0% found this document useful (0 votes)
41 views

Generator Winding

The document discusses a case study of detecting and confirming an endwinding problem in a large, hydrogen cooled turbo generator that had been rewound. Periodic online testing revealed a sharp rise in endwinding activity on one phase. Offline partial discharge testing quickly located and identified high partial discharge activity between the phase lead and a coil leg.
Copyright
© Attribution Non-Commercial (BY-NC)
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
41 views

Generator Winding

The document discusses a case study of detecting and confirming an endwinding problem in a large, hydrogen cooled turbo generator that had been rewound. Periodic online testing revealed a sharp rise in endwinding activity on one phase. Offline partial discharge testing quickly located and identified high partial discharge activity between the phase lead and a coil leg.
Copyright
© Attribution Non-Commercial (BY-NC)
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 1

CASE STUDY: Detection and confirmation of endwinding problem in a rewound, large, hydrogen cooled turbo generator.

Company: Ratings: A midwest U.S. utility 690MW Turbine Generator, 3600RPM, 20kV, Hydrogen cooled @ 59 PSI

Manufacturer: Confidential Related Info: PD Sensors: Installed in 1984, rewound in 2000 SSCs and two 80pF couplers per phase installed in 1999-2000

Details: After a rewind, periodic online testing utilizing both SSCs and 80pF EMCs revealed two trends; an overall downward trend in slot PD, an expected result following a rewind, and an alarmingly sharp rise in endwinding activity on C phase. A Qm of 177 mV is higher than 98% of similar machines in the Iris database. The activity was suspected to be a single point of phase to ground activity on C phase that was also coupling to the other phases. In December 2001, a recommendation for close monitoring and visual inspection at the earliest convenience was made. In March 2002, Iris Power Engineering was requested by the customer to perform a visual inspection and off- line PD testing as required on the unit. During the offline testing a site of visible, high PD activity was quickly located using a Corona probe in conjunction with a stator wiring diagram. The source of high PD activity was identified and verified as occurring between the phase lead on C phase in slot 36 and the second coil leg down (top bar) on the A phase in slot 35. The plots below illustrate the 2D test results for Endwinding and Slot discharges acquired with the SSC in slot #36.