Tutorial 4 - Solution
Tutorial 4 - Solution
3. What are the three capabilities that a manufacturing system must process in order to be flexible?
(1) the ability to identify and distinguish among the different incoming part or product styles processed by the system, (2) quick changeover of operating instructions, and (3) quick changeover of physical setup.
4. Name the four tests of flexibility that a manufacturing system must satisfy in order to be classified as flexible?
(1) Part variety test. Can the system process different part styles in a non-batch mode? (2) Schedule change test. Can the system readily accept changes in production schedule: changes in either part mix or production quantities? (3) Error recovery test. Can the system recover gracefully from equipment malfunctions and breakdowns, so that production is not completely disrupted? (4) New part test. Can new part designs be introduced into the existing product mix with relative ease?
6. What are four benefits that can be expected from a successful FMS installation?
(1) increased machine utilization, (2) fewer machines required to accomplish the same amount of work, (3) reduction in factory floor space required, (4) greater responsiveness to change, (5) reduced inventory requirements, (6) lower manufacturing lead times, (7) reduced labor requirements and higher labor productivity, and (8) opportunity for unattended operation.
7. A flexible manufacturing cell consists of two machining workstations plus a load/unload station. The load/unload station is station 1. Station 2 performs milling operations and consists of one server (one CNC milling machine). Station 3 has one server that performs drilling (one CNC drill press). The three stations are connected by a part handling system that has one work carrier. The mean transport time is 2.5 min. The FMC produces three parts, A, B, and C. The part mix fractions and process routings for the three parts are 1 Dr Chong _ Solution Tutorial 4
presented in the table below. The operation frequency fijk = 1.0 for all operations. Determine (a) maximum production rate of the FMC, (b) corresponding production rates of each product, (c) utilization of each machine in the system (d) number of busy servers at each station.
Part j A Part mix pj 0.2 Operation k 1 2 3 4 1 2 3 4 1 2 3 4 Description Load Mill Drill Unload Load Mill Drill Unload Load Drill Mill Unload Station i 1 2 3 1 1 2 3 1 1 3 2 1 Process time tijk 3 min 20 min 12 min 2 min 3 min 15 min 30 min 2 min 3 min 14 min 22 min 2 min
0.3
0.5
(a)
WL1 = (3+2)(0.2)(1.0) + (3+2)(0.3)(1.0) + (3+2)(0.5)(1.0) = 5.0 min WL2 = 20(0.2)(1.0) + 15(0.3)(1.0) + 22(0.5)(1.0) = 19.5 min WL3 = 12(0.2)(1.0) + 30(0.3)(1.0) + 14(0.5)(1.0) = 18.4 min nt = 3(0.2)(1.0) + 3(0.3)(1.0) + 3(0.5)(1.0) = 3, WL4 = 3(2.5) = 7.5 min
Bottleneck station has largest WLi/si ratio: Station WLi/si ratio 1 (load/unload) 5.0/1 = 5.0 min 2 (mill) 19.5/1 = 19.5 min 3 (drill) 18.4/1 = 18.4 min 4 (material handling) 7.5/1 = 7.5 min
Bottleneck
Bottleneck is station 2: Rp* = 1/19.5 = 0.05128 pc/min = 3.077 pc/hr (b) RpA = 0.05128(0.2) = 0.01026 pc/min = 0.6154 pc/hr RpB = 0.05128(0.3) = 0.01538 pc/min = 0.9231 pc/hr RpC = 0.05128(0.5) = 0.02564 pc/min = 1.5385 pc/hr U1 = (5.0/1)(0.05128) = 0.256 = 25.6% U2 = (19.5/1)(0.05128) = 1.0 = 100% U3 = (18.4/1)(0.05128) = 0.944 = 94.4% U4 = (7.5/1)(0.05128) = 0.385 = 38.5% BS1 = (5.0)(0.05128) = 0.256 servers BS2 = (19.5)(0.05128) = 1.0 servers BS3 = (18.4)(0.05128) = 0.944 servers BS4 = (7.5)(0.05128) = 0.385 servers
(c)
(d)
8. Solve the P7 except the number of servers at station 2 (CNC milling machines) = 3 and the number of servers at station 3 (CNC drill process) = 2. Note that with the increase in the number of machines, the FMC is now a FMS.
