data and test certificates to be enclosed

DATA/MATERIAL

20

21

22

23

.. T/t, Nama & Cop Pengilang

T/t, Nama & Cop Kontraktor Elektrik

SPECIFICATION FOR ROAD LIGHTING INSTALLATION

Hak Cipta :1999 Cawangan Elektrik JKR Malaysia


31/49

L-S20 (August 1999)

APPENDIX A-4 SCHEDULE OF LUMINAIRE (100W HPSV/SON)

ITEM A
1 2 3 4

DESCRIPTION MAKE
Manufacturer Country of manufacture Brand of Luminaire Model of Luminaire

DATA/MATERIAL

B
5 6 7 8 9 10 11

MATERIAL
Lamp Compartment Control Gear Compartment Sealing Gasket Reflector Cover Bowl Lampholder Bowl Retainer Catch

C
12 13 14 15

PHOTOMETRY
Standard Position Facilities for Directional Light Control Optical Compartment (Degree of Protection) Control Gear Compartment (Degree of Protection)

...cont. pg. 34/49


SPECIFICATION FOR ROAD LIGHTING INSTALLATION

Hak Cipta :1999 Cawangan Elektrik JKR Malaysia


32/49

L-S20 (August 1999)

APPENDIX A-4 SCHEDULE OF LUMINAIRE (100W HPSV/SON)

ITEM
16 17 18 19

DESCRIPTION
Relevant Standard of Conformity Total Light Output Ratio - TLOR Downward Light Output Ratio-DLOR Direction of maximum intensity measured from the downward vertical (Cd/1000 lm) Maximum intensity at 80 from the downward vertical (Cd/1000 lumen) Maximum intensity at 88 from the downward vertical (Cd/1000 lumen) Maximum intensity above the horizontal (Cd/1000 lumen) Relevant pamphlets to substantiate the above mentioned data and test certificates to be enclosed

DATA/MATERIAL

20

21

22

23

...... T/t, Nama & Cop Pengilang

T/t, Nama & Cop Kontraktor Elektrik

APPENDIX B
SPECIFICATION FOR ROAD LIGHTING INSTALLATION

Hak Cipta :1999 Cawangan Elektrik JKR Malaysia


33/49

L-S20 (August 1999)

SCHEDULE OF TECHNICAL DATA - HPSV LAMPS ITEM 1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16 17 18 19 20 DESCRIPTION Manufacturer Country of manufacture Model number Lamp type Wattage Efficacy (Lumen/Watt) Operating position Rated life (Hours) Luminous flux after 100 burning hours Colour temperature (K) Operating voltage Operating lamp current Max. starting current Waveband in which 80% of the spectral energy distribution will occur Time to reach 80% of max. luminous flux after switching Time to re-strike after power interruption Light depreciation after 5000 burning hours Mortality rate after 5000 burning hours Relevant Standards of conformity Relevant pamphlets to substantiate the above-mentioned data and test certificates to be enclosed ..... T/t, Nama & Cop Pengilang T/t, Nama & Cop Kontraktor Elektrik APPENDIX C 400W 250W 150W 100W

SPECIFICATION FOR ROAD LIGHTING INSTALLATION

Hak Cipta :1999 Cawangan Elektrik JKR Malaysia


34/49

L-S20 (August 1999)

SCHEDULE OF TECHNICAL DATA - CONTROL GEAR BALLAST FOR THE FOLLOWING HPSV LAMPS ITEM 1 2 3 4 5 6 7 8 9 10 11 12 13 14 DESCRIPTION Manufacturer Model number Country of manufacture Nominal wattage Losses (in watts) Rated max. operating temperature of ballast winding - tw (C) Max. winding temperature rise (C) Impedance Resistance Inductance Lamp current crest factor Power factor before correction Power factor after correction Expected life t 400W 250W 150W 100W

