Just in Time Construction Method
Just in Time Construction Method
Just in Time Construction Method
TABLE OF CONTENT
1.1 Definitions 5
in Construction Industry 18
3.5 Conclusion 35
Page 1
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
Case Study 2 53
Case Study 3 56
Chapter 7 : Conclusion 68
References 70
Page 2
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
Report Objectives :
Task Framework :
Page 3
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
CHAPTER 1
INTRODUCTION OF JUST-IN-TIME
JIT is a technique developed by Taichi Ohno and his fellow workers at Toyota.
Ohno's fundamental purpose was to change production's directives from estimates
of demand to actual demand--a purpose originally rooted in the absence of a mass
market and the need to produce small lots of many product varieties. It was based
on lean manufacturing, that an outgrowth of the Toyota Production system was
developed by Taichii Ohno in the 1950s. Ohno had observed mass production at
Ford Motor Corporation’s manufacturing facilities in the U.S. and recognized that
there was much waste everywhere.
Page 4
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
Schonberger describes the JIT system as to: "produce and deliver finished
goods just in time to be sold, sub-assemblies just in time to be assembled into
finished goods, and purchased materials just in time to be transformed into
fabricated parts". Schonberger also categorises the benefits of JIT into the following
five groups:
(2) Quality — fast detection and corrections, and higher quality of parts purchased.
(5) Productivity — reduced rework, reduced inspection and reduced parts delay.
Page 5
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
Monden describes JIT as "a production system to produce the kind of units
needed, at the time needed and in the quantities needed". Whilst Harper describes
it as "the hottest and most controversial subject facing manufacturers and
distributors". The interest in JIT amongst manufacturers, suppliers and distributors
is understandable especially if their products have to face home and international
competition from manufacturers who have implemented the JIT principles
effectively.
Hall states that JIT "is not confined to a set of techniques for improving
production defined in the narrowest way as material conversion. It is a way to
visualize the physical operations of the company from raw material to customer
delivery". There is no aspect of management which JIT does not touch.
Page 6
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
The JIT philosophy, also commonly known as the Toyota production system,
originates from Japan. Toyota was the first company to implement this system
which streamlined production with minimum holding inventory. Land costs in Japan
are high due to its scarcity. Inventory takes up space and down capital. In the JIT
philosophy, raw materials are not stocked up. Instead, they are delivered in the
Page 7
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
right quantities, in the right condition, to the right place, and at the right time for
production. JIT has proven to work well in the manufacturing sector (Lim and Low,
1992; and Chan 1997).
The fundamentals of JIT are very much intertwined and related to another. To
simplify this management philosophy, its concept can be explained using the
following six key principles:
3. Elimination of waste
Under the JIT concept, waste is defined as anything that does not as add
value to the final product. Excess inventory is regarded as waste since no
value is added by stoking up inventory. In addition, inventories takes up
space, tie down capital, incurs storage cost, as well as security and insurance
costs; not to mention the risk of damage during storage as well as the risk of
obsolescence.
Page 8
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
The JIT concept therefore calls for zero inventory or buffer stocks. Waiting
time, inspection time and time spent at rectifying defects deemed wasteful.
Thus, getting things done the first “time right” is another doctrine of the JIT
concept.
Page 9
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
This is, in turn, works well for the production company as the supplier is able
to supply better quality materials and at the lower cost. It would be easier to
manage smaller group of suppliers. Manager will be able to spend more
quality time with the reduce number of suppliers. Managers will be able to
spend more quality time with the reduce number of suppliers and ensure that
the JIT production is well supported by all the crucial JIT deliveries.
Page 10
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
CHAPTER 2
Svensson (2001) in his journal argued that the basic of JIT is “no non-
essential activity should be committed prior, during and after any production
phases and wherever beneficial outsourcing is regarded as good as in-house
production”. JIT is understood as event driven production concept which has been
carefully planned and structured to ensure all its components are ready whenever
needed. It is also known as inventory-less production method which allows
minimum stock level only needed for the current manufacturing phase.
Page 11
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
This is to minimize lead times which in turn will boost the production capacity of the
industry as well as its flexibility to response to the market needs. Since this
industry requires large stock to meet the production needs, a better inventory
management system such as JIT will be helpful in reducing costs (Claycomb, 1999).
Ramarapu (1995) stated that, most authors agreed that successful JIT
implementation requires five key elements to be considered.
