Cycling Articles
Cycling Articles
Cycling operations, that include on/off startup/shutdown operations, on-load cycling, and high frequency MW changes for automatic generation control (AGC), can be very damaging to power generation equipment. This is especially true when the plants have not
Steven A Lefton is a chemical engineer with extensive experience (30 years) in USA and European design power plant operations, startup, costs, cost analysis, testing, life assessment, chemistry, maintenance and reliability.
exibility, faster MW response and improved protability. WHY ANALYZE CYCLING DAMAGE AND COSTS? Knowledge of operating costs in real-time is critical to the competitive power business. During high prot times, operators should be able to respond faster to changes in load while at the same time operating at or above the units maximum rating. During low power price periods, an operator must decide to either shutdown and incur signicant cycling damage or to operate at minimum load. Other questions include: What, in terms of fuel costs and cycling costs, is the least expensive combination of units to meet system load? Can I reduce the cost/price of base-load power in a long-term power sales contract? How much savings is there if I reduce the number of unit cycling operations? Does one maintain plant equipment on the basis of operating time, or on the basis of number of accumulated cycles? Passing the high cost to cycle power plants on to competitive utilities, by not cycling on/off or going to two-shift operation for specic units with low cycling costs, is an effective competitive strategy when cycling costs are analyzed. ANALYSIS AND DAMAGE MODELING APTECH has analyzed the cycling costs in more than 300 power-generating plants, including more than 250 American units, 20 Canadian units and 16 European Union units. The units have included 15 MW to 1300 MW coal, oil, and gas red units with sub critical drum-type and supercritical once through Benson type boilers with varying turbine, boiler, and balance of plant manufacturers. All of the units had a range of designs and operational regimes. Some were designed for cycling with European style turbine bypass systems, plants designed for base-loaded operations and units subjected to heavy cyclic operations. Many of the units were being operated at or above the units maximum continuous rating operation (MCR). Although running a plant above MCR may be costly, it can save a rapid costly start up on another unit in the eet. Regardless of type, each unit in the eet should have its cost analyzed so that the utility can dispatch a unit with similar cost.
Philip M. Besuner is a reliability engineer. He as a MS in mechanical engineering with special emphasis on fracture mechanics and probabilistic statistical modeling and analysis of power plants and their components/failures/ remaining life and costs.
Figure 1: Cumulative tube leaks versus unit starts for a 600 MW coal-red unit
been designed for cycling operations. A comprehensive analysis conducted on more than 150 coal-red units has shown that the nancial costs associated with cycling operation are very high. An analysis of selected older coal-red plants has found them to be more rugged and cost effective to cycle than the newest combined cycle units. Low fuel prices are another advantage of coal. Making the decision to cycle coal-red units should be carefully considered, as there are numerous long term effects, component damage and signicant costs that need to be carefully calculated. The true cost of on/off, load cycling and high load operations of 90-120 percent of rated capacity are often not known or not well understood by utility operators. Even when a unit is designed for cycling, there are external effects in the balance of plant design, water chemistry, pulverizer and coal/ash types. To optimize operations and determine the true cost of each operation, cycling of units should be subjected to a thorough analysis of their cycling operations. Utilizing this knowledge, a power plant is able to signicantly reduce costs, have more operational
16
DAMAGE MECHANISMS OF CYCLING Denitions of cycling have varied from on/off starts, (normally dened as hot, warm, and cold starts) and two-shifting to load cycling and high frequency load variations. Inclusion of all cyclic operations is critical to proper analysis. Many units have only a few starts, but provide a large amount of intra hour load following and AGC services. However, this can signicantly add to a units cyclic damage. Hot starts are typically dened to have very high, 700F to 900F , boiler/turbine temperatures and less than 8 to 12 hours off-line. Warm starts have boiler/turbine temperatures of 250F - 700F and are off-line for 12 to 48 hours. Cold starts are ambient temperature starts, with boiler turbine temperatures below FATT fracture appearance transition temperatures, 250F or less, and have 48 to 120 hours off-line. These denitions may vary due to unit size, manufacturer and dispatcher/Independent System Operator (ISO) denitions. Damage manifests itself in terms of known past and future maintenance and capital replacements, forced outages and deratings from cycling. It can also result from high load operation. Often the damage mechanism is fatigue and corrosion of the boiler tubes. Boiler tube damage, from cycling operations on a constantly red cyclone red boiler, is shown in Figure 1. Replacement of major plant components versus cycles and operating time are shown in Figure 2. The time to failure from cycling operation in a new plant can be from 5 to 7 years and in older plants ninemonths to two-years after start of signicant cycling.
