This document provides a paint handbook for estimating labor hours required for various real property maintenance painting tasks. It outlines new and revised standardized tasks for brush, roller, and spray painting, as well as glazing, surface preparation, and traffic striping. The handbook is intended to help produce more realistic, consistent, and timely labor estimates for maintenance activities. Comments and feedback are solicited from users to further improve the handbook.
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
147 views56 pages

P 710

This document provides a paint handbook for estimating labor hours required for various real property maintenance painting tasks. It outlines new and revised standardized tasks for brush, roller, and spray painting, as well as glazing, surface preparation, and traffic striping. The handbook is intended to help produce more realistic, consistent, and timely labor estimates for maintenance activities. Comments and feedback are solicited from users to further improve the handbook.
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 56

ENGINEERED PERFORMANCE STANDARDS

for Real Property Maintenance Activities

Paint Handbook
ARMY TB 420-18 NAVFAC P-710.0 AIR FORCE AFM 85-49 OCT 1990

DEPARTMENTS OF THE ARMY, THE NAVY AND THE AIR FORCE

DISTRIBUTION ARMY Active Army, ARNG, USAR: To be distributed in accordance with DA Form 12-34C, requirements for TB 420 series.

NAVY (for Public Works) (4 cys each unless specified otherwise) SNDL Part 1: 2451; 27G (Detachment Christ Church only); 39B1; 3982; 49 Part 2: A6 (LFF-2); B1; C37A2 (Annapolis Laboratory, White Oak Laboratory only); C43 (Kamiseya only); C4F48A (Kamiseya only); E3A, 8 cys (Washington only); FA6 (Bermuda, Brunswick, Cecil Field, Jacksonville, Key West, Virginia Beach, only); FA7 (Guantanamo Bay, Keflavik, Mayport, Panama, Roosevelt Roads only); FA10; FA18; FA23 (Argentia only); FB6 (Atsugi, El Centro only); FB7 (Fallon, Lemoore, Moffett Field, Oak Harbor, San Diego only); FB10 (Adak only); FB13 (Bremerton only); FB31 (Lualuale only); FB34 (Kadena, Sasebo only); FB36 (Adak only); FC4 (Sigonella only); FC7; FE2, 5 cys; FE4 (Adak, Winter Harbor only); FF1, 20 cys; FF6; FF19 (New Orleans, Seattle only); FF38, 25 cys; FG2 (Diego Garcia, Exmouth, Stockton only); FG3 (Cutler, Washington DC only); FH3 (Beaufort only); FKA1C; ; FKM13; FKM15; FKN1, 100 cys ea; FKN2; FKNS, 30 cys ea; FKN10; FKP1B (Concord, Colts Neck, Seal Beach, Yorktown only); FKP1E; FKP1J, 15 cys; FKP1M; FKP4C; FKP7 (Bremerton, Charleston, Long Beach, Philadelphia, Portsmouth NH, Portsmouth VA, Mare Island only); FKR1A, 15 cys; FKR3A; FKR3H; FKRS; FR3; FT6, (Beeville, Corpus Christi, Kingsville, Millington, Meridian, Milton only); FT22 (Dam Neck only); FT28, 5 cys; FT31 (Orlando only); FT37, 10 cys; FT55; FT73; V5 (Beaufort, Cherry Point-10 cys, Iwakuni, Kaneohe Bay, El Toro, Yuma only); V8; V12, 20 cys; V14; V16 (Camp Lejuene, Camp Pendleton, Camp Smedley D. Butler only); V23. Additional copies may be obtained from: Naval Publications and Forms Center 5801 Tabor Ave., Philadelphia, PA 19120 (Available in paper or microfiche copy) AIR FORCE (for Base Civil Engineer) F Additional copies may be obtained from: Air Force Publication Distribution Center 2800 Eastern Blvd. Baltimore, MD 21220 Via: Activity Publications Distribution Office ii

FOREWORD This handbook provides guidance to Planners-Estimators in projecting labor hour requirements for-workers to perform typical facilitiesmaintenance tasks. Proper use of the data in this handbook will help provide more realistic,-consistent, and timely labor hour estimates.These estimates provide bench marks that enable managers to evaluate and control actions based on improvement. More effective response and support at minimum cost can, in turn, be realized. Comments and suggestions regarding the handbook are invited and should be sent to: Director NAVFAC Industrial Engineering Center (NIEC) Atlantic Division Naval Facilities Engineering Command Norfolk, VA 23511-6287 Telephone (804) 444-9831 or AUTOVON 565-2297 To facilitate forwarding of comments, addressed feedback forms are included in the back of this handbook. For Air Force installations, send copies of comments and/or suggestions to: Headquarters Air Force Engineering and Services Center (AFESC/DEMG) Tyndall Air Force Base, FL 32403-6001 This publication supersedes TB 420-18, NAVFAC P-710.0 and AFM 85-49 of July 1984. By order of the Secretaries of the Army, the Navy, and the Air Force. Official: R. L. DILWORTH Brigadier General, U.S. Army The Adjutant General Official: CARL E. VUONO General, U. S. Army Chief of Staff LARRY D. WELCH General, USAF Chief of Staff DONALD B. CAMPBELL CAPT, CEC, U.S. Navy For the Commander Naval Facilities Engineering Command
iii

MARSHALL NAY Colonel, USAF Commander, Air Force Engineering and Services Center

(THIS PAGE INTENTIONALLY LEFT BLANK)

iv

CONTENTS Page DISTRIBUTION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . FOREWORD . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SYNOPSIS OF CHANGES . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SUPPLEMENTAL TASK LISTING . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . SUMMARY OF GENERAL DATA . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . PAINT SURVEY FORM . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . INTRODUCTION . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . CRAFT TIME ADJUSTMENT (CTA) CHART . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . I. TASK TIME SUMMARY. . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Brush Painting . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Glazing . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Roller Painting . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Spray Painting . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Signs . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Surface Preparation . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . Traffic Striping . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .. . . . . . . . . . . . II. TASK TIME DETAILS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . ii iii vii viii ix X xi xiii 1 3 5 7 9 11 13 17 19 37

III. EPS FEEDBACK SHEETS . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . . .

(THIS PAGE INTENTIONALLY LEFT BLANK)

vi

SYNOPSIS OF CHANGES

The following is a summary of new and revised standards found in this edition of ARMY TB 420-18, NAVFAC P-710.0, AIR FORCE AFM 85-49.

NEW BRUSH PAINT OBJECTS GLAZING INSTALL GLASS PANE IN NEW WOOD SASH ROLLER PAINTING SURFACE SURFACE PREPARATION ABRASIVE CLEANING USING HANDTOOLS FLAT, SLIGHTLY CURVED OR UNOBSTRUCTED SURFACE IRREGULAR, ANGULAR OR DIFFICULT TO REACH SURFACE OBJECTS

PT-132, PT-133, PT-134, PT-135, PT-136

PT-241

PT-330, PT-340

PT-604, PT-631, PT-632, PT-633, PT-634

PT-608, PT-635, PT-636, PT-637, PT-638

PT-621, PT-623, PT-624, PT-625, PT-626, PT-627, PT-628, PT-629 PT-678, PT-680, PT-681, PT-684, PT-685

REPAIR SURFACE

REVISED BRUSH PAINTING PT-101, PT-106, PT-123, PT-128, PT-153, PT-172, PT-102, PT-107, PT-124, PT-129, PT-154, PT-173 PT-103, PT-108, PT-125, PT-131, PT-155, PT-104, PT-121, PT-126, PT-151, PT-163, PT-105, PT-122, PT-127, PT-152, PT-171,

GLAZING ROLLER PAINTING SPRAY PAINTING

PT-221, PT-223, PT-224, PT-225 PT-301, PT-320, PT-350 PT-411, PT-412, PT-415, PT-417, PT-421, PT-422, PT-425, PT-427 PT-622

SURFACE PREPARATION

vii

viii

ix

PAINT SURVEY
SITE ID SITE CONTACT SITE PHONE WORK REQUEST # SURVEY BY SURVEY DATE

CONSTRUCTION: concrete, plaster, plywood, metal, etc. dimensions: PREPARATION: Type: wipe, scrape, sandblast, etc.

percent requiring preparation Special: mask, glaze, patch, cover, columns, ducts, pipes, etc.

Equipment: ladder, compressor, etc. Help from other crafts? COVERING: Application: brush, roll, spray Coats Required: Type Paint: alkyd, latex, vinyl, etc. Units: SF, LF, QTY, S p e c i a l : cut in, stencil, stripe, etc. OTHER:

SITE NOTES & SKETCH:

INTRODUCTION

The major changes appearing in this revision are the expansion of existing standards into more useful segments of work. The largest areas of concentrated effort are reflected in Brush Painting and Surface Preparation. Other additions or changes occur in the Glazing, Roller Painting and Spray Painting areas. "Two man job" and "More than two men" entries have been removed from the Supplemental Task sheet and are now included in all painting tasks except Traffic Striping. The Ladder listing has been removed from the Paint Handbook and placed on the Supplemental Task sheet to make it more readily accessible to all crafts. Task Listing. One page is used for each major classification of work except for Surface Preparation, which has two pages. The page titles are identical to the titles listed in the table of contents. The task descriptions are brief, yet give a quick overview of what tasks are available. If the task does not appear on this page, it does not exist. If there was a question as to where a task should be placed, it will appear in all classifications where it could possibly be listed. Explanation and Scope of Standards. Each task listing page has a facing page of explanations. This page gives a detailed description of the task limitations and applications. Also on this page is a short paragraph on materials and an example of how the task would appear on a Job Phase Calculation Sheet (JPCS). Task Time Details. The Task Time Details no longer include times for each detail line. These reformatted details are listed numerically in the back of this handbook. They are provided for your use in researching the contents of the task. General Information. All task times are shown in labor hours. These labor hours do not include time for staging required materials at the job site. Activities such as material handling time, travel time and job preparation time are covered in the Planner-Estimator's Deskguide. Engineered Performance Standards (EPS) should be applied by personnel who have attended an EPS training course. New users of EPS should attend a formal initial EPS training course as soon as possible. In the interim, new users should be assisted and their planning and estimating work reviewed by personnel formally trained and experienced in using EPS.

xi

(THIS PAGE INTENTIONALLY LEFT BLANK)

xii

CRAFT TIME ADJUSTMENT APPLICATION PROCEDURE Craft Time Adjustment (CTA) can be used to modify EPS task times in this book. Use CIA only when work content comparison shows the planned job to require more or less work than the listed task. a. The CTA Chart shows the amount that, the calculated EPS craft time can be adjusted up or down (+/-) after occurrences have been multiplied by the Task-Time-Standard. The CTA HOURS are based on the differences between EPS Group Times (see DESKGUIDE Table 2.1).

b.

