Transformer Testing

The document discusses various types of tests that are performed on transformers, including routine tests, type tests, additional tests, and erection/commissioning tests. Routine tests are carried out on every unit manufactured to check quality requirements, while type tests are designed to prove the design meets specifications. Example routine tests listed include winding resistance measurement, voltage ratio measurement, and short-circuit impedance measurement. Example type tests include temperature rise tests. Additional tests discussed include dissolved gas analysis of transformer oil and tests for vibrations. Erection tests focus on inspection for damage and verification of specifications. Pre-commissioning tests check insulation resistance, turns ratios, and relay testing. Commissioning tests confirm protection schemes and load operation.

Uploaded by

ramprakashpatel
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
127 views64 pages

Transformer Testing

The document discusses various types of tests that are performed on transformers, including routine tests, type tests, additional tests, and erection/commissioning tests. Routine tests are carried out on every unit manufactured to check quality requirements, while type tests are designed to prove the design meets specifications. Example routine tests listed include winding resistance measurement, voltage ratio measurement, and short-circuit impedance measurement. Example type tests include temperature rise tests. Additional tests discussed include dissolved gas analysis of transformer oil and tests for vibrations. Erection tests focus on inspection for damage and verification of specifications. Pre-commissioning tests check insulation resistance, turns ratios, and relay testing. Commissioning tests confirm protection schemes and load operation.

Uploaded by

ramprakashpatel
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 64

TRANSFORMERTESTING

VIVEK JHA
VIVEK JHA 1

Transformers: coreofelectricitysupply

Transformer:mostvitalequipmentofthesupplysystem Types:

EHVTransformer HTTransformer LTTransformer InstrumentTransformers

VIVEK JHA

NECESSITYOFTESTS

Toprovethatthedesignmeetsthespecifiedjobrequirementsandtoobtaintransformer characteristics. Tocheckthatthequalityrequirementshavebeenmetandthatperformanceiswithinthe toleranceguaranteed.

TestsperformedfortheformerpurposearereferredtoasTypetests andthatforthelater purposearereferredtoasRoutinetests (carriedoutoneveryunitmanufactured). InAdditiontothesetwocategoryoftests,specialtests Mayalsobeperformedtoobtaininformationusefultothe Userduringoperationormaintenanceofthetransformer.

VIVEK JHA

TransformerTests

Reference standard : IEC 60076

EXAMPLE:ROUTINETESTS Measurementofwindingresistance Measurementofvoltageratio,polarityandcheckofvoltagevectorrelationship Measurementofnoloadlossandexcitationcurrent Measurementofshortcircuitimpedanceandloadloss Measurementofinsulationresistance Switchingimpulsevoltagewithstandtest Lightningimpulsevoltagewithstandtest Magneticcircuit(isolation)test EXAMPLE: TYPETESTS

Meaurementofpowertakenbycoolingcircuits TempRiseTest

VIVEK JHA

ADDITIONALTESTS

TESTWITHLIGHTNINGIMPULSECHOPPEDONTHETAIL MAGNETICCIRCUIT(ISOLATION)TEST MAGNETICBALANCETESTONTHREEPHASETRANSFORMERS DISSOLVEDGASANALYSIS(DGA)OFOILFILLEDINTHETRANSFORMER DETERMINATIONOFCAPACITANCESANDTANDELTABETWEENWINDINGTOEARTHANDBETWEEN WINDINGS

MECHANICALTESTS

MEASUREMENTOFVIBRATIONONTRANSFORMERTANK VACUUMTESTONTRANSFORMERTANK OILPRESSURETESTONCOMPLETELYASSEMBLEDTRANSFORMER JACKINGTESTANDDYEPENETRATIONTEST PRESSURERELIEFDEVICETEST

VIVEK JHA

TestsonTransformers

Erectiontests(installationTests) Precommissioningtests CommissioningTests

Erection tests:
Thorough checking for any damage
Verification of technical specifications Foundation etc

VIVEK JHA

ERECTIONATSITE:INSPECTION

Makevisualinspectionforanytransitdamage Checknitrogenpressure. Checkvariousaccessoriesforanytypeoftransitdamage. Makeinternalinspectionofthetransformertotheextent possibleforanyvisiblediscrepancy.

