Completed Compute A Project BOM
Completed Compute A Project BOM
M)
EAC-B01
The purpose of this lesson is to provide you with the knowledge to estimate the material requirements for a vertical construction project.
Provided a vertical construction mission,a scientific calculator, a computer, software applications, and references, compute a project bill of materials to account for all Class IV quantities per the references. (1361-SRVY-2003)
3
(1). Provided written project specifications, design drawings, a scientific calculator, blank material takeoff sheets, and references, calculate concrete requirements per the FM 5-428. (1361-SRVY-2003a)
(2). Provided written project specifications, design drawings, a scientific calculator, blank material takeoff sheets, and references, calculate masonry requirements per the FM 5-428. (1361-SRVY-2003b)
(3). Provided written project specifications, design drawings, a scientific calculator, blank material takeoff sheets, and references, calculate lumber/plywood 4 requirements per
(5). Provided written project specifications, design drawings, a scientific calculator, completed lumber/plywood consolidations, blank material estimate sheets, and references, estimate construction hardware quantities per the FM 5426. (1361-SRVY-2003e)
EVALUATION
Fire
Tornado
Safety is Paramount
QUESTIONS
PRINCIPLES OF ESTIMATING
Estimating is the calculation of the approximate amount of material and/or labor requirements to build a construction project.
Estimates are prepared from finished working drawings and project specifications.
10
QUALIFICATIONS:
Be able to read and scale drawings. Posses a good working knowledge of math. Be able to visualize the work required. Working knowledge of construction methods and materials. Knowledge and ability to assemble materials into working units.
11
2 BASIC CALCULATIONS
Measurement:
Descriptions
of work. Dimensions of items of work, and materials required. Calculating the quantities of materials, and items of work.
Pricing:
Arithmetic
12
Name some of the qualifications an estimator need to have in order to compile accurate estimates. What are the two basic calculations involved in construction project estimations?
13
MATHEMATICAL EQUATIONS
The application of basic mathematical computations is all that is necessary to compile accurate project material and/or labor requirements.
Three
basic conversions:
14
LINEAR CONVERSION
(INCHES / FEET)
Conversions used to determine such items of work such as: rafter, joist & stud requirements. Feet x 12 = inches
3 x 12 = 36
36 12 = 3
Numerator / denominator = Decimal parts of an inch. : 3 4 = 0.75 Decimal parts of an inch / 12 = Decimal parts of a foot. 0.75 12 = .0625
15
Fractions:
Decimals:
16
AREA CONVERSION
(SQUARE FEET)
Conversion used to determine such items of work such as: plywood, paint, siding & concrete block requirements. Rectangles:
Walls:
L (ft) x H (ft) = Area (sqft/sf) Floors: L (ft) x W (ft) = Area (sqft/sf) 10 x 8 = 80 sqft
Triangles:
Base
10
x 10 = 25sqft
Trapezoids:
H
(ft) x the sum of the parallel sides = Area (sqft/sf) 10 x ((20 + 40) 2) = 300 sqft
17
18
VOLUME CONVERSION
(CUBIC FEET & CUBIC YARDS)
Conversions used to determine such items as concrete, sand, aggregate & mortar.
