User Manual Installation BOM Extraction For Elevators - Draft

The document provides instructions for extracting and posting installation material bills of materials (BOMs) and man hours for elevator installation projects in SAP. It outlines the process flow and provides step-by-step guidance on how to add and post installation material and man hours to a project using transaction codes in SAP. The user manual is intended to help Mitsubishi Elevator ETA India Pvt. Ltd estimate and track installation material and labor for elevator installation projects.

Uploaded by

sudhakp
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
672 views10 pages

User Manual Installation BOM Extraction For Elevators - Draft

The document provides instructions for extracting and posting installation material bills of materials (BOMs) and man hours for elevator installation projects in SAP. It outlines the process flow and provides step-by-step guidance on how to add and post installation material and man hours to a project using transaction codes in SAP. The user manual is intended to help Mitsubishi Elevator ETA India Pvt. Ltd estimate and track installation material and labor for elevator installation projects.

Uploaded by

sudhakp
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 10

SAP IMPLEMENTATION PHASE II (Installation Material)

USER MANUAL FOR ELEVATORS INSTALLATION BOM EXTRACTION

for

Mitsubishi Elevator ETA India Pvt. Ltd


(Formerly ETA MELCO Engineering Co. Pvt. Ltd)

This is a hardcopy of document maintained on electronic media. It is the latest version.

November 2013

User Manual: Installation BOM Extraction for Escalators

Table of Contents
Table of Contents....................................................................................................... 2
Process Flow:........................................................................................................... 3
Installation Material and Man Hours........................................................................4
To add Installation Material:.................................................................................... 6
To post Installation Material:................................................................................... 7
To add Man Hours:.................................................................................................. 8
To post Man Hours:.................................................................................................. 9

User Manual: Installation BOM Extraction for Escalators

Process Flow:

Inquiry
Inquiry

Quotation
Quotation

Sales Contract

Post Installation
Material

Post Man Hours

User Manual: Installation BOM Extraction for Escalators

Installation Material and Man Hours


T.Code: ZINST_MAT - Material Installation and Man Hour
Select Elevator from the Menu under Installation Material

Select the Sales Contract and the Item Number for which the installation material
and Man Hours to be estimated and click on Fetch Data

User Manual: Installation BOM Extraction for Escalators

The screen will be populated with the data as below:

If the data retrieved by the system needs to be changed, Click on


change the values and click on Save after updating.

to

User Manual: Installation BOM Extraction for Escalators


Click on Simulate to get the list of Installation Local Material and Man Hours.

To add Installation Material:


The installation material can be added under the Add Installation Material Tab, by
using

and

User Manual: Installation BOM Extraction for Escalators

To post Installation Material:


Click on

to post the installation material to the project.

Installation Material will be posted to the project and the status of upload will be
displayed with remarks as below.

User Manual: Installation BOM Extraction for Escalators

To add Man Hours:


The Man Hours can be added under the Add Man Hour Tab, by using

and

User Manual: Installation BOM Extraction for Escalators

To post Man Hours:


Click on
selected project.

to post Man Hours under Installation Labour of the

Validate the uploaded data in the project explorer


T Code: CJ20N

User Manual: Installation BOM Extraction for Escalators

10