Primavera P6 Exercise Worksheet

Ten Six Consulting recommends that you download and install your own standalone copy of Primavera P6 Professional for use with this course. Hardware requirements include an Intel compatible CPU, 1 GHz or better and 4GB of Memory or greater. Software requirements include Java 7 Update 15 runtime environment (JRE) or Software Developer Kit (jdk)

Uploaded by

dyeyson30
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
95% found this document useful (19 votes)
9K views35 pages

Primavera P6 Exercise Worksheet

Ten Six Consulting recommends that you download and install your own standalone copy of Primavera P6 Professional for use with this course. Hardware requirements include an Intel compatible CPU, 1 GHz or better and 4GB of Memory or greater. Software requirements include Java 7 Update 15 runtime environment (JRE) or Software Developer Kit (jdk)

Uploaded by

dyeyson30
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 35

Primavera P6 Exercise Worksheet

P6 Exercise Worksheet
Preparing for the Exercises
Ten Six Consulting recommends that you download and install your own standalone copy of Primavera P6 Professional for use with this course. The following instructions will assist you in obtaining and installing your own Primavera P6 Professional system:

Hardware Requirements
Intel compatible CPU, 1 GHz or better 4GB Memory or greater Microsoft Windows 7 Home, Professional or Ultimate. (Windows 8 not recommended)

Software Requirements
Java 7 Update 15 runtime environment (JRE) or Software Developer Kit (JDK). Oracle Primavera P6 Professional for EPPM R8.3 installation Media zip file V37499-01.zip. See Downloading Primavera P6 Professional.PDF for detailed instructions on obtaining Primavera P6 Professional from the edelivery web site. Microsoft .NET Framework 4 (x86 and x64) may already be installed on your system

Overview
Primavera P6 Professional R8.3 stand-alone is installed from a single media package that can be downloaded from Oracle e-delivery software cloud at https://edelivery.oracle.com/. See Downloading P6 Professional.PDF for detailed instructions.

Installation
To learn how to install Primavera P6 Professional standalone on your computer, see: Primavera P6 Professional Installation Instructions.pdf This is a file that is available for download as part of the course setup instructions.

Primavera P6 Video Training Exercise Worksheet. Copyright Ten Six Consulting, LLC. 2013. All rights reserved.

Exercises
Introduction
These exercises are for use in support of the Ten Six Consulting Primavera P6 Professional video training course. At the completion of each video you will be prompted to complete one or more exercises to gain hands-on experience with Primavera P6 Professional R8.3.

This worksheet provides you with exercises that will build a simple construction project schedule called New Home Construction.

Important Note:
Some of the following exercises have a large number of data entry items. You DO NOT have to load all the data in the exercise tables. Just enter some of the data, perhaps the first five rows to get some practice, and then load the rest using the .XER project files that you downloaded at the start of this course. Instructions for import project data from an XER file can be found at the back of this Exercise Worksheet.

Primavera P6 Video Training Exercise Worksheet. Copyright Ten Six Consulting, LLC. 2013. All rights reserved.

1 Introduction to P6
1.1 Exercise:
1. Using your own standalone copy of Primavera P6 Professional, familiarize yourself with the P6 interface. Access the main views such as the Projects view, WBS view and Activities view.

2. Open and close some select sample projects using the right-click and/or File | Open menu methods. Right-click method Select one or more projects and right-click to open them.

Primavera P6 Video Training Exercise Worksheet. Copyright Ten Six Consulting, LLC. 2013. All rights reserved.

3. File | Open method

4. In the Activities view, select different views in the bottom layout area using the Bottom Layout tool group.

5. Explorer and familiarize yourself with the main menus of P6.

Primavera P6 Video Training Exercise Worksheet. Copyright Ten Six Consulting, LLC. 2013. All rights reserved.

