Tunnel Construction Programme

This project schedule outlines the construction of the Jammu-Udhampur Road in Jammu, India. It involves tunneling work on four tunnels (Tunnels 1 through 4) between October 2012 and June 2014. Each tunnel will involve initial activities like surveying, geotechnical investigations, and engineering design. Then the main tunneling activities will begin, including open excavation, slope protection, tunnel headings on both sides, benching, lining, and construction of portals and connecting road works. The project concessionaire is SP Jammu Udhampur Highways (P) Ltd and the EPC contractor is AFCONS Infrastructure Ltd.

Uploaded by

Joe PS
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
135 views2 pages

Tunnel Construction Programme

This project schedule outlines the construction of the Jammu-Udhampur Road in Jammu, India. It involves tunneling work on four tunnels (Tunnels 1 through 4) between October 2012 and June 2014. Each tunnel will involve initial activities like surveying, geotechnical investigations, and engineering design. Then the main tunneling activities will begin, including open excavation, slope protection, tunnel headings on both sides, benching, lining, and construction of portals and connecting road works. The project concessionaire is SP Jammu Udhampur Highways (P) Ltd and the EPC contractor is AFCONS Infrastructure Ltd.

Uploaded by

Joe PS
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 2

Jammu-Udhampur Road Project (Jammu Section)

Activity ID

Activity Name

11-Oct-12

Original Start
Duration

Finish
Apr

145 28-Jun-12

Initial Activities

21-Dec-12

2012
May Jun
Jul
28-Jun-12

Aug

Sep

Oct

Nov

Dec

Jan Feb
21-Dec-12

Mar

J.TN.IA.010

Survey

10 10-Aug-12*

22-Aug-12

J.TN.IA.020

Geotechnical Invest...

30 20-Aug-12

25-Sep-12

Geotechnical Investigation - Boreholes

J.TN.IA.030

Geotechnical Invest...

30 27-Aug-12

03-Oct-12

Geotechnical Investigation - Reports

J.TN.IA.050

Engineering design...

45 15-Sep-12

10-Nov-12

J.TN.IA.060

Design approval

65 04-Oct-12

21-Dec-12

J.TN.IA.070

Mobilisation

120 28-Jun-12*

22-Nov-12

260 31-Oct-12

15-Oct-13

Tunnel 1LHS

1 of 2

Apr

2013
Jun
Jul

May

Aug

Sep

Oct

31-Oct-12

26 31-Oct-12

30-Nov-12
19-Apr-13

TN1.L.030

Benching

73 20-Apr-13

15-Jul-13

TN1.L.040

Lining

40 27-Jul-13

14-Sep-13

Lining

TN1.L.050

Portal P2

38 16-Jul-13

29-Aug-13

Portal P2

TN1.L.070

Tunnel T1 Road W...

19 17-Sep-13

15-Oct-13

260 31-Oct-12

15-Oct-13

Benching

Tunnel T1 Road Works


31-Oct-12

15-Oct-13

Open Excavation, S...

26 31-Oct-12

30-Nov-12

Heading

115 01-Dec-12

16-Apr-13

TN1.R.030

Benching

73 17-Apr-13

11-Jul-13

TN1.R.040

Lining

40 24-Jul-13

11-Sep-13

Lining

TN1.R.050

Portal P2

38 12-Jul-13

26-Aug-13

Portal P2

TN1.R.070

Tunnel T1 Road W...

Access Road Const...

43 31-Oct-12

20-Dec-12

TN2.L.020

Open Excavation fo...

21 21-Dec-12

15-Jan-13

TN2.L.030

Slope Protection & ...

30 16-Jan-13

20-Feb-13

TN2.L.040

Heading

160 20-Apr-13

31-Oct-13

TN2.L.050

Benching

83 01-Nov-13

07-Feb-14

TN2.L.060

Lining

52 24-Feb-14

24-Apr-14

TN2.L.070

Portal P1

38 11-Feb-14

26-Mar-14

TN2.L.080

Tunnel T2 Road W...

Tunnel 2RHS

25 02-Jun-14

30-Jun-14

477 31-Oct-12

30-Jun-14

TN2.R.010

Access Road Const...

43 31-Oct-12

20-Dec-12

TN2.R.020

Open Excavation fo...

21 21-Dec-12

15-Jan-13

TN2.R.030

Slope Protection & ...

30 16-Jan-13

20-Feb-13

TN2.R.040

Heading

183 23-Apr-13

30-Nov-13

TN2.R.050

Benching

87 06-Dec-13

18-Mar-14

TN2.R.060

Lining

49 03-Apr-14

30-May-14

TN2.R.070

Portal P1

39 19-Mar-14

03-May-14

TN2.R.080

Tunnel T2 Road W...

25 02-Jun-14

30-Jun-14

477 31-Oct-12

30-Jun-14

Tunnel 3LHS
TN3.L.010

Access Road Const...

43 31-Oct-12

20-Dec-12

TN3.L.020

Open Excavation fo...

21 21-Dec-12

15-Jan-13

TN3.L.030

Slope Protection & ...

30 16-Jan-13

20-Feb-13

TN3.L.040

P1 side Heading

25 18-Sep-13

18-Oct-13

Actual Work
Remaining Work
Critical Remaining Work
Milestone
Summary

PROJECT:
JAMMU UDHAMPUR ROAD PROJECT
(JAMMU SECTION)

Aug
Sep

Heading

TN1.R.020

TN2.L.010

Jul

Open Excavation, Slope protection and RCC portal

TN1.R.010

Tunnel 2LHS

Jun

15-Oct-13

118 01-Dec-12

30-Jun-14

2014
Apr May

Mar

Design approval

Heading

15-Oct-13

Feb

Mobilisation

Open Excavation, S...