CTA Application Steps (1) Select the proper EPS task by reading and understanding the EPS task descriptions and the Task-Time-Standard details in the back of the hard copy EPS Handbook. (2) Use the normal procedure of writing the selected EPS task reference, description, unit hours, occurrence and calculated EPS CRAFT TIME. (Write 'WCC' below the EPS reference (Col #7) if Work Content Comparison is used.) (3) Decide if CTA is needed, based on P-E craft knowledge. If so, look up the EPS CRAFT TIME range and determine the CTA HOURS from the CTA Chart. Note: Use only the plus or minus value indicated under CTA hours shown. Do not select from a range.

On a separate JPCS line, just below the related EPS task: (4) Write "CTA" in the Reference column (#7). (5) Write a short explanation for the CTA in the Description column (#8). Compare the work content to the EPS task. (6) leave the Unit Hours column (#9a) blank. (7) Show a "+" or "-" sign in the Occurrence column (#9b). (When using a "-", remember to subtract while totaling.) (8) Write the CTA time in the Craft Time column (#9c). (Only use one CTA occurrence per EPS task.) For conditions needing adjustment time exceeding CTA hours: (9) Write a non-EPS estimate or select another EPS task.

xiii

(THIS PAGE INTENTIONALLY LEFT BLANK)

xiv

I. TASK TIME SUMMARY

PAGE

BRUSH PAINTING
EXPLANATION AN0 SCOPE OF STANDARDS

Application These standards apply to brush painting a prepared surface that is within
reach when standing. Task time standards for surface preparation and ladder use must be added as required. The door size that was selected for brush painting is 3'X7' and the window size that was selected is 3'-8" X 5'-0". Remarks These task time standards were developed for one coat application, but may be used for multiple coats by occurrencing the unit hours as needed. These standards are to be used for priming and applying finish coats. When painting pipes or columns in excess of 8" in diameter, use the task time standard for painting metal surface (PT-106). Task time standard for exposed wood rafters (PT-129) is in units of linear feet of roof. Materials Wiping cloth, brushes, paint, b u c k e t s , d r o p c l o t h s , s t i r r i n g p a d d l e s , p r y i n g t o o l , screwdriver, hammer, solvents, pigments, fire or safety permits, fire extinguisher, warning tags or signs, barricades, safety clothing.

6. JOB PHASE DESCRIPTION

Brush paint one coat on inside surface of door, door jamb, two windows and related trim in Room 197. (Door is 3' X 7' and windows are six panes over six panes.)

9. EPS ESTIMATED TIME REFERENCE 7 TASK DESCRIPTION 8 UNIT HOURS a. OCCURRENCE b. CRAFT TlME
C.

I NON-EPS ESTIMATED TIME 10

PT-136 PT-132

Paint one side of door, one coat Paint one side of door jamb/casing, one coat

.1750 .2821

1 1

.2 .3 1.9

PT-135

Paint one side of two windows, one coat NOTE: Add surface preparation and ladder use if appropriate to complete craft time.

.9438

TOTALS (Craft & Estimated Time)

CHAPTER
REF.

10

BRUSH PAINTING
TASK DESCRlPTlON

REVISION UNIT HOURS

PAGE UNIT

SURFACE PT-101 PT-102 PT-103 PT-104 PT-105 PT-106 PT-107 PT-108 PT-131 Fiber block or acoustical ceiling Clapboard Concrete, smooth Metal, corrugated/perforated Metal, expanded Metal, smooth (includes beams) Terra cotta block Wood, plywood or plaster Wood, plywood or plaster up to 6" wide .0078 .0077 .0061 .0067 .0135 .0064 .0067 .0049 .0036 SQ FT SQ FT SQ FT SQ FT SQ FT SQ FT SQ FT SQ FT LIN FT

OBJECTS PT-136 PT-132 PT-133 PT-134 PT-135 PT-121 PT-122 PT-123 PT-124 PT-125 PT-126 PT-127 PT-128 PT-129 Door, wood or metal (smooth or paneled) Door jamb/casing or doorway Window, one pane over one pane Window, two panes over two panes Window, six panes over six panes Door, panel (wood or metal) Door, edge (wood or metal) Door jamb/casing or doorway Grille, metal Gutter, 4" round Pipe, .5" to 1.5" dia. Pipe, over 1.5" to 4" dia. Pipe or column, over 4" to 8" dia. Rafter, exposed, wood (also includes fascia, eave section and eave block) SIDE .1750 SIDE .2821 .6565 SIDE .7779 SIDE .9438 SIDE .0049 SQ FT LIN FT .0041 .0055 LIN FT .0135 SQ FT .0196 LIN FT .0060 LIN FT .0109 LIN FT .0202 LIN FT .0498 LIN FT

COATINGS/COVERINGS PT-151 PT-152 PT-153 PT-154 PT-155 Aluminum paint - waterproof tar Enamel - metal surface Red lead - metal surface Shellac - plaster or wood surface Zinc chromate - metal surface .0041 .0073 .0090 .0049 .0118 SQ FT SQ FT SQ FT SQ FT SQ FT

TRIM/CUT IN PT-163 All narrow surfaces (up to 3" wide) SAFETY STRIPE PT-177 PT-172 PT-173 Metal surface, corrugated Metal surface, smooth Wood panel .2151 .0426 .0701 SQ FT SQ FT SQ FT .0059 LIN FT

4
PAGE

GLAZING
EXPLANATION AND SCOPE OF STANDARDS

Application These standards apply to installing glass in doors or windows that are within reach when standing. Task time standards for surface preparation and ladder use must be added as required. Remarks The removal and installation of framed window screens has been developed as a separate standard. This standard is added when it is necessary to remove a screen to gain access to a pane that needs work. Materials Hand tools, glass, spacer shims, glazer points, glazing compound, putty, caulking compound and sealants.

6. JOB PHASE DESCRIPTION

Replace twenty (20) panes of 24" X 24" glass in wood sashes.

Removal of screens and cutting of glass are required.

9. EPS ESTIMATED TIME REFERENCE 7 TASK DESCRIPTION 6 UNIT HOURS a. OCCURRENCE b. CRAFT TIME
C.

NON-EPS ESTIMATED TIME 10

PT-231 PT-213

Remove and i n s t a l l (20) screens

.0488

20

1.0

Remove and install (20) panes of 24" X 24" glass .0466 in wood sashes when cutting of glass is required

20

9.4

NOTE:

Add ladder use if appropriate to complete craft time.

10

11

12

13

14

15

16

17

(THIS PAGE INTENTIONALLY LEFT BLANK)

18

II. TASK TIME DETAILS

19

(THIS PAGE INTENTIONALLY LEFT BLANK)

20

PT-101 BRUSH ONE COAT OF PAINT ON CELO-TEX FIBER BLOCK OR ACOUSTICAL CEILING NO WORK UNIT DESCRIPTION ==================================================== 1 APPLY ONE COAT OF PAINT ON CELO-TEX FIBER BLOCK OR ACOUSTICAL CEILING WITH BRUSH 2 IN-PROCESS SETUP AND HANDLING TIME 3 ADDITIONAL JOB PREPARATION TIME FOR PAINTING PT-101 = .00777 HRS PER SQ FT

PT-105 BRUSH ONE COAT OF PAINT ON ONE SIDE OF EXPANDED METAL NO WORK UNIT DESCRIPTION ==================================================== 1 APPLY ONE COAT OF PAINT ON EXPANDED METAL (ONE SIDE) WITH BRUSH 2 IN-PROCESS SETUP AND HANDLING TIME 3 ADDITIONAL JOB PREPARATION TIME FOR PAINTING VT-105 = .01342 HRS PER SQ FT

PT- 102 BRUSH ONE COAT OF PAINT ON CLAPBOARD SURFACE NO WORK UNIT DESCRIPTION ==================================================== 1 APPLY ONE COAT OF PAINT ON CLAPBOARD SURFACE WITH BRUSH 2 IN-PROCESS SETUP AND HANDLING TIME 3 ADDITIONAL JOB PREPARATION TIME FOR PAINTING PT-102 = .00764 HRS PER SQ FT

PT-106 BRUSH ONE COAT OF PAINT ON FINISHED/SMOOTH METAL SURFACE NO WORK UNIT DESCRIPTION ==================================================== 1 APPLY ONE COAT OF PAINT ON FINISHED/SMOOTH METAL SURFACE WITH BRUSH 2 IN-PROCESS SETUP AND HANDLING TIME 3 ADDITIONAL JOB PREPARATION TIME FOR PAINTING PT-106 = .00635 HRS PER SQ FT

PT-103 BRUSH ONE COAT OF PAINT ON FLAT CONCRETE SURFACE NO WORK UNIT DESCRIPTION ==================================================== 1 APPLY ONE COAT OF PAINT ON FLAT CONCRETE SURFACE WITH BRUSH 2 IN-PROCESS SETUP AND HANDLING TIME 3 ADDITIONAL JOB PREPARATION TIME FOR PAINTING PT-103 = .00602 HRS PER SQ FT

PT-107 BRUSH ONE COAT OF PAINT ON TERRA COTTA BLOCK NO WORK UNIT DESCRIPTION ==================================================== 1 APPLY ONE COAT OF PAINT ON TERRA COTTA BLOCK WITH BRUSH 2 IN-PROCESS SETUP AND HANDLING TIME 3 ADDITIONAL JOB PREPARATION TIME FOR PAINTING PT-107 = .00667 HRS PER SQ FT

PT-104 BRUSH ONE COAT OF PAINT ON CORRUGATED OR PERFORATED METAL SURFACE NO WORK UNIT DESCRIPTION ==================================================== 1 APPLY ONE COAT OF PAINT ON CORRUGATED OR PERFORATED METAL SURFACE WITH BRUSH 2 IN-PROCESS SETUP AND HANDLING TIME 3 ADDITIONAL JOB PREPARATION TIME FOR PAINTING PT-104 = .00669 HRS PER SQ FT

PT- 108 BRUSH OWE COAT OF PAINT ON WOOD, PLYWOOD OR PLASTERED SURFACE NO WORK UNIT DESCRIPTION ==================================================== 1 APPLY ONE COAT OF PAINT ON WOOD, PLYWOOD OR PLASTERED SURFACE WITH BRUSH 2 IN-PROCESS SETUP AND HANDLING TIME 3 ADDITIONAL JOB PREPARATION TIRE FOR PAINTING PT-108 = .00486 HRS PER SQ FT

21

PT-121 BRUSH ONE COAT OF PAINT ON DOOR PANEL(S) OR SIDE(S) NO WORK UNIT DESCRIPTION ==================================================== 1 APPLY A COAT OF PAINT ON DOOR PANEL(S) OR SIDE(S) WITH BRUSH 2 IN-PROCESS SET UP AND HANDLING TIME 3 ADDITIONAL JOB PREPARATION TIME FOR PAINTING PT-121 = .00486 HRS PER SQ FT