2 Lesson 2 Working with Project Schedules


2.1 Exercise:
1. In the Projects view, use the Add button or right-click menus Add option to run the Create a new project wizard. Create a project with the following attributes: EPS Node: E&C (Engineering and Construction) Project ID: EC00720 Project Name: New Home Construction Project Planned Start: 04-FEB-2013 Data Date: 04-FEB-2013 (typically will be automatically set to Project Planned Start) These next images will help guide you through the process.

Primavera P6 Video Training Exercise Worksheet. Copyright Ten Six Consulting, LLC. 2013. All rights reserved.

Primavera P6 Video Training Exercise Worksheet. Copyright Ten Six Consulting, LLC. 2013. All rights reserved.

Primavera P6 Video Training Exercise Worksheet. Copyright Ten Six Consulting, LLC. 2013. All rights reserved.

The final project should appear as follows in the Projects view:

Primavera P6 Video Training Exercise Worksheet. Copyright Ten Six Consulting, LLC. 2013. All rights reserved.

3 Lesson 3 Work Breakdown Structure


3.1 Exercise:
1. Using the techniques described in the training video, create the following Work Breakdown Structure for your New Home Construction project:

To create a child WBS element: 1. Right-click on the parent WBS element 2. Select Add from the drop-down menu 3. Enter a description for the WBS element in the WBS Name column To create a sibling WBS element: (recommended method) 1. Right-click on the parent WBS element 2. Select Add from the drop-down menu 3. Enter a description for the WBS element in the WBS Name column 4. Use the Move Left button to outdent the child WBS element and make it a sibling of the original parent element. Note: This exercise data can be imported from the Lesson 03 New Home Construction Project.xer file that is included in your training data package. See last page for import instructions.

Primavera P6 Video Training Exercise Worksheet. Copyright Ten Six Consulting, LLC. 2013. All rights reserved.

4 Lesson 4 Activities
4.1 Exercise:
1. Create a new layout called Activity Entry with the following columns selected:

2. Using any of the methods demonstrated in the lesson 4 video, add the following activities to your New Home Construction project:

Note: This exercise data can be imported from the Lesson 04 New Home Construction Project.xer file that is included in your training data package. See last page for import instructions.

Primavera P6 Video Training Exercise Worksheet. Copyright Ten Six Consulting, LLC. 2013. All rights reserved.

10

Primavera P6 Video Training Exercise Worksheet. Copyright Ten Six Consulting, LLC. 2013. All rights reserved.

11

The final schedule should appear similar to the following:

Primavera P6 Video Training Exercise Worksheet. Copyright Ten Six Consulting, LLC. 2013. All rights reserved.

12

5 Lesson 5 Relationships and Constraints


5.1 Exercise:
1. Using the techniques learned in the video, enter the following relationships in P6:
Predecessor ID A1000 A1000 A1010 A1030 A1040 A1050 A1060 A1070 A1080 A1080 A1080 A1080 A1080 A1100 A1090 A1110 A1120 A1130 A1140 A1150 A1160 A1170 A1180 A1190 A1200 A1200 Predecessor Name Successor ID A1010 A1030 A1020 A1040 A1050 A1060 A1070 A1080 A1090 A1110 A1160 A1180 A1100 A1240 A1190 A1120 A1130 A1140 A1150 A1020 A1170 A1020 A1190 A1200 A1210 A1230 Successor Name Relationship Type SS SS FF FS FS FS FS FS FS FS FS FS FS FS FS FS FS FS SS FF FS FF FS SS FS FS Lag