Page 12
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
Production of Ford latest small car, the Ford KA has been a dramatic
improvement compared to Ford previous product, Fiesta (Kochan, 1997). This is a
real example of successful JIT implementation with all its outsourcing strategies.
The production target of 1,100 KA cars per day has been reached only within 8
weeks since the launch date, compared to 15 weeks required for Fiesta. Ford found
that the initial bottleneck was caused by material handling, assembly time and
inbound logistic. Some of the components in Fiesta are supplied by various
suppliers and these components had to be made, loaded in the container and
scheduled for delivery before finally delivered by trucks. This common process is
found to be inefficient as every part has to be continuously handled by human and
this causes big risks of damages, misplaced and imperfection in quality, especially
for cosmetically sensitive and fragile parts such as instrument consoles, electrical
wiring and airbags.
With the new developed JIT system supported with sophisticated aerial
tunnels connecting Ford with its suppliers, production lead times can be minimised,
product quality can be improved, responsiveness towards customer demands can
me boosted and the most important thing is inventory, space requirements,
handling and transportation cost can be dramatically reduced (Kochan, 1997). Ford
is now connected with more than 50 suppliers in Valencia with specifically designed
aerial tunnels. These tunnels are also very useful to transport bulky and heavy
items such as seats and fuel tank. The brain of this amazing system is DAD (direct
automated delivery) which will integrate the whole processes virtually as one
extended manufacturing warehouse.
Page 13
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
The main objectives of JIT are obtaining low-cost high quality products and
on-time production as well as eliminating waste and stagnant stock (Svensson,
2001). Even though most of JIT implementation has similar aim and purposes, the
strategies involved may differ from industry to industry or company to company.
Ford has smartly chosen the right methods and strategies by reducing the barriers
in relation with its suppliers.
Page 14
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
Page 15
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
COSTS BENEFITS
Page 16
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
CHAPTER 3
Much had been discussed on raising the productivity level of the construction
industry which consistently lagged behind other sectors of the economy. The use of
buildable designs was singled out as a means to improve productivity. In so far as
construction management is concerned, the Just-In-Time (JIT) philosophy can be
applied for logistics management on worksites to help raise productivity levels
(Akintoye, 1995).
Explorative studies have been completed in recent years to see how JIT can
be applied into the construction industry to reap the benefits of the system. Most of
these studies have concluded that it is possible to apply the techniques of JIT in the
construction industry with some modifications. Given the very different conditions
in the construction setting, it is inevitable that modifications have to be made to
some of the JIT principles where application is concerned (Low and Chan, 1997).
Page 17
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
Therefore, in this chapter, the discussion will view on the application of JIT in
construction whether this approach can be applied on the construction industry.
The fundamental philosophy of JIT is to eliminate waste and under the JIT concept,
construction waste can be classified into the following categories:
1. Waste from over-production
2. Waste from delays
3. Waste from transportation
4. Waste from unnecessary processing
5. Waste from excess inventory
Page 18
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
There are two types of inventories that can serve the function of buffering
downstream construction processes from flow variation. The most familiar type is
piles of stuff; materials, tools, equipment, manpower, etc. These piles of stuff may
originate in decisions to insert certain time intervals between scheduled activities,
e.g. between fabrication and installation of pipe spools. Consequently, while they
take the form of stuff, they often also represent time added to project duration, so
it call these as "schedule buffers".
Page 19
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
This is clearly a vicious circle. Large schedule buffers between suppliers and
construction may shield the contractor from the impact of late deliveries, but does
nothing to address the root causes of variation. Further, the shielding is expensive,
both in time and money. There is a better way. A suggested rule: Place schedule
buffers just after processes with variable output. For example, that suggests placing
schedule buffers between engineering and fabrication, rather than between
fabrication and installation. The fabrication and delivery processes are highly
predictable, unless drawings are incorrect or incomplete, or drawings are pulled out
of fabrication to be revised.
Page 20
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
Another suggested rule: Size schedule buffers to the degree of uncertainty and
variation to be managed. Research has shown that schedule buffers are sized
without regard to the toughness of projects; i.e. their level of uncertainty. This
amounts to wasting time and money accumulating piles of stuff not all of which is
needed
Schedule buffers do not replace plan buffers. Plan buffers are necessary even
when schedule buffers are in place because having a pile of pipe does not provide a
piping crew with workable assignments. Pipe spools must match with valves,
controls, hangers, etc. Structures for supporting the pipe must be in place.