PT-126 BRUSH ONE COAT OF PAINT ON 1/2 DIA TO 1-1/2 DIA PIPE NO WORK UNIT DESCRIPTION ==================================================== 1 APPLY ONE COAT OF PAINT ON 1/2 TO 1-1/2 DIA PIPE WITH BRUSH 2 ADDITIONAL JOB PREPARATION TIME FOR PAINTING PT-126 = .00596 HRS PER LIN FT

PT-122 BRUSH ONE COAT OF PAINT ON DOOR EDGES NO WORK UNIT DESCRIPTION ==================================================== 1 APPLY ONE COAT OF PAINT ON DOOR EDGES WITH BRUSH 2 ADDITIONAL JOB PREPARATION TIME FOR PAINTING PT-122 = .00403 HRS PER LIN FT

PT-127 BRUSH ONE COAT OF PAINT ON OVER 1-1/2 DIA TO 4 DIA PIPE NO WORK UNIT DESCRIPTION ----==================================================== 1 APPLY ONE COAT OF PAINT ON OVER 1-1/2 DIA TO 4 OR COLUMN WITH BRUSH 2 ADDITIONAL JOB PREPARATION TINE FOR PAINTING PT-127 = .01083 HRS PER LIN FT

PT-123 BRUSH COAT OF PAINT ON DOORWAY OR DOOR JAMB AND CASING NO WORK UNIT DESCRIPTION ==================================================== 1 APPLY ONE COAT OF PRIMER OR PAINT ON DOOR JAMB OR CASING WITH BRUSH 2 IN-PROCESS SET UP AND HANDLING TIME 3 ADDITIONAL Jo8 PREPARATION TIME FOR PAINTING PT-123 = .00548 HRS PER LIN FT

PT-128 BRUSH ONE COAT OF PAINT ON OVER 4 DIA TO 8" DIA PIPE OR COLUMN NO WORK UNIT DESCRIPTION ==================================================== 1 APPLY ONE COAT OF PAINT ON OVER 4 DIA TO 8 DIA PIPE WITH BRUSH 2 ADDITIONAL JO8 PREPARATION TIME FOR PAINTING PT-128 = .02017 HRS PER LIN FT

PT-124 BRUSH FINISH COAT OF PAINT ON METAL GRILLE NO WORK UNIT DESCRIPTION ==================================================== 1 APPLY OWE COAT OF PAINT ON METAL GRILLE USING 5 BRUSH 2 IN-PROCESS SETUP AND HANDLING TIME 3 ADDITION JOB PREPARATION TIME FOR PAINTING PT-124 = .01344 HRS PER SQ FT

PT-129 BRUSH COAT OF PAINT ON EXPOSED RAFTERS (16-20 -24 C.C.), ALSO INCLUDES TWO SIDES AND EDGE OF FASCIA, EAVE SECTION (UNDERSIDE OF SHEATHING BETWEEN RAFTERS), AND EDGE AND SIDE OF EAVE BLOCKS (PER LIN FT OF ROOF) NO WORK UNIT DESCRIPTION ==================================================== 1 APPLY COAT OF PAINT ON FASCIA, 2 SIDES AND 1 EDGE 2 APPLY COAT OF PAINT ON RAFTERS, 2 SIDES AND 1 EDGE 3 APPLY COAT OF PAINT ON EAVE SECTION 4 APPLY COAT OF PAINT ON EAVE BLOCKS, 2 SURFACES 5 ADDITIONAL JOB PREPARATION TIME FOR PAINTING PT-129 = .04976 HRS PER LIN FT

PT-125 BRUSH ONE COAT OF PAINT ON 4 GUTTER NO WORK UNIT DESCRIPTION ==================================================== 1 APPLY ONE COAT OF PAINT ON 4 GUTTER USING BRUSH 2 ADDITIONAL JOB PREPARATION TIME FOR PAINTING PT-125 = .01956 HRS PER LIN FT

22

PT-131 BRUSH ONE COAT OF PAINT ON WOOD, PLYWOOD OR PLASTERED SURFACE, UP TO 6 WIDE. NO WORK UNIT DESCRIPTION ==================================================== 1 APPLY ONE COAT OF PAINT ON WOOD, PLYWOOD AND PLASTERED SURFACE UP TO 6 IN WIDTH USING A BRUSH 2 IN-PROCESS SET UP AND HANDLING TIME 3 ADDITIONAL JOB PREPARATION TIME FOR PAINTING PT-131 = .00358 HRS PER LIN FT

PT-135 BRUSH COAT OF PAINT ON EXTERIOR OR INTERIOR SIDE OF DOUBLE HUNG WINDOW, SIX PANES OVER SIX PANES, INCLUDING SASHES AND RELATED TRIM NO WORK UNIT DESCRIPTION ==================================================== 1 RAISE AND LOWER (2) SASHES 2 APPLY COAT OF PRIMER OR FINISH COAT OF PAINT ON WINDOW SASHES AND RELATED TRIM MATERIAL WITH BRUSH 3 WIPE PAINT FROM GLASS PANES 4 IN-PROCESS SET UP AND HANDLING TIME 5 ADDITIONAL JOB PREPARATION TIRE FOR PAINTING PT-135 = .94379 HRS PER SIDE

PT-132 BRUSH COAT OF PAINT ON DOOR JAMB OR DOORWAY NO WORK UNIT DESCRIPTION ==================================================== 1 APPLY ONE COAT OF PRIMER OR PAINT ON DOOR CASING WITH BRUSH 2 APPLY COAT OF PRIMER OR PAINT ON DOOR JAMB WITH BRUSH 3 IN-PROCESS SETUP AND HANDLING TIME 4 ADDITIONAL JOB PREPARATION TIME FOR PAINTING PT-132 = .28201 HRS PER SIDE

PT-136 BRUSH ON COAT OF PAINT ON DOOR NO WORK UNIT DESCRIPTION ==================================================== 1 APPLY ONE COAT OF PRIMER OR PAINT ON DOOR PANEL WITH BRUSH 2 APPLY ONE COAT OF PRIMER OR PAINT ON DOOR EDGES WITH BRUSH 3 IN-PROCESS SET UP AND HANDLING TIME 4 ADDITIONAL JOB PREPARATION TIME FOR PAINTING PT-136 = .17500 HRS PER SIDE

PT-133 BRUSH COAT OF PAINT ON EXTERIOR OR INTERIOR SIDE OF DOUBLE HUNG WINDOW, ONE PANE OVER ONE PANE INCLUDING SASHES AND RELATED TRIM NO WORK UNIT DESCRIPTION ==================================================== 1 RAISE AN0 LOWER (2) SASHES 2 APPLY COAT OF PRIMER OR FINISH COAT OF PAINT ON WINDOW SASHES AND RELATED TRIM MATERIAL WITH BRUSH 3 WIPE PAINT FROM GLASS PANES 4 IN-PROCESS SET UP AND HANDLING TIME 5 ADDITION JOB PREPARATION TIME FOR PAINTING PT-133 = .65641 HRS PER SIDE

PT-151 BRUSH ONE COAT OF ALUMINUM PAINT ON WATERPROOF TAR SURFACE NO WORK UNIT DESCRIPTION ==================================================== 1 APPLY ALUMINUM COAT ON WATERPROOF TAR SURFACE (NEW) WITH 4 BRUSH 2 IN-PROCESS SETUP AND HANDLING TIME 3 ADDITIONAL JOB PREPARATION TIME FOR PAINTING PT--151 = .00403 HRS PER SQ FT

PT-134 BRUSH COAT OF PAINT ON EXTERIOR OR INTERIOR SIDE OF DOUBLE HUNG WINDOW, TWO PANES OVER TWO PANES, INCLUDING SASHES AND RELATED TRIM NO WORK UNIT DESCRIPTION ==================================================== 1 RAISE AND LOWER (2) SASHES 2 APPLY COAT OF PRIMER OR FINISH COAT OF PAINT ON WINDOW SASHES AND RELATED TRIM MATERIALS 3 WIPE PAINT FROM GLASS PANES 4 IN-PROCESS SET UP AND HANDLING TIME 5 ADDITIONAL JOB PREPARATION TIME FOR PAINTING PT-134 = .77790 HRS PER SIDE

PT-152 BRUSH ONE COAT OF ENAMEL PAINT ON METAL SURFACE NO WORK UNIT DESCRIPTION ==================================================== 1 APPLY FINISH COAT OF ENAMEL PAINT ON METAL SURFACE WITH 4 BRUSH 2 IN-PROCESS AND HANDLING TIME 3 ADDITIONAL JO8 PREPARATION TIME FOR PAINTING PT-152 = .00724 HRS PER SQ FT

23

PT-153 BRUSH ONE COAT OF RED LEAD ON SMOOTH METAL SURFACE NO WORK UNIT DESCRIPTION ==================================================== 1 APPLY ONE COAT OF RED LEAD ON METAL SURFACE USING BRUSH 2 IN-PROCESS SETUP AND HANDLING TIME 3 ADDITIONAL JOB PREPARATION TIME FOR PAINTING PT-153 = .00894 HRS PER SQ FT

PT-171 BRUSH PAINT SAFETY STRIPES ON CORRUGATED METAL SURFACE NO WORK UNIT DESCRIPTION ==================================================== 1 PAINT SAFETY STRIPE ON CORRUGATED METAL WITH 1" WIDE BRUSH 2 ADDITIONAL JOB PREPARATION FOR PAINTING PT-171 = .21504 HRS PER SQ FT

PT-154 BRUSH ONE COAT OF SHELLAC ON PLASTER AND/OR WOOD SURFACE (FLAT) NO WORK UNIT DESCRIPTION ==================================================== 1 APPLY COAT OF SHELLAC ON WOOD OR PLASTER SURFACE USING BRUSH 2 IN-PROCESS SETUP AND HANDLING TIME 3 ADDITIONAL JOB PREPARATION TIME FOR PAINTING PT-154 = .00488 HRS PER SQ FT

PT-172 BRUSH PAINT SAFETY STRIPES ON SHEET METAL SURFACE NO WORK UNIT DESCRIPTION ==================================================== 1 PAINT SAFETY STRIPE ON SMOOTH METAL WITH 1" WIDE BRUSH 2 ADDITIONAL JOB PREPARATION TIME FOR PAINTING PT-172 = .04254 HRS PER SQ FT

PT-173 PT-155 BRUSH ONE COAT OF ZINC CHROMATE ON SMOOTH METAL SURFACE NO WORK UNIT DESCRIPTION ==================================================== 1 PRIME COAT METAL WITH ZINC CHROMATE USING 4" BRUSH 2 IN-PROCESS SETUP AND HANDLING TIME 3 ADDITIONAL JOB PREPARATION TIME FOR PAINTING PT-155 = .01174 HRS PER SQ FT BRUSH PAINT SAFETY STRIPES ON WOOD PANEL SURFACE NO WORK UNIT DESCRIPTION ==================================================== 1 PAINT SAFETY STRIPE ON WOOD SURFACE WITH 1" BRUSH 2 ADDITIONAL JOB PREPARATION TIME FOR PAINTING PT-173 = .07004 HRS PER SQ FT

