PS Protection Manual
PS Protection Manual
Note: This manual is in the formative stage. Not all the experiments have been covered here though they are operational in the laboratory. When the full manual is ready, we will make it available here.
Electrical Engineering Department, Birla Vishvakarma Mahavidyalaya (BVM) Engineering College, Vallabh Vidyanagar, Gujarat, India Pin:388120.
Section I
Section II
Section III
S
Source
A R1
Transmission Line
B R2
C R3
D
Fuse To Load
Fig. 1.1. A Typical Radial Transmission Line If the fault occurs in distribution network, fuse should isolate the faulty section. Should the fuse fail, relay R3 shall give back-up protection. Relays R1, R2, and R3 act as primary relays for faults in section I, section I, and section III respectively. If fault in section III is not cleared by relaying scheme at relaying point R3, relay R2 will act as a back-up. Similarly back-up protection is provided by relay R1 for faults in section II. A,B, C and D are substations in fig. 1.1. Generally Inverse time overcurrent relays with Definite Minimum Time feature (IDMT relays) are used in practice. There are many types of such relays available in relaymarket, viz. normal inverse relays, very inverse relays and extremely inverse relays. The characteristics of these relays are shown in fig. 1.2. The other types of o/c relays are 3 second relay and 1.3 second relay. This means the time of operation of the relay is either 3 or 1.3 second at Plug Setting Multiplier (PSM) equal to 10. Long time inverse relays are used for o/c cum overload application. Voltage restrains o/c relays have their own application. Very inverse relays are less prone to the ratio ZS/ZL. Extremely inverse relays are yet better. Very inverse relays are faster in operation for close-in faults yet maintaining the discrimination with fuse and other relays. Extremely inverse relays are more meritorious 1
in this aspect too. Instantaneous o/c relays are not immune to ZS/ZL ratio. Definite time o/c relays are 100 % immune to this ratio. Very inverse relays can be used with an additional advantage while protecting a machine or a transformer as they match with the heating characteristic of equipment better than their normal inverse equivalent. Extremely inverse relays can best co-ordinate with the fuse characteristic. The aim of this experiment is to reveal these facts experimentally.
Laboratory Simulations:
Referring to a.c. circuit of fig. 1.3. a live model of a radial feeder fed from one end can be self-understood.
Section - I 10/5 C1-1 9 Section - II 10/5 C2-1 9 10/5 Section - III C3-1
A R1
230 V, 50 Hz 1-phase, V ac supply S1
R2
S2
R3
S3
MCB
This is only a single phase version of a radial feeder. Transmission lines are simulated by 9 ohms resistors as we are studying only the steady state behavior of the relays and the network. Circuit breakers are simulated by contactors. Distributor is protected by a 0.5 Amp M.C.B. Semaphore indicators on the panel show the status of the contactor(whether ON or OFF). Visual neon lamp indictors are also used. Faults in different sections can be created by switches S1, S2 and S3. Fault limiting resistance of 18 ohms is used for practical purposes only, as otherwise the source would get shorted for a fault at start of the first section. For fault in distributor, Ohmic value of load rheostats can be decreased. MCB simulates fuses or MCCB. In actual practice C.T. secondary rated current (1 Amp or 5 Amp) and relay rating should be same. Here C.T. secondary rating is 5 Amp and relay rating is 1 Amp. This is contradicting the practice for for practical purpose.
A1-1 A2-1 A3-1 PB-3 PB-3 PB-3
T2
T3 R3-1
L1
L2
L3
R1-1
R2-1 A3-2
C1 110 V DC Supply
C1-2 PB-1 PB-2
C2
C2-2 PB-1 PB-2
C3
A1-2
A2-2
C3-2 PB-1
A1
PB-2
A2
A3
(a)
C1-3
C2-3
C3-3 Buzzer
110 V DC Supply
S-1 S-2 S-3
bulb
(b)
Referring to control circuit of figure 1.4(a) and (b), any section can be manually charged or made off using start (PB1) and stop (PB2) push buttons, which are spring loaded. On occurrence of fault, the corresponding section relay will operate and the concerned auxiliary relay A1, A2 or A3 will energize giving signal to the concerned contactor and making it off. This will also activate the buzzer and bulb which can be reset using Accept pushbutton PB3. Back up can be shown by using switches T1 and T2 on the panel. Time of operation of relays can be measured by a time interval counter connected as shown in fig. 1.4 (c).