VIVEK JHA

OILFILLING

Beforefillingtheoilintotransformerchecktheoilcarefullyfor

Breakdownvoltage Moisturecontent Tandeltaandcapacitance

Iftheoilisnothavingthepropertiesasrecommendedbythe standards,itmustbefilteredwithfilterswithbuiltinheaters and vacuumpumpsforimprovingthequalityofoil. Fortransformersdispatchedgasfilled,oilfillingmustalwaysbe doneundervacuum.

VIVEK JHA

GENERALTESTSAFTERTRAFOINSTALLATION

(GetClearanceforTesting&Commissioningactivities) Physicalinspection Fireprotectionsystemavailable Oillevelchecking,nooilleakage Powerandcontrolcablingchecking, CoolerfanandPumpcontrolcktchecking Buch.Relaycorrectlymounted,airreleasedfromBuchrelay, Coolingsystem&radiators,OLTC BreatherinstallationOk,silicagelcolourblue

OTI&WTICalibration

VIVEK JHA

PrecommissioningTests

IRvalueoftransformerandcables WindingResistance TransformerTurnsRatio PolarityTest MagnetizingCurrent VectorGroup MagneticBalance Bushing&WindingTanDelta(HV) Protectiverelaytesting Transformeroiltesting Hipottest

VIVEK JHA

10

CommissioningTests:

RemoteAnnunciationandcontrolschemes PowercableIdentification&Tests Chargingthetransformer:noloadandfullloadoperation

andObservationforanyabnormality Confirmingtheoperationofallprotection,interlocksand meteringschemes

VIVEK JHA

11

1.ChecktheoperationoftheBuchholtzalarmandtripbyinjectingairthroughthetestpet cock. 2.TesttheOTIforalarmandtrip. 3.TesttheWTIforalarmandtrip. 4.ChecktheworkingoftheWTI/RTD(ResistanceTemperatureDevice)repeatersatthe controlroom. 5.TesttheOLTC Oilsurgerelayfortrip. 6.Checkalarmforlowoillevel. 7.Checkvariousrelaysforcurrent&timesettings 8.Checkthecoolerunitfor overcurrentsettingoffansandoilpumps coolersupplyfailurealarm fan/pumptripalarm .anymal operationofthetransformerBuchholtzrelaywhenalltheoilpumpsare switchedonsimultaneouslyinforcedoilcooledtransformers

VIVEK JHA

12

FIELDTESTS:
NoLoad Windingresistance TurnsRatio. Polarity, connectiongroupand Excitationcurrent. Onload shortcircuittest, Impedancemeasurement

VIVEK JHA

13

InsulationResistance
Thistesthasbeenthemostusual

historically,beingcalledto megger thetransformer (thetermcomesfromthefirmof thefirstIRsystems).

VIVEK JHA

14

InsulationResistanceandPolarizationIndex

Equivalent diagram of the dielectric circuit of a transformer. Ri is the insulation resistance, Cg the geometric capacitance and the different Ra/Ca emulate the equivalent dielectric absorption circuit.

VIVEK JHA

15

WindingResistance
Thisisnothingbuttheresistancemeasurementofthewindingsbyapplyingasmall

d.cvoltagetothewindingandmeasuringthecurrentthroughthe same
Themeasuredresistanceshouldbecorrectedtoacommontemperaturesuchas

75Cor85Cusingthefollowingformula:

where RCisthecorrectedresistance,RMisthemeasuredresistance CFisthecorrectionfactorforcopper(234.5)oraluminum(225) windings CTisthecorrectedtemperature(75Cor85C) WTisthewindingtemperature(C)attimeoftest

VIVEK JHA

16

WindingResistance.
Withthistestwedeterminatethepure

ohmicresistancefromeachphasewindings bothinhighandlowvoltageandeach positionoftapchanger.

inafirstapproachseemseasytomeasure,

itsnotso,becauseitisnecessarytomake flowrelativelyhighcurrentstoregisterthe usuallowresistancevalues/m / with therequiredprecision.Thiscurrentsmust alsoflowthroughtheequivalentinductance ofthetransformer.

