Cane Roads Progress Report - Docx (St. Elizabeth) - Report 2 (01!11!13)
Cane Roads Progress Report - Docx (St. Elizabeth) - Report 2 (01!11!13)
Cane Roads Progress Report - Docx (St. Elizabeth) - Report 2 (01!11!13)
PROGRESS REPORT PROPOSED NATIONAL CANE ROADS PROGRAMME AT APPLETON SDA ST. ELIZABETH
: MOAF/STU/CR-2013/008 : B.F. Pavement and Consultants Limited : (A) Lancaster Two Mile Wood (B) Bogue - Elem
LENGTH OF ROAD
ORIGINAL CONTRACT SUM AMOUNT CERTIFIED TO DATE COMMITMENT TO DATE PROPOSED DURATION PROPOSED STARTING DATE ACTUAL STARTING DATE SCHEDULE COMPLETION DATE
: J$30,286,716.25 : 1,460,200.00 : 6,288,325.00 : Four (4) Months : September 09, 2013 : September 10, 2013 : January 09, 2014
Problems/Comments: While some of the NWC leaks have been repaired, there are others that still need attention. A failure in the road structure needed to be excavated and filled with suitable material.