.. T/t, Nama & Cop Pengilang

. T/t, Nama & Cop Kontraktor Elektrik

...cont. pg. 37/49

APPENDIX C SCHEDULE OF TECHNICAL DATA - CONTROL GEAR


SPECIFICATION FOR ROAD LIGHTING INSTALLATION

Hak Cipta :1999 Cawangan Elektrik JKR Malaysia


35/49

L-S20 (August 1999)

IGNITOR FOR THE FOLLOWING HPSV LAMPS ITEM 1 2 3 4 5 6 7 8 9 10 11 DESCRIPTION Manufacturer Model number Country of manufacture Nominal voltage Peak ignition voltage Losses (in watts) Max. housing temperature (C) Max. operating temperature (C) Conventional or electronic superimposed pulse type Timed type ( Yes / No ) Guaranteed life (no. of strikes) CAPACITOR FOR THE FOLLOWING HPSV LAMPS ITEM 1 2 3 4 5 DESCRIPTION Manufacturer Model number Country of manufacture Capacitance Material of container 400W 250W 150W 100W 400W 250W 150W 100W

.. T/t, Nama & Cop Pengilang

T/t, Nama & Cop Kontraktor Elektrik APPENDIX D

SUBMISSION OF COMPUTER PLOTS.


SPECIFICATION FOR ROAD LIGHTING INSTALLATION

Hak Cipta :1999 Cawangan Elektrik JKR Malaysia


36/49

L-S20 (August 1999)

Electrical Contractors are required to submit computer plots of typical road sections as per format described in the layouts given. APPENDIX D1 (1 to 4) - Computer Calculation Format For Road Lighting Installation (To be submitted for various typical layout and sections as given in the Tender Document or obtained from JKR) APPENDIX D2 (1 to 2) - Tabulated Summary Of Lighting Level Calculation/Data For Road Lighting Installation The computer plots shall also be attached. In addition, the photometric data of item 3.0 shall be submitted. All the above plots and data shall be certified by the respective manufacturer.

................................................................... Tandatangan dan Nama Kontraktor Elektrik

..................................... Cop Kontraktor Elektrik

Tarikh

SPECIFICATION FOR ROAD LIGHTING INSTALLATION

Hak Cipta :1999 Cawangan Elektrik JKR Malaysia


37/49

L-S20 (August 1999) APPENDIX D1-1

DESCRIPTION OF THE LAYOUT

Cross section (transversally) * Road surface type : R Lave = 2 cd/m2 Cht Uo = Lmin/Lave 40% Ul= Lmin/Lmax 70% Lw T.I. 15% (Threshold Increment) * Qo : .. * Maintenance factor : * Source : HPSV(Son-T) .Watts * Flux (klm) : . klm Tilting Angle : 50 * Overhang : . SR (Surround Ratio) 0.5
Cs

Mw

Rw

Position of the calculation grids Plan view [m]

X LEGEND: Cht - Column height (m) Cs - Column spacing (m) Lw - Lane width (m) Mw - Median width (m) Rw - Road width (m) * - Data to be filled in by JKR/Designer Y

Grid A

SPECIFICATION FOR ROAD LIGHTING INSTALLATION Hak Cipta :1999 Cawangan Elektrik JKR Malaysia

39/49

L-S20 (August 1999) APPENDIX D1-2 ILLUMINANCE ON THE 'GRID A' (TYPICAL FOR 3 LANE ROAD)
Y[m] Lw(17/6) Lw(15/6) Lw(13/6) Lw(11/6) Lw(3/2) Lw(7/6) Lw(5/6) Lw/2 Lw/6 X[m] 0.9Cs [LUX]

0.0

0.1Cs

0.2Cs

0.3Cs

0.4Cs

0.5Cs

0.6Cs

0.7Cs

0.8Cs

Eave = _______Lux Emin = _______Lux Emax =_______Lux

Uo = Emin/Eave = ______ % Ug = Emin/Emax = ______%

Type of luminaire : Data for 30 points per lane. LEGEND : Cs - Column spacing in metres Lw - Lane width in metres

Tandatangan Pengilang

Tandatangan Kontraktor Elektrik

Cop Pengilang

Cop Kontraktor Elektrik

Nama:

Nama:

Jawatan:

Jawatan:

SPECIFICATION FOR ROAD LIGHTING INSTALLATION Hak Cipta :1999 Cawangan Elektrik JKR Malaysia

40/49

L-S20 (August 1999) APPENDIX D1-3 LUMINANCE ON THE 'GRID A' (TYPICAL FOR A 3-LANE ROAD) (Observer's position : X= - 60.0m Y= Lw/2 H= 1.5m)
Y[m] Lw(17/6) Lw(15/6) Lw(13/6) Lw(11/6) Lw(3/2) Lw(7/6) Lw(5/6) Lw/2 Lw/6 X[m] 0.9Cs [CD/M2]

0.0

0.1Cs

0.2Cs

0.3Cs

0.4Cs

0.5Cs

0.6Cs

0.7Cs

0.8Cs

Lave = _______cd/m2 Lmin = _______cd/m2 Lmax =_______cd/m2

Uo = Lmin/Lave = ______% Ul = Lmin/Lmax = _______%

Type of luminaire : Data For 30 Points Per Lane LEGEND : Cs - Column spacing in metres Lw - Lane width in metres

Tandatangan Pengilang

Tandatangan Kontraktor Elektrik

Cop Pengilang

Cop Kontraktor Elektrik

Nama:

Nama:

Jawatan: SPECIFICATION FOR ROAD LIGHTING INSTALLATION Hak Cipta :1999 Cawangan Elektrik JKR Malaysia

Jawatan:

41/49

L-S20 (August 1999) APPENDIX D1-4

LONGITUDINAL UNIFORMITY FOR EACH LANE (FOR A 3-LANE ROAD)

Observer on the axis Y = + Lw/2 m X= L= 0.0 0.1Cs 0.2Cs 0.3Cs 0.4Cs 0.5Cs 0.6Cs 0.7Cs 0.8Cs 0.9Cs [m] [cd/m2]

UgI1 = Lmin/Lmax = ________%

Observer on the Y = + Lw(3/2) m X= L= 0.0 0.1Cs 0.2Cs 0.3Cs 0.4Cs 0.5Cs 0.6Cs 0.7Cs 0.8Cs 0.9Cs [m] [cd/m2]

UgI2 = Lmin/Lmax = ________%

Observer on the Y = + Lw(15/6) m X= L= 0.0 0.1Cs 0.2Cs 0.3Cs 0.4Cs 0.5Cs 0.6Cs 0.7Cs 0.8Cs 0.9Cs [m] [cd/m2]

UgI3 = Lmin/Lmax = ________%

Tandatangan Pengilang

Tandatangan Kontraktor Elektrik

Cop Pengilang

Cop Kontraktor Elektrik

Nama:

Nama:

Jawatan:

Jawatan:

SPECIFICATION FOR ROAD LIGHTING INSTALLATION Hak Cipta :1999 Cawangan Elektrik JKR Malaysia

42/49

L-S20 (August 1999) APPENDIX D2-1

TABULATED SUMMARY OF LIGHTING LEVEL CALCULATION/DATA (LUMINANCE) FOR ROAD LIGHTING INSTALLATION

PROJEK :

NO. RUJUKAN : PKR(L)

Luminaire Brand / Model No. : .

Please key in the results from the computer print-out or exact calculated values into the table below.
Luminance (cd/m2) GLARE Uo = (Lmin/Lav) (Lmin/Lmax) Ul = THRESHOLD INCREMENT MOUNTING HEIGHT (m) SPACING (L av) 2 (cd/m ) (L min) (cd/m2) (L max) (cd/m2) SR SURROUND RATIO COMPUTER CALCULATION NUMBER

VARIOUS ROAD

CROSS-SECTIONS/

WATTAGE

JUNCTIONS NUMBER#

NOTES:-

1. The Tenderer shall provide the required data for all sections/junctions of the Road Lighting Installation.

2. The Tenderer shall make duplicate copies of this Form to be filled as necessary.

3. The coss-sections/junctions numbers are given in the Tender Document.

Tandatangan, Nama, Alamat dan Cop Pembekal :

Tarikh : .

