Modern Approach To Overall Equipment Effectiveness (Oee)
Modern Approach To Overall Equipment Effectiveness (Oee)
SEMINAR REPORT
Submitted by
To
The University of Kerala
In partial fulfilment of the requirements for the award of the degree
Of
Bachelor of Technology in Mechanical Stream Industrial Engineering
CERTIFICATE
This is to certify that the report entitled “Modern approach to Overall Equipment
Effectiveness (OEE)”, submitted by “Kailas Sree Chandran, S7N, 27432” to the
University of Kerala in partial fulfilment of the requirements for the award of the Degree of
Bachelor of Technology in Mechanical Stream Industrial Engineering, is a bonafide record of
the seminar presented by him, under our guidance and supervision.
PROF. P. VINCENT
HEAD OF THE DEPT OF MECHANICAL ENGINEERING
COLLEGE OF ENGINEERING
THIRUVANANTHAPURAM
ACKNOWLEDGEMENT
Smt. MINI R.S., Lecturer and Staff Advisor, Department of Mechanical Engineering,
College of Engineering, Thiruvananthapuram for their direct and indirect helps for the
Last but not least, I am grateful to my parents, friends and classmates for their help
Under current economic conditions, severe global competition and postponement of new
equipment purchases are causing business executives to be sensitive about all aspects of
manufacturing operational costs. In this context Overall Equipment Effectiveness (OEE) has
become a hot topic among many manufacturers. It provides a simple way to “keep score” of
effectively manufacturing equipment is utilised. The results are stated in a generic form
which allows comparison against benchmark defined for the industry. Comparisons can also
be made in between shifts, products, machines, departments, lines and plants etc. In simple
OEE breaks the performance of a manufacturing unit into three separate but measurable
the process that can be targeted for improvement. OEE may be applied to any equipment.
This tool also allows for drilling down for very specific analysis, such as a particular part
number, shift, or any of several other parameters. It is unlikely that any manufacturing
process can run at 100% OEE. Many manufacturers benchmark their industry to set a
1. Introduction 1
5. OEE Factors 10
8. Sample Problem 20
9. Objectives of OEE 23
13. Conclusion 30
14. References 31
1. INTRODUCTION
There are many different approaches for measuring manufacturing efficiency and generally
most companies will have some measures already in place. Many now argue that none of
these are as comprehensive or far reaching as the Overall Equipment Effectiveness (OEE)
OEE was first used by Seiichi Nakajima, the founder of Total Productive Maintenance
equipment running smoothly, but on creating a sense of joint responsibility between operators
OEE embodied in the first of the original pillars of TPM, guided all TPM activities and
measured the results of these loss-focused activities. The use of OEE evolved into the current
1
2. DEFINITION OF OVERALL EQUIPMENT EFFECTIVENESS
Overall equipment effectiveness is a measure of total performance- the degree to which the
asset is doing what it is supposed to do [1]. The effectiveness of equipment is the actual
output over the reference output [4]. Equipment Effectiveness shows how effectively the
equipment is utilized. The value of the OEE is a measure for the effectiveness of the
equipment in the available time for production. Overall Equipment Effectiveness shows the
means the machine that produce maximum output at best quality. It doesn‟t have any loss or
breakdowns. So it is only an imaginary machine. OEE compares the equipment with the same
Planned Productive time is the time in which normally production is planned or realized.
Fully productive time is the time which remains after subtracting all losses in a production
system. Therefore OEE is the ratio between Fully Productive Time and Planned Production
Time.
2
3. SIX BIG LOSSES
One of the major goals of TPM and OEE programs is to reduce and/or eliminate what are
called the SIX BIG LOSSES- the most common causes of efficiency loss in manufacturing.
This was put forwarded by Nakajima in 1989. There are 3 OEE loss categories; Down Time
Loss, Speed Loss and Quality Loss. Each of these categories have been divided into two.
These are called Six Big Losses. OEE is generally measured in terms of these six losses.
They are
i. Breakdown Losses
For a longer period, if the output is zero, the installation produces nothing. The unused
segments of time, during the examined period are down time losses. Down Time Losses are
divided into two; Breakdown losses and Setup & Adjustments losses.