VIVEK JHA

17

VIVEK JHA

18

TransformerTurnsRatio(TTR):
Transformer Turns Ratio (TTR): quotient between high voltage / low voltage. Must match with protocol /nameplate values. In the power transformer with tap changer, take readings for each position (giving extra information on its status and that of the On Line Tap Changer (OLTC)

VIVEK JHA

19

VIVEK JHA

20

Transformer Turns Ratio: Doble kit

VIVEK JHA

21

VIVEK JHA

22

VIVEK JHA

23

PolarityTest

VIVEK JHA

24

Opencircuittest&Excitationcurrent
Excitationcurrentisthecurrentflowingintothehighvoltagewinding

withthelowvoltagesideopen.

VIVEK JHA

25

FIELDTESTS:Loadtest
shortcircuittest, Impedancemeasurement

VIVEK JHA

26

ShortCircuittest

VIVEK JHA

27

ShortCircuittest
shortcircuittest isbasedintheapplicationofavoltageinonewinding

(highvoltageone)withtheotherwindingshortcircuited.Itisusualto registernominalandextremepositionsifthetransformerhadan OLTC.

VIVEK JHA

28

Impedancemeasurement
Shortcircuitvoltage:voltagerequiredtocirculatefullloadcurrent. shouldbeneartheprotocol/nameplatevaluefromthetransformer. Itschangewillindicateirregularitiesinthemagneticcore,winding,

displacement,shortcircuits,mechanicaldeformations

VIVEK JHA

29

VIVEK JHA

30

FrequencyResponseAnalysis

Themainpurposeofthistestistodeterminatethefrequencyresponse

graphoftheequivalentelectric/dielectric/magnetic/mechanic altogetherevaluated.

VIVEK JHA

31

FrequencyResponseAnalysis

VIVEK JHA

32

DIELECTRICSYSTEMTESTS.
Liquiddielectric(usuallymineraloil) ORsoliddielectric(usuallypaper)

Dielectriccircuittests.
InsulationResistanceandPolarizationIndex(IR,PI). Capacitance,Dissipation(power)factor(tan)andinsulationlosses indielectricbushing. PartialDischarge(PD).

Oilsampling.
DielectricStrength. Moisturecontent. DissolvedGases. FuranAnalysis.

VIVEK JHA

33

Oiltestingandmaintenance
Therearethreeimportantpurposesoftheoilina transformer: 1.Gooddielectricstrength 2.Efficientheattransferandcooling 3.Topreservethecoreandassembly
Byfillingvoids(toeliminatepartialdischarge) Bypreventingchemicalattackofcore,copperandinsulationby

having lowgascontentandnaturalresistancetoageing.

OilTesting

Visualchecks OilBDVtest Powerfactor(tandelta)test Aciditytest Moisture(ppm) DGA

Transformer BDV test set


VIVEK JHA 35

Breakdownvoltage.

Oildegradationcanbeeasilyappreciatedwiththisparameter

tested.Thetestisbasedintheinsertionofelectrodesimmersedin oilandincreasingvoltageuptobreakdown. Testisrepeatedsixtimestogetarepeatablemeasurement. Theonlydisadvantageisthatitisnecessarytoextractfromthe transformerasignificantsample(testcellwillhave350...600ml).

