DAILY PROGRESS REPORT

Supervisor DATE AREA : : 5/1/2013 IPP PLTG Senipah Pipeline (Pemedas, Security Road, PPA) Weater : 07.00-13.30 13.30-15.30 15.30-17.00 TOTAL QUANTITY 73 54 46 6 41 23 34 31 71 4 383 Pcs Pcs Pcs Pcs Pcs Pcs Pcs Pcs Pcs Pcs TOTAL Pemedas Area Folio 1 Folio 2 Folio 3 Welding Joint Folio 4 Folio 5 Folio 6 PPA Area TOTAL Pemedas Area PIPELINE Folio 1 Folio 2 NDT - Radiography Folio 3 Folio 4 Folio 5 Folio 6 PPA Area TOTAL Pemedas Area Folio 1 Folio 2 Folio 3 Coating Folio 4 Folio 5 Folio 6 PPA Area TOTAL Pemedas Area Folio 1 Folio 2 Trenching Folio 3 Folio 4 Folio 5 Folio 6 TOTAL Pemedas Area Folio 1 Folio 2 Lowering & Backfill Folio 3 Folio 4 Folio 5 Folio 6 TOTAL m m m m m m m m m m m m m m Joint Joint Joint Joint Joint Joint Joint Joint Joint Joint Joint Joint Joint Joint Joint Joint Joint Joint Joint Joint Joint Joint Joint Joint 73 54 46 6 41 23 34 31 71 4 383 73 56 56 50 60 47 50 4 396 73 56 56 50 60 47 50 4 396 73 56 56 50 60 47 50 4 396 893 638 614 546 618 639 519 4467 893 638 614 546 618 639 519 4467 Clear Rainy Clear PROGRESS RATE 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 94% 75% 64% 100% 100% 0% 91% 100% 100% 0% 72% 100% 93% 88% 100% 73% 74% 94% 0% 78% 100% 93% 88% 100% 68% 74% 88% 0% 76% 100% 95% 89% 96% 60% 53% 80% 0% 72% 100% 23% 82% 97% 40% 0% 0% 43% 100% 24% 0% 0% 0% 0% 0% 16% PROJECT : Afiawan Malik

1. QUANTITY OF MATERIAL ITEM Area/ Location Pemedas Area Area A Area B Area C Area D 8" Pipe Unloading Area E Area F Area G Area H PPA Area TOTAL Pemedas Area Area A Area B Area C Area D 8" Pipe Stringing Area E Area F Area G Area H PPA Area UNIT Pcs Pcs Pcs Pcs Pcs Pcs Pcs Pcs Pcs Pcs ACTUAL 79 20 80 10 70 0 34 46 68 8 415 79 20 80 10 70 0 34 46 68 8 415 73 56 56 50 60 47 50 4 396 0 73 56 56 50 60 47 50 4 396 50 0 0 0 0 0 0 0 0 0 0 0 0 2 1 AMOUNT OF WORK YESTERDAY TODAY TOTAL 79 20 80 10 70 0 34 46 68 8 415 74 15 51 10 70 0 31 46 68 0 365 73 52 49 50 44 35 47 0 350 73 52 49 50 41 35 44 0 344 73 53 50 48 36 25 40 0 325 893 144 504 530 250 0 0 2321 893 156 0 0 0 0 0 1049 REMAIN 0 5 5 29 0 0 0 3 0 0 8 50 0 4 7 0 16 12 3 0 42 4 7 0 19 12 6 0 48 3 6 2 24 22 10 67 494 110 16 368 988 0 -

DAILY PROGRESS REPORT


Supervisor Afiawan Malik

2. WORKER Type of Occupation PT. KID (NDT SERVICE) PT. KCG (Team Pak Ramdani) Local Contractor (Team Pak Andi Zakaria) PT. KRS direct worker Total YESTERDAY 3 3 0 13 TODAY 0 3 0 13 TOTAL 173 2106 1193 4164 7636 Type of Occupation YESTERDAY TODAY TOTAL REMARK

3. EQUIPMENT Type of Equipment Bulldozer Excavator Mobil Crane Welding Machine Chain Block YESTERDAY 0 0 0 1 0 TODAY 0 0 0 1 1 TOTAL 0 0 0 2 1 Type of Equipment Grinding Machine Welding handle bar Cutting Tosh YESTERDAY 0 0 0 TODAY 2 1 0 TOTAL 2 1 0 REMARK

4. DETAILS Today's work Administration Administration Tomorrow's work

Hot Work Permit (Welding, Repair Joint, Cutting and Grinding Activities) Cool Work Permit(Coating activities)
Construction & Operation

Hot Work Permit (Welding, Repair Joint, Cutting and Grinding Activities) Cool Work Permit(Coating activities)
Construction & Operation

Welding Joint 6" pipe at PPA Area 1 (1 Joint)

Continue welding joint 6" & 2" pipe and lifting 6" pipe at PPA area 1

Today's Issue

Today's Counter Meassure

5. PHOTOGRAPH

Prepared By,

Acknowledge,

Afiawan Malik Akbar

Priawan Gautama