If the flange is required to connect the output shaft of an electric motor to a shaft of a centrifugal pump. The motor delivers 20 KW power at 720 r.p.m. The starting torque of a motor can be assumed to be 130% of the started torque. It is required to design the bolts and the flange, if the number of bolts are 4 and its allowable shear & compressive stresses are 35 N/mm2 & 100 N/mm2 respectively, while the flange allowable shear stress for the flange material is 20 N/mm2
P.T.O
1|Page
Question 3: A multiple disk clutch has the following specification Number of discs on driven shaft = 2 Number of discs on driving shaft = 3 Coefficient of friction of lining material = 0.25 Inner diameter of lining material = 20 cm Outer diameter of lining material = 28 cm Maximum intensity of pressure = 0.85 kg / cm2
The power transmitted is 40 HP at 1500 r.p.m and should allow for an over load 20%.calcuate the axial force required to engage the clutch and check if this clutch could withstand the applied torque Question 4: A machine shaft running at 600 r.p.m is supported on bearings as shown in figure below.15 KW is supplied from the shaft through a spur gear located 250 mm to the right of the left bearing. The tangential force (ft) on the gear is 2400 N while the radial force (fs) is 870 N. The belt drive is 60o above the horizontal, the pulley weights 800 N. The ratio of belt tensions
2
material selected has an allowable shear stress of 70 MN /m .determine the necessary diameter. Use Kb = 1.5, Kt = 1.0
2|Page