Tandatangan, Nama, Alamat dan Cop Kontraktor Elektrik : .....................................................................

SPECIFICATION FOR ROAD LIGHTING INSTALLATION Hak Cipta :1999 Cawangan Elektrik JKR Malaysia

43/49

L-S20 (August 1999)

APPENDIX D2-2

TABULATED SUMMARY OF LIGHTING LEVEL CALCULATION/DATA (ILLUMINANCE) FOR ROAD LIGHTING INSTALLATION.

PROJEK :

NO. RUJUKAN : PKR(L)

Luminaire Brand / Model No. : ..

Please key in the results from the computer print-out or exact calculated values into the table below.
Illuminance (lux) WATTAGE MOUNTING HEIGHT SPACING (m) (E av) (E min) (E max) Uo= Ug= Emin/Eave Emin/Emax COMPUTER CALCULATION NUMBER

VARIOUS ROAD

CROSS-SECTIONS/ JUNCTIONS #

NOTES:-

1. The Tenderer shall provide the required data for all sections/junctions of the Road Lighting Installation.

2. The Tenderer shall make duplicate copies of this Form to be filled as necessary. 3. The cross-sections/junctions numbers are given in the Tender Document.

Tandatangan, Nama, Alamat dan Cop Pembekal :

Tarikh :.

Tandatangan, Nama, Alamat dan Cop Kontraktor Elektrik : .....................................................

SPECIFICATION FOR ROAD LIGHTING INSTALLATION Hak Cipta :1999 Cawangan Elektrik JKR Malaysia

44/49

L-S20 (August 1999)

APPENDIX E TECHNICAL SCHEDULE OF COLUMNS AND BRACKET ARMS


ITEM DESCRIPTION DATA

COLUMN a Name of manufacturer b Address & country of manufacturer/fabricator of column c Type of column Hot-Dipped Galvanised Steel / * Pre-Stressed Spun Concrete /* *Delete whichever not applicable. Fibreglass Reinforced Type 1/Type2* Others.* d Compliance with relevant section of BS 5649 (EN40)* *Delete whichever not applicable. ANSI C-136.20 & ASTM D 4923-89* Others (Specify)*............................... e Name of hot-dip galvanising company f Address & country of manufacturer of steel tubes g Galvanising standards & minimum. weight per m2. (g/ m2) h Overall height of column (m) i Tapering ratio j Weight of columns (kg) - Whole Upper section Lower section k Thickness of steel column (mm.) / Concrete wall thickness (mm) l Name of company applying bituminous paint m Address of company applying bituminous paint n Dry film thickness of bituminous paint (mm) o Equivalent weight of bituminous coating per sq.m. (g/m2 ) p Longitudinal seam weld minimum penetration (%) q Reference standard of welding test (Latest relevant B.S.)

. T/t, Nama & Cop Pengilang

T/t, Nama & Cop Kontraktor Elektrik ...cont. pg. 46/49 APPENDIX E

SPECIFICATION FOR ROAD LIGHTING INSTALLATION

Hak Cipta :1999 Cawangan Elektrik JKR Malaysia


45/49

L-S20 (August 1999)

TECHNICAL SCHEDULE OF COLUMNS AND BRACKET ARMS


ITEM DESCRIPTION DATA

BRACKET ARM a Name of manufacturer b Address & country of manufacturer c Material of bracket arm d Name of hot dip galvanising company e Bracket arm projection (m) f Grade of steel used/standards complied g Weight of bracket (kg) h Thickness of steel bracket (mm)

. T/t, Nama & Cop Pengilang

T/t, Nama & Cop Kontraktor Elektrik

SPECIFICATION FOR ROAD LIGHTING INSTALLATION

Hak Cipta :1999 Cawangan Elektrik JKR Malaysia


46/49

L-S20 (August 1999) APPENDIX F

VOLTAGE DROP CALCULATION FOR THE ROAD LIGHTING INSTALLATION

PROJEK :

FEEDER PILLAR No. (To be filled for each Feeder Pillar) :

REFERENCE DATA :-

LUMINAIRES WATTAGE : .. CURRENT (Amps.) PER LUMINAIRE : . CABLE SIZE AND TYPE : ..