EC00720 New Home Construction Project Start Project Start Project Management Survey and Mark Out Site Grade Site Install Foundation Forms Install Slab Plumbing Pour and Float Slab Concrete Erect Exterior Wall Frames Erect Exterior Wall Frames Erect Exterior Wall Frames Erect Exterior Wall Frames Erect Exterior Wall Frames Install OSB Exterior Cladding Erect Interior Stud Walls Install Trusses Install Roof Sheeting Install Paper and Shingles Install HVAC Ducting Install HVAC Unit Inst. Brkr Box & Rough Wiring Finish Wiring Install Rough Plumbing Lines Install Drywall Sheeting Tape and Mud Tape and Mud Project Management Survey and Mark Out Site Project Complete Grade Site Install Foundation Forms Install Slab Plumbing Pour and Float Slab Concrete Erect Exterior Wall Frames Erect Interior Stud Walls Install Trusses Install Breaker Box and Rough Wiring Install Rough Plumbing Lines Install OSB Exterior Cladding Install Windows Install Drywall Sheeting Install Roof Sheeting Install Paper and Shingles Install HVAC Ducting Install HVAC Unit Project Complete Finish Wiring Project Complete Install Drywall Sheeting Tape and Mud Install Doors Install Kitchen 0 0 0 0 0 0 0 7 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0 0

EC00720.1 Grading

EC00720.2 Foundation

EC00720.3.1 Framing

EC00720.3.2 Roof

EC00720.3.3.1 Mechanical

EC00720.3.3.2 Electrical

EC00720.3.3.3 Plumbing EC00720.3.3.4 Drywall

Primavera P6 Video Training Exercise Worksheet. Copyright Ten Six Consulting, LLC. 2013. All rights reserved.

13

EC00720.3.3.5 Decor A1210 A1230 A1220 A1240 A1250 A1260 Install Doors Install Kitchen Door Casings and Baseboards Install Windows Install Siding Lay Turf and Plant Trees A1220 A1020 A1020 A1250 A1260 A1020 Door Casings and Baseboards Project Complete Project Complete Install Siding Lay Turf and Plant Trees Project Complete FS FF FF FS FS FF 0 0 0 0 0 0

EC00720.3.4 Exterior

EC00720.4 Landscaping

Note: This exercise data can be imported from the Lesson 05 New Home Construction Project.xer file that is included in your training data package. See last page for import instructions.

Primavera P6 Video Training Exercise Worksheet. Copyright Ten Six Consulting, LLC. 2013. All rights reserved.

14

6 Lesson 6 Critical Path Analysis


6.1 Exercise:
Perform a Schedule process on your copy of the New Home Construction project and verify the project planned finish date.

Note: This exercise data can be imported from the Lesson 06 New Home Construction Project.xer file that is included in your training data package. See last page for import instructions.

Primavera P6 Video Training Exercise Worksheet. Copyright Ten Six Consulting, LLC. 2013. All rights reserved.

15

The final result should appear similar to the following:

Primavera P6 Video Training Exercise Worksheet. Copyright Ten Six Consulting, LLC. 2013. All rights reserved.

16

7 Lesson 7 Resources
7.1 Exercise:
1. Add the following resources to the E&C Trades resource:
Resource ID Foreman HVACEng Surveyor Siding Concrete Resource Name Site Forman HVAC Engineer Land Surveyor Siding Contractor Concrete Max Units/Time 8/d 8/d 8/d 8/d 0/d Standard Rate $55.00/h $40.00/h $65.00/h $47.00/h $115.00 Per CY Resource Type Labor Labor Labor Labor Material

7.2

Exercise:
1. Make the following resource assignments in the New Home Construction schedule:
Budgeted Units / Time 8/d 8/d 8/d 8/d 8/d 8/d 8/d 8/d 8/d 8/d 8/d 8/d 8/d 8/d 8/d 8/d 8/d 8/d 8/d 8/d 8/d 8/d 8/d 8/d 8/d 8/d

Activity ID A1010 A1030 A1040 A1050 A1050 A1060 A1070 A1080 A1090 A1100 A1110 A1120 A1130 A1140 A1150 A1160 A1170 A1180 A1190 A1200 A1210 A1220 A1230 A1240 A1250 A1260