Preferably, the spools that can be installed are those that should come next in an
optimum constructability sequence. Assembling physical components, reserving
shared resources, determining optimum sequencing, and sizing assignments to
absorb the productive capacity of the crew is best done prior to making
assignments and committing to what work will be done in the plan period, usually
one week.
Page 21
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
need, it may have shielded itself from unreliable inflow using piles of stuff or
schedule spacing. However, it only needs those piles of stuff if supplier processes
cannot reliably do what they say they are going to do. If supplier processes
consistently achieve PPCs near 100%, customer processes can plan their work and
match resources to it. Reduction of schedule buffers and better matching of
resources to work flow both contribute to reduction of project time and cost.
Page 22
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
Page 23
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
Page 24
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
Logically, it is necessary to fix the problems rather than simply passing bad
product down the line. The problems which arise also became highly visible because
it may result in line stoppages. Forced confrontation with problems together with
analysis to root causes produced a progressively more streamlined and smoother
running production process, with fewer end-of the-line defects and higher
throughput.
Page 25
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
The changes made by the parties may not impact the end dates if the original
schedule has sufficient slack in the impacted activities. The situation will be
different compared to the construction project which is the schedule has a little or
no slack. The players are pressured to make it up in accelerated production. In fact,
this situation may caused delay to construction project which is could bring waste
of times, money, energy, man power and etc. In order to implement the application
of JIT, the priority objective of this application is to eliminate or minimized the
variation and wastage. By the fact show above, is it possible to implement
the JIT on construction?
Page 26
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
Can we imagine that how much more our land can afford for construction
waste? The disposal of the construction waste need a large scale of land whereas all
over the world faced a shortage of land in order to fulfill the demand of
accommodation, agriculture, manufacturing, education and etc. C&D waste disposal
triggers a sequence of adverse effects that are not always apparent to building
professionals. These include the loss of useful property, wasted materials and
embodied energy, greenhouse gas generation, and environmental stressors
associated with producing new materials instead of using existing materials. The
number of C&D landfills is declining, which means fewer disposal options, greater
hauling distances, and increased fuel consumption and vehicle emissions. Capping,
closing, and monitoring landfills, and cleaning up leaking or contaminated landfill
sites drain public funds.
For the fast track construction of process plants such as petroleum, chemical,
food processing, pulp and paper, etc, frequently the construction begins before
design is completed. Therefore the contractors demand to have earlier delivery
which is reducing the time available for engineering to complete the structure
drawings. These situations exist due to late delivery of drawings and materials and
it is possible caused more delivery problems and demands for even earlier
deliveries. In order to avoid or shield the contractors from the impact of late
delivery, the management may provide a large schedule buffer between the
suppliers and construction. However, it does nothing to address the root cause of
variation in construction projects. Even more, the shield is expensive for time and
money.
Page 27
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
For the members, the incentives structure direct them toward viewing the
supply chain as one integrated chain competing with other supply chains and
success is ensured by making one own supply chain the best one. For actors in the
construction industry, every project is a one-off happening where the incentive
structure motivates them to make the most profit out of each project. This
discontinuity is detrimental to construction project productivity and can probably
only be changed by altering the practices of how “construction chains” are
Page 28
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
The long-term relation with the supplier also plays a big factor in effecting
the construction project. The good track record of supplier should be recommended
for other construction project in order to achieve the objectives of the projects.
However, it is rarely happened in construction industry because it involves other
factors such as transportation, limited materials and etc. Therefore, in order to run
a construction projects within the available budget, the management have to avoid
any extra expenses especially in context of getting the right materials and amount
from the suppliers. This situation related to another concept of JIT; producing the
right part in the right place and the right time.
So, it is important to ensure that the supplier can produce the right part of
materials as been asked in contract and also they can guarantee that they can
supply the materials on the right time. However, even the suppliers can supply the
Page 29
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
materials on the right times, the construction site must have efficient place to store
the materials to avoid any damages which caused extra expanses. Even more, the
delivery of the materials from suppliers is much depends on the transportation
which may involve unexpected traffic. From this view, it shows that a lot of things
need to put into consideration in implementing the application of JIT on
construction industry.
From the presentation paper by Veiseth, Rostad and Andersen (2003) the actors
that they have interviewed have identified several problem-areas. In this paper we
will focus on three of them:
• The problems in the interface between the builder, the advisers and the
executors. This problem is often referred to as “early phase- problems” that
emphasize the whole project.
• Logistics problems for building materials and other products used during the
construction process.