Breakdown Losses are by far the biggest of the “Six Big Losses”. The breakdown is often
referred to as sudden, dramatic failure in which the equipment stops completely [1]. Such
unexpected breakdowns are clearly losses, because production is stopped. Even if the cause
lies in a single specific function, the break down results in cessation of all equipment
3
functions. Problems and losses related to deterioration are also considered as break down
losses.
Eliminating unplanned Down Time is critical to improving OEE. Other OEE factors cannot
be addressed if the process is down. It is not only important to know how much Down Time
your process is experiencing but also to be able to attribute the lost time to the specific source
Setup and Adjustment occurs when the production of one product ends and the equipment is
adjusted to meet the requirements of another product. The loss of time during this delay is
Setup and Adjustments time is generally measured as the time between the last good part
produced before setup to the first consistent good parts produced after setup. This often
includes substantial adjustments and/or warm-up time in order to consistently produce parts
that meet quality standards. Usually the loss of time should be less than 10 minutes.
The output is smaller than the output at reference speed, these are called speed losses. When
considering speed losses, one does not check if the output conforms to quality specifications.
Speed Losses are divided into two; Small stops and Reduced speed.
Small stops losses occur when equipment stops for a short time as the result of a temporary
problem. For example, a minor stoppage occurs when a work-piece is jammed in a chuck or
when a sensor activates and shuts down the machines. As soon as someone removes the
jammed work-piece or resets the sensor, it operates normally again. These losses also include
4
idling losses that occur when equipment idles. i.e. that it continues to run without producing.
Since idling and minor stoppages interrupt functions, they can also be categorized as
breakdowns. Even so, the two are essentially different in that a minor stoppage and the
Reduced speed refers to the difference between designed speed and actual operating speed
[3]. Equipment may be run at less than designed speed for various reasons: non-standard or
difficult raw materials, mechanical problems, history of past problems, or fear of overloading
the equipment. This loss of speed is converted into time during OEE calculation.
The produced output either does or does not conform to quality specifications. If it does not
comply, this is considered a quality loss. Quality loss is divided into two; Startup Rejects and
Production Rejects.
Some equipment requires warm-up time and certain adjustments to obtain optimum output.
Startup losses are yield losses that occur in the early stages of production, from machine
setup to stabilization of product quality. The volume of losses varies with degree of stability
Production Rejects are quality losses that are not attributed to startup. These losses occur
when products produced are not conforming to the specifications. Parts that require rework of
any kind should be considered rejects. These losses occur during steady-state production.
5
Six big losses with three categories are shown in Figure 1. Six big losses are categorized with
examples in Table 1.
6
Table 1. Categories of SIX BIG LOSSES with examples.
Tooling Failures
Unplanned Maintenance
Break Downs
DOWNTIME LOSS
General Breakdowns
Equipment Failure
Setup/ Changeover
Material Shortages
Setup and Adjustments Operator Shortages
Major Adjustments
Warm-Up Time
Obstructed Product Flow
Component Jams
Miss-feeds
Small Stops
Sensor Blocked
SPEED LOSS
Delivery Blocked
Cleaning/Checking
Rough Running
Under Nameplate Capacity
Reduced Speed Under Design Capacity
Equipment Wear
Operator Inefficiency
Scrap
Rework
Startup Rejects In-Process Damage
QUALITY LOSS
In-Process Expiration
In-correct Assembly
Scrap
Rework
Production Rejects In-Process Damage
In-Process Expiration
In-correct Assembly
7
4. COMPONENTS OF PLANT OPERATING TIME
OEE analysis starts with Plant Operating Time. It is the amount of time the facility is open
and available for equipment operation. It is the maximum amount of time and is a constant. A
day always consists of 24 hours of 60 minutes. A week always consists of 7 days of 24 hours.
A year always consists of 52 weeks. It is also called Theoretical Production Time. This Plant
Operating Time consists fully productive time and different losses like speed and quality loss.