To optimize operations and determine the true cost of each operation, cycling of units should be subjected to a thorough analysis of their cycling operations.
METHODOLOGY: CALIBRATING DAMAGE TO COSTS The vast number, of unit types, equipment manufacturers, balance of plant types, and operational regimes makes the cycling costs difcult to categorize. However, damage models have been developed that include creep and fatigue and their interaction for each unit type, pressure range and temperatures. These models account for cyclic operation, baseloaded operation, and operation above MCR. The models are calibrated with plant signature data (temperatures and pressures) for key unit components
operating during typical load transients. Damage model validation process includes the assessment of key components with nite element analysis and creep/fatigue analysis methods. By utilizing these models, it is possible to determine the remaining useful component life. Life cycle analyses of key high cycling cost components are statistically calibrated to the failure history of the components. All of the damage is calibrated to actual plant costs. Traditionally, un-calibrated engineering fatigue and creep analyses are rarely useful, and are often misleading in predicting cycling costs. Critical components wher detailed plant signature data is analyzed include: Steam drum Water wall /evaporator tubing First/second pass water wall tubing Superheater and reheater tubing and headers Economizer inlet Start up system components In addition, analysis is carried out for the turbine/ generator-related components: Valves, cases, generator windings and steam chests. The maximum temperature ramp rate and the overall range of temperature change experienced by a component during the transient are key indicators of cycling-related creep and fatigue damage. All of the parameters are used to quantify the severity of each units load, start up, and shut down transients. Signature data is also used in evaluating and troubleshooting a units cycling operations. Using this information, the operators are able to determine the recommended temperature for the ramp rate limits for the superheater and economizer during all types of start up, and shut down and cooling. With this information the operators are able to minimize damage, maximize the assets life and reliability while reducing maintenance costs. cONTINue TO NEXT paGe
17
cONTINueD fROm pReVIOus paGe Signature data is utilized by APTECH to calibrate its cost control of operations and maintenance program. This real-time code displays temperature ramp rates in key components and alerts the operators of excessive ramp rates. Ramp rates that should not be exceeded are displayed in green (OK), yellow (caution) and red (high damage do not exceed). It also calculates the wear and tear/cycling costs of the startup, load change, or steady state plant operation Figure 3. Damage modeling is combined with historical capital maintenance spending and unit loading over time, to derive cost per unit-specic typical load cycle. Typically, annual capital and maintenance spending information for a minimum of seven years, is evaluated. Costs not related to unit operation are not used. An example of total (raw) screened (candidate) and smoothed cycling costs for a large power plant is shown in Figure 4. Hourly MW data is evaluated, for the same period, and based on correlation of MW output to historical capacity factors, starts and total annual generation, is generally extrapolated back in time to the units startup date. One-minute MW data is analyzed for
18
several typical months of operations when the unit provides automatic generation control, MVAR, and voltage support. Outage data and availability, plus outage cause code data, is evaluated for the entire operational period since unit startup. CYCLING COSTS The overall range of cycling costs, compared with commonly assumed costs is shown in Figure 5. This includes all cycle types of hot, warm, and cold starts for the three types of small drum and large supercritical boilers. The units specic analysis results depend on the regression analysis of the costs versus cycles and the unit signature data during cyclic operations at all load changes. The increased incremental costs attributed to cycling fall into the following categories: Increases in maintenance and overhaul capital expenditures Forced outage effects, including forced outage time, replacement energy, and capacity Cost of increased unit heat rate, long-term efciency and efciency at low/variable loads Cost of startup fuels, auxiliary power, chemicals and additional manpower required for unit startup cONTINue TO NEXT paGe
cONTINueD fROm pReVIOus paGe Long-term generation capacity costs increase due to a shorter unit life. Measurement of unit heat rate cycling, while at steady state indicates there is signicant degradation in unit heat rate when power plants cycle extensively. Poor efciency is due to low load operation, load following, unit startups and unit shutdowns. The cumulative long term effects of cycling can increase the unit heat rate due to fouled heat exchangers, warn seals and wear/tear on valves and controls. The resulting cost increase for a base-loaded plant is signicant. REDUCING CYCLING COSTS As a result of the analysis of the signature data during cycling operations, recommendations are made for operational changes, chemistry improvements and hardware additions and/or modications. Operational changes consist of modifying temperature ramp rates of key components. To increase unit response and minimize damage and costs, it is recommended that the on-line ramp rates be increased by a factor of 2 to 10. This is accomplished by decreasing the ramp rate during cold and warm startup/shutdown operations. Startups and rapid shutdowns are generally the most
20
Page 1 of 12
August 1, 2011
http://www.powermag.com/print/issues/features/Make-Your-Plant-Ready-for-Cycling-Ope... 8/11/2011
Page 2 of 12
1. Common problems in cycling plants. A survey of 215 steam plants found many common equipment problems. Source: Intertek-Aptech
Locating Failures
