Work Instruction

CJ06 - JPN - Create Project Definition

Purpose Project definition will be created as project header and need to be created prior to Work Breakdown structure creation. We may create project definition from scratch or copying from existing project definition. This simulation will show you the basic steps to create project definition. Trigger Perform this procedure when there is a need to create project definition. Menu Path Use the following SAP Easy Access menu path(s) to begin this transaction: Accounting > Project System > Project > Special Maintenance Functions > Work Breakdown Structure (WBS) > Project Definition > CJ06 - Create

Transaction Code CJ06

Wednesday, July 15, 2009

CO_CJ06_JPN_Create Project Definition.udc

1/35

Work Instruction

CJ06 - JPN - Create Project Definition

Screen Flow

Wednesday, July 15, 2009

CO_CJ06_JPN_Create Project Definition.udc

2/35

Work Instruction

CJ06 - JPN - Create Project Definition

Wednesday, July 15, 2009

CO_CJ06_JPN_Create Project Definition.udc

3/35

Work Instruction

CJ06 - JPN - Create Project Definition

Procedure 1. In SAP, start the transaction using the menu path or transaction code. SAP Easy Access

2. Double-click the Accounting node 3. Double-click the Project System node 4. Double-click the Project node .

. .

5. Double-click the Special Maintenance Functions node .

Wednesday, July 15, 2009

CO_CJ06_JPN_Create Project Definition.udc

4/35

Work Instruction

CJ06 - JPN - Create Project Definition

6. Double-click the Work Breakdown Structure (WBS) node . 7. Double-click the Project Definition node 8. Double-click the CJ06 - Create node Create Project Definition: Initial Screen . .

9. Click the Project Def. edit field 10 As required, complete/review the following fields: .

Wednesday, July 15, 2009

CO_CJ06_JPN_Create Project Definition.udc

5/35

Work Instruction

CJ06 - JPN - Create Project Definition

A R/O/C framewor k for a business undertaki ng with a fixed goal to achieve with given resources .The project definition contains dates and organizati onal informatio n that are binding for the entire project. Field Example: I-SK-08019 R Project Def.

Description

11 Click the Project Profile drop down list . 12 Click the UL CAPEX projects list item . .

Wednesday, July 15, 2009

CO_CJ06_JPN_Create Project Definition.udc

6/35

Work Instruction

CJ06 - JPN - Create Project Definition

13 Click the Enter button . Create Project Definition:

Wednesday, July 15, 2009

CO_CJ06_JPN_Create Project Definition.udc

7/35

Work Instruction

CJ06 - JPN - Create Project Definition

14 Click the Project Def. Description edit field . . 15 As required, complete/review the following fields: . A R/O/C framewor k for a business undertaki ng with a fixed goal to achieve with given resources .The project definition contains dates and organizati onal informatio n that are binding for the entire project. Field Example: ULI Skin Project 2008 Description

Wednesday, July 15, 2009

CO_CJ06_JPN_Create Project Definition.udc

8/35

Work Instruction

CJ06 - JPN - Create Project Definition

R Project Def. 16 Click the Person Respons. edit field . . .

17 Click the Person Respons. possible entries button .

Number of the responsible person (project manager) (1) 7 Entries found

Wednesday, July 15, 2009

CO_CJ06_JPN_Create Project Definition.udc

9/35

Work Instruction

CJ06 - JPN - Create Project Definition

18 Click the 00000001 Project Engineer item . 19 Click the Enter button . Create Project Definition: .

20 Click the Start date edit field .

. .

21 Click the Start date possible entries button .

Wednesday, July 15, 2009

CO_CJ06_JPN_Create Project Definition.udc

10/35

Work Instruction

CJ06 - JPN - Create Project Definition

Calendar

22 Click the Friday, August 1, 2008 item .

Wednesday, July 15, 2009

CO_CJ06_JPN_Create Project Definition.udc

11/35

Work Instruction

CJ06 - JPN - Create Project Definition

Create Project Definition:

23 Click the Finish date edit field .

. .

24 Click the Finish date possible entries button .

Wednesday, July 15, 2009

CO_CJ06_JPN_Create Project Definition.udc

12/35

Work Instruction

CJ06 - JPN - Create Project Definition

Calendar

25 Click the Wednesday, October 1, 2008 item .

Wednesday, July 15, 2009

CO_CJ06_JPN_Create Project Definition.udc

13/35

Work Instruction

CJ06 - JPN - Create Project Definition

Create Project Definition:

26 Click the CO area edit field .

. .

27 Click the CO area possible entries button .

Wednesday, July 15, 2009

CO_CJ06_JPN_Create Project Definition.udc

14/35

Work Instruction

CJ06 - JPN - Create Project Definition

Controlling area for the project (1) 40 Entries found

28 Click the ID01 UL Indonesia list item .


Wednesday, July 15, 2009

.
15/35

CO_CJ06_JPN_Create Project Definition.udc

Work Instruction

CJ06 - JPN - Create Project Definition

29 Click the Enter button .

Wednesday, July 15, 2009

CO_CJ06_JPN_Create Project Definition.udc

16/35

Work Instruction

CJ06 - JPN - Create Project Definition

Create Project Definition:

30 Click the Company code edit field .

. .