When a category of time called Planned Shut Down is subtracted from Plant Operating Time,
the remaining is Planned Production Time. The planned shut down includes all events that
should be excluded from efficiency analysis because there was no intension of running
production [3]. E.g. Breaks. Lunch breaks, scheduled maintenance or periods where there is
nothing to produce. Planned Production Time is also known as Available Production Time.
OEE begins with Planned Production Time and scrutinizes efficiency and productivity losses
that occur, with the goal of reducing or eliminating these losses. OEE starts with Plant
Operating Time and end up at Fully Productive Time, showing the sources of Productive loss
From Planned Production Time, Down Time loss is subtracted to get Operating Time.
Downtime losses includes any events that stop planned production for an appreciable length
of time (usually several minute-long enough to log as a traceable event). Examples include
equipment failures, material shortages, and changeover time. Change over time is included in
OEE analysis, since it is a form of downtime. While it may not be possible to eliminate
8
changeover time, in most cases it can be reduced. The remaining available time is called
From Operating Time, speed loss is subtracted which includes any factors that causes the
process to operate at less than the maximum possible speed while running. Examples include
machine wear, substandard materials, miss-feeds, and operator inefficiency. The remaining
From Net Operating Time, Quality Loss is subtracted which accounts for produced pieces
that do not meet quality standards, including pieces that require rework. The remaining time
is called Fully Productive Time. The goal is to maximize Fully Productive Time. It is also
Plant operating Time= Fully Productive Time + Quality Loss + Speed Loss + Down Time
is shown in Figure 2.
FULLY
QUALITY LOSS
PRODUCTIVE TIME
9
5. OEE FACTORS
The OEE calculation is based on the three OEE factors; Availability, Performance and
5.1 Availability
The availability portion of the OEE Metric represents the percentage of scheduled time that
Uptime that is designed to exclude the effects of quality, Performance, and scheduled
Downtime Events.
It is calculated by
When downtime losses are zero, the availability is 1or 100%, the gross operating time equals
the available time for production. i.e. Operating time equals Planned Production time. 100%
availability means the process has been running without any recorded stops.
5.2 Performance
Performance takes into account Speed loss. Performance is the ratio between Net Operating
The performance portion of the OEE Metric represents the speed at which the equipment runs
speed that is designed to exclude the effects of Quality and Availability [1].
10
Performance does not penalize for rejects, which means even if the work is rejected or it‟s a
It is calculated as:
Ideal Cycle Time is the minimum cycle time that your process can be expected to achieve in
optimal circumstances. It is sometimes called Design Cycle Time, Theoretical Cycle Time or
Nameplate Capacity.
Since Run Rate is the reciprocal of Cycle Time, Performance can also be calculated as:
Performance is capped at 100%, to ensure that if an error is made in specifying the Ideal
Cycle Time or Ideal Run Rate, the effect on OEE will be limited. 100% Performance means
the process has been consistently running at its theoretical maximum speed.
5.3 Quality
The Quality portion of the OEE metric represents the Good Units produced as a percentage of
the total units produced [1]. The Quality metric is a pure measurement of process yield that is
designed to exclude the effects of Availability and Performance. Quality is the ratio of Fully
11
It is calculated as
The three effectiveness factors offer a second way to quantity the OEE;
Therefore OEE is the product of its effectiveness factors; Availability, Performance and
Quality. The individual value of the three effectiveness factors lies between 0 and 1. The
study of each of these effectiveness factors will improve the Overall Equipment
Effectiveness.
During analysis, the analyst can concentrate each category of losses separately. As shown in
Figure 2, Availability takes into account Downtime losses, Performance takes into account
speed losses and quality factor takes into account Quality loss. The main aim of OEE
measurement is to reduce these losses and by analysis and improving the factors, the losses
can be reduced or eliminated and OEE can be improvement. The use of effectiveness factors
helps with prioritizing the size, but does not indicate the financial consequences that can
differ per factor. Overall Equipment Effectiveness calculation and Losses are shown in
Figure3.
12
Figure 2. OEE Factors and its losses.