(a) WL1 = (3+2)(0.2)(1.0) + (3+2)(0.3)(1.0) + (3+2)(0.5)(1.0) = 5.0 min WL2 = 20(0.2)(1.0) + 15(0.3)(1.0) + 22(0.5)(1.0) = 19.5 min WL3 = 12(0.2)(1.0) + 30(0.3)(1.0) + 14(0.5)(1.0) = 18.4 min nt = 3(0.2)(1.0) + 3(0.3)(1.0) + 3(0.5)(1.0) = 3, WL4 = 3(2.5) = 7.5 min
Bottleneck station has largest WLi/si ratio: Station WLi/si ratio 1 (load/unload) 5.0/1 = 5.0 min 2 (mill) 19.5/3 = 6.5 min 3 (drill) 18.4/2 = 9.2 min 4 (material handling) 7.5/1 = 7.5 min
Bottleneck
Bottleneck is station 3: Rp* = 2/18.4 = 0.1087 pc/min = 6.522 pc/hr (b) RpA = 0.1087(0.2) = 0.02174 pc/min = 1.3043 pc/hr RpB = 0.1087(0.3) = 0.03261 pc/min = 1.9565 pc/hr RpC = 0.1087(0.5) = 0.05435 pc/min = 3.261 pc/hr U1 = (5.0/1)(0.1087) = 0.544 = 54.4% U2 = (19.5/3)(0.1087) = 0.706 = 70.6% U3 = (18.4/2)(0.1087) = 1.00 = 100% U4 = (7.5/1)(0.1087) = 0.815 = 81.5% BS1 = (5.0)(0.1087) = 0.544 servers BS2 = (19.5)(0.1087) = 2.12 servers BS3 = (18.4)(0.1087) = 2.0 servers BS4 = (7.5)(0.1087) = 0.815 servers
(c)
(d)
9. A FMS consists of three stations plus a load/unload station. Station 1 loads and unloads parts using two servers (material handling workers). Station 2 performs horizontal milling operations with two servers (identical CNC horizontal milling machines). Station 3 performs vertical milling operations with three servers (identical CNC vertical milling machines). Station 4 performs drilling operations with two servers (identical drill presses). The machines are connected by a part handling system that has three (3) work carriers and a mean transport time = 3.5 min. The FMS produces four parts, A, B, C, and D, whose part mix fractions and process routings are presented in the table below. The operation frequency fijk = 1.0 for all operations. Determine (a) maximum production rate of the FMS (b) utilization of each machine in ths system (c) average utilization of the system U s .
Part j A
Operation k 1
Description Load
Station i 1
0.2
0.25
0.35
2 3 4 5 1 2 3 4 5 6 1 2 3 4 1 2 3 4
H. Mill V Mill Drill Unload Load Drill H. Mill V. Mill Drill Unload Load H. Mill Drill Unload Load V. Mill Drill Unload
2 3 4 1 1 4 2 3 4 1 1 2 4 1 1 3 4 1
15 min 14 min 13 min 3 min 4 min 12 min 16 min 11 min 17 min 3 min 4 min 10 min 9 min 3 min 4 min 18 min 8 min 3 min
(a) WL1 = (4+3)(0.2)(1.0) + (4+3)(0.2)(1.0) + (4+3)(0.25)(1.0) + (4+3)(0.35)(1.0) = 7.0 min WL2 = 15(0.2)(1.0) + 16(0.2)(1.0) + 10(0.25)(1.0) = 8.7 min WL3 = 14(0.2)(1.0) + 11(0.2)(1.0) + 18(0.35)(1.0) = 11.3 min WL4 = 13(0.2)(1.0) + (12+17)(0.2)(1.0) + 9(0.25)(1.0) + 8(0.35)(1.0) = 13.45 min nt = 4(0.2) + 5(0.2) + 3(0.25) + 3(0.35) = 3.6, WL5 = 3.6(3.5) = 12.6 min Station 1 (load/unload) 2 (drill) 3 (H. mill) 4 (. mill) 5 (material handling) WLi/si ratio 7.0/2 = 3.5 min 8.7/2 = 4.35 min 11.3/3 = 3.77 min 13.45/2 = 6.725 min 12.6/3 = 4.2 min
Bottleneck
