Boiler & Auxiliaries Maintenance Manuall Qn1 Sec G 04 TP 009
Boiler & Auxiliaries Maintenance Manuall Qn1 Sec G 04 TP 009
Boiler & Auxiliaries Maintenance Manuall Qn1 Sec G 04 TP 009
.(blade handle
hanging on steady bearing.).
2. Push it into the hole of impeller guide ring through
blade handle in accordance with the preassembled
guide bearing components of figure 5-2 until the
side surface touching the nut of blade handle.
3. Toggle sealing O-ring and maze-design sealing
push-in blade handle and bearing tray, lubricating
grease shall be applied to seals, fitting surface and
groove side in advance.
4. Put preloaded spring (belleville spring) on the
bearing tray which lies in the hole of guide ring.
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 176 -
Rev. : A
5. Preload the spring with retainer ring.
6.Loose blade handle nut slightly and take off the
filling block under balance weight.
7.Tighten blade handle nut until the preloaded
spring on bearing tray touching tapering annulus
(torque is increased abruptly). Maybe blade handle
nuts need further tightening to have the hlade
handle nut aimed at the groove of blade
handle.Wringing reversely is prohibitted.
(7) Disassembly
and assembly of
impeller
1.The disassembly force of wheel hub shall be fixed
at 300kN.
(8) Coupling
maintenance
No parts of RIGIFLEX coupling with detachable
flange hollow shaft is suffered from friction and
wear. The ratcheting of the flexible coupling is
pinned; its diaphragm is made of special high grade
spring steel, and the diaphragm shall be configured
in pair in order to allow the connected machine to
move freely in three directions.Such RIGlFLEX
coupling needs no maintenance and lubricating, and
is unlikely to be out of commission..
1.Assembling:
Loose joint bolt from the complete set of coupling,
disassemble intermediate shaft. The heating
temperature of coupling shall not exceed 150
when installing the half couping on mechanical main
shaft head that is reday for connecting. Heating
shall be carried out in heating furnace which can
provide temperature control to avoid flame heating,
since local overheating will weaken the strength of
coupling parts.
Intermediate shaft shall be installed with proper
distance M. Note: after the alignment of central
connecting bolts of flange hallow shaft, the
diaphragm is not allowed to be of bending but can
only extend parallelly along the flange in normal
position.
2.Alignment:
Perform precise alignment of the coupling,
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 177 -
Rev. : A
provided the opening size is Y
. Both of opening size Y
max
and Y
min
shall be
measured out( figure 5-8). Displacement deviation
will be caculated based on the measured value.
Table 5-2 Size Y used for aligning the coupling
precisely
Allowance
displacemnet of
each end side
(mm)
Couplin
g type
Openi
ng
Y(mm)
a
1max
r
1max
MA
(Nm)
1001 23.5 3 6.5 410
Allowance error for the alignment of RIGIFLEX coupling with detachable
flange hollow shaft
English Chinese
Grid-flexible coupling
Intermediate shaft
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 178 -
Rev. : A
Grid-flexible coupling
: Allowance error of the coupling end surface
deflection (angle)
: Measured deflection value
Measured diameter
Allowance Error of Coupling Alignment
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 179 -
Rev. : A
Chinese English
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 180 -
Rev. : A
Grid-flexible coupling
Intermediate shaft
Grid-flexible coupling
: Allowance error of the coupling end surface
deflection (angle)
: Measured deflection value
Measured diameter
VIII Attachment VIII: Allowance alignment error
of intermediate shaft
Maintenanc
e item
Workmanship and precautions Quality standard
(1) Radial displacement:
r
1
Ymax-Ymin (mm)
100r
1
/ r
1max
%
1
Refer to table 5-2 for the value of r
1max
.
(2)Axial displacement:
a
1
(Ymax+Ymin)/2-Y (mm)
(Note:+ a
1
refers to the couplings being detached
from each other; -a
1
refers to the couplings being
combined.)
100a
1
/
1max
%
2
Refer to table 5-2 for the value of a
1max
.
Generally, r
1
0.20mm will
meet operation
requirements.
(3) Allowable values of the radial and axial
displacements interrelated percentage, which shall
comform to the following formula:
1
2
100%
E.g.:if 40% of
1
has been used, 60% of
2
can
be used at most.
With the alignment finished, tighten the joint bolts
in accorance with the tightening torque of table
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 181 -
Rev. : A
5-2.
(9) Stagger
angle
measureme
nt of the
blade
Check whether on-off angles (position) of the
max. and min. blades are +15 and
-30respectively. Methods: measure out the
included angle between blade section and air flow,
then check whether the measured angle matchs
the indication value shown in blade angle dial.
Tightening Procedure Chart of Impeller Fixing Bol t
Hydraulic Regulating System Chart of Force Draft Fan
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 182 -
Rev. : A
English Chinese
Blade
Regulating bar
Piston
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 183 -
Rev. : A
Hydraulic cylinder
Piston shaft
Control head
Servo valve
Regulating bar
Control shaft
Indication shaft
Return oil
Pressure oil
Regulating bar
5.3 Induced Draft Fan Maintenance
5.3.1 Technical specifications of induced draft fan
Fan model: Axial Induced Draft Fan with Meridional Acceleration
Fan type: G158/273
Manufacturer: Shanghai Blower Works
Installation site: Vietnam Quang Ninh Power Plant
Project No. of Shanghai Blower Works:2007-20
Direction of rotation: The impeller rotates clockwise being seen from the direction of air
flow.