VIVEK JHA

36

IEC 156

VIVEK JHA

37

TransformerOilSpecifications
Characteristics Breakdownvoltage Requirementasper IS:18661983 50KV(min)for>145KV 40KV(min)for72.5KVto145KV 30KV(min)for<72.5KV 25ppm(max)for>145KV 35ppm(max)for<145KV 0.2(max)for>145KV 1.0(max)for<145KV >0.1X10E12 <0.5 >140

Watercontent Tandeltaat50deg.C Specificresistanceat90deg.Cohmcm NeutralizationvaluemgKOH/gm Flashpoint(degreeC)

VIVEK JHA

38

Capacitance/Tandelta (DissipationFactor)

VIVEK JHA

39

Capacitance/Tandelta (DissipationFactor)

Anotherusualapproachwhenperformingdielectricevaluationistan

delta.ThistestusesACandpursuestoknowlossangleofthetested element.
Thismeasurementincludesinformationofthemoistureand

contaminationdegreeandemulatesthebehaviourandvoltage aggressionssimilartoserviceones.
Itisimportanttotakenoteoftransformertemperatureand

environmentalmoisture(surfaceleakage).

VIVEK JHA

40

VectorGroupTest:Dy11

VIVEK JHA

41

VectorGroupTest:Dy11

Dy11

VIVEK JHA

42

Vectorgrptest

VIVEK JHA

43

VectorGroupDy1

VIVEK JHA

44

VectorGroupDy1

VIVEK JHA

45

PartialDischargetest.
Partialdischargearesmalldischargesthatappearinsideofthe dielectricasasignofits

degeneration.Theyappearasaresultoftheincreaseoftheelectricfieldinsmall gaseousvoidsinsidetheoilandalsoinsidethepaper,epoxyor asaresultofthe presenceofmetalliccontamination,etc.Thisdischargeacceleratethethermal degradationeffectsandleadsometimesexponentiallytothepowertransformer destruction.

Therearetwousualdetectionsystems,

Acousticsystemusessoundmechanicmanifestation(inultrasonicrange Electric systemsdeterminatesdischargesandcorrelatesthemwithInsulation healthiness.

VIVEK JHA

46

SomeotherTests,normallyperformed atManufacturersworks

TemperatureRiseTest LighteningImpulseTest VacuumAndPressureTest LightningImpulseWithstand SwitchingImpulseWithstand

VIVEK JHA

47

History/Trending

VIVEK JHA

48

VIVEK JHA

49

VIVEK JHA

50

VIVEK JHA

51

Conclusion
Testingisanart&scienceofmanagingMachine,Manpower,Material, Quality,Time Peopleresponsibleforupkeepofelectricalapparatusneedto cultivateawatchfulattitudeto Look (eye) Listen (ear) Smell (nose) Feel (finger/skin) forsymptomsofimpendingtrouble Adaptnewtechniques. Keeponlearningfromtheexperiencesworldwide,avoid obsolescence DevelopIntegratedPredictiveDiagnosticSystem KeepitSystemOrientedtoensuresustainability (Avoidsubjectivity&individualbias)
VIVEK JHA 52

Conclusion

SafetyFirst GoodTestequipment peopletohaveadeepknowledge Takecareofenvironmentalconditionswhilecomparingresults Workpressureandshortdowntime Keepyourmindcool

VIVEK JHA

53

SomeReferences

NATIONALSTANDARDSIS2026(PARTIII) IEC600765:2000.Powertransformers.Part5:Abilitytowithstandshortcircuit. IEC60726:2003.Drytypepowertransformers. IEC600763Testlevels&testmethodrequirementfordifferenttests ANSI/IEEEStd621995.IEEEGuideforDiagnosticFieldTestingofElectricPowerApparatus Part1:OilFilledPowerTransformers,Regulators,andReactors.IEEEPowerEngineeringSociety1995. ANSI/IEEEStdC57.12.901993.IEEEStandardTestCodeforLiquidImmersedDistribution.Power andRegulatingTransformersandIEEEGuideforShortCircuitTestingofDistributionandPower Transformers. ANSI/IEEEStd.C57.12.001993.IEEEStandardGeneralRequirementsforLiquidImmersed Distribution,PowerandRegulatingTransformers. EN601561995.Insulatingliquids.Determinationofthebreakdownvoltageatpowerfrequency. Testmethod.. EN608141997.Insulatingliquids.Oilimpregnatedpaperandpressboard.Determinationofwater byautomaticcoulometricKarlFischerTitration. EN605671992.Guideforthesamplingofgasesandofoilfromoilfilledelectricalequipmentand fortheanalysisoffreeanddissolvedgases . EN60599:1999.Mineraloilimpregnatedelectricalequipmentinservice Guidetothe interpretationofdissolvedandfreegasesanalysis.. EN61620:1999.Insulatingliquids.Determinationofthedielectricdissipationfactorby measurementoftheconductanceandcapacitance.Testmethod. EN61198:1994.Mineralinsulatingoils.Methodforthedeterminationof2furfuralandrelated compounds.