PT-201 GLAZING - INSTALL GLASS PANE (24" X 24") IN NEW WOOD SASH, INCLUDING CUTTING GLASS TO SIZE NO WORK UNIT DESCRIPTION ==================================================== 1 INSTALL PANE IN NEW WOOD SASH ON JOB SITE WHERE NO GLASS TO BE REMOVED (PANE 14" X 20" - ONE PERSON 2 CUT AVERAGE SIZE PANE OF WINDOW GLASS PT-201 = .16697 HRS PER PANE

PT-163 BRUSH ONE COAT OF PAINT ON TRIM MATERIAL AND OTHER NARROW SURFACES UP TO 3" WIDE TO INCLUDE WOOD, METAL, CONCRETE, PLASTER AND TERRA COTTA MATERIALS NO WORK UNIT DESCRIPTION ==================================================== 1 APPLY COAT OF PAINT ON WOOD TRIM OR "CUT IN WOOD STRIP UP TO 3" WIDE WITH BRUSH 2 APPLY COAT OF PAINT ON SMOOTH OR FINISHED METAL STRIP UP TO 3" WIDE OR "CUT IN" WITH BRUSH 3 APPLY COAT OF PAINT ON PLASTER SURFACE UP TO 3" WIDE OR CUT IN" WITH BRUSH 4 APPLY COAT OF PAINT ON CORRUGATED METAL STRIP UP 3" WIDE OR "CUT IN WITH BRUSH 5 APPLY COAT OF PAINT ON CONCRETE SURFACE UP TO 3" WIDE OR "CUT IN" WITH BRUSH 6 APPLY COAT OF PAINT ON TERRA COTTA SURFACE UP TO 3" WIDE OR "CUT IN" WITH BRUSH 7 IN-PROCESS SET UP MD HANDLING TIME 8 ADDITIONAL JOB PREPARATION TIRE FOR PAINTING PT-163 = .00586 HRS PER LIN FT

24

PT-202 GLAZING -- INSTALL LARGE SIZE GLASS PANE (24" X 24 TO 36 X 36) IN NEW WOOD SASH, INCLUDING CUTTING GLASS TO SIZE NO WORK UNIT DESCRIPTION ==================================================== 1 INSTALL PANE IN NEW WOOD SASH ON JOB SITE WHERE NO GLASS IS TO BE REMOVED W/MINIMUM DIMENSIONS OF 24 X24 AND UP TO A MAXIMUM DIMENSION OF 36X36 (ONE PERSON) 2 CUT AVERAGE SIZE PANE OF WINDOW GLASS 3 ADDITIONAL MATERIAL HANDLING PT-202 = .24196 HRS PER PANE

PT-212 GLAZING -- REMOVE AND INSTALL SMALL TO MEDIUM SIZE WIRE INSERTED PRECUT GLASS PANE (TO 24 X 24 IN SIZE) IN STEEL SASH NO WORK UNIT DESCRIPTION ==================================================== 1 REMOVE AND INSTALL EXTRA HEAVY WIRE INSERTED WIN DOW PANE IN STEEL SASH 14 X 20 (ONE PERSON) PT-212 = .76820 HRS PER PANE

PT-213 GLAZING -- REMOVE AND INSTALL GLASS PANE (TO 24" x 24 IN SIZE) IN WOOD SASH, INCLUDING CUTTING GLASS TO SIZE NO WORK UNIT DESCRIPTION ==================================================== 1 REMOVE AND INSTALL AVERAGE SIZE WINDOW PANE IN WOOD SASH --TWO PEOPLE 2 CUT AVERAGE SIZE PANE OF WINDOW GLASS PT-213 = .46592 HRS PER PANE

PT-203 GLAZING - INSTALL MEDIUM SIZE PRECUT GLASS PANE (TO 24 X 24 IN SIZE) IN WOOD SASH NO WORK UNIT DESCRIPTION ==================================================== 1 INSTALL PANE IN NEW WOOD SASH ON JOB SITE WHERE NO GLASS TO BE REMOVED (PANE 14 X 20 - ONE PERSON PT-203 = .13604 HRS PER PANE

PT-214 PT-204 GLAZING -- INSTALL LARGE SIZE PRECUT GLASS PANE (TO 36 X 36 IN SIZE) IN NEW WOOD SASH NO WORK UNIT DESCRIPTION ==================================================== 1 INSTALL PANE IN NEW WOOD SASH ON JOB SITE WHERE NO GLASS IS TO BE REMOVED WITH MINIMUM DIMENSIONS OF 24 X 24 AND UP TO A MAXIMUM DIMENSION OF 36 X 36 (ONE PERSON) 2 ADDITIONAL MATERIAL HANDLING PT-204 = .21103 HRS PER PANE GLAZING -- REMOVE AND INSTALL LARGE SIZE GLASS PANE (TO 36" X 36" IN SIZE) IN WOOD SASH, INCLUDING CUTTING GLASS TO SIZE NO WORK UNIT DESCRIPTION ==================================================== 1 REMOVE AND INSTALL WINDOW PARE IN WOOD SASH - TWO PEOPLE ARE REQUIRED REPLACE PANE WITH MINIMUM DIMENSIONS OF 24 X 24 AND UP TO A MAXIMUM DIMENSION OF 36 X 36. 2 CUT AVERAGE SIZE PANE OF WINDOW GLASS PT-214 = .64154 HRS PER PANE

PT-211 GLAZING - REMOVE AND INSTALL SHALL TO MEDIUM SIZE WIRE INSERTED GLASS PANE (TO 24 X 24 IN SIZE), INCLUDING CUTTING GLASS TO SIZE NO WORK UNIT DESCRIPTION ==================================================== 1 REMOVE AND INSTALL EXTRA HEAVY WIRE INSERTED WINDOW PANE IN STEEL SASH 14 X 20 (ONE PERSON) 2 CUT AVERAGE SIZE PANE OF WINDOW GLASS. PT-211 = .79913 HRS PER PANE

PT-215 GLAZING -- REMOVE AND INSTALL PRECUT GLASS PANE (14 X 20) IN WOOD SASH NO WORK UNIT DESCRIPTION ==================================================== 1 REMOVE AND INSTALL AVERAGE SIZE WINDOW PANE IN WOOD SASH (ONE PERSON) PT-215 = .20203 HRS PER PANE

25

PT-216 GLAZING - REMOVE AND INSTALL LARGE SIZE PRECUT GLASS PARE (TO 36" X 36" IN SIZE) IN WOOD SASH NO WORK UNIT DESCRIPTION ==================================================== 1 REMOVE AND INSTALL WINDOW PANE IN WOOD SASH WHEN TWO MEN ARE REQUIRED. REPLACE PANE WITH MINIMUM DIMENSIONS OF 4" X 24" AND UP TO A MAXIMUM DIMENSION OF 36" X 36" (TWO PEOPLE) PT-216 = .57968 HRS PER PANE

PT-225 GLAZING - REMOVE AND INSTALL ALL PUTTY AROUND 36" X 36" GLASS PANE IN A WOOD SASH WINDOW NO WORK UNIT DESCRIPTION ==================================================== 1 REMOVE DETERIORATED PUTTY IN VARIOUS PLACES ON WOOD SASH AND REPLACE WITH NEW PUTTY (ONE PERSON) PT-225 = .89136 HRS PER PANE

PT-231 PT-221 GLAZING -- REMOVE AND INSTALL ALL PUTTY AROUND ONE OF TEN GLASS PANES IN A 6'9" X 6'9" STEEL SASH NO WORK UNIT DESCRIPTION ==================================================== 1 REMOVE DETERIORATED PUTTY IN VARIOUS PLACES ON STEEL SASH AND REPLACE WITH NEW PUTTY (ONE PERSON) PT-221 = .52708 HRS PER PARE REMOVE WINDOW SCREEN TO GAIN ACCESS AND REPLACE AFTER JOB IS COMPLETED NO WORK UNIT DESCRIPTION ==================================================== 1 REMOVE AND INSTALL WINDOW SCREEN PT-231 = .04880 HRS PER SCREEN

PT-241 GLAZING--INSTALL GLASS PANES (12"X14") IN NEW WOOD SASH WINDOW, 6 PANES OVER 6 PANES-INCLUDES CUTTING GLASS TO SIZE NO WORK UNIT DESCRIPTION ==================================================== 1 CUT GLASS 10 12"X14" SIZE PANES 2 INSTALL GLASS PANES (12"X14") IN SASHES OF NEW WINDOW, 6 PANES OVER 6 PANES PT-241 = 2.00364 HRS PER WINDOW

PT-222 GLAZING -- REMOVE AND INSTALL ALL PUTTY AROUND A 8" X 10" GLASS PANE IN WOOD SASH NO WORK UNIT DESCRIPTION ==================================================== 1 REMOVE DETERIORATED PUTTY IN VARIOUS PLACES ON WOOD SASH AND REPLACE WITH NEW PUTTY (ONE PERSON) PT-222 = .22284 HRS PER PANE

PT-223 GLAZING -- REMOVE AND INSTALL ALL PUTTY AROUND ONE GLASS PANE IN A 24" X 24" WOOD SASH OF A DOUBLE HUNG WINDOW (SIX PANES OVER SIX PANES) NO WORK UNIT DESCRIPTION ==================================================== 1 REMOVE DETERIORATED PUTTY IN VARIOUS PLACES ON WOOD SASH AND REPLACE WITH NEW PUTTY (ONE PERSON) PT-223 = .24760 HRS PER PANE

PT-301 APPLY ORE COAT OF PAINT TO ACOUSTICAL CEILING WITH ROLLER NO WORK UNIT DESCRIPTION ==================================================== 1 ROLLER PAINT ONE COAT ON CEILING 2 ADDITIONAL JOB PREPARATION TIME FOR PAINTING PT-301 = .00239 HRS PER SQ FT

PT-320 PT-224 GLAZING -- REMOVE AND INSTALL ALL PUTTY AROUND ONE GLASS PANE IN A 30" X 30" WOOD SASH OF A DOUBLE HUNG WINDOW (ONE PANE OVER ONE PANE) NO WORK UNIT DESCRIPTION ==================================================== 1 REMOVE DETERIORATED PUTTY IN VARIOUS PLACES ON WOOD SASH AND REPLACE WITH NEW PUTTY (ONE PERSON) PT-224 = .74280 HRS PER PARE APPLY ONE COAT OF PAINT TO A FLAT INTERIOR OR EXTERIOR SURFACE WITH ROLLER NO WORK UNIT DESCRIPTION ==================================================== 1 ROLLER PAINT ONE COAT TO WALL 2 ADDITIONAL JO8 PREPARATION TIME FOR PAINTING PT-320 = .00212 HRS PER SQ FT