S1 S2 S3 A1-4 A2-4 A3-4
(c) Fig. 1.4 Control Circuit in the Experiment. Observations and calculations: 1. Measure the fault currents for extreme faults in sections I, II and III by adjusting the corresponding rheostat in minimum (zero resistance) and maximum (full resistance) positions and using the corresponding fault-switch S1, S2, or S3 (refer fig. 1.3). Maximum fault currents in sections I, II and III are denoted by F1, F2, F3 respectively and the minimum fault currents by F1, F2, F3 respectively. Deactivate the relays for this purpose. Record the readings in table 1:
Fault Location F1 F1 F2 F2 F3 F3
Table:1.1 Measured fault currents for extreme faults in each section 2. Calculate the plug settings (or Tap Value) of relays R1, R2 and R3. (Plug settings will be same irrespective of type of relays ). For this purpose, assume the number of distributors each of 0.5 Amp rating from the following possibilities (The experiment 4
is a simulation and hence the distributor current is 0.5 Amp. In actual practice it may be 500 Amp or more or less): Number of distributors: 1, 2, 3 or 4. (Calculations of the plug setting shall be done w.r.t. following considerations.) (I) The plug setting shall be more than or equal to the maximum full-load current passing through the relay. (II) The pick up of the relay varies from 1.05 to 1.3 times the plug setting of the relay. (III) For back up, relay R1 shall reach for the fault F2 and R2 for the fault F3. 3. Time Settings. (Normal Inverse Relays) For deciding time-settings, co-ordinate the characteristic of relay R3 with that of an MCB.( Refer figures 1.5 and 1.6.) Use discriminating time-interval of 1.0 second between two characteristics. This will decide TMS of R3. Why discrimination time of 1.0 second? (Try answer to this question.) For coordinating R2 with R3, use the worst possible current to decide TMS of R2 (F3 in table:1.1). Similarly decide TMS of R1 by using F2 and setting of R2. Use discriminating time interval between two successive relays as 0.4 seconds (why 0.4 seconds?) for these calculations. Tabulate the results as follows: Normal inverse Relays.
Relay R1 R2 R3
P.S.
TMS
Table:1.2 Calculated relay settings. 4. Time-settings (Very Inverse Relays) Similar exercise as at Sr. No. 3 above can be carried out for very inverse relays also. The results are to be tabulated as in the case of normal inverse relays as per calculated settings. Use figure 1.5 and 1.7 for deciding TMS of very inverse relays. 5. Set the normal inverse relays as per the settings in table 1.2. 6. Calculate the time of operation of the main and back-up relays for extreme faults in each section using the relay settings in table:1.2 and the fault current readings recorded in table:1.1. Enter these in table:1.3 as Calculated Time of Operation. 7. Vary the 550 ohms load resistance such that the current in the radial feeder varies from 0.5 Amp to about 4 Amp. See that MCB trips and relay R3 does not trip. 8. Now create extreme faults (one by one) in each section starting from section III. For each fault, measure the time of operation of the main and the back-up relay (to measure time of operation of back-up relay, the main relay has to be deactivated using switches T2 or T3 (as the case may be) in fig. 1.4). Record these in table 1.3 as Measured Time of Operation. Calculate the error between the calculated and the measured time of operation for each fault and record it in table: 1.3. 9. Derive the table 1.4 from table 1.3 as follows:
Relays
Table 1.4 Difference in time of operation of relays for extreme faults. Section Observed Calculated
R1 R2 R3
I II III
10. Replace the normal inverse relays by very inverse relays. 11. Repeat steps at Sr. No. 5 to 9 for very inverse relays. 12. Draw your own conclusion.
Questions:
1. Explain the circuit of the experiment. 2. What is the function of semaphore indicator? 3. Why are the settings of the earth-fault relays lower than the settings of the overcurrent relays? 4. Draw an a.c. circuit and d.c. control circuit for two overcurrent and one earth-fault scheme of protection of a feeder used in practice. How does our experimental scheme differ from that? Why? 5. What do you understand by time discrimination? 6. What do you understand by overshoot of a relay? 7. What is the significance of resetting time of a relays? 8. What do you understand by back-up protection? Explain remote back-up protection. 9. How does the source impedance affect the choice of relay to be used in radial feeder protection? 10. Why are the IDMT relays popular in practice? 11. What are the factors to be considered for deciding settings of phase relays and ground relays?
1.3
A R1
F1
B R3
To Load
S
Source
3 D R2
F2
C R4
Fig. 1 Parallel feeder network It is required that for fault at F1, CB 1 and 2 should trip. Similarly CB 3, 4 should trip for fault at F2. In this scheme if we use all overcurrent relays, the following problem arises: If fault occurs at F1, R3 should operate and R4 should give back-up to relay R3. This means, time of operation of R4 should be more than that of R3, current being same. Let the settings be done according to this criterion. Now, for the fault at F2, it is required that relay R4 operate and relay R3 operates to provide backup. This fact requires that relay R3 should operate later than R4. But the relay settings are not satisfying this condition. Hence by using simple IDMT o/c relays it is impossible to fulfill both the criteria. To solve this problem we have to introduce an additional directional feature in the relays R3 and R4. These relays will operate only if the fault current is flowing away from the bus. Relays R1 and R2 are kept as non-directional IDMT o/c relays. Now, for the fault at F2 since the current through R3 is in the non-operative direction, the relay doest not operate. Relay R4 operates as the directional criterion is satisfied. Hence for fault at F2, R2 and R4 operate and if R4 fails to operate R1 provides the backup. Relays operate on similar lines for fault at F1.