L (ft) x W (ft) x H (ft) = Volume (cuft/cf) 10 x 10 x 8 = 800 cuft Volume (cf) 27 = Volume (cuyd/cy) 800 cf 27 = 29.63 cuyd Volume (cy) x 27 = Volume (cuft/cf) 29.63 cy x 27 = 800 cuft
19
20
PERIMETER RULE
Footing dimensions: Length: 32.67 Width: 16.67 Height: 0.67 Depth: 1.33 (Outside length (ft) + Inside width (ft) ) x 2 = Total perimeter length (ft) (32.67 + 14.01) x 2 = 93.36 Total perimeter length (ft) x H (ft) = Area (sqft/sf) 93.36 x 0.67 = 62.55 sqft Area (sf) x D (ft) = Volume (cuft/ft) 62.55 (sf) x 1.33 = 83.19 cuft
21
Irregular Shaped:
Pentagon (5 sides) Footing Length (one side): 20.48 Height: 0.67 Depth: 1.33 Total outside perimeter length: 102.4 Total inside perimeter length: 95.75 (Outside Length (ft) + Inside Length (ft)) 2 = Total continuous perimeter length (ft) (102.4 + 95.75) 2 = 99.08 Total continuous perimeter length (ft) x H (ft) = Area (sqft/sf) 97.58 x 0.67 = 66.38 sqft Area (sf) x D (ft) = Volume (cuft/cf) 66.38 sqft x 1.33 = 88.28 cuft
22
23
Used to determine the optimum length of lumber to minimize waste, when cutting specific small items of work. Used for:
Bridging
Blocking
Treads
24
14 x 12 = 168 16 x 12 = 192
Number of LIP Pieces (ea): Number of LIP pieces that can be cut from each Standard Length of Lumber.
Standard lumber length (in) LIP Measurement (in) = LIP pieces per standard lumber length. (Round Down)
96 21 = 4 Lip Pieces
Number of Standard Lengths (ea): How many Standard Lengths required to cut all LIP Pieces.
Total LIP Requirements 4 Total LIP Pieces per Standard Lumber Length = Total Standard Lumber Lengths required. (Round Up)
13 4 = 4 8 Lengths of Lumber
26
Standard Lumber Length x Number of LIP Pieces which can be cut from that length = Total Linear feet of Standard Lumber Length. 8 x 4 = 32 Compare each value. The lowest value will identify the Standard Lumber Length with the minimal amount of waste.
27
13 pieces of floor bridging, 1-9 long are needed to stiffen the floor joists.
LIP pcs cut from std lgth Number of std lgth Standard lgth to use
13 4 = 4 13 5 = 3 13 6 = 3 13 8 = 2 13 9 = 2
8 x 4 = 32 10 x 3 = 30 12 x 3 = 36 14 x 2 = 28 16 x 2 = 32
Round
Round
28
29
PRACTICAL APPLICATION
Math Review
30
Why would you want to select the lowest value of your LIP calculations off of the standard lumber length? What are the three fundamental conversion formulas that are used to estimate material requirements?
31
all drawings, notes & specifications. Measure everything as shown. Measure everything you can see.
32
TIME SAVERS
Never use long words if short ones will do. Use abbreviations. Keep all dimensions, figures and notes. Always start in the same place on each drawing. Highlight / mark-off items, notes and specifications when completed. Take advantage of duplication of design.
33
MTO - PRECEDENCE
If a work item is different, list it separately on the MTO. The items of work are estimated in a logical sequence using the following order of precedence:
1st EXCAVATION 2nd CONCRETE
34
Excavation:
cuyd/cy Calculate amount by using the dimension measurements for the outside face of the footings dimensions of the outside face of the walls.
Concrete:
Ready-Mix Batch Mix Reinforcement Bar Wire Mesh Poly Vapor Barrier Expansion Joint Filler Base Course
35
Lumber as the number of standard lumber lengths. Plywood & Siding by the square footage to be covered. Finish Trim by the linear foot.
Rough Carpentry
Floor Framing (lumber & plywood) Wall Framing (lumber & plywood) Roof Framing (lumber & plywood) Wooden Forms (lumber & plywood)
Finish Carpentry
Siding Trim Work
36
Finish materials are items required to finish the exterior and interior of a structure:
Doors
& Windows
ea
Shingles
Drywall
sqft/sf
sqft/sf
Paint
Insulation
sqft/sf
sqft/sf
37
38
39
40
41
Item of Work
Dimensions
Concrete Volume (L x W x H)
Masonry Area (L x H)
Project: Estimator:
cf sf
43
Bridging Calculation: LIP Converted Standard Length 8' x 12" = 96" 10' x 12" = 120" 12' x 12" = 144" 14' x 12" = 168" 16' x 12" = 192" LIP pieces cut from std lgth Number of std lgth Standard lgth to use
Project: Estimator:
Date: Sheet of
45
PRACTICAL APPLICATION
Part #1 Material Takeoff Sheets
46
What is a materials takeoff sheet used for? Where does the information come from to create a MTO?