31 Click the Company Code possible entries button .

Wednesday, July 15, 2009

CO_CJ06_JPN_Create Project Definition.udc

17/35

Work Instruction

CJ06 - JPN - Create Project Definition

Company code for the project (1) 95 Entries found

32 Click the ID01 UL Indonesia list item .


Wednesday, July 15, 2009 CO_CJ06_JPN_Create Project Definition.udc

.
18/35

Work Instruction

CJ06 - JPN - Create Project Definition

33 Click the Enter button .

Wednesday, July 15, 2009

CO_CJ06_JPN_Create Project Definition.udc

19/35

Work Instruction

CJ06 - JPN - Create Project Definition

Create Project Definition:

34 Click the Plant edit field .

. .

35 Click the Plant possible entries button .

Wednesday, July 15, 2009

CO_CJ06_JPN_Create Project Definition.udc

20/35

Work Instruction

CJ06 - JPN - Create Project Definition

Plant (1)

36 As required, complete/review the following fields: . A plant is R/O/C an organizati onal unit for dividing an enterprise according to productio
Wednesday, July 15, 2009

Description

CO_CJ06_JPN_Create Project Definition.udc

21/35

Work Instruction

CJ06 - JPN - Create Project Definition

n, procurem ent, maintena nce, and materials planning. It is a place where materials are produced, or goods and services are provided. Field Example: 9* R Plant 37 Click the Enter button . .

Wednesday, July 15, 2009

CO_CJ06_JPN_Create Project Definition.udc

22/35

Work Instruction

CJ06 - JPN - Create Project Definition

Plant (1) 42 Entries found

38 Click the ID01 UL Indonesia list item . 39 Click the Enter button . .

Wednesday, July 15, 2009

CO_CJ06_JPN_Create Project Definition.udc

23/35

Work Instruction

CJ06 - JPN - Create Project Definition

Create Project Definition:

40 Click the Profit Center edit field .

. .

41 Click the Profit Center possible entry button .

Wednesday, July 15, 2009

CO_CJ06_JPN_Create Project Definition.udc

24/35

Work Instruction

CJ06 - JPN - Create Project Definition

Profit Center (1)

42 Click the Profit Center edit field .

43 As required, complete/review the following fields: . Example: Field 9003* R Profit Center 44 Click the Enter button . . R/O/C Description

Wednesday, July 15, 2009

CO_CJ06_JPN_Create Project Definition.udc

25/35

Work Instruction

CJ06 - JPN - Create Project Definition

Profit Center (1) 4 Entries found

45 Click the 9003441639 ID01 list item .

Wednesday, July 15, 2009

CO_CJ06_JPN_Create Project Definition.udc

26/35

Work Instruction

CJ06 - JPN - Create Project Definition

46 Click the Enter button .

Wednesday, July 15, 2009

CO_CJ06_JPN_Create Project Definition.udc

27/35

Work Instruction

CJ06 - JPN - Create Project Definition

Create Project Definition:

47 Click the Proj.currency edit field .

. .

48 Click the Proj.currency possible entries button .

Wednesday, July 15, 2009

CO_CJ06_JPN_Create Project Definition.udc

28/35

Work Instruction

CJ06 - JPN - Create Project Definition

WBS currency (project definition) (1) 189 Entries found

49 Click the IDR Indonesian Rupiah list item . . 50 Click the Enter button . .

Wednesday, July 15, 2009

CO_CJ06_JPN_Create Project Definition.udc

29/35

Work Instruction

CJ06 - JPN - Create Project Definition

Create Project Definition:

51 Click the Control data tab .

Wednesday, July 15, 2009

CO_CJ06_JPN_Create Project Definition.udc

30/35

Work Instruction

CJ06 - JPN - Create Project Definition

Create Project Definition:

52 Click the Enter button . 53 Click the Save button . 54 Click the Enter button .

. . .

Wednesday, July 15, 2009

CO_CJ06_JPN_Create Project Definition.udc

31/35

Work Instruction

CJ06 - JPN - Create Project Definition

Create Project Definition: Initial Screen

55 Click the Exit button .

A success message is displayed indicating that the project has been created in the system.

Wednesday, July 15, 2009

CO_CJ06_JPN_Create Project Definition.udc

32/35

Work Instruction

CJ06 - JPN - Create Project Definition

Result You have successfully created a project definition.

Wednesday, July 15, 2009

CO_CJ06_JPN_Create Project Definition.udc

33/35

Work Instruction

CJ06 - JPN - Create Project Definition

Scenario Situation You want to create a project definition. Instructions In this simulation you are required to: Create Project Definition in SAP ECC 6.0 Required Data This section provides the field data required to complete this exercise. Refer to this data sheet as necessary while performing the exercise. IDR 9003441639 9003 2408 ID01 01.10.2008 01.08.2008 Project Engineer ULI Skin Project 2008 Field Proj.currency Profit Center Plant Company code CO area Finish date Start date Person Respons. Project Def. I-SK-08019 Project Def. Value

Wednesday, July 15, 2009

CO_CJ06_JPN_Create Project Definition.udc

34/35

Work Instruction

CJ06 - JPN - Create Project Definition

Wednesday, July 15, 2009

CO_CJ06_JPN_Create Project Definition.udc