Project Management Charter PDF
Project Management Charter PDF
Define Scope
Change Log
Ad Hoc Reports
Status Report
Meeting Agenda
Risk Assessment
Closure Report
January 2010
Page ii
Table of Contents
1. Project Description ....................................................................................................... 1 2. Business Objectives and Success Criteria ..................................................................... 1 3. Preliminary Project Scope ............................................................................................. 1 4. Cost-Benefit Analysis .................................................................................................... 2 5. Assumptions and Dependencies ................................................................................... 3 6. Milestones..................................................................................................................... 4 7. Business Risks................................................................................................................ 4 8. Resources ...................................................................................................................... 4 9. Approvals ...................................................................................................................... 5 10. Revision History ............................................................................................................ 5
Page 1
1. Project Description
This projects goal is to replace the legacy phone systems in allocations with a new Voice Over IP (VoIP) system that gives users better call quality while vastly expanding the features offered to manage both incoming and outgoing phone calls, which ultimately will help improve the customer experience.
Page 2
4. Cost-Benefit Analysis
The primary costs for the project initially is the physical hardware (phones, server, etc). Long term costs, mostly on a monthly basis, include the cost of phone lines, a per minute charge on incoming 800 calls, etc. The IT Department will be responsible for the labor of deploying the phone system, with the potential for some outside help with running wire. Major benefits include: lower monthly charges, integration with current and future sites, better reporting, and more advanced features like call cascading, caller ID, DIDs, voicemail, etc.
Cost Estimate
This estimate is based on quotes from several vendors on the required equipment and services. Costs and cost savings have been calculated based on replacing all phone systems throughout the company. This estimate does not include any internal resource time required for testing and implementation; it solely covers the physical costs of hardware, software, and services.
Quantification
800 incoming rate goes from 2.9 to 2.1 per minute, lines cost $25 vs. $38, outgoing long-distance is no extra charge, yearly maintenance is $1,500 less, and we will have a unified bill instead of two separate phone systems
Estimated Impact
$ 26,000 a year savings
$26,000
Page 3
Dependencies: DE-001: Project success will be largely dependent on commitment and support from company management for budget and resources
Page 4
6. Milestones
Event or Deliverable
Project charter approved Project plan completed Project plan approved Phone System Ready For Testing Phone System Sign-off by key stakeholders Training Completed Acceptance
Target Date
Responsibility
Sponsor Project Manager Sponsor Project Team Project Team Users / Project Team Sponsor / Project Team
7. Business Risks
Risk
Project resources will be taken away to work in their core functions New system call quality will not meet expectations **Additional risks will be document during Risk Analysis
Probability
HIGH LOW
Impact
Delays Cost, Inconvenience
Mitigation
Old phone system will remain in place to fail back to for several months
8. Resources
Resource
John Doe James Doe Joe Doe Technical Oversight, IT Technical Support, IT Technical Support, IT
Page 5
9. Approvals
Approval Decision: Approved, development project plan is authorized Approved, project funding is authorized Approved, but project is on hold until future notice Revise charter and resubmit for approval Project is rejected
Role or Title
President CFO
Date
Page 1
13.
John Doe
14. 15.
1 of 2
Page 2
Will have their work disrupted by this project? Will have to change their systems or processes because of this project? Will benefit from this project? (If this is a large group, who will represent this group?) Will perform the work on this project? (This includes all vendors and subcontractors as well as employees) Will participate in phase gate decisions to approve moving the project to the next phase?
n/a n/a At some level, anyone in the company. Main beneficiaries will be employees that interact with the phone more than others. John Doe, Jimmy Doe James Doe, Juan Doe, John Doe
19. 20.
Name:
1. 2. 3. 4. What is their contribution to the project? To whom do they report? What authority do they have over the project? What is their goal for the project (what is their stake in the project) and how does it relate to their organizations goal or other personal goals? (What makes this a win for them?) Do they present a specific threat or opportunity? What perception do you want them to have about the project?
Title:
5. 6.
Plan Communication
Use the Communication Plan and Responsibility Matrix templates to document roles and responsibilities and how youll keep your stakeholders engaged and informed.
