RACI Chart (Roles and Responsibilities Matrix) : Process Name / Description
RACI Chart (Roles and Responsibilities Matrix) : Process Name / Description
Date
Note all team members/functions who developed and agreed to this RACI
Function A
First Responsibility Second Third Fourth Fifth Sixth
Function B
Function C
Function D
Function E
Plant maintenance project: Repair and resurface plant parking lot during plant shutdown in July
Jan-12
Revision:
4/1/2012
Kelly Bradley (facilities mgr), Mike Cole (plant manager), Joe Pallino (HR), Brian Sullivan (security), Billy Ownens (project manager)
Facilities Mgr Identify a minimum of three asphalt contractors from Angie's List Arrange for contractor visits and quotes Review quotes and references, make contractor selection Review and finalize contract, lock in plant shutdown week Provide security gate access codes for asphalt crew by June 15 Communicate project to shutdown maintenance crew, make sure all vehicles are removed from the lot Provide security gate access codes for asphalt crew by June 15 Oversee the project during the plant shutdown week, ensure it is completed on time C I A I I I
Plant Mgr I I I
HR I A R
Security R I
Project Mgr R R R R I I