Failures in coal plant equipment caused by frequent cycling are not isolated events but often occur at unexpected times throughout a plant. Many of the failure modes and locations are not unexpected, but others may be surprising even to an experienced plant operator. Prevention of these failures or managing failure rates is key to success. One approach to reducing cycling damage is to modify the units low-load limit to prevent cycling damage. By reducing the low-load limit on a 750-MW supercritical gas-fired unit from 150 MW to 28 MW at night, it was possible to make the daily cycling load profitable, but it was no small task. The following subsections are provided to give you a sense of the magnitude of systems and components within a typical coal-fired plant designed for baseload operation that are affected by cycling and load-following service. Although they are not listed separately, controls are also affected; some plants must upgrade old analog controls to digital controls in order to improve response to remotely supplied automatic generation controls before they are capable of cycling. Steam Turbine Generators. The life of a steam turbine is directly related to thermal transients experienced over time. In fact, the typical steam turbine startup ramp rate is well-defined by the manufacturer, as there are limits to the heating rates of the rotating parts. Steam turbines require slow temperature changes to manage the thermal stress in their heavy metal components (Figure 2).
http://www.powermag.com/print/issues/features/Make-Your-Plant-Ready-for-Cycling-Ope... 8/11/2011
Page 3 of 12
An essential design element of a reliable cycling unit is a steam bypass system. When in operation, high-temperature steam is pressure-reduced and cooled by mixing condensate with the hot steam in a desuperheater and then bypassed around the steam turbine to the condenser. Additional steam bypass to the condenser often requires condenser modifications. In some steam turbine designs, the steam seals may need to be replaced to prevent steam flow from bypassing the rotor stages or sections. Finally, an electric heated turbine blanket system may be beneficial during hot restarts to reduce thermal stress and distortion, ensuring a quicker start. Boiler. In the superheater section, damage to tubing is usually caused by overheating that results from low or no flow of cooling steam through the tubes during startup and/or poor combustion gas temperature management. Damage to superheater tubing is usually evident by severe bowing and thermal distortion due to overheating damage of tubes fully exposed in the gas path. Also, superheater tube damage can result from condensate, and stagnate or reverse steam flows during startup. Similar overheating damage often occurs in reheater tubing (Figures 3 and 4).
http://www.powermag.com/print/issues/features/Make-Your-Plant-Ready-for-Cycling-Ope... 8/11/2011
Page 4 of 12
3. Tube bending. Thermal forces bowed and permanently bent this boiler superheater tubing, including the water-cooled support tube and clips. Courtesy: Intertek-Aptech
4. Breaking bad. Corrosion fatigue damage in the steam-cooled wall in the heat recovery area is evident in this photo. The steam-cooled sidewall has a damaged economizer header penetration. Cycling caused differential thermal growth, and the penetration is badly damaged. Note the numerous repair welds and the broken and missing refractory caused by thermal growth. Courtesy: Intertek-Aptech
The effects of cycling the steam generator usually materialize as stress cracking in the waterwall tubing at attachments like the windbox, corner tubes, and wall box openings. Stress cracking in the waterwall tubing at the buckstay attachments is usually caused by nonuniform thermal movement of the boiler and its support system (Figures 5 and 6).
http://www.powermag.com/print/issues/features/Make-Your-Plant-Ready-for-Cycling-Ope... 8/11/2011
Page 5 of 12
5. Wobbly walls. Outside the boiler we see the thermal damage in supports. The photo shows thermal damage on the boiler support structure, specifically the sidewall buckstay at the windbox attachment. Courtesy: Intertek-Aptech
http://www.powermag.com/print/issues/features/Make-Your-Plant-Ready-for-Cycling-Ope... 8/11/2011
Page 6 of 12
6. Bending corners. Boilers are typically rectangular boxes rather than round or spherical. This photo shows waterwall corrosion fatigue damage at the lower furnace seal and attachment of the front wall vee bottom to the sidewall, showing weld repairs. It is an example of cycling damage at a corner or a change in shape. Courtesy: Intertek-Aptech
Although temperature levels are much lower in the economizer, thermal damage can still occur there. Economizer tube failures are usually caused by thermal shocking of the inlet header and tubing with relatively cold water, often during startup. Corrosion may also occur in areas of the economizer where cold water reduces the metal temperature (structure or tubing) below the acid dew point of the stack gas during low-load operation. When the stack gas is reduced below the acid dew point, the minute portions of sulfur that remain in the gas can combine with the condensed moisture and form dilute solutions of very corrosive sulfuric acid on tubes and structures. In addition to boiler design- and operation-caused tube failures, poor boiler water chemistry control can be a contributing cause. In some plants, the entire water chemistry program must be reformulated to optimize remaining boiler tube life. Often, the key to reducing waterwall tube wastage is simply using a nitrogen blanket over the internal tube wetted surfaces when the boiler is removed from service or draining it. Also consider a nitrogen blanket in the condensate storage tank to minimize the oxygen content in the condensate during starts. In heat recovery steam generators (HRSGs), the typical cycling problems can be traced back to superheater and reheater drains that fail to clear accumulated condensate. Flow-accelerated corrosion (FAC) in the low-pressure
http://www.powermag.com/print/issues/features/Make-Your-Plant-Ready-for-Cycling-Ope... 8/11/2011
Page 7 of 12
evaporator and failure of feedwater heaters from thermal shock and FAC also are often found (Figures 7 and 8).