26

PT-330 ROLLER PAINT WALLS OF A ROOM WITH 8 TO 10 HIGH CEILING, (INCLUDES CUTTING IN CORNERS, BASEBOARD, CEILING, AROUND DOOR(S) AND WINDOWS WITH BRUSH) (PER SQ FT OF WALL BEING PAINTED) NO WORK UNIT DESCRIPTION ==================================================== 1 CUT IN CORNERS IN A ROOM USING BRUSH 2 "CUT-IN BASEBOARD AND CEILING IN A ROOM USING BRUSH 3 CUT IN AROUND DOOR(S) AND WINDOWS USING BRUSH 4 APPLY PAINT TO WALLS USING ROLLER 5 ADDITIONAL JOB PREPARATION FOR PAINTING PT-330 = .00352 HRS PER SQ FT

PT-412 AIRLESS SPRAY PAINTING REQUIRING EXTRA CARE FOR A QUALITY FINISH NO WORK UNIT DESCRIPTION ==================================================== 1 AIRLESS SPRAY PAINTING REQUIRING EXTRA CARE 2 ADDITIONAL JOB PREPARATIW TIME FOR PAINTING PT-412 = .00177 HRS PER SQ FT

PT-415 AIRLESS SPRAY PAINTING OF IRREGULAR SURFACE NO WORK UNIT DESCRIPTION ==================================================== 1 AIRLESS SPRAY PAINTING OF IRREGULAR SURFACE 2 ADDITIONAL JOB PREPARATION TIME FOR PAINTING PT-415 = .00209 HRS PER SQ FT

PT-340 ROLLER PAINT WALLS AND CEILING OF A ROOM WITH 8 TO 10 HIGH CEILING, (INCLUDES CUTTING IN CORNERS, BASEBOARD, AROUND DOOR(S) AND WINDOWS WITH BRUSH (PER SQ FT OF LULL BEING PAINTED) NO WORK UNIT DESCRIPTION ==================================================== 1 CUT IN CORNERS IN A ROOM USING BRUSH 2 CUT IN BASEBOARD IN ROOM USING BRUSH 3 CUT IN AROUND DOOR(S) AND WINDOWS USING BRUSH 4 APPLY PAINT TO WALLS USING A ROLLER 5 APPLY PAINT TO CEILING USING A ROLLER 6 ADDITIONAL JOB PREPARATION FOR PAINTING PT-340 = .00420 HRS PER SQ FT

PT-417 AIRLESS SPRAY PAINTING OF STRUCTURAL MEMBERS NO WORK UNIT DESCRIPTION ==================================================== 1 AIRLESS SPRAY PAINTING OF STRUCTURAL MEMBERS 2 ADDITIONAL JOB PREPARATION TIME FOR PAINTING PT-417 = .00173 HRS PER SQ FT

PT-350 APPLY ONE COAT OF PAINT TO BOTH SIDES OF A CHAIN LINK FENCE WITH ROLLER NO WORK UNIT DESCRIPTION ==================================================== 1 ROLL PAINT BOTH SIDES OF CHAIN LINK FENCE 2 ADDITIONAL JOB PREPARATION TIME FOR PAINTING PT-350 = .00363 HRS PER SQ FT

PT-421 CONVENTIONAL SPRAY PAINTING OF FLAT SURFACE NO WORK UNIT DESCRIPTION ==================================================== 1 SPRAY ONE COAT ON FLAT SURFACE 2 ADDITIONAL JOB PREPARATION TIRE FOR PAINTING PT-421 = .00160 HRS PER SQ FT

PT-422 PT-411 AIRLESS SPRAY PAINTING OF FLAT SURFACE NO WORK UNIT DESCRIPTION ==================================================== 1 AIRLESS SPRAY PAINTING OF FLAT SURFACE 2 ADDITIONAL JOB PREPARATION TIME FOR PAINTING PT-411 = .00111 HRS PER SQ FT CONVENTIONAL SPRAY PAINTING REQUIRING EXTRA CARE FOR A QUALITY FINISH NO WORK UNIT DESCRIPTION ==================================================== 1 CONVENTIONAL SPRAY ON SURFACE REQUIRING EXTRA CARE 2 ADDITIONAL JOB PREPARATION TIME FOR PAINTING PT-422 = .00253 HRS PER SQ FT

27

PT-425 CONVENTIONAL SPRAY PAINTING OF IRREGULAR SURFACE NO WORK UNIT DESCRIPTION ==================================================== 1 SPRAY ONE COAT ON IRREGULAR SURFACE 2 ADDITIONAL JOB PREPARATION TIME FOR PAINTING PT-425 = .00304 HRS PER SQ FT

PT-552 LAYOUT AND PAINT LETTER OR NUMBER UP TO 3.5 HIGH ON PREVIOUSLY PREPARED SURFACE. NO WORK UNIT DESCRIPTION ==================================================== 1 LAYOUT .5 TO 3.5 LETTER AND PAINT WITH ONE COAT PT-552 = + .02500 HRS PER SIGN .03253 HRS PER LETTER

PT-427 CONVENTIONAL SPRAY PAINTING OF STRUCTURAL MEMBERS NO WORK UNIT DESCRIPTION ==================================================== 1 CONVENTIONAL SPRAY OF BEAR OR TRUSS 2 ADDITIONAL JOB PREPARATION TIME FOR PAINTING PT-427 = .00247 HRS PER SQ FT

PT-553 PAINT ADDITIONAL COAT, SHADOW EFFECT OR HIGHLIGHT TO PREVIOUSLY PAINTED LETTER UP TO 3.5 HIGH NO WORK UNIT DESCRIPTION ==================================================== 1 PAINT SECOND COAT ON PREVIOUSLY PAINTED LETTER UP TO 3.5 HIGH PT-553 = .01210 HRS PER LETTER

Pi-501 BRUSH PAINT SIGN BLANK WITH PRIMER AND FINISH COAT NO WORK UNIT DESCRIPTION ==================================================== 1 CLEAN SIGN BLANK 2 APPLY PRIME COAT OR FIRST COAT OF PAINT ON SIGN BLANK WITH BRUSH 3 BRUSH PAINT FINISH OR SECOND COAT ON SIGN BLANK 4 IN-PROCESS SETUP AND HANDLING TIME PT-501 = + .01105 HRS PER SIGN .01687 HRS PER SQ FT PT-554 LAYOUT AND PAINT LETTER OR NUMBER 4 TO 6 HIGH ON PREVIOUSLY PREPARED SURFACE NO WORK UNIT DESCRIPTION ==================================================== 1 LAYOUT 4 TO 6 LETTER AND PAINT WITH ONE COAT 2 PAINT SECOND COAT ON 4 TO 6 LETTER PT-554 = + .02500 HRS PER SIGN .04528 HRS PER LETTER

PT-503 SPRAY PAINT SIGN WITH PRIMER AND FINISH COAT NO WORK UNIT DESCRIPTION ==================================================== 1 CLEAN SIGN BLANK 2 SPRAY SIGN WITH TWO COATS PT-503 = + .01105 HRS PER SIGN .00657 HRS PER SQ FT

PT-556 LAYOUT AND PAINT LETTER OR NUMBER 7 TO 15 HIGH ON PREVIOUSLY PREPARED SURFACE NO WORK UNIT DESCRIPTION ==================================================== 1 LAYOUT 7 TO 15 LETTER AND PAINT WITH TWO COATS PT-556 = + .02500 HRS PER SIGN .08520 HRS PER LETTER

PT-519 AFFIX SCOTCHLITE BACKGROUND TO METAL SIGN BLANK NO WORK UNIT DESCRIPTION ==================================================== 1 CLEAN METAL SIGN BLANK 2 AFFIX SCOTCHLITE BACKGROUND FILM TO SIGN BLANK 3 PROCESS SCOTCHLITE SIGN IN HEAT APPLICATOR MACHINE PT-519 = + .05443 HRS PER SIGN .01480 HRS PER SQ FT

PT-558 LAYOUT AND PAINT LETTER OR NUMBER 16 TO 24 HIGH ON PREVIOUSLY PREPARED SURFACE NO WORK UNIT DESCRIPTION ==================================================== 1 LAYOUT 16 TO 24 LETTER AND PAINT WITH TWO COATS PT-558 = + .02500 HRS PER SIGN .12180 HRS PER LETTER

28

PT-569 AFFIX SCOTCHLITE CHARACTER TO SCOTCHLITE SIGN NO WORK UNIT DESCRIPTION ==================================================== 1 SET SIGN BACKGROUND FILM WITH SHORT HEAT CYCLE 2 AFFIX SCOTCHLITE CHARACTER TO SIGN BLANK PT-569 = + .11014 HRS PER SIGN .00765 HRS PER CHARACTER

PT-587 PREPARE SILK SCREEN AND PAINT CHARACTER ON PREVIOUSLY PREPARED SIGN BLANK NO WORK UNIT DESCRIPTION ==================================================== 1 CUT STENCILED CHARACTER FROM FILM FOR SILK SCREEN 2 ATTACH SILK SCREEN TO FRAME 3 ADHERE FILM ON SILK 4 WALK TO SIGN BLANK 5 SET UP SILK SCREEN FOR SIGN PAINTING 6 STENCIL SILK SCREEN SIGN IN SHOP PT-587 = + .13830 HRS PER SIGN .00109 HRS PER CHARACTER

PT-580 PREPARE STENCIL AND BRUSH PAINT CHARACTER ON PREVIOUSLY PREPARED SURFACE NO WORK UNIT DESCRIPTION ==================================================== 1 PREPARE STENCIL FOR SIGN BAKING 2 BRUSH PAINT SIGN CHARACTERS USING STENCIL PT-580 = + .05921 HRS PER SIGN .00200 HRS PER CHARACTER

PT-589 PREPARE SILK SCREEN AND PAINT CHARACTER ON PREVIOUSLY PREPARED EQUIPMENT OR VEHICLE NO WORK UNIT DESCRIPTION ==================================================== 1 CUT STENCILED CHARACTER FROM FILM FOR SILK SCREEN 2 ATTACH TO FRAME AND ADJUST 3 SET UP SILK SCREEN FOR SIGN PAINTING 4 STENCIL SILK SCREEN SIGN ON VEHICLE OR EQUIPMENT PT-589 = + .10130 HRS PER SIGN .00739 HRS PER CHARACTER

PT-584 PREPARE STENCIL AND SPRAY PAINT LETTER UP TO 4 HIGH ON PREVIOUSLY PREPARED SURFACE NO WORK UNIT DESCRIPTION ==================================================== 1 PREPARE STENCIL AND POSITION FOR PAINTING 2 SPRAY PAINT STENCIL OF 3/4 TO 1 HIGH CHARACTERS 3 SPRAY PAINT STENCIL OF 2 TO 4 HIGH CHARACTERS PT-584 = + .04213 HRS PER SIGN .00165 HRS PER CHARACTER

