Vico Indonesia: Job Safety Analysis

This document outlines the job safety analysis for task ADQ15 - Unjay Packer on Rig 453. It describes 6 steps of the task including setting up equipment, inspecting components, setting and removing slips, attaching the torque indicator, working the drill string, and resetting slips if needed. Potential hazards are identified for each step such as damaged equipment, tripping hazards, and movement of heavy components. Controls include visual inspections, function tests, staying clear of moving parts, and using appropriate safety clothing.

Uploaded by

Dian Sikumbang
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
66 views3 pages

Vico Indonesia: Job Safety Analysis

This document outlines the job safety analysis for task ADQ15 - Unjay Packer on Rig 453. It describes 6 steps of the task including setting up equipment, inspecting components, setting and removing slips, attaching the torque indicator, working the drill string, and resetting slips if needed. Potential hazards are identified for each step such as damaged equipment, tripping hazards, and movement of heavy components. Controls include visual inspections, function tests, staying clear of moving parts, and using appropriate safety clothing.

Uploaded by

Dian Sikumbang
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 3

VICO INDONESIA

JOB SAFETY ANALYSIS.

RIG 453
TASK NO Created UNJAY PACKER 18 / 12 / 1997 TASK NO ADQ15 Review Date PAGE 1 OF 3 / / 19..

NO. 1(A).

STEP SET UP EQUIPMENT AND CHECK.

HAZARD SNUB LINES DAMAGED. EQUIPMENT FAULTY.

CONTROL VISUALLY CHECK ALL LINES, SHACKLES, PINS FIXING POINTS AND EQUIPMENT TO BE USED. CHECK SHACKLES AND SAFETY PINS (SPLIT PINS). ARRANGE HOSE TO MINIMISE TRIP HAZARDS. CHECK FOR CONDITION, SECURITY AND SERVICIBILITY.

1(B)

MAKE UP TORQUE SENSOR ON MAKE UP SNUB LINE.

SECURITY OF TORQUE INDICATOR. TRIP HAZARD OF LINE TO GAUGE.

1(E)

CHECK SLIPS.

WORN DIES. DAMAGED/MISSING BOLTS SAFETY PINS. WORN DIES. DAMAGED/MISSING BOLTS. SAFETY PINS. UNLOCKED BUSHINGS.

1(C)

CHECK SLIPS.

CHECK FOR CONDITION, SECURITY AND SERVICIBILITY.

1(D)

CHECK BUSHING.

CHECK BUSHINGS LOCKED.

APPROPRIATE SAFETY CLOTHING AND EQUIPMENT MUST BE WORN AND USED

VICO INDONESIA
JOB SAFETY ANALYSIS.

RIG 453
TASK NO Created NO. 1(E) UNJAY PACKER 18 / 12 / 1997 STEP INSPECT TUGGER, HOOK FITTINGS. HAZARD DAMAGE TO TUGGER LINE, HOOK FITTINGS. TUGGER NOT FUNCTIONING. FAILURE OF SNUB LINE WHEN NEEDED. TASK NO ADQ15 Review Date CONTROL CHECK EQUPMENT. FUNCTION TEST. PAGE 2 OF 3 / / 19..

1(F)

INSPECT SNUB LINES.

CHECK FOR CONDITION (ESPECIALLY IN END OF TONG FITTINGS). STAY CLEAR. STAY CLEAR. STAY CLEAR. BE AWARE OF TORQUE GENERATED. ONE MAN OPERATION. STAY BELOW HEIGHT OF TONG. MOVE AWAY FROM ARC OF TONG ASAP. LIAISE CLOSELY WITH DRILLER. STAY RIGHT OUT OF AREA, USE TUGGER TO LIFT SLIPS.

2.

SET SLIPS AND ROTATE ROTARY AS REQUIRED.

TORQUE IN DRILL STRING. SLIPS COMING OUT. MOVEMENT OF ROTARY TABLE.

3.

ATTACH MAKE UP TORQUE.

TORQUE IN DRILL STRING.

4.

PULL SLIPS WITH TUGGER.

PULLING SLIPS TOO EARLY (BEFORE DRILL STRING LIFTED). BEING NEAR TONG/ROTARY WHEN PULLING SLIPS.

APPROPRIATE SAFETY CLOTHING AND EQUIPMENT MUST BE WORN AND USED

VICO INDONESIA
JOB SAFETY ANALYSIS.

RIG 453
TASK NO Created NO. 5. UNJAY PACKER 18 / 12 / 1997 STEP WORK DRILL STRING UP/DOWN TO UNJAY. IF FAILURE TO UNJAY RE SET SLIPS. HAZARD TORQUE. TONG UNLATCHING. ALL THE PREVIOUS HAZARDS. TASK NO ADQ15 Review Date CONTROL STAY CLEAR OF AREA OF ROTARY AND TONG AND SNUB LINE AREA. STAY BELOW TONG WHEN SETTING SLIPS. KEEP HANDS AND BODY PARTS CLEAR. MOVE WELL CLEAR WHEN ROTARY ACTIVATED. PAGE 3 OF 3 / / 19..

6.

APPROPRIATE SAFETY CLOTHING AND EQUIPMENT MUST BE WORN AND USED