VOLTAGE DROP FOR THE ABOVE CABLES.


Please insert the data below for each phase. (Refer Tender Drawings) QTY* TOTAL WATTS (Volts) VOLT DROP CATATAN TOTAL

CIRCUIT

ITEM

No.

PHASE

Circuit 'a'

Circuit 'b' (if any)

Circuit 'c' (if any)

R Y B R Y B R Y B Tandatangan, Nama, Alamat dan Cop Kontraktor Elektrik:


........................................................................... ........................................................................... ...........................................................................

NOTES :-

1. The total voltage drop along the one complete circuit for each phase must not exceed 20 volts.

2. The Tenderer shall attach together with this Form the complete voltage drop calculation.

3. All calculation shall be in accordance with the Tender Drawings.

4. * - State the quantity of luminaires in this particular circuit.

Tarikh : .......................................

SPECIFICATION FOR ROAD LIGHTING INSTALLATION

Hak Cipta :1999 Cawangan Elektrik JKR Malaysia


47/49

L-S20 (August 1999) APPENDIX G SERVICE AND MAINTENANCE FOR THE ROAD LIGHTING SYSTEM (For use during the Defects liability Period) PROJEK : NO. RUJUKAN : PKR(L) Period of Service and Maintenance : ( /.../.. to /.../.... ) (dd/mm/yyyy) Schedule of work to be carried out at 3 monthly intervals. ITEM A COLUMNS
(Please specify column number/circuit under REMARK' for any defects found)

DESCRIPTION

ACTION

REMARK

1 Column Number or circuit label 2 Ensure all columns straight 3 Ensure all service door covers intact 4 Replace missing service doors 5 Clear debris around base/foundation 6 Check Labels present and clean 7 Check for column damage 8 Others (please specify) B BASE SECTION - CABLE TERMINATION 1 Check all cable termination for signs of loose contact and corrosion 2 Clean and tighten where necessary 3 Replace faulty MCBs, junction boxes for each column C LUMINAIRES 1 Check functionality 2 Replace faulty lamp ...cont. pg. 49/49
SPECIFICATION FOR ROAD LIGHTING INSTALLATION

Hak Cipta :1999 Cawangan Elektrik JKR Malaysia

48/49

L-S20 (August 1999) APPENDIX G SERVICE AND MAINTENANCE FOR STREET LIGHTING SYSTEM (For use during the Defects liability Period) PROJEK : Period of Service and Maintenance : ( ./...../... to ./...../...... ) (dd/mm/yyyy) Schedule of work to be carried out at 3 monthly intervals. ITEM DESCRIPTION 3 Replace faulty ignitor 4 Replace faulty capacitor 5 Replace faulty ballast 6 Clean luminaire bowl (once in 12 months) D FEEDER PILLARS 1 Check and clean Feeder Pillars - both internally and the surrounding area. 2 Check and replace faulty components MCBs, timeswitches, relays, cabling, luminaires, contactors, changeover switch, etc. E TESTING AND RECORDS 1 Test system/installation and record all test results, inspection and work done ACTION REMARK

PERAKUAN KONTRAKTOR ELEKTRIK Kami mengaku telah melaksanakan kerja-kerja penyelenggaraan seperti tercatit dalam kedua-dua muka surat borang Appendix G. Adalah disahkan kerja-kerja di atas telah dilaksanakan dan perkara-perkara bertanda **(asterisk) perlu/akan diambil tindakan oleh Kontraktor Elektrik

Tandatangan Kontraktor Elektrik : Nama : Alamat & Cop rasmi : Tarikh :


SPECIFICATION FOR ROAD LIGHTING INSTALLATION

Tandatangan Pegawai JKR : Nama : Jawatan :

Tarikh :

Hak Cipta :1999 Cawangan Elektrik JKR Malaysia

49/49

You might also like