• Problems in the construction project planning and management.
Most of the actors we have interviewed argue that the problems in a typical
construction project come into being in the interface between the builder, the
advisers and the executors (see figure 1). The advisers are the architect and the
consulting engineers, while the executors are the building contractors and
supporters.
Builder
Advisers
Executors
Page 30
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
Fig 2: Problem area; the interface between the builder, the advisers and the
executors Builder Advisers Executors
In their opinion they interfaces are of a special interest because much of the
premises for the ensuing productivity and logistics are created here. The problems
could be due to several things like communications problems between different
professions and cultures and that the architects are thinking too little about the
building process in their drawings. But the thing we will point out is that the actors
in the three categories, most of the times do vary from project to project. This is in
contrast to e.g. manufacturing industries where the bindings between actors in e.g.
a supply chain are more often a long-term relationship. Furthermore, in the very
beginning of a typical project, in the idea-phase, it is often just the builder and the
architect who are participating. This can maybe also explain the fact that many of
our respondents claiming that there often are a lack of technical expertise in this
phase.
Another impotent area is purchase routines. Today, most of the purchases are
done by telephone, even though most of the interviewed actor’s wish to do most of
this through the Internet. This could be due to that many are not familiar with a
computer.
Page 31
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
A typical problem, pointed out by many of the interviewed subjects, is that a lot
of actors are utilizing the slack in the plans completely, i.e. never starts work until
they really have to start to reach the deadline. This leads to that the project
decreases its possibilities to catch up for unforeseen problems.
Another aspect pointed out is the meeting-procedures: How often should the
different meetings be held, who should participate and how should the meetings be
structured. This could be the reason why some claims that many decisions are
taken too late and that they often to fuzzy.
Page 32
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
Production Process
the Last Planner (LP) initiative, has been described in some detail in previous
papers . Although it has been experimentally tested in both the United States and
South America (Venezuela), it may be helpful to consider it as a research
hypothesis.
Page 33
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
Methodology:
• Written weekly work plans for each front line supervisor and work group.
• Assignments drawn from a backlog of workable assignments created by
screening for constraints and by acquiring necessary resources.
• Assignments expressed at the level of detail necessary for screening -Weekly
work plans sized to target productivity.
• Front line supervisors participate in the selection and sizing of assignments,
provide reasons why planned work was not done, -Craft
superintendents/Discipline supervisors see that others act on reasons
beyond the reach of the craft or discipline.
The long term goal of replacing schedule buffers with plan buffers.
Page 34
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
1) Project duration can be reduced by reducing the buffers between EPC functions,
and buffer sizes can be reduced if work flow variation can be reduced. 2) If work
flow can be made more predictable, labor and other resources can be better
matched to work flow, thus improving productivity.
Methodology:
Phase I: Identify and analyze examples of successful efforts (tools and techniques)
to increase the predictability of work flow.
3.5 Conclusion
Page 35
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
The rationale for this study is to see application of Just in Time (JIT) in
construction industry. In this context, the JIT philosophy appears to hold
tremendous potentials for improving the movement of construction site.
The space constraints for storage and the traffic congestion at the worksite can
then be alleviated.
Page 36
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
CHAPTER 4
The term ‘Just-In-Time’ (JIT), used for instance to describe the delivery of
materials to a construction site, suggests that materials will be brought to their
location for final installation and be installed immediately upon arrival without
incurring any delay due to storage in a laydown or staging area. JIT is a concept
developed by the Japanese who created the Toyota Production System, later
translated into English as the lean production system. The ultimate objective of
JIT production is to supply the right materials at the right time and in the
right amount at every step in the process.
Thus, IBS is one example of JIT in construction. Rahman and Omar (2006)
defined IBS as a construction system that is built using pre-fabricated components.
The manufacturing of the components is systematically done using machine,
formworks and other forms of mechanical equipment.
Page 37
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
According to Badir- Razali, generally, there are four types of building systems
currently available in Malaysia’s building system classification (Badir et al. 1998),
namely conventional, cast in-situ, prefabricated and composite building systems.
Each building system is represented by its respective construction method which is
further characterised by its construction technology, functional and geometrical
configuration.
Page 38
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
Page 39
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
Page 40
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
The steel formwork is prefabricated in the factory and then installed on site.
However the steel reinforcement and services conduit are installed on site before
the steel formwork are installed. The installation of this formwork is easy by using
simple bracing system. Then concrete is poured into the formwork and after seven
days, the formwork can be removed and there is some system whereby the
formwork served as a part of the structure itself after concreting. The steel
formwork systems are used in tunnel forms, beams, column moulding forms and
permanent steel formworks.