7. Inflexible headers. Reheater outlet header and tube-to-header weld fatigue damage at the end of the header is shown. The high-stress location is the short run of tubing where the tube cracked, due to low tube flexibility. The stress is a result of thermal loading and deflection during startup cycles. Courtesy: IntertekAptech
8. Leaky heaters. This HRSG feedwater heater tube was one of many failures that resulted from cold-end corrosion during cycling. There were numerous leaks at the
http://www.powermag.com/print/issues/features/Make-Your-Plant-Ready-for-Cycling-Ope... 8/11/2011
Page 8 of 12
Fuel Systems. Coal pulverizers are prone to fireside explosions, especially when using western coals. They require careful fuel purging and the addition of an inert gas blanket (inerting) when they are cycled off-line. Also, pulverizers are prone to much increased mechanical wear when they are cycled or operated at the low end of their design minimum flow rates. (For more information on proper operating and maintenance of coal pulverizers, see Blueprint Your Pulverizer for Improved Performance, March 2009 and To Optimize Performance, Begin at the Pulverizers, February 2007 in the POWER archives at http://www.powermag.com.) Another unanticipated consequence of cycling a solid-fuel plant is the additional maintenance required on the coal silos. When burn rates are difficult to predict, the holding time of western coals in silos can extend beyond six or seven days, the maximum time considered safe. Longer storage of western coals often causes an increase in the frequency of hot spots and fires inside the coal silos. The same safety issues apply to coal pile management and inventory control, as burn rates constantly change due to plant load cycling or low-load following. Air and Gas Systems. The forced and induced draft fans on coal-fired units can range from a few hundred to well over a thousand horsepower. Frequent starting and stopping of the fansand, just as importantly, the motors that drive the fanswill increase failure rates, inspection intervals, and motor-fan maintenance. In some cases, fans have required retrofit of new drive systems for soft or low-stress starting. Additionally, air heaters and baghouses are subject to wet gas corrosion, plugging, and damage caused by operating below the wet gas dew point during low-load operations. Water Systems. It may seem counterintuitive, but makeup water consumption greatly increases for a cycling unit because of the large amounts of water used during startup. In fact, its possible that the plants demineralized water supply and water storage may need to increase to support the increased boiler water usage. The entire feedwater system is affected by thermally cycling plants. For example, feedwater heaters are subject to cooldown and rapid heating during a hot or warm startup cycle, and this often leads to early tube failures. Boiler feed pumps are normally designed for full-load operation and experience accelerated wear when operated at low loads. Also, boiler feed pumps may be required to stop and start several times for one startup cycle, thus causing many feedwater transients. In some plants, a smaller, low-load feedwater pump may be necessary for a cycling unit to limit damage to the main feedwater pumps. In others, boiler feedwater and condensate pumps may require added recirculation capability, and the economizer may require recirculation to keep exit water temperatures in check. Combustion Turbines. Gas-fired combined cycles may be quick-acting in comparison with a coal-fired plant, but they are not immune to the same thermal stressrelated equipment damage described above. Based on our experience with combined cycle plants, we have found that the largest line item on a plants operating and maintenance budget is costs related to cycling. One reason cycling costs are proportionally higher in combined cycles is that turbine inspection and repair intervals are transitioned to being principally based on numbers of starts rather than operating hours. Therefore, the cost to maintain combined cycle availability is high on a per-unit-of-electricity-produced basis. The cost of replacement parts found damaged during overhauls, or parts fallout due to cycling, is often a factor of two or more over the plant life compared with baseload operation.
http://www.powermag.com/print/issues/features/Make-Your-Plant-Ready-for-Cycling-Ope... 8/11/2011
Page 9 of 12
http://www.powermag.com/print/issues/features/Make-Your-Plant-Ready-for-Cycling-Ope... 8/11/2011
Page 10 of 12
included in that specific claim and contrasts common rules of thumb with hard data. Table 2 summarizes the estimated cycling costs for a 500-MW conventional coal-fired plant developed as part of a recently completed cycling study. The estimates developed using the approach described in the following sections were several times larger than customers estimates.
