02 04 13 PDF

Download as pdf or txt
Download as pdf or txt
You are on page 1of 1

EBSM UPGRADING PROJECT DAILY REPORT

TO CC.
1.00 2.00

Report No : Date :

2013/ENS/TET/D-090 2 April 2013 1 April 2013 8.00-20.00


21.00 22.00 23.00

Rev. 2

K. Surachead P. Worachart P. , Preecha K., Chotepong S., Aphichart S., K. Kawin T., Krisada B., Leartsak Ch., Deaunphen R.
WEATHER CONDITION 3.00 4.00 5.00 6.00 7.00 8.00 S 9.00 S 10.00 S Symbols Yesterday = 11.00 S 12.00 S 13.00 S Cloudy (C), 14.00 S 15.00 S 16.00 S 17.00 S 18.00 S

Working Date Working Time


19.00 S 20.00 S

24.00

Sunshine (S),

Rainy (R) Today

MANPOWER REPORT Normal Time man hours Over Time man hours Normal Time man hours Over Time man hours

No.

Description

Total M/D

Total MH

No.

Description

Total M/D

Total MH

ENSURE INTERNATIONAL CO., LTD. A 1 2 3 4 5 6 7 8 9 10 11 B 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Foreman Welder Fitter Pipe Fitter Structure Helper Driver Scaffolder Fire wach man Insulation Safety Technic Qc Inspector Carpenter Mason Electrician Total A+B No. 1 2 3 No. 1 2 3 4 5 6 7 8 9 Griding M/C 4" Griding M/C 7" Activities (Yesterday) Install Steel Structure Trim Cooler First Alignment For Pump 03P020A/B/C Remove sand Bag From Gutter Install Steel Structure Reactor 03R003 Installation Insulation For 02E007A Installation Insulation For 05T009 Fabrication Pipe 24",28" 304H Shop Fabrication Steel Structure Area 03A 03B 03B 03B 02 05 Shop Shop Description Welding M/C 300 Amp. Unit ea ea ea Unit Set Set Set Set Set Set Set DB Kg. Q'ty 4 12 9 Q'ty 1 13 3 1 1 1 1 52 9246 No. 4 5 6 No. 1 2 3 4 5 6 7 Drill Generator Haib 5 T CONSTRUCTION ACTIVITIES Activities (Today) Install Steel Structure Trim Cooler Remove sand Bag From Gutter Install Steel Structure Reactor 03R003 First Alignment For Pump 03P020A/B/C Installation Insulation For 02E007A Installation Insulation For 05T009 Fabrication Pipe 24",28" 304H Area 03A 03B 03B 03B 02 05 Shop Unit Set Set Set Set Set Set DB Q'ty 1 13 26 3 1 1 28 No. 1 2 3 4 5 6 7 Activities (Tomorrow) Install Steel Structure Trim Cooler Remove sand Bag From Gutter Install Steel Structure Reactor 03R003 Installation Insulation For 05T009 Fabrication Pipe 24",28" 304H Area 03A 03B 03B 05 Shop Unit Set Set Set Set Set Set DB Q'ty 1 26 1 3 1 1 24 Project Manager Site Manager Site Engineer Safety Office QA/QC Manager Draftman Material Control Administrator Storekeeper Document Control Supervisor Direct 6 3 17 10 8 2 9 4 4 4 3 6 5 1 48 24 136 80 64 16 72 32 32 32 24 48 40 8 6 5 1 1 1 3 1 17 10 6 1 9 3 51 30 18 3 3 3 18 15 3 6 3 17 10 8 2 9 4 4 4 3 6 5 1 100 57 27 187 110 82 19 72 35 32 35 24 66 55 11 983 Description 2 1 2 4 Indirect 1 2 3 1 1 1 8 16 24 8 8 8 16 8 16 32 2 1 1 1 2 1 1 3 6 3 3 3 3 6 1 2 3 1 1 1 2 1 2 4 8 19 30 11 11 8 19 11 16 38 A 1 2 3 4 5 6 7 8 9 10 11 B 1 2 3 4 5 6 7 8 9 10 11 12 13 14 Foreman Welder Fitter Pipe Fitter Structure Helper Driver Scaffolder Fire wach man Insulation Safety Technic Qc Inspector Carpenter Mason Electrician Total A+B Unit ea ea ea Q'ty 3 3 No. 7 8 9 Crane 55T. Crane 70T. Trailer Description Project Manager Site Manager Site Engineer Safety Office QA/QC Manager Draftman Material Control Administrator Storekeeper Document Control Supervisor Direct 7 3 17 11 9 2 15 4 4 4 3 6 5 1 56 24 136 88 72 16 120 32 32 32 24 48 40 8 7 3 17 11 9 2 15 4 4 4 3 6 5 1 109 Unit ea ea ea 56 24 136 88 72 16 120 32 32 32 24 48 40 8 872 Q'ty 2 1 2 4 Indirect 1 2 3 1 1 1 8 16 24 8 8 8 16 8 16 32 1 2 3 1 1 1 2 1 2 4 8 16 24 8 8 8 16 8 16 32

EQUIPMENT AND MACHINERY REPORT

Install Steel Structur Cooling water Pipe Support 03A

Install Formwork Foundation Cooling Water 03A First Alignment For Pump 03P020A/B/C 03B

ENSURE INTERNATIONAL CO., LTD. (Sub-contractor)


Prepared By : ... ( ........) Date : . / . / Note : The sub-contractors have to sumit this report to TET before 9.00 am every working day.

TECHNIP ENG. (THAILAND) CO., LTD. (Contractor)


Checked By : ... ( Surachead....Pudjareon....) Date : . / . /

IRPC PUBLIC CO., LTD. (Owner)


Approved By : ... ( ........) Date : . / . /

Page 1 of 1

You might also like