Page 41
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
The elements of steel framing system are rolled into the specific sizes and
then the elements are fabricated that involves cutting, drilling, shot blasting,
welding and painting. Fabricated elements are sent to the construction site to be
then erected whereby welding and the tightening of bolts at joints are conducted.
The elements include steel beams and columns, portal frames and roof trusses.
The elements are fabricated and cured in the factory. The elements are
normally used as bricks in structures and interlocking concrete block pavement.
Page 42
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
We borrowed such symbols from Rother and Shook (1998) and used them to
Page 43
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
fixed quantity. A dashed line with an arrow designates the flow of product. A
Fabricator and erector work as a tightly knit team. The GC will meet with
them during bid preparation. They must assess the project site constraints to
position the erector’s crane, as it determines not only the steel erection sequence
but also the layout of other temporary facilities and thus the flow of many
construction resources. This sequencing in turn drives the fabrication schedule.
Page 44
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
It must of course meet the GC’s master schedule but must also be efficient4.
The fabricator who subcontracts the erection work has an incentive to minimize that
work and does so by thoroughly planning the sequencing and site delivery of steel
pieces in the order they will be needed.
As for logistics, a big difference between the industrial and the building
sector is that more often than not building space is very tight, especially on projects
located in an urban environment. Industrial projects tend to be more remotely
sited. Materials deliveries to building projects accordingly are constrained by traffic
patterns and transportation permit requirements. Trucks parked in the street along
the edge of a site ready to off-load steel may not remain there for any extended
time. When deliveries take place, the crane gets dedicated to off-loading and
moving pieces to a staging area, namely the highest floor with decking, from where
steel will subsequently be picked up and moved into final position. Only in
exceptional cases will steel be erected directly off the flatbed truck. This saves extra
handling steps but can be done only when it is acceptable to tie up the truck longer
and provided the steel has been loaded in inverse order needed.
Page 45
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
In a true JIT system, this timeliness pertains not only to a single hand-off
between two production steps, but rather, one aims at achieving JIT flow between
all production steps. In the idealistic extreme, this means having no buffers at all!
In practice, this means buffers must be determined strategically. Admittedly, doing
so is not an easy task, especially in a production system of complex products that
involve several organizations as is the case for structural steel. But this is what lean
Page 46
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
production systems design is all about: achieving flow where possible and
thoughtfully locating buffers and sizing them to achieve cost-effective
decoupling with minimal impact on cycle time.
The current practice of buffering stems from the desire to optimize labor and
machine utilization and from admitting that uncertainties exist in the supply chain.
Many uncertainties are the result of variability, which could be understood better if
at least it were measured and explicitly accounted for. This is not the current
practice in construction. Uncertainties and variability should not be taken for
granted. They should be acknowledged, managed, and minimized to a reasonable
degree. In fact, one technique to identify them is to reduce buffer sizes in-between
various production steps in order to see and learn the extent to which they are
needed. Process improvement efforts can then focus on those steps where the
impact on throughput of the system as a whole will be most significant. Example
improvements in construction are those that aim at reducing uncertainty, as is done
Page 47
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
for instance through reliable planning by the Last Planner (Ballard and Howell
1998), work methods design, and work structuring (Ballard et al. 1999).
Page 48
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
CHAPTER 5
A case study pertains contractors who bids on projects from County of San
Francisco, the Public Utilities Commission as well as the Water Department. Most of
these jobs include concrete of a well-defining and widely-used kind through
quantities usually small in comparison to what is needed for residential or office
building projects.
In urban settings, the task of delivering concrete moreoften than not has
been delegated to ready-mix batch plants and contractors has to rely on the timing
and reliability of their service. Although this set-up puts the contractor’s project
somewhat at the mercy of the batch plant, most batch plants perform at their very
best to meet their customers’ schedules.
On-time delivery is part of the product they sell. The interplay between
contractors and batch plants is interesting. On one hand, the contractor must order
a large enough quantity, sufficiently long ahead of time to ensure available batch
plant capacity and timely delivery service in order to maximize productivity of their
placing crew.
On the other hand, the batch plant tries to time its deliveries so that all projects
are served according to the contractors’ needs and the plant as well as the trucks
and drivers have little idle time. This balancing act between the two parties is not
always achieved due to the nature of concrete and the nature of the production
systems being used.