PT-601 WIPE FIAT, SLIGHTLY CURVED OR UNOBSTRUCTED SURFACE WITH CLOTH NO WORK UNIT DESCRIPTION ==================================================== 1 WIPE FLAT SURFACE WITH CLOTH (FIRST SQ FT) 2 WIPE FLAT SURFACE WITH CLOTH (ADDL SQ FT) 3 BEND AND ARISE WHILE WIPING A FLAT SURFACE 4 WALK TO NEXT AREA PT-601 = .OO091 HRS PER SQ FT

PT-585 PREPARE STENCIL AND SPRAY PAINT LETTER 4 TO 7 HIGH ON PREVIOUSLY PREPARED SURFACE NO WORK UNIT DESCRIPTION ==================================================== 1 PREPARE STENCIL AND POSITION FOR PAINTING 2 SPRAY PAINT STENCIL OF 5 TO 7 HIGH CHARACTERS PT-585 = + .04213 HRS PER SIGN .00460 HRS PER CHARACTER

PT -602 SAND 25% OF FLAT, SLIGHTLY CURVED OR UNOBSTRUCTED SURFACE AND WIPE 100% OF SURFACE WITH CLOTH NO WORK UNIT DESCRIPTION ==================================================== 1 PREPARE TO SAND 25% OF SURFACE 2 SAND AND INSPECT 25% OF GOOD SURFACE 3 BEND AND ARISE WHILE SANDING SURFACE 4 WIPE 100% OF UNOBSTRUCTED SURFACE WITH CLOTH PT-602 = .00119 HRS PER SQ FT

29

PT-603 SCRAPE OR WIRE BRUSH 25% OF FIAT, SLIGHTLY CURVED OR UNOBSTRUCTED SURFACE, SAND 50% AND WIPE 100% NO WORK UNIT DESCRIPTION ==================================================== 1 CLEAN 12.5% OF SURFACE WITH WIRE BRUSH 2 CLEAN 12.5% OF UNOBSTRUCTED SURFACE WITH SCRAPER 3 BEND AND ARISE WHILE SCRAPING AND WIRE BRUSHING 4 PREPARE TO SAND 50% OF SURFACE 5 SAND AND INSPECT 50% OF GOOD SURFACE 6 BEND AND ARISE WHILE SANDING SURFACE 7 WIPE 10% OF SURFACE WITH CLOTH PT-603 = .00271 HRS PER SQ FT

PT-607 SCRAPE OR WIRE BRUSH 25% OF IRREGULAR, ANGULAR OR DIFFICULT TO REACH SURFACE, SAND 50% AND WIPE 100% NO WORK UNIT DESCRIPTION ==================================================== 1 CLEAR 12.5% OF SURFACE WITH WIRE BRUSH 2 CLEAN 12.5% OF OBSTRUCTED SURFACE WITH SCRAPER 3 BEND AND ARISE WHILE SCRAPING AND WIRE BRUSHING SURFACE 4 PREPARE TO HAND SAND 50% OF AN OBSTRUCTED SURFACE 5 SAND AND INSPECT SD% OF AN OBSTRUCTED SURFACE 6 WIPE 100% OF AN OBSTRUCTED SURFACE WITH CLOTH PT-607 = .00569 HRS PER SQ FT

PT-604 SAND 100% OF FLAT, SLIGHTLY CURVED OR UNOBSTRUCTED SURFACE AND WIPE 100% OF SURFACE WITH CLOTH NO WORK UNIT DESCRIPTION ==================================================== 1 PREPARE TO SAND SURFACE 2 SAND AND INSPECT 100% OF UNOBSTRUCTED SURFACE 3 BEND AND ARISE WHILE SANDING SURFACE 4 WIPE 100% OF UNOBSTRUCTED SURFACE WITH CLOTH PT-604 = .00204 HRS PER SQ FT

PT-608 SAND 100% OF IRREGULAR, ANGULAR OR DIFFICULT TO REACH SURFACE AND WIPE 100% OF SURFACE WITH CLOTH NO WORK UNIT DESCRIPTION ==================================================== 1 PREPARE TO SAND 100% OF AR OBSTRUCTED SURFACE 2 SAND AND INSPECT 100% OF AN OBSTRUCTED SURFACE 3 BEND AND ARISE WHILE SANDING 100% OF SURFACE 4 WIPE 100% OF OBSTRUCTED SURFACE WITH CLOTH PT-608 = .00546 HRS PER SQ FT

PT-605 WIPE IRREGULAR, ANGULAR OR DIFFICULT TO REACH SURFACE WITH CLOTH NO WORK UNIT DESCRIPTION ==================================================== 1 WIPE IRREGULAR SURFACE WITH CLOTH (FIRST SQ FT) 2 WIPE IRREGULAR SURFACE WITH CLOTH (ADDL SQ FT) 3 BEND AND ARISE WHILE WIPING IRREGULAR SURFACE 4 WALK TO NEXT AREA PT-605 = .00181 HRS PER SQ FT

PT-612 SAND AND WIPE UP TO 1.5 DIAMETER PIPE OR COLUMN NO WORK UNIT DESCRIPTION ==================================================== 1 PREPARE TO SAND SURFACE OF PIPE OR COLUMN 2 SAND AND INSPECT 100% OF PIPE OR COLUMN 3 WIPE 100% OF PIPE OR COLUMN PT-612 = .00138 HRS PER LIN FT

PT-613 PT-606 SAND 25% OF IRREGULAR, ANGULAR OR DIFFICULT TO REACH SURFACE AND WIPE 100% OF SURFACE WITH CLOTH NO WORK UNIT DESCRIPTION -----==================================================== 1 PREPARE TO SAND 25% OF SURFACE 2 SAND AND INSPECT 25% OF BAD SURFACE 3 BEND AND ARISE WHILE SANDING SURFACE 4 WIPE 100% OF OBSTRUCTED SURFACE WITH CLOTH PT-606 = .00273 HRS PER SQ FT SAND AND WIPE 2 TO 4 DIAMETER PIPE OR COLUMN NO WORK UNIT DESCRIPTION ==================================================== 1 PREPARE TO SAND SURFACE OF PIPE OR COLUMN 2 SAND AND INSPECT 100% OF PIPE OR COLUMN 3 WIPE 100% OF PIPE OR COLUMN PT-613 = .00414 HRS PER LIN FT

30

PT-614 SAND AND WIPE 4.5 TO 8 DIAMETER PIPE OR COLUMN NO WORK UNIT DESCRIPTION ==================================================== 1 PREPARE TO SAND SURFACE OF PIPE OR COLUMN 2 SAND AND INSPECT 100% OF PIPE OR COLUMN 3 WIPE 100% OF PIPE OR COLUMN PT-614 = .00829 HRS PER LIN FT

PT-624 WIPE OR BRUSH INTERIOR OR EXTERIOR OF DOOR (PANE-ED OR SMOOTH) PRIOR TO PAINTING NO WORK UNIT DESCRIPTION ==================================================== 1 WIPE OR BRUSH DOOR PANEL PRIOR TO PAINTING 2 WIPE OR BRUSH DOOR EDGES PRIOR TO PAINTING 3 IN-PROCESS SET UP AND HANDLING TIME PT-624 = .06005 HRS PER SIDE

PT-621 WIPE OR BRUSH INTERIOR OR EXTERIOR OF WINDOW SASH AND RELATED TRIM PRIOR TO PAINTING NO WORK UNIT DESCRIPTION ==================================================== 1 PREPARE OBSTRUCTED SURFACE FOR PAINTING 2 RAISE AN0 LOWER WINDOW SASH 3 IN-PROCESS SET UP AND HANDLING TIME PT-621 = .14800 HRS PER SIDE

PT-625 SAND AND WIPE INTERIOR OR EXTERIOR OF DOOR (PANELED OR SMOOTH) PRIOR TO PAINTING NO WORK UNIT DESCRIPTION ==================================================== 1 SAND AND WIPE DOOR PANEL PRIOR TO PAINTING 2 SAND AND WIPE DOOR EDGES PRIOR TO PAINTING 3 IN-PROCESS SET UP AND HANDLING TIME PT-625 = .14401 HRS PER SIDE

PT-622 SAND AND WIPE INTERIOR OR EXTERIOR OF WINDOW SASH AND RELATED TRIM PRIOR TO PAINTING NO WORK UNIT DESCRIPTION ==================================================== 1 PREPARE OBSTRUCTED SURFACE FOR PAINTING 2 RAISE AND LOWER SASH 3 IN-PROCESS SET UP AND HANDLING TIME PT-622 = .36346 HRS PER SIDE

PT-626 SCRAPE OR WIRE BRUSH, SAND AND WIPE INTERIOR OR EXTERIOR OF DOOR (PANELED OR SMOOTH) PRIOR TO PAINTING NO WORK UNIT DESCRIPTION ==================================================== 1 PREPARE DOOR PANEL PRIOR TO PAINTING 2 PREPARE DOOR EDGES PRIOR TO PAINTING 3 IN-PROCESS SET UP AND HANDLING TIME PT-626 = .15173 HRS PER SIDE

PT-623 SCRAPE OR WIRE BRUSH, SAND AND WIPE INTERIOR OR EXTERIOR OF WINDOW SASH AND RELATED TRIM PRIOR TO PAINTING NO WORK UNIT DESCRIPTION ==================================================== 1 PREPARE OBSTRUCTED SURFACE FOR PAINTING 2 RAISE AND LOWER WINDOW SASH 3 IN-PROCESS SETUP AND HANDLING TIRE PT-623 = .37966 HRS PER SIDE PT-621 WIPE OR BRUSH INTERIOR OR EXTERIOR OF DOORWAY/JAMB AN0 CASING PRIOR TO PAINTING NO WORK UNIT DESCRIPTION ==================================================== 1 WIPE OR BRUSH INTERIOR OR EXTERIOR OF DOORWAY/JAMB AND CASING PRIOR TO PAINTING 2 IN-PROCESS SET UP AND HANDLING TIME PT-627 = .04845 HRS PER SIDE

31

PT-628 SAND AND WIPE INTERIOR OR EXTERIOR OF DOORWAY/JAMB AND CASING PRIOR TO PAINTING NO WORK UNIT DESCRIPTION ==================================================== 1 SAND AND WIPE INTERIOR OR EXTERIOR OF DOORWAY/JAMB MO CASING PRIOR TO PAINTING 2 IN-PROCESS SET UP AN0 HANDLING TIME PT-628 = .09367 HRS PER SIDE

