0% found this document useful (0 votes)
75 views

Earth Testing at New CCE Office STF Area.: Location Result

This document contains the results of earth testing conducted at a new CCE office STF area. It lists the location of various generators, tanks, pumps, and building frames that were tested and reports the resistance measurement in ohms for each, ranging from 2.4 to 2.5 ohms. A note indicates that PB-4 and PB-5 are connected to DP-1.
Copyright
© Attribution Non-Commercial (BY-NC)
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
75 views

Earth Testing at New CCE Office STF Area.: Location Result

This document contains the results of earth testing conducted at a new CCE office STF area. It lists the location of various generators, tanks, pumps, and building frames that were tested and reports the resistance measurement in ohms for each, ranging from 2.4 to 2.5 ohms. A note indicates that PB-4 and PB-5 are connected to DP-1.
Copyright
© Attribution Non-Commercial (BY-NC)
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

Earth Testing @ New CCE Office STF Area.

Location
Generator 053 Generator 054 MTS Diesel Tank For Generator Fire Water Pump Portable Water Pump Disconnect Switch For Pumps DP-1 Building Frame East Side 1 Building Frame East Side 2 Building Frame West Side 1 Building Frame West Side 2 PB-1 PB-2 PB-3 PB-6 PB-7 PB-8

Result
2.5 2.5 2.4 2.5 2.5 2.5 2.5 2.5 2.4 2.5 2.5 2.5 2.4 2.5 2.5 2.5 2.4 2.5

Note: PB-4 & 5 are connected from DP-1