Page 49
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
In addition to contractors and batch plants, this balancing act also involves the
suppliers of raw materials to the batch plant, crews on site that erect formwork and
tie reinforcing basin preparation for concrete placement, as well as others.
The batch plant could, in order to level its load, vary its unit price of ready-mix
concrete based on the time and day of the week at which concrete is to be
delivered. This would illustrate a market mechanism at work, however, we are not
aware of such differential pricing being advertised in the industry today.
As one can imagine the city imposes limits on working hours in order to avoid
congestion during peak traffic times, excessively long closure of a road for vehicular
or of a sidewalk for pedestrian traffic, undue inconvenience of road users and
complaints about noise from citizens or area residents. In addition, contractors
must obtain a work permit from the city in order to work at a specific location.
Page 50
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
This contractor has its trucks pull into any batch- plant during operating
hours and order concrete. The contractor-owned trucks simply join the line of plant
trucks waiting to be loaded. The driver then goes to the operator’s walk-up window
and orders the needed mix design and quantity. The batch plant fills these trucks in
the same way as it fills its own in a first-in-first-out manner. The contractor then
gets billed on a regular basis for exact amount loaded. At the site, the driver works
with the crew in placing concrete.
Providing one’s own ready-mix trucks does not mean that the unit price of
concrete is any cheaper but it overcomes many scheduling hassles. No advance
order needs to be placed to reserve plant capacity as only a few cubic yards of
commodity mix are needed each time.
By taking control over the transportations process and the contractors crew
can work at their own pace and not have to fret over when concrete would arrive.
This kanban system work well especially on these projects where timing of need is
not dictated exclusively be the contractor, but as is the case here also to a
significant extent by the owner.
This contractors has its trucks pull into any batch-plant during operating
hours and order concrete. The contractor-owned truck simply join the line of plant
trucks waiting to be loaded. The driver then goes to the operators walk-up window
and orders the needed mix design and quantity.
The batch plant fills these trucks in the same way as it fills its own, in a first-
in-first –out manner. The contractor then gets billed on a regular basis for exact
amount loaded. At the site the driver works with the crew in placing concrete.
Providing ones own ready mix trucks does not mean that the unit price of
concrete is any cheaper but it overcomes many scheduling hassle. No advance
order needs to be placed to reserve plant capacity as only a few cubic yards of
commodity mix are needed each time.
Page 51
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
By taking control over the transportation process and using trucks as kanban
each time concrete is needed, the contractor’s crew can work at their own pace and
not have to fret over when concrete would arrive. This kanban system works well
especially on these projects where timing of need is not dictated exclusively by the
contractor, but as is the case here, also to a significant extent by the owner.
Should one batch plant not be able to serve his needs, he can easily go
elsewhere. The contractors pays for this ability. He now needs to have capital tied
up in trucks and is responsible for hiring and training drivers. Because he has a
fairly steady need for concrete from one project to the next(contrary to many
other who need concrete only for one phase of their work.)he can keep them
gainfully employed.
One alternative is favored over the other depending on the amount of control
the contractor wants in terms of on-time delivery of concrete and the variability in
the contractor’s demand for concrete project after project.
While these practices clearly exemplify JIT production, the paper was limited
in scope. No data was included to characterize the actual performance in terms of
timeliness, buffer sizes, error rates, etc. Moreover, the paper focused on batching
and delivery, which are only parts of the entire concrete production system.
Page 52
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
Current practices for managing the concrete supply chain upstream in terms
of raw materials acquisition or prerequisite work on site are not geared toward JIT
production. Further investigation is therefore warranted and significant process
improvements may be achieved by those working towards fully implementing a lean
construction system.
Page 53
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
Establishment JIT.
Implementation
Page 54
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
JIT ensures that suppliers deliver directly to the production floor to achieve
either a reduction in inventory or zero inventory and consequently a reduction in
production costs. Implementation of JIT building material management in
construction has the potential to realize the same far reaching benefits experienced
in manufacturing.
Page 55
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
Up till now Byggelogistik has been tested on six housing schemes, the first
being Sophiehaven approximately 20 miles north of Copenhagen. The project is a
typical Danish social housing project comprising 100 flats in two stories blocks,
erected in two phases - not a big project on an international scale (Bertelsen 1993,
1994-1, 1994-2). Contractually the project was undertaken by a general contractor
and approximately 10 trade contractors. The general contractor's staff participated
in the whole planning of the project.