VIVEK JHA

54

TESTING OF TRANSFORMERS

LIGHTNINGIMPULSETEST

TosimulatethesystemdisturbancesduetoLightningstroke Canberepresentedbythreebasicwaveshapes

FullwaveLI Choppedwave(Choppedontail) Choppedwave(Choppedonfront)

Lightningdisturbancesdonotalwayshavethesebasicwaveshapes.However,by

definingtheamplitudeandshapeofthesewaves,itispossibletoestablishaminimum impulsedielectricstrengththatatransformershouldmeet.

Ifalightningdisturbancetravelssomedistancealongthelinebeforeitreachesatransformer,its waveshapeapproachesthatofthefullwave.Itisgenerallyreferredtoas1.2/50wave.Awave travelingalongthelinemightcauseflashoveracrossaninsulatorafterthepeakofthewavehas beenreached.Thiswaveissimulatedbyachoppedwavewhichisofthesamemagnitudeasthefull wave.Ifalightningstrokehitsdirectlyatorveryneartoatransformerterminal,theimpulse voltagemayrisesteeplyuntilitisrelievedbyaflashover,causingsudden,verysteepcollapsein voltage.Thisconditionisrepresentedbythefrontofwave

VIVEK JHA

55

TESTSONTRANSFORMERS

LIGHTNINGIMPULSETEST

1.2/50SLIWAVE

CURRENTWAVEFORMDURINGLI

TYPICAL TEST LEVELS FOR LI TEST : H1 : 1300 kVp,


VIVEK JHA 56

TESTSONTRANSFORMERS

LIGHTNINGIMPULSETEST

1.2/50SLIWAVECHOPPEDAT3.7S

CURRENTWAVEFORMDURINGCHOPPEDLI

VIVEK JHA

57

SWITCHINGIMPULSETEST

Switchingimpulselevelisconductedtoverifytheintegrityoftransformerundervarious switchingsurgesonAC/DCline. ThetypicalwaveshapeofSwitchingimpulseis250/2500SasperIEC60060&itsmagnitudeis lowerthanthecorrespondingLIwavebutforlongerduration. Inviewofthedifficultiesingeneratingthesewaveshapesinlaboratoriesandmoretominimize thecoresaturationduringtestingoftransformers,IEC60076Part3hasspecifiedaswitching impulsewavehavingavirtualfronttimeofatleast100s,durationabove90%ofthespecified amplitudeofatleast200sandatotaldurationtothefirstzeropassageofatleast1000s. Unlikeinthecaseofacwinding,boththeterminalsofvalvewindingexperiencefulldcvoltage ofthebridgetowhichtheyareconnected.Thereforevalvewindingistestedtoprovethe insulationofthewindingwiththerespecttoground.Switchingimpulsesareappliedtothe valvewindingterminalsconnectedtogether.Theotherwindingterminalsnotundertestare shortcircuitedandgrounded.

