Delay Reporting Sheet

The document is a table listing 25 reasons for delays in a construction project. It provides the description of the delay, date reported, how it was reported, date resolved, and number of pending days for each issue. The delays range from 1 to 61 days with issues including excavation work stopped due to neighborhood requirements, extra time needed for excavation and additional work, design issues, and delays in invoice processing and payment.

Uploaded by

Muhammad Waqas
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
221 views3 pages

Delay Reporting Sheet

The document is a table listing 25 reasons for delays in a construction project. It provides the description of the delay, date reported, how it was reported, date resolved, and number of pending days for each issue. The delays range from 1 to 61 days with issues including excavation work stopped due to neighborhood requirements, extra time needed for excavation and additional work, design issues, and delays in invoice processing and payment.

Uploaded by

Muhammad Waqas
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 3

202 S.

No Description / Reason for Delay Date of Submission / issue reported on 5-May-13 issue Reported Issue via Resolved on Pending Days

Excavation Work stopped on instructions of Al-Rumaih as per requirement by neighbors

official letter

11-May-13

2 3 4 5 6 7 8 9 10 11

Extra Time consumed during excavation stage Extra work for perforted pipes Ramp design issue Floor Trench at B-1 location and detailing Checking of R/F for B-1 Slab (Ceiling of B-2) Invoice # 2 submitted on 2-Nov-2013 , paid on 23-Nov-2013 (7-10 days for process time) Invoice # 3 submitted on 18-Dec-2013 , paid on 15-Jan-2014 (7-10 days for process time) Invoice # 4 submitted on 04-Feb-2014 , paid on 23-Feb-2014 (7-10 days for process time)

1-May-13 14-Jul-13 12-Mar-14 6-Jan-14 11-Jan-14 12-Nov-13 28-Dec-13 14-Feb-14

official letter official letter in person email RFI official letter official letter official letter

30-Jun-13 26-Aug-13 1-Apr-14 10-Jan-14 15-Jan-14 23-Nov-13 15-Jan-14 23-Feb-14

61 44 21 5 5 12 19 10 1 1

12 13 14 15 16 17 18 19 20 21 22 23 24 25

1 1 1 1 1 1 1 1 1 1 1 1 1 1

26 27

1 1 202