2 of 2
Page 1
Last Updated:2010.08.31
Description
The new phone system should be able to receive both local, long distance, and all of our 800 calls The new phone system should be able to place both local, long distance, and 800 calls The system should be able to page the warehouse over bull horns The system should be able to handle DID's so individuals can have a personal phone number The new system should be scalable, easily extended to our current and any future remote locations It should support having our own custom hold music It should be able to forward calls to specified numbers or extensions based on rules Users should be notified by email when they have a voicemail The system should support different types of call groups and queue's based on business need Specified individuals should receive automated reports on call volume and individual performance All 800 numbers and several local numbers must be able to be ported to the new system In case of a downed line, etc, there has to be a viable and economical backup solution The new system should be able to be run in a virtual environment The new system should integrate with AD to reduce the amount of user management overhead for administrators General General Joe Doe Jose Doe General
Requestor
Juanita Doe Josh Doe General General Jill Doe General Jose Doe John Doe John Doe
Page 1
Scope Statement
This project is responsible for implementing a new VoIP telephony solution. Specifically, the project will: Purchase the necessary equipment to deploy a new phone PBX and new phones to the entire company, only replacing existing phones, not adding additional ones. Recreate the existing phone business rules on the new phone system Implement voicemail and DIDs on specified numbers (dictated by the functional manager) Train users on how to use the new phones at group meetings pre go-live
The following activities are beyond the scope of the project: Any integration of the new VoIP solution and our ERP application Adding any additional lines, phones, or functionality that does not already exist in the current phone system and has not been specifically mentioned in the scope statement.
Page 1
1.0 Research
1.1 Compare IP-PBX Options 1.2 Document Capabilities 2.1 Evaluate potential IP-PBX Options 2.2 Recreate existing PBX functionality on test IP-PBX 2.3 Implement and test new features IP-PBX offers 2.4 Work with stakeholders to identify best fit solution 3.1 Procure hardware
VoIP Implementation
2.0 Testing
3.2 Migrate test system settings to new production IP-PBX system 3.0 Implementation
3.3 Test new system with stakeholders input 3.4 Deploy and implement to secondary location first 3.5 Deploy and implement to primary location second
ID 1 2 3 4 5 6 7 8 9 10 11 12
WBS
Task Name
Cost $400.00 $80.00 $160.00 $160.00 $400.00 $320.00 $40.00 $120.00 $800.00 $160.00 $1,600.00 $1,600.00
Duration 5 days 1 day 2 days 2 days 1 wk 2 days 0.5 days 1.5 days 2 wks 1 day 4 wks 4 wks
Start Mon 8/30/10 Mon 9/6/10 Tue 9/7/10 Thu 9/9/10 Mon 9/13/10 Mon 9/20/10 Wed 9/22/10 Thu 9/23/10 Mon 9/27/10 Mon 10/11/10 Tue 10/12/10 Tue 11/9/10
Finish
Predecessors
Resource Names 22 John Doe John Doe John Doe John Doe John Doe Juan Doe John Doe John Doe John Doe Juan Doe John Doe John Doe
1.1 Research IP-PBX solutions and document about each 2.1 Compare requirements to advertised functionality 2.2 Recreate existing PBX functionality on test IP-PBX 2.3 Implement new PBX features 2.4 Work with stakeholders to identify best solution 2.4.1 Project manager decides on solution 3.1 Procure Hardware 3.2 Migrate test system to production 3.3 Test systems with stakeholder input 3.3.1 Get final stakeholder signoff 3.4 Deploy and implement to test location 3.5 Deploy and implement to primary location
Fri 9/3/10 Mon 9/6/10 1 Wed 9/8/10 2 Fri 9/10/10 3 Fri 9/17/10 4 Tue 9/21/10 5 Wed 9/22/10 6 Fri 9/24/10 7 Fri 10/8/10 8 Mon 10/11/10 9 Mon 11/8/10 10 Mon 12/6/10 11
Sep '10 Oct '10 29 5 12 19 26 3 John Doe John Doe John Doe John Doe John Doe 9/21 John Doe John Doe
10
17
24
Nov '10 31
14
21
Dec '10 28 5
12
19
26
Jan '11 2
16
23
Feb '1 30
August 2010
Sunday 1 Monday 2 Tuesday 3 Wednesday 4 Thursday 5 Friday 6 Saturday 7
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
September 2010
Sunday Monday Tuesday Wednesday 1 Research IP-PBX solutions and document about each, 5 days Thursday 2 Friday 3 Saturday 4
10
11
Compare requirements to advertised Recreatefunctionality existing PBX ,1 functionality day on test IP-PBX, 2 days
12
13
14
15
16
17
18
19
21
22
23
24
25
26
27
28
30
October 2010
Sunday Monday Tuesday Wednesday Thursday Friday 1 Test systems with stakeholder input, 2 wks Saturday 2
10
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
November 2010
Sunday Monday 1 Tuesday 2 Wednesday 3 Deploy and implement to test location, 4 wks Thursday 4 Friday 5 Saturday 6
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
December 2010
Sunday Monday Tuesday Wednesday 1 Deploy and implement to primary location, 4 wks Thursday 2 Friday 3 Saturday 4
10
11
12
13
14
15
16
17
18
19
20
21
22
23
24
25
26
27
28
29
30
31
Page 1
Stakeholder
Information needs
Frequency
Medium
Joe Doe Jose Doe Josh Doe Jill Doe Juanita Doe
Status update Status update Status update Status update Status update
1. 2. 1. 2. 1. 2. 1. 2. 1. 2.