VIVEK JHA

58

SWITCHINGIMPULSETEST

WAVESHAPEOFSWITCHINGIMPULSEASPERIEC60060

STANDARD250/2500SSWITCHING IMPULSEWAVE

TYPICAL SWITCHING IMPULSE LEVELS : H1 : 1080 kVp, X1-X2 : 1290 kVp, X3-X4: 980 kVp

VIVEK JHA

59

SWITCHINGIMPULSETEST

Switchingimpulselevelisconductedtoverifytheintegrityoftransformerundervarious switchingsurgesonAC/DCline. ThetypicalwaveshapeofSwitchingimpulseis250/2500SasperIEC60060&itsmagnitudeis lowerthanthecorrespondingLIwavebutforlongerduration. Inviewofthedifficultiesingeneratingthesewaveshapesinlaboratoriesandmoretominimize thecoresaturationduringtestingoftransformers,IEC60076Part3hasspecifiedaswitching impulsewavehavingavirtualfronttimeofatleast100s,durationabove90%ofthespecified amplitudeofatleast200sandatotaldurationtothefirstzeropassageofatleast1000s. Unlikeinthecaseofacwinding,boththeterminalsofvalvewindingexperiencefulldcvoltage ofthebridgetowhichtheyareconnected.Thereforevalvewindingistestedtoprovethe insulationofthewindingwiththerespecttoground.Switchingimpulsesareappliedtothe valvewindingterminalsconnectedtogether.Theotherwindingterminalsnotundertestare shortcircuitedandgrounded.

VIVEK JHA

60

SWITCHINGIMPULSETEST

WAVESHAPEOFSWITCHINGIMPULSEASPERIEC60060

STANDARD250/2500SSWITCHING IMPULSEWAVE

TYPICAL SWITCHING IMPULSE LEVELS : H1 : 1080 kVp, X1-X2 : 1290 kVp, X3-X4: 980 kVp

VIVEK JHA

61

VIVEK JHA

62

Magnetic balance test


Done on TRANSFORMER to see whether the transformer core is magnetically balanced or not...AND ALSO WINDING CONDITION.... for example we r having delta HV and star winding LV side ... HV SIDE WE WIL BE HAVING THREE BUSHINGS....THOSE R 1U,1V,1W.. HV SIDE WE WIL BE HAVING FOUR BUSHINGS.....2U,2V,2W,2N... WE CAN DO THIS MBT (MAGNETIC BALANCE TEST)WITH 1PHASE SUPPLY(1PHASE AND NEUTRAL(230V)) OR WITH 2-PHASE SUPPLY(2PHASES(440V)) 1ST STEP OF MBT: GIVE POWER SUPPLY 1-PHASE OR 2 PHASE BETWEEN 1U AND 1V ,MEASURE THE VOLTAGES BETWEEN 1V-1W AND 1U-1W AND ALSO 2U-2N,2V-2N,2W-2N.. SO HERE IF THE CORE IS CORRECTLY BALANCED THEN WE WILL GET RESULTS AS FOLLOWS 1U-1V 1V-1W 1U-1W 2U-2N 2V-2N 2W-2N 440 300 140 90 50 40 THAT MEANS HV SIDE : 1U-1V = 1V-1W + 1U-1W I.E 440V = 300 + 140 AND ALSO LV SIDE : 2U-2N = 2V-2N + 2W-2N 90 = 50 + 40 STEP 2: AFTER DOING THIS ..INTERCHANGE THE CONNECTIONS BETWEEN 1V-1W AND MEASURE THE VALUES AS ABOVE... STEP 3: AFTER DOING THIS ..INTER CHANGE THE CONNECTIONS BETWEEN 1U-1W AND MEASURE THE VALUES AS ABOVE... IF ANY FAULT IS THERE IN TRANSFORMER WE CAN NOT FIND GOOD RESULTS.... IF THE WINDING IS DAMAGED .... WE WILL GET ZERO VALUES .... ex: HV SIDE 1U-1V = 1V-1W + 1U-1W 440V = 440 + 0 AND ALSO LV SIDE : 2U-2N = 2V-2N + 2W-2N 90 = 90 + 0 THIS IS THE ACTUAL APPLICATION OF MANGNETICA BALANCE TEST...

VIVEK JHA

63

VIVEK JHA

64