Activity Name Project Management Survey and Mark Out Site Grade Site Install Foundation Forms Install Foundation Forms Install Slab Plumbing Pour and Float Slab Concrete Erect Exterior Wall Frames Erect Interior Stud Walls Install OSB Exterior Cladding Install Trusses Install Roof Sheeting Install Paper and Shingles Install HVAC Ducting Install HVAC Unit Install Breaker Box and Rough Wiring Finish Wiring Install Rough Plumbing Lines Install Drywall Sheeting Tape and Mud Install Doors Door Casings and Baseboards Install Kitchen Install Windows Install Siding Lay Turf and Plant Trees

Resource ID Foreman Surveyor Operator RCarp GenLabor Plumb GenLabor RCarp RCarp RCarp RCarp RCarp Roofing HVACEng HVACEng Elec Elec Plumb Drywall Drywall FCarp FCarp FCarp FCarp Siding GenLabor

Quantity 1 1 1 1 1 1 4 3 2 3 3 3 3 1 1 1 1 1 2 2 1 1 2 1 1 3

Primavera P6 Video Training Exercise Worksheet. Copyright Ten Six Consulting, LLC. 2013. All rights reserved.

17

Note: This exercise data can be imported from the Lesson 07 New Home Construction Project.xer file that is included in your training data package. See last page for import instructions.

8 Lesson 8 Baselines
8.1 Exercise:
1. Go to the Project menu and use the Maintain Baselines dialog to create a baseline of your New Home Construction project.

2. Assign your new baseline to the Project Baseline and Primary Baseline fields.

Primavera P6 Video Training Exercise Worksheet. Copyright Ten Six Consulting, LLC. 2013. All rights reserved.

18

9 Lesson 9 Project Status


9.1 Exercise:
1. Create a Status Layout for your system using the following columns:

2. Save the Layout as Status Layout using the View | Layout | Save Layout As menu option. 3. Enter the following status for week 1 of the New Home Construction project:

Activity ID A1000 A1030 A1040

Activity Name Project Start Survey and Mark Out Site Grade Site

Activity Status Completed Completed In Progress

Actual Start 04-Feb-13 04-Feb-13 07-Feb-13

Actual Finish

06-Feb-13

Activity % Complete 100% 100% 60%

4. Open the Schedule dialog (F9). 5. Enter a Data Date of 10-Feb-13 . 6. Click the Schedule button. Note: This exercise data can be imported from the Lesson 09 - New Home Construction Project Part A.xer file that is included in your training data package. See last page for import instructions.

Primavera P6 Video Training Exercise Worksheet. Copyright Ten Six Consulting, LLC. 2013. All rights reserved.

19

Your schedule should appear similar to the following:

7. Now enter the following status data for week 2 of the New Home Construction project:
Activity ID A1040 A1050 Activity Name Grade Site Install Foundation Forms Activity Status Completed Completed Actual Start 07-Feb-13 13-Feb-13 Actual Finish 12-Feb-13 14-Feb-13 Activity % Complete 100% 100%

8. Open the Schedule dialog (F9). 9. Enter a Data Date of 17-Feb-13. 10. Click the Schedule button.

Note: This exercise data can be imported from the Lesson 09 - New Home Construction Project Part B.xer file that is included in your training data package. See last page for import instructions.

Primavera P6 Video Training Exercise Worksheet. Copyright Ten Six Consulting, LLC. 2013. All rights reserved.

20

Your schedule should now appear similar to the following:

10 Lesson 10 - Publishing and Reporting


10.1 Exercise:

1. Open the Gantt Chart Layout in the Activities view and go to the File | Print Preview menu option. 2. Familiarize yourself with the tool bar in the Print Preview dialog.

3. In the Print Preview dialog, experiment with the Page Layout options to timescale settings to the Project Earliest Start (PS) and Project Latest Finish (PF) dates.

Primavera P6 Video Training Exercise Worksheet. Copyright Ten Six Consulting, LLC. 2013. All rights reserved.