In person Via Email In person Via Email In person Via Email In person Via Email In person Via Email
WBS
1.0
Assigned
John Doe
Description
Project resources will be taken away to work on other tasks/projects Risk that some potential options might be overlooked Risk that some things will not be able to be recreated by the new IP-PBX Some stakeholders will not buy into new solution Delays in procuring hardware or software licensing Risk that moving fax or phone lines over will delay implementation
Strategy
Inform stakeholders of consequences of loss of resources Consult with several vendors on best-inclass IP PBX options Test and work with vendor to establish what the new system can and can not do
Status
Ongoing battle
2 3
2.1 2.2
6 2
2010.08.07 2010.08.01
Completed Completed
2010.08.05 2010.08.07
2.4
2010.08.01
Joe Doe
3.1
2010.08.01
John Doe
3.4
2010.08.01
John Doe
Inform, communicate with, and interact In Progress to meet needs and address concerns of stakeholders Consult hardware and software suppliers Completed to ensure product is will be in stock at time of order placement Work with phone providers to get In Progress information in their hands as soon as possible and ensure information is correct
2010.08.23
Description of fields:
Risk Id: A unique identifier WBS: WBS number of the task(s) related to this risk Likelihood: What are the chances that this risk will occur? Rank with 10= highest and 1=lowest. Date found: Date risk became known. yyyy.mm.dd Assigned to: Person who is assigned to manage this risk Description: High level description of risk event, impact and probability Strategy: What will be done to reduce the probability, impact, or both? Status: On-going log of changes to risk, in order from most recent to oldest. Format: yyyy.mm.dd action/update Close out date: When did the risk probability go to zero? Describe in the final status. Remove any rank from this risk.
Design, build, test, and implement a 1 VoIP phone solution Determine stakeholder expectations in 2 order to define a course of action
3
Scope Comparison
Additional scope No additional scope added to project. Decreased scope Scope was not decreased during project
Cost Performance
Cost Categories Internal Labor hours External costs Labor (consultants, contract labor) Equipment, hardware or software List other costs such as travel & training Explanation of cost variance Additional hours were required for configuration, testing, and implementation. 0 50,000 5,000 0 42,180 3,500 Approved 160 Actual 200
Schedule Performance
Approved Project completion date Explanation of schedule variance Implementation was smooth and telephone providers were able to deliver ahead of schedule. 2010.10.01 Actual 2010.09.25
Closure Acceptance
Role or Title
President CFO Project Manager Project Sponsor
Date
Description of fields:
Change Id: A unique identifier Date Submitted: Date issue became known. yyyy.mm.dd Requested by: Person who is requesting the change Description: Describe the change being requested. Impact: Describe the impact to cost or schedule. Status: Approved or Pending or Rejected and date.
Impact Analysis Schedule Cost Related affects to other projects or parts of this project
Attended?
Agenda Item 1. [topic description] [topic discussion] [topic resolution] 2. [topic description] [topic discussion] [topic resolution] 3. [topic description] [topic discussion] [topic resolution] 4. [topic description] [topic discussion] [topic resolution] 5. [topic description] [topic discussion] [topic resolution]
Whos Responsible
Time Allotted
Cost performance 0 % under/over budget Planned cost to date $13,000 Actual cost to date $13,000 Approved project cost baseline $50,000 Estimated cost at completion $48,000 Schedule performance 0% ahead/behind schedule attach a tier 1 Gantt chart with baseline and current schedule
Issues identified this period and required action 1. Phones blinking even if no voicemail present 2. Reception phone needs to be configured
Major accomplishments scheduled for next week 1. Final configuration to replicate call routing 2. Meeting with key usage stakeholders to discuss details and any additional requirements