Table 1. Cost to cycle a unit, per operation. The true cost of cycling a unit is often much larger than the estimates used by many plant operators. Source: Intertek-Aptech
Table 2. Typical cycling costs for a 500-MW coal-fired power plant. Costs are shown in 2008 dollars. Source: IntertekAptech
Cost-of-Cycling Estimates
The Intertek-Aptech staff has developed two approaches to developing cycling cost estimates, such as the one summarized in Table 2, so that results can be compared and validated: the top-down estimate and the bottom-up estimate. Unit- and plant-specific information and industry data on similar units are also used in these analyses. Top-Down Estimates. Top-down estimates use historical unit operating data and historical cost data to determine the costs of cycling operations (hot, warm, and cold starts and shutdowns; load following; and ancillary services such as
http://www.powermag.com/print/issues/features/Make-Your-Plant-Ready-for-Cycling-Ope... 8/11/2011
Page 11 of 12
regulation and ramping). Fundamentally, we take wear and tear costs and other cycling-related costs and statistically determine the costs of cycling using detailed multivariable regression techniques that examine cost versus total cycling damage. The first step to determining operating costs is to examine the actual validated plant maintenance costs, primarily found in work orders. The costs we take into account include the operating, maintenance, and capitalized maintenance costs incurred by the unit, while those unrelated to equipment maintenance are eliminated. Other cycling -related costssuch as the cost of fuel and chemicals for water treatment used for startups, and costs related to the increased outages caused by cyclingare also accounted for. These costs are then analyzed, processed, and tallied to create annual candidate cycling costs for the unit. All of these costs are candidates for our analyses, which determine the relationship between costs and the units total cycling operational damage. The second step is to add cycling damage to the maintenance cost estimates. The damage the unit accumulates from cycling is determined by examining the plants operating records. Specifically, the hourly average power output of the units generator is analyzed to count cycles (all types of cycling and load-following) and determine the historical damage that the unit has accumulated versus baseload operation. We calibrate the damage during load transients and starts to plant signature data obtained during typical transients and starts. Finally, we take the accumulated damage and historical costs to calculate a statistical best estimate of the cycling costs and calculate the upper and lower bounds using statistical regression techniques. In sum, we develop probabilistic estimates of the effects of cold, warm, and hot starts; shutdowns; and load-following operating modes. We prove these estimates are valid by backcasting historical costs as a function of cycling costs. We know past costs are the best predictors of future costs when unit cycling remains constant. However, a significant increase in cycling and ramp rates can significantly accelerate equipment damage and increase future costs. Bottom-Up Estimates. The other cost-estimating process is the bottom-up analysis. It is referred to as a bottom-up because it starts with the detailed work order history and a review of failure events and analysis completed earlier. The bottom-up review includes seven to 10 years worth of plant work orders, when available. The review includes a detailed analysis of work orders by a subject matter expert (SME), often including the plant personnel, to classify the costs as either related to cycling or to normal plant (baseload operation) costs. Actual failure reports, overhaul records, and prior inspection reports are also checked to determine the root cause of previous failures so that the costs can be properly classified. This analysis uses actual plant signature data from representative starts and shutdowns and gives consideration to known design and operations issues. Load-following and actual plant ramp rates are examined, including the absolute temperature change from carefully selected data points to validate the type of damages.
http://www.powermag.com/print/issues/features/Make-Your-Plant-Ready-for-Cycling-Ope... 8/11/2011
Page 12 of 12
Develop startup and shutdown procedures, and ensure that operators adhere to them, so that desired operating results are achieved and are repeatable. Perform a comprehensive cost-of-cycling study to develop a specific set of cost-justified modifications and target cycling countermeasures with a known payback. Many items identified in the cost-of-cycling study can be implemented immediately and at low cost, such as revised operating procedures or control system modifications. Employ a cost-monitoring system, such as Intertek-Aptechs COSTCOM (Cost Control of Operations and Maintenance or Cost COMmunication) real-time software, to alert operators when the plant is using a damaging ramp rate or operating mode, and then display real-time costs to operators. Keep offline time short and the equipment hot to reduce cold starts, especially with the boiler/heat recovery steam generator.
