Checklist For Brickwork

The check sheet lists 10 stages of blockwork construction with multiple items to be checked at each stage by subcontractors, consultants, and HMR staff. Key checks include surface preparation, layout survey, reinforcement installation, joint widths, lintels, and water curing of completed blocks. Sign off is required from quality control engineers at various stages to approve proceeding to the next trade.

Uploaded by

zawadimran
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
676 views1 page

Checklist For Brickwork

The check sheet lists 10 stages of blockwork construction with multiple items to be checked at each stage by subcontractors, consultants, and HMR staff. Key checks include surface preparation, layout survey, reinforcement installation, joint widths, lintels, and water curing of completed blocks. Sign off is required from quality control engineers at various stages to approve proceeding to the next trade.

Uploaded by

zawadimran
Copyright
© © All Rights Reserved
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as XLSX, PDF, TXT or read online on Scribd
You are on page 1/ 1

HABTOOR MURRAY & ROBERTS JV

PROJECT : SAADIYAT ST. REGIS BEACH RESORT

SITE NO.: 831 SHEET No. Related I.R. ref.

CHECK SHEET FOR BLOCKWORKS

SECTION OF WORK

LOCATION
CHECKED BY SUBCONTRACTOR / DATE CHECKED BY CONSULTANT / DATE

Stage

Item

CHECKED BY HMR / DATE

SUR/PE
1.

SUR/PE

Layout survey carried out surveyor marks all points SE/PE SE/PE

2.

Surface preparation, (lightly scabbled and clean the surface) Setting-out done for 1st course prior to fixing (opening for MEP services) as per approved shop drawing. Check source certificate of blocks, sand and cement as per approved materials. Check the mix proportion of mortar as per approved method statement. Mortar mix 1:5 Blocks wet 30 mins prior to use SE/PE SE/PE SUR/PE SUR/PE

3.

SE/PE

SE/PE

4.

SE/PE

SE/PE

5.

SE/PE SETTING OUT


6.

SE/PE

7.

Provide DPC sandwich between an even mortar bed SE/PE SE/PE

8.

Vertical joint width uniform 10mm SE/PE SE/PE

9.

Check Toothing at joints of main wall with partitions.

10. MEP provision coordinated with clearance obtained

MEP

MEP

APPROVAL TO PROCEED WITH THE NEXT TRADE Check alignment / width of perpends. Vertical and horizontal joint uniform 10mm with polysterene strip inplace in every course Provide SS/GI Lath mesh fixed at 1st and 2nd course and after every 2nd layer. Check metal ties and accessories are fixed in accordance to approved materials and approved drawings. Provide expanded metal type reinforcement in first two courses, below and above all windows and above doors. Reinforcement extends 600mm past the opening Check raked out joints.

QCE SE/PE

QCE SE/PE

1.

SE/PE

SE/PE

2.

SE/PE

SE/PE

3.

SE/PE

SE/PE

4.

SE/PE 5. BLOCKWORKS COMPLETION

SE/PE

SE/PE 6. Check compliance of chases with specifications. S0/PE 7. Adequacy of Platform Working at Height. SE/PE 8. Provide lintel beam on openings greater than 400mm SE/PE 9. Soffit ties fixed 400mm on center as required SE/PE 10. Water curing of completed course

SE/PE

S0/PE

SE/PE

SE/PE

SE/PE

APPROVAL TO PROCEED WITH NEXT TRADE

QCE

QCE

SO-SAFETY OFFICER,SUR-SURVEYOR , SE-SITE ENGINEER, PE-PROJECT ENGINEER, QCE-QUALITY CONTROL ENGINEER,

Doc. No.: HMR-831-C-QAC-009-F09