Bottleneck is station 4: Rp* = 2/13.45 = 0.1487 pc/min = 8.92 pc/hr (b) U1 = (7.0/2)(0.1487) = 0.520 = 52.0% U2 = (8.7/2)(0.1487) = 0.647 = 64.7% U3 = (11.3/3)(0.1487) = 0.560 = 56.0% U4 = (13.45/2)(0.1487) = 1.00 = 100% U5 = (12.6/2)(0.1487) = 0.624 = 62.4%
Us =
(c)
= 0.668 = 66.8%
10. A semi-automated flexible manufacturing cell is used to produce three products. The products are made by two automated processing stations followed by an assembly station. There is also a load/unload station. Material handling between stations in the FMC is accomplished by mechanized carts that move tote bins containing the particular components to be processed and then assembled into a given product. The carts transfer tote bins between stations. In this way the carts are kept busy while the tote bins are queued in front of the workstations. Each tote bin remains with the product throughout processing and assembly. The details of the FMC can be summarized as follows: 4 Dr Chong _ Solution Tutorial 4
Station 1 2 3 4 5
Number of servers 2 human workers 1 automated server 1 automated server 2 human workers Number of carriers to be determined.
The product mix fractions and station processing times for the parts are presented in the table below. The same station sequence is followed by all products: 1 2 3 4 1.
Product j A B C Product mix pj 0.35 0.25 0.40 Station 1 3 min 3 min 3 min Station 2 9 min 5 min 4 min Station 3 7 min 8 min 6 min Station 4 5 min 5 min 8 min Station 1 2 min 2 min 2 min
The average cart transfer time between stations is 4 minutes. a. What is the bottleneck station in the FMC, assuming that the material handling system is not the bottleneck? b. At full capacity, what is the overall production rate of the system and the rate for each product? c. What is the minimum number of carts in the material handling system required to keep up with the production workstations? d. Compute the overall utilization of the FMC. e. What recommendations would you make to improve the efficiency and/or reduce the cost of operating the FMC?
(a) WL1 = (3+2)(0.35 + 0.25 + 0.4) = 5.0 min WL2 = 9(0.35)(1.0) + 5(0.25)(1.0) + 4(0.4)(1.0) = 6.0 min WL3 = 7(0.35)(1.0) + 8(0.25)(1.0) + 6(0.4)(1.0) = 6.85 min WL4 = 5(0.35)(1.0) + 5(0.25)(1.0) + 8(0.4)(1.0) = 6.2 min nt = 4 for all parts, WL5 = 4(4) = 16.0 min WLi/si ratio 5.0/2 = 2.5 min 6.0/1 = 6.0 min 6.85/1 = 6.85 min 6.2/2 = 3.1 min 16.0/nc
Bottleneck
Bottleneck is station 3: Rp* = 1/6.85 = 0.146 pc/min = 8.76 pc/hr RpA = 0.35(8.76) = 3.07 pc/hr RpB = 0.25(8.76) = 2.19 pc/hr RpC = 0.4(8.76) = 3.50 pc/hr Minimum number of carts required in system: 16.0/nc = 6.85 Rearranging, nc = 16/6.85 = 2.34 Use 3 carts U1 = (5.0/2)(0.146) = 0.365 = 36.5% U2 = (6.0/1)(0.146) = 0.876 = 87.6% U3 = (6.85/1)(0.146) = 1.0 = 100% U4 = (6.2/2)(0.146) = 0.453 = 45.3%
(c)
(d)
(e)
Recommendations: (1) reduce number of servers at station 1 to 1 server, and (2) reduce number of servers at station 4 to 1 server.