0% found this document useful (0 votes)
70 views1 page

MRP

The document provides an MRP plan for item X which has an independent demand. The plan shows a projected weekly requirement of the item over 12 weeks, with a safety stock of 40 units and order lead time of 4 weeks. The order quantity is 70 units and scheduled receipts are shown to maintain enough inventory on hand to meet the projected demand.

Uploaded by

Shanky Jain
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
70 views1 page

MRP

The document provides an MRP plan for item X which has an independent demand. The plan shows a projected weekly requirement of the item over 12 weeks, with a safety stock of 40 units and order lead time of 4 weeks. The order quantity is 70 units and scheduled receipts are shown to maintain enough inventory on hand to meet the projected demand.

Uploaded by

Shanky Jain
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOC, PDF, TXT or read online on Scribd
You are on page 1/ 1

Complete the MRP Plan for item X (an item having independent demand requiring a safety stock of 40 units)

shown below
Order qty =70 Lead time =4 weeks Safety stock=40 Projected requirement Scheduled receipts On hand at the end of period 65

Week 1 20 2 20 70 3 25 4 20 5 20 6 25 7 20 8 20 9 30 10 25 11 25 12 25

Planned order release