PT-633 SCRAPE OR WIRE BRUSH 25% OF FLAT, SLIGHTLY CURVED OR UNOBSTRUCTED SURFACE, SAND 50% AND WIPE 100% NO WORK UNIT DESCRIPTION ==================================================== 1 BRUSH CLEAN 12.5% OF SURFACE WITH WIRE BRUSH 2 SCRAPE 12.5% OF UNOBSTRUCTED SURFACE WITH SCRAPER 3 BEND AND ARISE WHILE SCRAPING AND WIRE BRUSHING UNOBSTRUCTED SURFACE 4 PREPARE TO SAND 50% OF UNOBSTRUCTED SURFACE 5 SAND AN0 INSPECT 50% OF UNOBSTRUCTED SURFACE 6 WIPE 100% OF UNOBSTRUCTED SURFACE WITH CLOTH PT-633 = .00097 HRS PER LIN FT

PT-629 SCRAPE OR WIRE BRUSH, SAND AND WIPE INTERIOR OR EXTERIOR OF DOORWAY/JAMB PRIOR TO PAINTING NO WORK UNIT DESCRIPTION ==================================================== 1 PREPARE INTERIOR OR EXTERIOR OF DOORWAY/JAMB AND CASING PRIOR TO PAINTING 2 IN-PROCESS SET UP AND HANDLING TIME PT-629 = .09707 HRS PER SIDE

PT-634 SAND 100% OF FLAT, SLIGHTLY CURVED OR UNOBSTRUCTED SURFACE AND WIPE 100% OF SURFACE WITH CLOTH NO WORK UNIT DESCRIPTION ==================================================== 1 PREPARE TO SAND UNOBSTRUCTED SURFACE 2 SAND AND INSPECT 100% OF UNOBSTRUCTED SURFACE 3 BEND AND ARISE WHILE SANDING UNOBSTRUCTED SURFACE 4 WIPE 100% OF UNOBSTRUCTED SURFACE WITH CLOTH PT-634 = .00080 HRS PER LIN FT

PT-631 WIPE FLAT, SLIGHTLY CURVED OR UNOBSTRUCTED SURFACE WITH CLOTH NO WORK UNIT DESCRIPTION ==================================================== 1 WIPE FLAT SURFACE WITH CLOTH (FIRST LIN FT) 2 WIPE FLAT SURFACE WITH CLOTH (ADDL LIN FT) 3 BEND AND ARISE WHILE WIPING A FLAT SURFACE 4 WALK TO NEXT AREA PT-631 = .O0037 HRS PER LIN FT

PT-635 WIPE IRREGULAR, ANGULAR OR DIFFICULT TO REACH SURFACE WITH CLOTH NO WORK UNIT DESCRIPTION ==================================================== 1 WIPE IRREGULAR SURFACE WITH CLOTH (FIRST LIN FT) 2 WIPE IRREGULAR SURFACE WITH CLOTH (ADDL LIN FT) 3 BEND AND ARISE WHILE WIPING IRREGULAR SURFACE 4 WALK TO NEXT AREA PT-635 = .00065 HRS PER LIN FT

PT-632 SAND 25% OF FLAT, SLIGHTLY CURVED OR UNOBSTRUCTED SURFACE AND WIPE 100% OF SURFACE WITH CLOTH NO WORK UNIT DESCRIPTION ==================================================== 1 PREPARE TO SAND 25% OF UNOBSTRUCTED SURFACE 2 SAND AND INSPECT 25% OF UNOBSTRUCTED SURFACE 3 BEND AND ARISE WHILE SANDING UNOBSTRUCTED SURFACE 4 WIPE 100% OF UNOBSTRUCTED SURFACE WITH CLOTH PT-632 = .00048 HRS PER LIN FT

PT-636 SAND 25% OF IRREGULAR, ANGULAR OR DIFFICULT TO REACH SURFACE AND WIPE 100% OF SURFACE WITH CLOTH NO WORK UNIT DESCRIPTION ==================================================== 1 PREPARE TO SAND 25% OF SURFACE 2 SAND AND INSPECT 25% OF OBSTRUCTED SURFACE 3 BEND AND ARISE WHILE SANDING 25% OF OBSTRUCTED SURFACE 4 WIPE 100% OF OBSTRUCTED SURFACE WITH CLOTH PT-636 = .00099 HRS PER LIN FT

32

PT-637 SCRAPE OR WIRE BRUSH 25% OF IRREGULAR, ANGULAR OR DIFFICULT TO REACH SURFACE, SAND 50% AND WIPE 100% NO WORK UNIT DESCRIPTION ==================================================== 1 BRUSH CLEAN 12.5% OF SURFACE WITH WIRE BRUSH 2 SCRAPE 12.5% OF OBSTRUCTED SURFACE WITH SCRAPER 3 BEND AND ARISE MILE SCRAPING AND WIRE BRUSHING 25% OF AN OBSTRUCTED SURFACE 4 PREPARE TO HAND SAND 50% OF AN OBSTRUCTED SURFACE 5 SAND AND INSPECT 50% OF AN OBSTRUCTED SURFACE 6 BEND AND ARISE WHILE SANDING 50% OF AN OBSTRUCTED SURFACE 7 WIPE 100% OF AN OBSTRUCTED SURFACE WITH CLOTH PT-637 = .00208 HRS PER LIN FT

PT-642 SANDBLAST FLAT OR SLIGHTLY ROUNDED METAL SURFACE, NEAR WHITE METAL BLAST NO WORK UNIT DESCRIPTION ==================================================== 1 LOAD 300 POUNDS OF SAND INTO SANDBLASTING POT 2 PREPARE TO SANDBLAST SURFACE 3 POSITION GUN PRIOR TO BLASTING 4 SANDBLAST FLAT OR SLIGHTLY ROUNDED METAL SURFACE, NEAR WHITE METAL BLAST 5 INSPECT SURFACE AFTER BLASTING 6 REMOVE SPENT SAND FROM SANDBLASTING AREA PT-642 = .03084 HRS PER SQ FT

PT-643 PT-638 SAND 100% OF IRREGULAR, ANGULAR OR DIFFICULT TO REACH SURFACE AND WIPE 100% OF SURFACE WITH CLOTH NO WORK UNIT DESCRIPTION ==================================================== 1 PREPARE TO SAND 100% OF AN OBSTRUCTED SURFACE 2 SAND AND INSPECT 100% OF AN OBSTRUCTED SURFACE 3 BEND AND ARISE WHILE SANDING 100% OF AN OBSTRUCTED SURFACE 4 WIPE 100% OF AN OBSTRUCTED SURFACE WITH CLOTH PT-638 = .00198 HRS PER LIN FT SANDBLAST FLAT OR SLIGHTLY ROUNDED METAL SURFACE, WHITE METAL BLAST NO WORK UNIT DESCRIPTION ==================================================== 1 LOAD 300 POUNDS OF SAND INTO SANDBLASTING POT 2 PREPARE TO SANDBLAST SURFACE 3 POSITION GUN PRIOR TO BLASTING 4 SANDBLAST FLAT OR SLIGHTLY ROUNDED METAL SURFACE, WHITE METAL BLAST 5 INSPECT SURFACE AFTER BLASTING 6 REMOVE SPENT SAND FROM SANDBLASTING AREA PT-643 = .05292 HRS PER SQ FT

PT-640 SANDBLAST MASONRY SURFACE NO WORK UNIT DESCRIPTION ==================================================== 1 LOAD 300 POUNDS OF SAND INTO SANDBLASTING POT 2 PREPARE TO SANDBLAST SURFACE 3 POSITION GUN PRIOR TO BLASTING 4 SANDBLAST MASONRY, CONCRETE OR STUCCO SURFACE 5 INSPECT SURFACE AFTER BLASTING 6 REMOVE SPENT SAND FROM SANDBLASTING AREA PT-640 = .00597 HRS PER SQ FT

PT-647 SANDBLAST METAL BEAMS, TRUSSES OR OTHER STRUCTURAL MEMBERS, COMMERCIAL BLAST NO WORK UNIT DESCRIPTION ==================================================== 1 LOAD 300 POUNDS OF SAND INTO SANDBLASTING POT 2 PREPARE TO SANDBLAST SURFACE 3 POSlTION GUN PRIOR TO BLASTING 4 SANDBLAST METAL BEAMS, TRUSSES OR OTHER STRUCTURAL MEMBERS 5 INSPECT SURFACE AFTER BLASTING 6 REMOVE SPENT SAND FROM SANDBLASTING AREA PT-647 = .02840 HRS PER SQ FT

PT-641 SANDBLAST FLAT OR SLIGHTLY ROUNDED METAL SURFACE, COMMERCIAL BLAST NO WORK UNIT DESCRIPTION ==================================================== 1 LOAD 300 POUNDS OF SAND INTO SANDBLASTlNG POT 2 PREPARE TO SANDBLAST SURFACE 3 POSITION GUN PRIOR TO BLASTING 4 SANDBLAST FLAT OR SLIGHTLY ROUNDED METAL SURFACE, COMMERCIAL BLAST 5 INSPECT SURFACE AFTER BLASTING 6 REMOVE SPENT SAND FROM SANDBLASTING AREA PT-641 = .01566 HRS PER SQ FT

33

PT-648 SANDBLAST METAL BEAMS, TRUSSES OR OTHER STRUCTURAL MEMBERS, NEAR WHITE METAL BLAST

PT-653 MASK WALL, TRIM, DOOR, WINDOW PERIMETER, ETC

NO WORK UNIT DESCRIPTION ==================================================== NO WORK UNIT DESCRIPTION ==================================================== 1 PICK UP SUPPLIES AND/OR EQUIPMENT AND LAY ASIDE 2 WALK TO MASK WALL, TRIM OR OBJECT 1 LOAD 300 POUNDS OF SAND INTO SANDBLASTING POT 3 APPLY TAPE TO WALL 2 PREPARE TO SANDBLAST SURFACE 4 REMOVE TAPE FROM WALL 3 POSITION GUN PRIOR TO BLASTING 4 SANDBLAST METAL BEAMS, TRUSSES OR OTHER STRUCTURAL 5 DISPOSE OF WASTE TO TRASH CAN OUTSIDE BUILDING MEMBERS, NEAR WHITE METAL BLAST PT-653 = 5 INSPECT SURFACE AFTER BLASTING .00393 HRS PER LIN FT 6 REMOVE SPENT SAND FROM SANDBLASTING AREA PT-648 = .05678 HRS PER SQ FT PT-673 V-OUT OLD CRACK AND APPLY PLASTER OR SPACKLE NO WORK UNIT DESCRIPTION ==================================================== 1 SET UP AND HANDLING TIME 2 V-OUT CRACK AND APPLY PLASTER OR SPACKLE

