Cane Roads Progress Report - Docx (St. Elizabeth) - Report 2 (01!11!13)

Download as docx, pdf, or txt
Download as docx, pdf, or txt
You are on page 1of 2

Period: (September 30, 2013 to October 31, 2013)

PROGRESS REPORT PROPOSED NATIONAL CANE ROADS PROGRAMME AT APPLETON SDA ST. ELIZABETH

CONTRACT No. CONTRACTOR ROAD SECTIONS

: MOAF/STU/CR-2013/008 : B.F. Pavement and Consultants Limited : (A) Lancaster Two Mile Wood (B) Bogue - Elem

LENGTH OF ROAD

: (A) 2,500 m : (B) 3,393 m : (Total) 5,893 m

ORIGINAL CONTRACT SUM AMOUNT CERTIFIED TO DATE COMMITMENT TO DATE PROPOSED DURATION PROPOSED STARTING DATE ACTUAL STARTING DATE SCHEDULE COMPLETION DATE

: J$30,286,716.25 : 1,460,200.00 : 6,288,325.00 : Four (4) Months : September 09, 2013 : September 10, 2013 : January 09, 2014

PERCENTAGE COMPLETION TO DATE: 21.1% PERIOD ELAPSED : 2 Months

Period: (September 30, 2013 to October 31, 2013)


Scope of Works: Site Clearance a) Bushing 6,430m b) Clean silt and mud from road edge 6,430m Drainage Clean existing culvert 4 m Construct earth drain 300 m Clean outlet/ inlet-earth drain 7 m Clan existing earth drain 463 m Earthworks Prepare formation 12000 m Excavation of soft spots 40 m Borrow to fill - 1809.65 m Base material 3000 m

Problems/Comments: While some of the NWC leaks have been repaired, there are others that still need attention. A failure in the road structure needed to be excavated and filled with suitable material.