http://www.powermag.com/print/issues/features/Make-Your-Plant-Ready-for-Cycling-Ope... 8/11/2011
Page 1 of 8
August 1, 2011
http://www.powermag.com/print/issues/features/Mitigating-the-Effects-of-Flexible-Operat... 8/11/2011
Page 2 of 8
growth. Since 1980, power producers have opted to build large-capacity, more-efficient units with supercritical steam conditions, which are also designed for baseload operation. New duty cycles force baseload plants and equipment to operate closer toor beyondnominal design limits and through more thermal cycles than originally anticipated. The operational impacts of flexible operation cited earlier result in significantly increased occurrences of thermal transients in the material of critical high-temperature boiler and turbine components. These transients, and other operational factors associated with flexible operation, have the following effects on coal-fired generating assets: Increased rate of wear on high-temperature components. Increased wear-and-tear on balance-of-plant components. Decreased thermal efficiency at low load (high turndown). Increased fuel costs due to more frequent unit starts. Difficulties in maintaining optimum steam chemistry. Potential for catalyst fouling in NOx control equipment. Increased risk of human error in plant operations. Additional wear on plant components requires increased spending on preventive and corrective maintenance. This requirement is often challenging to plants that are placed lower on the dispatch stack and that, therefore, receive less revenue and operating budget. Increased human error is due primarily to the increased amount of transient operation, which produces more opportunities for error. Major plant events caused by human error can result in costly equipment damage and related safety challenges.
Damage Mechanisms
Load following involves rapid increases and decreases in process temperatures, which create significant thermal stress on pressure boundaries. When plant loads change, the consequences are numerous: pulverizers or mills go off and on, furnace temperatures and heat profiles are altered, pollution control requirements change, and steam and flue gas velocities vary. All of these changes can force the unit to operate away from the original design point. A few important material damage mechanisms are responsible for the majority of the financial impacts caused by operating coal plants in flexible modes. The severity of the impact of these mechanisms can be mitigated to a certain extent through improved plant operation and process controls, but it is impossible to completely eliminate the reduction in major component life caused by flexible operation. Examples of these damage mechanisms follow. Thermal Fatigue. This phenomenon can produce cracking in thick-walled components, especially castings such as turbine valves and casings. Also affected are boiler superheater and reheater headers, where ligament cracking is commonly seen between tube stubs. These headers are expensive, thick-walled vessels operating under high steam pressure, making this damage of particular concern to plant owners. Header cracking (Figure 1) is caused by frequent, large temperature swings associated with flexible operation and, in some cases, by thermal quenching produced either by condensate formed during idle standby or poorly controlled attemperator sprays (again associated with transient operation).
http://www.powermag.com/print/issues/features/Mitigating-the-Effects-of-Flexible-Operat... 8/11/2011
Page 3 of 8
1. Cracked header. Cold feedwater introduced to a hot header caused the crack in this economizer header. The cold water created a large through-wall temperature gradient change in temperature during startup and during off-line top-off opportunities. Courtesy: EPRI
Thermal Expansion. Several systems in a coal plant consist of components that undergo high thermal growth relative to surrounding components. The most important example of this phenomenon is the large movement of boiler structures relative to the cooler support framework. This part of a plant includes waterwall sections, gas ductwork, and the ties used to support superheat and reheat tubing. These support ties are designed to accommodate growth but are subject to accelerated life consumption if the frequency of thermal cycling increases. Differential expansion also contributes to tube-to-header cracking in superheaters and reheaters (Figure 2).
http://www.powermag.com/print/issues/features/Mitigating-the-Effects-of-Flexible-Operat... 8/11/2011
Page 4 of 8
2. Leaky tubes. Tube-to-header cracking caused by thermal transients is shown in this photo. Variation in tube thermal expansion, caused by differences in tube length, increases stress in some tubes. Courtesy: EPRI
Corrosion-Related Issues. Two-shifting, or any other operation that challenges the ability of a plant to maintain water chemistry, can lead to increased corrosion and accelerated component failure. Increased levels of dissolved oxygen in feedwater can be the result of condenser leaks, aggravated by more-frequent shutdowns. Other factors affecting chemistry include the increased need for makeup water and the interruption in operation of the condensate polishers and deaerators. Corrosion and fatigue can combine to accelerate damage to waterwalls (Figure 3).