PT-649 SANDBLAST METAL BEAMS, TRUSSES OR OTHER STRUCTURAL MEMBERS, WHITE METAL BLAST

NO WORK UNIT DESCRIPTION ==================================================== .03370 HRS PER LIN FT PT-673 = 1 LOAD 300 POUNDS OF SAND INTO SANDBLASTING POT 2 PREPARE TO SANDBLAST SURFACE 3 POSITION GUN PRIOR TO BLASTING 4 SANDBLAST METAL BEAMS, TRUSSES OR OTHER STRUCTURAL PT-677 MEMBERS, WHITE METAL BLAST APPLY TAPE & 3 COATS OF COMPOUND TO PLASTER BOARD 5 INSPECT SURFACE AFTER BLASTING SEAM 6 REMOVE SPENT SAND FROM SANDBLASTING AREA PT-649 = .09805 HRS PER SQ FT

PT-651 MASK SMALL OBJECT WITH TAPE AND REMOVE NO WORK UNIT DESCRIPTION ==================================================== 1 PICK UP SUPPLIES AND/OR EQUIPMENT AND LAY ASIDE 2 WALK 20 PACES TO OBJECT 3 MASK SMALL OBJECT 4 REMOVE TAPE FROM SMALL OBJECT 5 DISPOSE OF WASTE TO TRASH CAN OUTSIDE BUILDING PT-651 = .01381 HRS PER OBJECT

NO WORK UNIT DESCRIPTION ==================================================== 1 SET UP AND HANDLING TIME 2 APPLY THREE COATS OF COMPOUND AND TAPE PT-677 = .02090 HRS PER SQ FT

PT-678 APPLY TAPE & COMPOUND TO PLASTER BOARD SEAM, INCLUDING SAND & WIPE AFTER 3RD COAT OF COMPOUND NO WORK UNIT DESCRIPTION ==================================================== 1 SET UP AND HANDLING TIME 2 APPLY THREE COATS OF COMPOUND AN0 TAPE 3 SAND PLASTER BOARD SEAM 4 WIPE PLASTER BOARD SEAM PT-678 = .02137 HRS PER SQ FT

PT-652 MASK MEDIUM SIZED OBJECT WITH TAPE AND REMOVE NO WORK UNIT DESCRIPTION ==================================================== 1 PICK UP SUPPLIES AND/OR EQUIPMENT AND LAY ASIDE 2 WALK 20 PACES TO OBJECT 3 MASK MEDIUM OBJECT 4 REMOVE TAPE FROM MEDIUM OBJECT 5 DISPOSE OF WASTE TO TRASH CAN OUTSIDE BUILDING PT-652 = .03621 HRS PER OBJECT

34

PT-680 FILL NAIL HOLES AND CRACKS IN WOOD SURFACES -PER SQ FT NO WORK UNIT DESCRIPTION ==================================================== 1 APPLY FILLER TO NAIL HOLES AND CRACKS IN WOOD SURFACE 2 BEND AND ARISE WHILE APPLYING FILLER 3 WALK TO NEXT AREA 4 IN-PROCESS SET UP AND HANDLING TIME PT-680 = .00378 HRS PER SQ FT

PT-701 LAY OUT FOR TRAFFIC STRIPE, CROSSWALK, OR PARKING STALL-SINGLE LINE NO WORK UNIT DESCRIPTION ==================================================== 1 LAY OUT FOR PAVEMENT STRIPING PT-701 = .00141 HRS PER LIN FT

PT-711 SPRAY TRAFFIC STRIPE--SINGLE LINE -PUSH TYPE STRIPING MACHINE NO WORK UNIT DESCRIPTION ==================================================== 1 SPRAY TRAFFIC STRIPE PT-711 = .00096 HRS PER LIN FT

PT-681 FILL NAIL HOLES AND CRACKS IN WOOD BOARDS -PER LIN FT NO WORK UNIT DESCRIPTION ==================================================== 1 APPLY FILLER TO NAIL HOLES AND CRACKS IN WOOD BOARDS 2 BEND AND ARISE WHILE APPLYING FILLER 3 WALK TO NEXT AREA 4 IN-PROCESS SET UP AND HANDLING TIME PT-681 = .00393 HRS PER LIN FT

PT-715 SPRAY CROSSWALK STRIPE--THREE AND ONE-HALF(3.5) FT WIDE WITH CROSSHATCHING AT TWO (2) FOOT INTERVALS --PUSH TYPE STRIPING MACHINE NO WORK UNIT DESCRIPTION ==================================================== 1 SPRAY CROSSWALK STRIPES PT-715 = .00876 HRS PER LIN FT

PT-684 APPLY CAULKING WITH HAND OPERATED CARTRIDGE GUN NO WORK UNIT DESCRIPTION ==================================================== 1 OBTAIN & ASIDE CAULKING GUN, CARTRIDGE AND KNIFE 2 REMOVE OLD, PREPARE & LOAD NEW CARTRIDGE IN GUN 3 APPLY CAULKING WITH HAND OPERATED CARTRIDGE GUN PT-684 = .00241 HRS PER LIN FT

PT-716 SPRAY CROSSWALK STRIPE--THREE AND ONE-HALF(3.5) FT WIDE WITH CROSSHATCHING AT FOUR(4) FOOT INTERVALS --PUSH TYPE STRIPING MACHINE NO WORK UNIT DESCRIPTION ==================================================== 1 SPRAY CROSSWALK STRIPE PT-716 = .00518 HRS PER LIN FT

PT-685 REMOVE OLD & APPLY NEW CAULKING WITH HAND OPERATED CARTRIDGE GUN NO WORK UNIT DESCRIPTION ==================================================== 1 OBTAIN & ASIDE TOOL FOR REMOVING OLD CHALKING 2 REMOVE DETERIORATED CAULKING WITH HAND TOOL 3 CAULK CRACK WITH HAND ACTIVATED CAULKING GUN PT-685 = .00537 HRS PER LIN FT

PT-717 SPRAY CROSSWALK STRIPE--SIX (6) FEET WIDE WITH CROSSHATCHING AT FOUR (4) FOOT INTERVALS -PUSH TYPE STRIPING MACHINE NO WORK UNIT DESCRIPTION ==================================================== 1 SPRAY CROSSWALK STRIPE PT-717 = .00486 HRS PER LIN FT

35

PT-725 SPRAY STRIPES FOR "CLASS 2" PARKING STALL --PUSH TYPE STRIPING MACHINE NO WORK UNIT DESCRIPTION ==================================================== 1 SPRAY STRIPES FOR PARKING STALL PT-725 = .02963 HRS PER STALL

PT-781 SPRAY TRAFFIC STRIPE (SINGLE LINE) --SELF-PROPELLED MACHINE NO WORK UNIT DESCRIPTION ==================================================== 1 SPRAY TRAFFIC STRIPE (SINGLE LINE) PT-781 = 1.03472 HRS PER JOB

PT-726 SPRAY STRIPES FOR "CLASS 3" PARKING STALL --PUSH TYPE STRIPING MACHINE NO WORK UNIT DESCRIPTION ==================================================== 1 SPRAY STRIPE FOR PARKING STALL PT-726 = .02072 HRS PER STALL

PT-731 SPRAY TRAFFIC STRIPE--SINGLE LINE --SELF-PROPELLED MACHINE NO WORK UNIT DESCRIPTION ==================================================== 1 SPRAY TRAFFIC STRIPE--SINGLE LINE --SELF-PROPELLED STRIPING MACHINE PT-731 = .00010 HRS PER LIN FT

PT-751 SPRAY STENCIL CHARACTER OR NUMBER ON PAVEMENT NO WORK UNIT DESCRIPTION ==================================================== 1 INITIAL SPRAY OR RE-SPRAY STENCIL NUMERAL 2 WALK DURING PERFORMANCE OF OPERATION PT-751 = .00915 HRS PER CHARACTER

PT-760 PLACEMENT AND REMOVAL OF TRAFFIC MARKERS NO WORK UNIT DESCRIPTION ==================================================== 1 PLACE AND PICK UP TRAFFIC MARKER PT-760 = .00979 HRS PER MARKER

36

LANTDIV NORVA 9-4122/1 (REV 3-88) Submitted by Date Phone Installation Address ATTN/Code City, State, Zip

EPS FEEDBACK SHEET The following questions are designed to assist the NAVFAC Industrial Engineering Center in its continuing effort to improve the overall quality of standard data presented in the EPS handbooks. You may phone us at (804) 444-9831 commercial or 564-9831 autovon. 1. List frequently recurring tasks which are not presently covered. attach any drawings or added descriptions: CRAFT HANDBOOK TASK DESCRIPTION Please

2 . List task for which, in your judgment, craft time is inaccurate - indicate whether time is too high or too low: CRAFT HANDBOOK TASK DESCRIPTION

3 . General comments (tasks presently covered which are never. used, format of data presentation, PE News letter, etc.):

37

FOLD POSTAGE REQUIRED

OFFICIAL BUSINESS
PENALTY FOR PRlVATE USE, $300

Commander Atlantic Division, Code 103 Naval Facilities Engineering Command Norfolk, V i r g i n i a 2 3 5 1 1 - 6 2 8 7

FOLD

38

LANTDIV NORVA 9-4122/1 (REV 3-88) Submitted by Date Phone Installation Address ATTN/Code City, State, Zip

EPS FEEDBACK SHEET The following questions are designed to assist the NAVFAC Industrial Engineering Center in its continuing effort to improve the overall quality of standard data presented in the EPS handbooks. You may phone us at (804) 444-9831 commercial or 564-9831 autovon. 1. List frequently recurring tasks which are not presently covered. attach any drawings or added descriptions: CRAFT HANDBOOK TASK DESCRIPTION Please

2 . List task for which, in your judgment, craft time is inaccurate - indicate whether time is too high or too low: CRAFT HANDBOOK TASK DESCRIPTION

3 . General comments (tasks presently covered which are never. used, format of data presentation, PE News letter, etc.):

39

FOLD POSTAGE REQUIRED

OFFICIAL BUSINESS
PENALTY FOR PRlVATE USE, $300

Commander Atlantic Division, Code 103 Naval Facilities Engineering Command Norfolk, V i r g i n i a 2 3 5 1 1 - 6 2 8 7

FOLD

40

LANTDIV NORVA 9-4122/1 (REV 3-88) Submitted by Date Phone Installation Address ATTN/Code City, State, Zip

EPS FEEDBACK SHEET The following questions are designed to assist the NAVFAC Industrial Engineering Center in its continuing effort to improve the overall quality of standard data presented in the EPS handbooks. You may phone us at (804) 444-9831 commercial or 564-9831 autovon. 1. List frequently recurring tasks which are not presently covered. attach any drawings or added descriptions: CRAFT HANDBOOK TASK DESCRIPTION Please

2 . List task for which, in your judgment, craft time is inaccurate - indicate whether time is too high or too low: CRAFT HANDBOOK TASK DESCRIPTION

3 . General comments (tasks presently covered which are never. used, format of data presentation, PE News letter, etc.):

41

FOLD POSTAGE REQUIRED

OFFICIAL BUSINESS
PENALTY FOR PRlVATE USE, $300