Laboratory Simulations:
Referring fig. 2, a model for parallel feeders fed from one end is self explanatory. This is a single-phase version of the parallel feeders. One feeder is simulated by two 9 , 12 A rheostats in series. Load is simulated using a 185 , 1.1 A rheostat. Faults are simulated using switches S1 and S2 and a limiting resistance of 9, 12 A is used to limit the fault current. The control circuit is similar to that in the radial feeder simulation (Refer to fig. 3, 4 and 5) except for the additional PT to feed directional overcurrent relay. Remote backup can be seen by closing a CT secondary shorting switch at the rear of the panel (thus, making the corresponding relay non-operational).
Procedure:
1. 2. 1. 3. Do the connections as per the circuit diagram. Set the relays according to your calculations. 3 Create the faults and observe whether relays are operating in desired manner. Observe the backup protection using C.T. shorting switch at rear of the panel.
Questions:
1. Draw at least three single line diagrams of power system network where Directional feature is required. 2. What are the problems of Directional relays. 3. What do you understand by Zero Torque Line, Maximum Torque Line, MTA characteristic, Dead Zone, Characteristic Angle? 4. Out of 300 , 600 and 900connection, which would you prefer? 5. Draw figures for phase advancing techniques in phase and ground directional relays.
110 V DC Supply
110 V DC Supply
3. Now to simulate prime-mover failure, make switch S1 on. Relay D1 will de-energize, hence D1X, deenrgizes. D1x-1 will close and the auxiliary relay A1 will operate. A1-1 will isolate the faulty turboalternator from bus. Buzzer, bulb and semaphore indicators operate the same way as for other experiments. 4. Open S1. Then open S3. Now make contactor C1 On with push button. 5. Close S2 to simulate zero power in alternator-2. On similar lines to what is explained in steps 1-3, contactor C2 will open. 6. Draw your own conclusion.
110 V DC
+
--
In early days, a time delay was used to deal with the magnetizing inrush. This compromised relay performance when the transformer energizes with a fault already present in the system. The present remedies are: 1. Even harmonic cancellation. 2. Harmonic restraint. 3. Harmonic blocking. 4. De-biasing. Laboratory Simulation Fig. 1 shows the main circuit for demonstrating the biased differential protection. The function of PB1, PB2 and PB3 is to start, stop and to reset the circuit respectively. The switches S1, S2, and S3 are provided to make the fault at different locations. S1 is for an external fault, S2 is for an internal fault, and S3 is for a severe internal fault. The transformer has primary taps for 230V, 199.8 V, 115 V, 53.3 V and secondary taps for 110 V, 95.48 V, 55 V and 25.5 V. Procedure: PART-A Application of DTTM-11 for protection of single phase transformer 1. From the rating of the transformer (230/115 V, 1 kVA), the CT ratings (10/5 A on primary, 20/5A on secondary), calculate the basic and bias settings of the relay, as well as the setting of the high-set unit. 2. Set the DTTM-11 relay according to calculations. Connect the circuit as shown. 3. Keep the secondary circuit open-circuited. Push PB1 button to energize the transformer with no load. Observe that the transformer can be energized without the relay operating. Repeat this process several times and observe the relay never operates while energizing the transformer. This is because DTTM-11 has the second harmonic restraint feature. This obviates the necessity of time delay during starting. 4. After switching the circuit off, complete the secondary circuit and make the circuit ON. Observe that relay does not operate for normal condition. 5. Make S1 ON, and observe that the relay does not operate for external faults as proved in the calculations. Switch S1 OFF. 6. Energize the circuit. Make S2 ON (internal fault on secondary side), and observe that relay 87 operates as proved in the calculations. Switch S2 OFF. 7. Energize the circuit. Make S3 ON (internal severe fault) and observe that unit 87 and the high set unit both operate as proved in the calculations. Switch S3 OFF. 8. Introduce a variable resistance across the secondary of CT on the secondary as shown in fig. 1. This simulates CT saturation or CT mismatch. Energize the circuit. Create an external fault using S1. Observe if the relay mal-operates. Decrease the CT secondary resistance till the relay mal-operates. Now switch off the supply, increase the bias setting and switch on the circuit again. Observe that for the same external fault, the relay does not operate. PART-B Effect of tap-changing and effect of inrush current: 1. Shift the transformer to another table that has similar set-up but has ABB-make type T relay. This relay does not have second harmonic restraint capability. Set this relay
2.
3. 4. 5.
with the same settings as for DTTM-11 relay. However, simulate the load resistance with an 18 rheostat. Repeat step 3 of part-A above. Observe that the relay mal-operates several times. The intensity of inrush depends on the instantaneous value of the input voltage when the transformer is energized, hence the relay does not mal-operate all the times. Now repeat the same process with increased time delay setting (this setting is provided with this relay). Observe the mal-operation ceases. However, this remedy is dangerous if the transformer is energized with an existing fault, especially in a part of system that has high fault levels. Keep the time delay in effect for the rest of the experiment. Switch off the circuit and connect the secondary circuit. Switch on the transformer and observe the relay not operating for normal operation. Change the primary tap to 199.8 V and repeat step-3. Observe the relay mal-operates. Increase the bias setting and switch on the circuit. Observe that the relay does not operate.
Fig. 1