13
EQUIPMENT EFFECTIVENESS LOSS OEE FACTORS
BREAK DOWN
DOWN
TIME
LOSS
OPERATING TIME AVAILABILITY
SMALL STOPS
OVERALL
SPEED
LOSS
STARTUP REJECTS
QUALITY
FULLY
QUALITY
LOSS
PRODUCTIVE
TIME
PRODUCTION REJECTS
World class OEE is a standard which is used to compare the OEE of the firm. The percentage of
Availability 90%
Performance 95%
Quality 99%
OEE 85%
These values of OEE factors are generally accepted but the values are different for different
industries. For Manufacturing, the value of World Class OEE is 85% but for Paper Industry and
Cement Industry, the value is 95% and 80% respectively. The aim of the firm is to achieve this
15
7. OEE CALCULATION METHODS
input data is needed for calculating OEE. The aim of OEE measurement and analysis is to
reduce the equipment losses to zero and has been recognized as a necessity for many
organizations [3].
For all these methods, the input data is same. The difference is the approach to the problem.
It involves finding the Planned Production Time and Fully Productive Time from the given
input data. Planned Production Time can be found out by subtracting Planned Shutdown from
Plant Operating Time. Plant Operating Time: Calendar time 24 hours/day, 7 days/week, 365
Planned Shutdown includes lunch breaks and tea breaks, shift change, planned maintenance etc.
Fully Production time can be found out by subtracting Downtime loss, Speed loss and Quality
loss from Planned Production time. Downtime loss should be given in the input data. Speed loss
16
can be calculated from ideal production rate and actual production rate. Quality loss can be
This method is a little complex and is not used practically. The main disadvantage of this
technique is that analysis from the results is very limited. Because the output is the OEE
percentage alone. In other two techniques, the result has more information which aids in further
analysis.
This method is used as a standard method for calculating Overall Equipment Effectiveness. It is
simple and uses minimum input data. This method uses the three effectiveness factors to
Therefore by using this method, three individual effectiveness values are calculated which can
be used for further analysis. Overall Effectiveness is the product of these effectiveness factors.
This is an automated method. This involves the use of computers in calculating OEE. The basic
approach is same as the OEE Factors Method but Software Method is more accurate and more
flexible. All modern firms use this method. Software method can be done with the same input
7.3.1 Spreadsheets
17
7.3.1 Spreadsheets
Spreadsheet makes calculating OEE easier but unfortunately, it won‟t help with collecting the
data. Manual collection and processing of data for OEE calculation is time consuming and
System software collects data in real-time directly from the equipment. It saves the time needed
to manually collect the data leaving staff available to do more productive work. The data is
highly accurate compared to manually collected data and it is available immediately. The
analyst can analyze OEE continuously and display it on the shop-floor so the staff can see
exactly how they are performing. OEE IMPACT, VISUAL OEE, OEE TOOLKIT, PROVIDEAM
are examples for System Software. These softwares not only calculate OEE, but also analyze
and report on key production information; machine setup times, product analysis, product
tracking, wastage, rework, maintenance times etc. They produce reports in the form of graphs,
18
Figure 4. Screenshots of OEE System Softwares.
19
8. SAMPLE PROBLEM
Some data about an equipment is given. Calculate Overall Equipment Effectiveness using all
three methods.
Rejected pieces = 52
Assure the equipment works only under the supervision of its operator.
Operating Time = Planned Production Time – Downtime loss = 400-48 = 352 minutes.
20
Ideal Production = (5 pieces/min) x 352 minutes = 1760 pieces.
Quality loss = No. of rejected items x Cycle time = 52 x 0.2 minutes = 10.4 minutes.
Performance = (Total pieces / Operating Time ) / Ideal Run Rate =(1600/352)/5 = 0.9091
A sample spreadsheet is used for calculating OEE. The input data is entered into the required
fields of the worksheet. The spreadsheet calculates OEE factors simultaneously while entering
data. The three factors Availability, Performance, Quality are calculated and OEE is also
calculated. These values are also compared with World Class OEE so that the analyst can know
the present condition of the equipment. The screen shot of the Excel Calculator is given in
Figure 5.
21
Figure 5. Screenshot of Excel Calculator.
22
9. OBJECTIVES OF OEE
OEE data (information) is used to identify and categorize major losses or reasons for
poor performance.