3. Waterwall cracks. Waterwall damage caused by corrosion fatigue is often found in steam generators. Courtesy: EPRI
Fireside Corrosion. Load cycling and relatively quick ramp rates under staged conditions will have a negative impact on both fireside corrosion and circumferential cracking.
http://www.powermag.com/print/issues/features/Mitigating-the-Effects-of-Flexible-Operat... 8/11/2011
Page 5 of 8
Rotor Bore Cracking. When subjected to transients in the temperature of the admitted steam, the high-pressure and intermediate-pressure steam turbine rotors can suffer thermo-mechanical stress excursions, resulting in low-cycle fatigue damage. This damage can result either from introducing hot steam to a relatively cold rotor exterior, or the opposite. In both scenarios, the problem arises from the massive rotor forging and the resulting time required for the metal temperature difference between the rotor exterior surface and the inner (bore) region to equilibrate.
http://www.powermag.com/print/issues/features/Mitigating-the-Effects-of-Flexible-Operat... 8/11/2011
Page 6 of 8
With this in mind, EPRI worked with the 40 members of the EPRI Cycle Chemistry Technical Advisors Group to develop cycle chemistry guidelines for all transient operations and shutdowns. The guidelines include specific procedures and advice for cycling, shutdown, startup, and layup for each boiler and feedwater treatment; they also cover all major water- and steam-touched surfaces. Correct layup procedures, combined with appropriate chemical treatment during shutdown and startup, will significantly reduce corrosion and deposits in the steam cycle equipment, including the boiler, steam-touched tubing, and the turbine. Two-Shift Operating Practice. Changes in operational practices can be an effective strategy for mitigating cycling damage. Several years ago, EPRI studied worldwide experience with two-shift operation (usually weekday starts with overnight shutdowns) and found that economic two-shifting can be achieved with due care and application of sound engineering and operational practice. Among the findings: Many utilities have performed trials on two-shift operation to reduce startup and shutdown time. Generally, startup times can be nearly halved from original base-load procedures so that large machines can be synchronized within 35 to 50 minutes of inserting the first burnersdepending on unit size and configuration and full load can be achieved in similar times. A target time to full load on a 500-MW machine is approximately 60 minutes. Thermal transientsboth in the form of quenching and high rates of temperature risecan be avoided by carefully managing the unit when off-load and by adding engineered systems to alleviate the potential problems. In the United Kingdom, natural-circulation drum boilers have been fitted with off-load circulating systems to pump water slowly around the evaporative section to balance temperature variations. The aim is to eliminate flow stagnation and tube-to-tube temperature differences. In addition, interstage drains or vents have also been fitted to promote flow through the superheater stages and avoid quenching problems that may arise when cold condensate from platen elements is otherwise pushed into the relatively hot final superheater stages. A primary constraint on ramping operation is matching steam and turbine metal temperatures. Sliding pressure offers advantages over throttle control during startup by establishing a flow to the turbine earlier in the sequence, with lower overall heat input and by retaining high temperatures on shutdown. Mitigating SCR Issues at Low Load. To avoid problems with SCR units during low-load operation, conventional design practice calls for a flue gas or water-side economizer bypass to elevate the flue gas temperature at low load to a level high enough to allow reagent injection. However, many units are not equipped with economizer bypass capabilities. In these cases, operators have a number of options to comply with the minimum operating temperature: Evaluate actual SCR inlet operating conditions (NH3 and SO3 concentrations, and temperature distribution), and compare them with the SCR design conditions. Modify current operational practices (such as fuel sulfur content and NOx reduction levels at low load). Improve the SCR inlet temperature distribution by installing a static mixer. Independent verification is needed to show that catalyst activity will recover during higher-temperature operation after ABS formation at low load. To address this and related issues, EPRI is conducting a laboratory-scale test program to study ABS formation and evaporation in SCR catalyst. EPRI is also assessing the impacts of an economizer bypass and potential alternatives, determining the impacts of low load on catalyst deactivation for specific application, and developing guidelines to minimize the impacts on SCR operation and performance.
http://www.powermag.com/print/issues/features/Mitigating-the-Effects-of-Flexible-Operat... 8/11/2011
Page 7 of 8
Future Research
Two new EPRI research projects are planned to get under way this year.
