Van'S Aircraft, Inc.: Figure 2: Installing Pins in The
Van'S Aircraft, Inc.: Figure 2: Installing Pins in The
Step 1: Route the remaining wires of the WH-RV12-TUNNEL harness back thorough the F-1206A and F-1207B Baggage Bulkheads. Step 2: Route WH-P30 Trim Wires and Static Line from the tailcone forward through the F-1207B and F-1206A Bulkheads, fuel pump cushioned clamp, F-1204 Center Section Assembly, F-1276C Systems Blocks, F-1203A and F-1202F Bulkheads, fuel flow cushioned clamp, around the back of the rudder pedals and up through the F-1202B Panel Base. Step 3: Route the WH-RV12-OAT harness and WH-RV12-TUNNEL harness through a snap bushing in the F-1207D-L Baggage Bulkhead Channel. Slip the ES HST 3/16 X 2" Heat Shrink over the ends of the wires. Insert the pins on the ends of both wiring harnesses through the heat shrink and into the ES 205203-3 9-Pin D-Sub Female connector according to Figure 2. Check with a gentle tug that each wire has snapped into place. Center the ES HST 3/16 X 2" Heat Shrink around the location where the wires will exit the ES 9 PIN BSHELL. Activate the heat shrink. Step 4: Following the routing of the Static Line, route the harnesses attached to the 9-Pin D-Sub up to the top center of the F-1208 Fuselage Frame, replacing plastic tie wraps as required.
WH-RV12-OAT WH-RV12-TUNNEL
F-1207B BAGGAGE BULKHEAD EDC-10A 9 PIN FEMALE D-SUB CONNECTOR NOTE: SNIP OFF ANY CABLE SHIELD COMING FROM THE END OF THE OAT HARNESS.
WH-P30
PIN 9: WH-F191 (WHT/GRN) PIN 8: WH-RV12-OAT (BLU) PIN 7: WH-RV12-OAT (RED) PIN 6: WH-F190 (WHT/BLU)
FIGURE 2: INSTALLING PINS IN THE EDC-10A D-SUB CONNECTOR (REAR VIEW / WIRE INSERTION SIDE)
F-1207C-L F-1207D-L STATIC LINE F-1206A
31-12
RV-12
REVISION:
DATE:
09/15/09