It was also from the staff of the general contactor that the provider was
recruited and his job developed, as the project progressed, into being the
production manager of the construction site.
Those not participating were repeatedly in the way of those who were. In
the second phase all trades participated and this problem was solved. Even though
the methods were developed with EDP in mind the first tests were restricted to
management by paper and pencil only. EDP was used in the usual manner in the
participants' own operations but no attempt was made to use IT in the logistics.
Page 56
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
The main objective is to look not only at direct transportation costs but at all
costs in the building procesrelated to materials delivery. Materials are not
considered delivered until the workers lay their hands on them in the exact quantity
as the first step in the construction.
In the planning of the operations all supplies are described in detail aiming at
JIT supply once a day, comprising only materials needed until the next day, and
packed for the various trades and heir individual tasks and work areas. Such
assemblies of materials are named 'units'. Each type of unit is carefully specified to
include all materials needed for the particular task, and form of packing as well as
equipment for the delivery is detailed. Each type of unit is given a specific number
for identification.
Page 57
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
Several participants in the project consider the unit the most original element
in the whole concept. The idea is taken from the Swedish furniture chain Ikea who
sells furniture in parts to be assembled by the customer but with all the parts - and
often tools and assembly instructions in the same box. In order to manage
sorting, packing and delivery a close co-operation with the wholesale dealers must
be established. In Denmark 3 kinds of dealers cover all necessary materials, and
their warehouses are used as store room for the building site.
The dealers' drivers are considered as part of the building team in as much
as the aim is to employ the same drivers to load the trucks and deliver the
materials every day thereby making them familiar with the ever changing lay out of
the building site and choose the best sequence for the unloading.
Planning must take place in close co-operation between designers and trade
contractors, and the wholesale dealer's employees should take part in this. Tests
have shown that this kind of co-operation has resulted in a good deal of
suggestions for more appropriate solutions and choice of materials. At the same
time better terms for delivery are obtained since favorable prices may be offered by
the producers due to early notice.
Page 58
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
Page 59
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
CHAPTER 6
Presint 9 is the selected project to be used as our case study in this task. The selection was
made because Presint 9 is one of the examples of constructions using the IBS technique.
Located in our Government administration areas, this Presint 9 is one of the projects in the
development of Putrajaya areas. Presint 9 is the residential area construct by Setia Putrajaya
Sdn. Bhd. The company had managed to complete the construction of Presint 9 in a minimum
time by using the IBS method of construction.
Based on the observation carried out by Putrajaya Holdings, noticed that the contractor
only need four (4) month to complete the full structure of the apartment until level six (6)
comparing to the used of conventional method that can only construct full structure of the
building until level four (4) in the same period. Based on this statement prove that by using the
IBS system to the construction of the building may reduced the time for the completion. It also
be noted that this IBS system not only give the advantages in term of time to this construction
but also give benefit in term of cost for the development. The contractor managed to reduced
cost on labor because this method will reduced the used of labor in the construction. Moreover,
there will be a reduction in the cost of project, this is because this method will reduced the waste
in the construction that will contribute to the minimizing the cost of project. These prove that the
application of IBS method is one of the techniques that can achieve the implementation of JIT
approach.
6.2 Problem in the implementation JIT Approach into the Construction Industries
JIT gives a lot of benefits to our construction industries, but there are several problems that may
contribute to the failure on its implementation. The problems that occur may contribute to the
inefficiency and ineffectiveness for JIT approach been implemented. The problems may occur
based on the unique characteristic of the construction industries itself. Below are several
problems that been identified faced in the implementation of JIT approach in the construction
industries.
6.2.2 Weather
The production place for the construction is unique and not similar to other manufacturing
production. Generally, construction activities located in the open space known as site comparing
with manufacturing production that were conducted in the building. Weather is one of the factors
that may contribute to the interruption in the construction activities. The uncertainty of weather
may contribute to the problems in the JIT implementation.
To fulfill the client satisfaction, most of the procurement methods in our industries give a space
for the client to makes changes in the design during the construction progress. This factor may
effect the time and the cost for the project. We cannot achieve the completion dates because
the changes may influence to extend and add the time of completion for the project. Therefore,
JIT approaches are not applicable to this kind of construction.
6.2.4 Cost
IBS system been said as the effective construction technique in the implementation the JIT
approach. IBS system may cut the time factor for the construction industries and reduce the
numbers of delays on the project. The problem is the cost to be used in this system is higher
compared to the conventional techniques used in this construction industry.