47
48
of work. Detailed description of materials. Units of measure of materials. Quantities of dissimilar materials. Quantities of like materials. Waste factor allowances. Total material quantities, including waste.
49
Ready-mix Concrete volumes from the MTO are converted and rounded up to the nearest whole cuyd.
The
appropriate waste factor is calculated and added, after the concrete volume is converted to cuyds.
50
Cement (Gravel)
1:2:3 mix concrete will achieve a compressive strength of 2000 psi at 28 days.
51
Total concrete volume from MTO x 1.5 (3/2 rule) = Concrete Proportion Ratio (CPR)
(1/6 x CPR) + Waste Factor = Total bags of Portland Cement. (Round up)
52
Nominal Dimensions:
16
x 8 x 8
Actual Dimensions
15
3/8
Estimate CMU by Square Feet One concrete block = 0.89 sqft of surface area.
53
Total masonry surface area from MTO (sf) 0.89 (sf) = Number of CMU blocks (ea)
Number of CMU + Waste Factor = Total CMU blocks (ea) (Round up to nearest whole block)
54
MES (MORTAR)
1:1:6 mix concrete will achieve a compressive strength of 2000 psi at 28 days. Bonded by a 3/8 mortar joint, bonding 0.054 cuft of block area.
55
Total number of blocks from MTO x 0.054 (cf) = Total amount of mortar to bond all blocks (cf)
(1/8 x total mortar) + Waste Factor = Total bags of Portland Cement. (Round up)
(1/8 x total mortar) + Waste Factor = Total bags of Masonry Cement. (Round up)
((6/8 x total mortar) 27) + Waste Factor = Total cuyds of Sand (Round up to the nearest half cubic
yard)
56
MES
(BOARDS, LUMBER, TIMBER & PLYWOOD)
The
unit of measure to estimate boards, lumber, and timber is board feet (bf).
One
board foot is equal to a piece of wood having 12 square inches of end area, and is 1 foot long.
The
Consolidate and total all like wood sizes & grades. Calculate board feet. Total all dissimilar wood sizes & grades. Calculate board feet. Board Feet Calculation
((Thickness (in) x Width (in) x Length (ft) x Quantity) 12) + Waste Factor = Total Board Feet (Round up)
Consolidate and total all like plywood sizes & grades. Calculate sheets required. Total all dissimilar plywood sizes & grades. Calculate sheets required. Sheet Calculation
Total Surface area to be covered from MTO 32 (sf) = Total sheets required + waste factor = Total sheets to order.
(Round up)
Unit of measure for nails by the pound (lb). Three formulas, based on nail size, are used to determine nail requirements.
2d
to 12d Nails:
size x Total bf of lumber to be fastened) 400) + Waste Factor = Total nails (lbs) (Round up)
((Nail
60
to 60d Nails:
((Nail
size x Total bf of lumber to be fastened) 600) + Waste Factor = Total nails (lbs) (Round up)
((32
61
Project: Estimator:
Date: Sheet of
63
64
PRACTICAL APPLICATION
Part #1 & #2 Material Estimate Sheets
65
66
67
All material descriptions Quantities NSNs Unit of issue Unit cost Total cost of individual items Total cost of all materials required
Source document used to order project materials. Manufacturers, venders, companies and acceptable replacement items are also listed to prevent poor substitutions.
68
Bill of Materials
Detailed Nomenclature Description NSN U/I Unit Cost Qty Req Total Cost Source/ Substitute
Project:
Estimator:
Date:
Sheet
of
71
SUMMARY
MATHEMATICAL CONVERSIONS MATERIAL TAKEOFF LISTS MATERIAL ESTIMATION SHEET BILL OF MATERIALS
72