OEE percentage is used to track and trend the improvement, or decline, in equipment
23
10. CAUTIONS FOR USING OEE
i. The calculated OEE is not included for use as a corporate or plant level measure.
ii. Calculated OEE is not valid for comparing or benchmarking different assets,
effectiveness compared to itself over a period of time. However, OEE can be used to
industry, 85% is World-class OEE at the same time, in process industry, it is 90%.
Manufacturing.
iv. OEE percentage calculations are not statistically valid. A calculated OEE percentage
assumes that all equipment – related losses are equally important and that any
not the case. For example, the calculation of OEE of same equipment at different
OEE = 80% x 99% x 95% = 75% OEE = 95% x 98% x 89% = 83%
In the second case, OEE increased by 8% but at the same time the quality reduced
24
11. MODIFIED OVERALL EQUIPMENT EFFECTIVENESS
In the Six Big Losses, Setup & Adjustments and Small time losses, both will create a loss of less
than 10 minutes. But both are given under different categories. So by combining these two
losses into one category, Stop Time Losses can be defined. The advantage is that it will be more
So by modifying the Six Big Losses as shown in Figure 6, a new category called Stop Time
By removing this Stop Time Losses from operating time, a new category of time called Running
Time is created. Based on this Running Time and Stop Time Losses, a new factor for OEE, ie
Usability is derived. Components of Plant Operating Time including Running Time are shown
in Figure 7. The inclusion of the Usability factor leads to more detailed categorization of
25
As shown in figure 8, the Usability factor takes into account Stop Time Losses. Now the
advantage is that, four factors are available for analysis. So a better analysis can be done
compared to the former. But this Modified OEE is still in proposal stage. No firms have
implemented this and no software is using this for standard calculations and analysis. The
26
11.1 Availability
There is no difference in calculating Availability. The only difference is that when calculating
11.2 Usability
Running time is calculated by subtracting Setup & Adjustments and Small Stops losses from
Operating time.
11.3 Performance
Performance takes into account Reduced Speed losses only. It is the ratio between Net
Quality is calculated by subtracting the output during Running time and rejects (including
27
EQUIPMENT EFFECTIVENESS LOSS OEE FACTORS
DOWN
TIME
LOSS
OPERATING TIME BREAK DOWN AVAILABILITY
STARTUP REJECTS
FULLY
SPEED
LOSS
PRODU QUALITY
CTIVE
TIME
PRODUCTION REJECTS
Use the previous problem itself for calculating Modified OEE. The Downtime loss of 48
minutes is divided into 20minutes of warm-up time and 28 minutes of equipment breakdown
Performance = (Total Pieces / Operating Time ) / Ideal Run Rate = (1600/352) / 5 = 0.9091
29
13. CONCLUSION
The definition and use of Overall Equipment Effectiveness over the years has been widely
debated. Many practitioners have found that OEE has several uses and definitions which have
to-company. Unfortunately, OEE was not designed to make comparisons from machine-to-
misuse. OEE is not a statistically valid metric, but it has been used as such for years.
OEE does not diagnose a specific reason why a machine is not running as efficiently as possible,
but it helps to categorize the areas for initiating the equipment improvement.
Modified Overall Equipment Effectiveness helps to analyze short time losses and long time
losses separately. Also it adds one more factor in calculation, Usability. It helps in more specific
analysis of losses and for initiatives to reduce these losses. But Modified OEE is still in
development stage.
30
14. REFERENCES
[1] Anil S. Badiger, „A proposal: evaluation of OEE and impact of six big losses‟, Int. J. Process
[2] Ravikumar M. M., „Improving Equipment Effectiveness‟, Int. Business Management, Vol. 3,
[3] Francis Wauters, „White Paper on Improving Plant Performance: OEE‟, ABB Inc, June
2002. www.abb.com
[5] Robert M. Williamson, „Whitepaper on OEE Implementation‟, Strategic Work Systems Inc,
2004. www.swspitcrew.com
[6] http://www.bestmanagementarticles.com
[7] http://www.maintenanceworld.com
[8] http://www.managementparadise.com
[9] http://www.oee.com
[10] http://www.oeetoolkit.com
[11] http://www.scribd.com
31