Page 61
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
•Improve quality
IBS JIT
•Reduce wastage
•Quality of work •Right Materials
•Less labour
•Speed up of •Right Quantities
•Faster
construction process •Right Quality
•Economies
•Increase production (large scale production)
Step 1:
•Cost Saving To achieve JIT
philosophy required
•Applicable to all type of
to fulfil JIT 6 key
buildings
1 principles
Fabrication Theory
Framework
Assignment Step 3:
Framework Analyze that what is
the correlation with the JIT Key Principles
3 project result and IBS
•Pull System
advantages
•Top Management Commitment & Employee
Case
Involvement
Study: 2
•Elimination of Waste
Contractor or
Step 2: Analyze the
Project that using case study with the •Total Quality Control (TQC)
IBS in Malaysia JIT 6 key principles
•Uninterrupted Work Flow
implementation
•Supplier Relation = One Source
Assignment Flow
Page 62
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
6.4 ANALYSIS
Page 63
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
4 Total Quality Control (TQC) IBS System maintain the quality and high
aesthetic end products for the whole building
structure and envelope as it ensure a proper
arrangement of prefabricated beam and column
that fits to the building. This method will gives a
fine look of the building without any design or
material discrepancies that will spoil the
architectural style of the building.
Page 64
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
Page 65
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
4 Cost Saving From applying supplier relation with only one (1)
source of supplier, Putrajaya Holding Sdn Bhd
admitted that it really influences the efficiency of
project. In a construction project, good efficiency
means good cost saving.
5 Applicable to all type of From applying pull system in their IBS project,
buildings Putrajaya Holding Sdn Bhd admitted that it helps
in expedite the construction of various types of
multilevel apartments of Presint 9. Even though
this still in one (1) project case but even in one (1)
project required a variety of apartments type.
From this project, it is optimistic that it can be
applicable in other kind of buildings.
Page 66
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
6.5 CONCLUSION
After doing two times analysis (see analysis I and II) we can see for this particular project how
the correlation between adopting JIT principles and advantages in IBS system. Putrajaya
Holding Sdn Bhd doing IBS system in their project in Presint 9. We can see that in their process
of implementation IBS project they fulfill six (6) JIT key principles in the first analysis. Then we
try to relate with the main advantages of IBS in second analysis. We can see that Putrajaya
Holding Sdn Bhd also can obtain all the main advantages of IBS. From this case study
analysis, as a conclusion we can say that if a contractor doing an IBS project and applying JIT
six (6) key principles completely, there is a big opportunity that the contractor can obtain the
maximal of IBS system. From the theory framework (see figure 2), it could be explained that this
parallel correlation between JIT and IBS because both of it comes from the manufacture
philosophy. And with this case study, we can recommend that if you want to gain maximal
advantages of IBS system, by applying JIT in the process can give you a big guaranty of the
successful of the project. This recommendation can be use if Malaysian promoting IBS system
in their construction industry in the future.
Page 67
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
CHAPTER 7
JIT : CONCLUSION
Page 68
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
Low and Mok (1999) suggested a more practical application of JIT principles
for site layout in reducing and minimizing the occurrence of waste, and concluded
that the Kanban system can be modified for use in ordering and delivering
materials to site. People-related problems were, however, singled out as the main
difficulties in the implementation of the JIT philosophy (Low and Mok, 1999).
Page 69
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
REFERENCES :
Page 70
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
Page 71
RMB 511 CASE STUDY: INNOVATION IN THE MALAYSIAN HOUSING INDUSTRY
24) Howell, Gregory and Glenn Ballard. "Lean Production Theory: Moving
Beyond 'Can-Do'." Conference on Lean Construction, Santiago, Chile.
September, 1994.
25) Howell, Gregory and Glenn Ballard. "Managing Uncertainty in the Piping
Process." Source Document (number to be applied). Construction Industry
Institute, Austin, Texas (publication pending).
26) Ballard, Glenn and Gregory Howell. "Implementing Lean Construction:
Stabilizing Work Flow." Conference on Lean Construction, Santiago, Chile.
September, 1994.
27) Huovila, Pekka, Lauri Koskela and Mika Lautanala. "Fast or Concurrent-The
Art of Getting Construction Improved." Conference on Lean Construction.
Santiago, Chile. September, 1994.
28) Shingo, Shigeo. Study of the Toyota Production System. Japan Management
Association, 1981
Page 72