19 17-Sep-13

Jan

Engineering design preparation and submission

TN1.L.020

477 31-Oct-12

Dec

Survey

TN1.L.010

Tunnel 1RHS

Nov

Open Excavation, Slope protection and RCC portal


Heading
Benching

Tunnel T1 Road Works


31-Oct-12

30-Jun-14
Access Road Construction
Open Excavation for Portal
Slope Protection & Portal Construction
Heading
Benching
Lining
Portal P1
Tunnel T2 Road Works

31-Oct-12

30-Jun-14
Access Road Construction
Open Excavation for Portal
Slope Protection & Portal Construction
Heading
Benching
Lining
Portal P1
Tunnel T2 Road Works

31-Oct-12

30-Jun-14
Access Road Construction
Open Excavation for Portal
Slope Protection & Portal Construction
P1 side Heading

CONCESSIONAIRE:
SP JAMMU UDHAMPUR HIGHWAYS (P) LTD

EPC CONTRACTOR:
AFCONS INFRASTRUCTURE LTD

Date
16-Aug-12
26-Mar-12
16-Mar-12
13-Feb-12
26-Dec-11
19-Oct-11

Revision
R4
Addendum-R3
R3
R2
R1
R0

Checked

Approved

Jammu-Udhampur Road Project (Jammu Section)


Activity ID

Activity Name

11-Oct-12

Original Start
Duration

Finish
Apr

TN3.L.050

P2 Side Heading

205 01-Apr-13*

04-Dec-13

TN3.L.060

Benching P1 & P2

91 16-Dec-13

01-Apr-14

TN3.L.070

Lining P1 & P2

43 11-Apr-14

31-May-14

TN3.L.080

Tunnel T2 Road W...

25 02-Jun-14

30-Jun-14

477 31-Oct-12

30-Jun-14

Tunnel 3RHS
TN3.R.010

Access Road Const...

43 31-Oct-12

20-Dec-12

TN3.R.020

Open Excavation fo...

21 21-Dec-12

15-Jan-13

TN3.R.030

Slope Protection & ...

30 16-Jan-13

20-Feb-13

TN3.R.040

P1 side Heading

65 18-Sep-13

06-Dec-13

TN3.R.050

P2 Side Heading

195 01-Apr-13

22-Nov-13

TN3.R.060

Benching P1 & P2

65 16-Dec-13

01-Mar-14

TN3.R.070

Lining P1 & P2

43 11-Apr-14

31-May-14

TN3.R.080

Tunnel T2 Road W...

Tunnel 4LHS

2 of 2

25 02-Jun-14

30-Jun-14

477 31-Oct-12

30-Jun-14

May

2012
Jun
Jul

Aug

Sep

Oct

Nov

Dec

Jan

Feb

Mar

Apr

May

2013
Jun
Jul

Aug

Sep

Oct

Nov

Dec Jan Feb Mar


P2 Side Heading

Aug
Sep

Tunnel T2 Road Works


31-Oct-12

30-Jun-14
Access Road Construction
Open Excavation for Portal
Slope Protection & Portal Construction
P1 side Heading
P2 Side Heading
Benching P1 & P2
Lining P1 & P2
Tunnel T2 Road Works

31-Oct-12

30-Jun-14

Access Road Const...

43 31-Oct-12

20-Dec-12

Open Excavation fo...

21 21-Dec-12

15-Jan-13

TN4.L.030

Slope Protection & ...

37 16-Jan-13

28-Feb-13

TN4.L.040

Open Excavation of...

25 01-Nov-12

30-Nov-12

TN4.L.050

Slope Protection & ...

25 01-Dec-12

31-Dec-12

TN4.L.060

P1 side Heading

140 01-Apr-13

14-Sep-13

P1 side Heading

TN4.L.070

P2 Side Heading

217 01-Jan-13

16-Sep-13

P2 Side Heading

TN4.L.080

Benching P1 & P2

105 17-Sep-13

27-Jan-14

TN4.L.090

Lining P1 & P2

75 11-Feb-14

09-May-14

TN4.L.100

Tunnel T2 Road W...

28 29-May-14

30-Jun-14
30-Jun-14

Jul

Lining P1 & P2

TN4.L.020

477 31-Oct-12

Jun

Benching P1 & P2

TN4.L.010

Tunnel 4RHS

2014
Apr May

Access Road Construction from P1


Open Excavation for Portal P1
Slope Protection & Portal Construction P1
Open Excavation of Portal P2
Slope Protection & Portal Construction P2

Benching P1 & P2
Lining P1 & P2
Tunnel T2 Road Works
31-Oct-12

30-Jun-14

TN4.R.010

Access Road Const...

43 31-Oct-12

20-Dec-12

TN4.R.020

Open Excavation fo...

21 21-Dec-12

15-Jan-13

Access Road Construction from P1

TN4.R.030

Slope Protection & ...

37 16-Jan-13

28-Feb-13

TN4.R.040

Open Excavation of...

25 01-Nov-12

30-Nov-12

TN4.R.050

Slope Protection & ...

25 01-Dec-12

31-Dec-12

TN4.R.060

P1 side Heading

128 01-Apr-13

29-Aug-13

P1 side Heading

TN4.R.070

P2 Side Heading

201 01-Jan-13

26-Aug-13

P2 Side Heading

TN4.R.080

Benching P1 & P2

95 29-Aug-13

06-Jan-14

TN4.R.090

Lining P1 & P2

87 20-Jan-14

30-Apr-14

TN4.R.100

Tunnel T2 Road W...

28 29-May-14

30-Jun-14

Open Excavation for Portal P1


Slope Protection & Portal Construction P1
Open Excavation of Portal P2
Slope Protection & Portal Construction P2

Benching P1 & P2
Lining P1 & P2
Tunnel T2 Road Works