21

4. Now experiment with the Activity Table, All Columns, Grid Lines and Gantt Chart options to see their effect on the output. 5. Close the Print Preview dialog. 6. Locate and run the standard report named RA-01 Resources Assignments, All Activities. Run this report in the Print Preview window. The result should appear as follows below:

Primavera P6 Video Training Exercise Worksheet. Copyright Ten Six Consulting, LLC. 2013. All rights reserved.

22

7. Locate and run the report named PR-01 Resources on Open Project. Load this report into an Excel Spreadsheet.

Primavera P6 Video Training Exercise Worksheet. Copyright Ten Six Consulting, LLC. 2013. All rights reserved.

23

The results should appear as shown in the following figure:

8. Create an activity status report using the Report Wizard with the following columns, grouping and filter option: Subject Area: Activities

Primavera P6 Video Training Exercise Worksheet. Copyright Ten Six Consulting, LLC. 2013. All rights reserved.

24

Columns:

Group and Sort:

Primavera P6 Video Training Exercise Worksheet. Copyright Ten Six Consulting, LLC. 2013. All rights reserved.

25

Filter:

Report Title: Activity Status and Progress Report

Primavera P6 Video Training Exercise Worksheet. Copyright Ten Six Consulting, LLC. 2013. All rights reserved.

26

The final report should appear as follows:

Primavera P6 Video Training Exercise Worksheet. Copyright Ten Six Consulting, LLC. 2013. All rights reserved.

27

11 Lesson 11 Exporting and Importing Project Data


11.1 Exercise:
1. Click on the File | Export menu option. 2. Export your New Home Construction project to an XER file in P6 R6.2 format using the Export Wizard.

Primavera P6 Video Training Exercise Worksheet. Copyright Ten Six Consulting, LLC. 2013. All rights reserved.

28

Primavera P6 Video Training Exercise Worksheet. Copyright Ten Six Consulting, LLC. 2013. All rights reserved.

29

Congratulations! You have just completed all the exercises for the Primavera P6 Fundamentals video training. Now the real learning starts when you begin to us Primavera P6 Professional out in the real world. We hope you have found this video course helpful in getting you started with the worlds leading highpower project scheduling systems. From all of us here at Ten Six Consulting we wish you every success in the future. If we can be of further help to you in getting started with Primavera P6, please do not hesitate to contact us.

www.tensixconsulting.com
Call: (703) 910-2600

Primavera P6 Video Training Exercise Worksheet. Copyright Ten Six Consulting, LLC. 2013. All rights reserved.

30

File Import Instructions


To save you time and some data entry, you can import the exercise data into your New Home Construction project using the .XER files provided with your Training Data Package. You can partially enter the exercise data to get some practice, but you dont have to input everything unless otherwise stated. The following instructions show how to load these files into your current New Home Construction project. 1. Go to the File menu and choose the Import option.

2. In the Import Format dialog, select Primavera PM (XER).

3. In the Import Type dialog, choose Project.

Primavera P6 Video Training Exercise Worksheet. Copyright Ten Six Consulting, LLC. 2013. All rights reserved.

31

4. In the File Name dialog, click on the ellipse button of the File Name field and locate the training data file you wish to import.

5. In the Import Project Options dialog, select Update Existing Project from the Import Actions dropdown field.

Primavera P6 Video Training Exercise Worksheet. Copyright Ten Six Consulting, LLC. 2013. All rights reserved.

32

6. Now click in the Import To field and select the project to which to import the data.

7. In the Update Project Options dialog, click Next >.

Primavera P6 Video Training Exercise Worksheet. Copyright Ten Six Consulting, LLC. 2013. All rights reserved.

33

8. In the Finish dialog, click Finish to import the updates to your New Home Construction project.

Your project will be updated with the data in the lesson XER file.

Primavera P6 Video Training Exercise Worksheet. Copyright Ten Six Consulting, LLC. 2013. All rights reserved.