http://www.powermag.com/print/issues/features/Mitigating-the-Effects-of-Flexible-Operat... 8/11/2011
Page 8 of 8
One project will coordinate plant field studies to demonstrate operational strategies for reducing the impact of twoshifting, ramping, and turndown on plant equipment. Multiple host units will allow the research to be conducted across a range of generating asset types and systems. The strategies will seek to reduce thermal transients experienced by components in the steam generating and turbine systems of coal-fired plants, and to manage impacts on environmental control equipment. The project will first apply cycle transient analyses to develop options and then run operational trials to refine processes. This strategy has been successfully demonstrated by power producers outside the U.S. A second project will develop guideline documents to help power companies successfully transition their fleets to flexible operation. The project will utilize existing EPRI research results on component-level cycling impacts and mitigation and will compile lessons learned and strategies used by organizations worldwide. Resources to be developed will include a Flexible Operation Readiness Guide, which will address the need to first assess equipment condition and organizational readiness for flexible operation duty; a Guidelines for Managing Flexible Operations; and a Primer on Fossil Plant Cycling for Power Marketing and System Operators. In addition to research aimed at existing coal units, EPRI will explore initiatives to define the design characteristics of the future coal-cycling unit. Some new European power plants have already been designed for flexible operation. Design changes for cyclic operation include installation of a turbine bypass, installation of more thermocouples and other monitoring equipment, modifications to standard boiler tube supports, upgrading the fan prime mover, use of variable-frequency drives on motors, and inclusion of bypass systems for use during startups. In the U.S., information on design characteristics for cycling units could be used in future procurement specifications in situations where the prime requirement is operating flexibility. Starting with a clean sheet of paper would be expected to yield significant improvements in unit flexibility. This research effort should start soon in order to be available for potential new-builds in the next decade. Steve Hesler ([email protected]) is program manager for EPRI Generation Fossil O&M. Close Window
http://www.powermag.com/print/issues/features/Mitigating-the-Effects-of-Flexible-Operat... 8/11/2011
Good Morning Im Gene Danneman, Operations Support Manager for Xcel Energy Supply and my co-speaker is Steve Lefton VP Power Division (Intertak Aptech Engineering Services). Xcel Energy, one of the nations largest utilities, owns a fleet of coal, gas, nuclear hydro, nuclear, hydro and wind plants that we must operate reliably reliably, economically and dispatch efficiently to meet system load requirements. I will be sharing some of the results of our Aptech Engineering Total Cost of cycling Analysis
Map illustrates the 8 states where we serve (in blue). gy was created in 2000 by y the merger g of Northern States Xcel Energy Power Company and Public Service Company of Colorado. Xcel Energy comprises four operating companies: NSP-MN (green) NSP-WI (yellow) Public Service Company of Colorado (red) Southwestern Public Service (gold) The company serves 3.4 million electric customers and 1.5 million gas customers.
The companys strategy involves delivering safe, reliable, affordable energy to its customers; And transforming the business through environmental leadership in 3 major ways: Advanced technology Energy efficiency Business innovation Last year, Xcel Energy began using a new tagline: RESPONSIBLE BY NATURE. It captures the approach for everything the company does: the responsibility to serve its customers, and to do so in an environmentally responsible way.
Xcel Energy is focused on its environmental responsibility, and that means building a clean energy future for its customers and the communities it serves. Through its environmental leadership, it is implementing business strategies that grow its position as one of the countries leading utilities for clean energy. Biomass: Xcel is retrofitting its coal-fired Bay Front generation station in Wisconsin to be the largest biomass power plant in the Midwest. Energybiz Leadership conference held March 10 We are witnessing an exciting transition in the energy industry as we apply new technology to make major differences in the economy and the environment. Challenges include developing transmission for wind; carbon legislation and renewable portfolio standards. The Edison electric Institute CEO stated: The country faces something like a perfect storm. No excess capacity left from the 70s and 80s over build; a deep economic recession and the need to address climate change.
4
According to the DOE report 20% Wind Energy by 2030, factors that facilitate the integration of wind power into the electric system and further improve overall reliability and cost-effectiveness include the following: Wind forecasting enhances system operation. Flexible, dispatchable generators, such as natural gas plants, facilitate wind integration. Aggregation and geographical spread of wind projects reduces variability; the more wind farms, the smoother the overall output can be. Large balancing areas reduce impacts, for wind and for all technologies. Changing load patterns, such as those enabled by a smart grid and plug-in electric vehicles, can complement wind power generation. So what is the problem? While we are scrambling to deal with climate change we change, e need to keep o our rc current rrent fleet economical and o our r staff safe from process hazards. Its ahidden problem that must be addressed and quickly.
This graphic shows partially smoothed composite hourly Megawatt production for the Minnesota wind farms. The intent of this slide is to show the variability of wind production as we see it today.
This three dimensional graph illustrates the hourly wind generation in megawatts for Minnesota plotted against the month and time of day. The highly variable generation data used to create this graph was smoothed 15 days forward and back to produce this graphic. Notice the high production in April, May, December and January (red). Notice the low production in Late July and Early August which is a summer peak period (dark blue) for native load. This smoothed graph shows what the current production would be from wind with some energy storage.