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 184 -
Rev. : A
Assembly Schematic Diagram of Induced Draft Fan
Fan Aerodynamic Parameters:
Serial
No.
Project
Name
T.B
BMCR
1 Fan inlet caculated flow
(m
3
/s)
281.39 232.5
2 System total pressure drop
(kpa)
4053 2895
4 Fan inlet flue gas
temperature ( )
138 127
5 Flue gas density (kg/m3) 0.85 0.883
6 Fan inlet dust content
(mg/Nm
3
)
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 185 -
Rev. : A
7 Rotate speed r/min 735
8 Fan shaft power (KW) 1416 809
9 Fan efficiency (%) 79.33 79.63
10 Fan rotary inertia
(J=0.25GD2)
330KgM2
11 Motor YKK710-8
5.3.1.1 Mechanical parameters
Fan inside diameter 2740
Impeller diameter 2730
Impeller series 1
Blade model 14G16
Blade number 14
Blade material 15MnV
Clearance between inside diameter of the casing and outside diameter of the blade
4-5.4mm
Regulating means: Inlet damper
Coupling type: Rigid-flexible coupling, specification: 5001Form14,
Support pattern: Double bracing
Weight of machine:( Heat insulating layer not included): 46152 kg
5.3.1.2 Performance curve
Fan type: G158/273
Customer: Quang Ninh
Power Plant
Fan rotate speed: 735r/min
Motor power: 1500KW
Fan blade model: 14G16
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 186 -
Rev. : A
5.3.1.3 Fan starting torque
Fan rotate speed: n=735r/min
Moment of inertia of rotor: 330 kg.m
2
Fan power (under max. working condition) 1416KW
Motor power 1500KW
Motor voltage 6600V
Being seen from the motor shaft end, the motor rotates clockwise, and the fan rotates
anticlockwise.
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 187 -
Rev. : A
Chinese English
Fan torque
Fan rotate speed
Full open of inlet guide blade
Full close of inlet guide blade
5.3.2 Function description
The fan is a variable stator blade induced draft fan designed and manufacured by our
company with the imported technology of Germany TLT Corporation.
The gas passes throuth the inlet regulating device of gas inlet box, and then enters into
impeller in a flow angle direction that corresponds with the inlet guide blade; it obtains the
needed energy of overcoming resisitence derived from pipe networks in the impeller.This
presents with total pressure rising of the gas.
In the variable stator blade induced draft fan, the realization of total pressure rising of gas
medium in the impeller relies largely upon the increase of dynamic pressure, while the
conversion of dynamic pressure to static pressure is realized in straightening guide blade and
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 188 -
Rev. : A
disffuser.
The impeller of the fan is designed in accordance with TLT developed G158 blade model,
with the characteristics of high efficiency and easy fabrication, and its working condition is
particularly well adapted for the induced draft fan of large scale power station.
5.3.2.1 Still Parts
Including the following components: (in the order of air flow direction)
Gas Inlet Box (52.00)
Flow through the rectangle inlet cross-section of gas inlet box, after a 90 turn, then axially
flow into inlet guide regulating device (87.00) from outlet circular passage of gas inlet box.
Inlet Guide Blade Regulating Device (87.00) 125
Inlet guide blade regulating device is equipped with airfoil-shaped front guide blade, and
connected with regulating mechanism, when the regulating mechanism acts to adjust, the fan
inlet front guide balde is brought to different positions to change the flow angle of fan inlet, thus
higher efficiency can be attained in different working conditions to adapt to the requirements of
boiler variable working conditions.
Casing (51.00)
It is an outer shell of the fan. By suitable treatment on the inside diameter, a clearance of
4-5mm between the casing and impeller shall be ensured.
There exists a set of fixed straightened guide blade (rear guide blade) in the backside of
the casing.
Diffuser (55.00)
The diffuser bears a certain diffusion angle; with the area increase of the flow passage, the
flow rate of the fan will decrease, converting the dynamic pressure to static pressure will made
transportation and deinstallation much easier.All of the above still parts are allowed to be
dissected.
5.3.2.2 Rotor
Mainly consists of:
Bearing box (11.00):
In consideration of thermal expansion influence, the casing and the diffuser is flexibly
connected by shroud so that thermal expansion cannt be a danger to the rotor under any
circumstances.
There exists two bearing boxes to support impeller weight and sustain the axial thrust
derived from air flow during the operation of the fan. Bearing box adopts split type, and is
featured by easy and reliable adjustment and installation.
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 189 -
Rev. : A
Impeller (12.00):
Impeller consists of impeller casing, stud and blade, and the whole impeller adopts welding
structure to reduce weight. blade the blade is produced in line with certain mode line heat
moulding, and welded on to wheel hub at a certain stagger angle. The impeller connects with
the main shaft firmly through high strength bolt.
Shaft description (11.11)
In order to faciliate the assembly and disassembly of impeller, the shaft is designed to be
sectional and flange is used to connect adjacent two sections; flange that connects the impeller
is welded on the shaft. Power transmission between coupling and shaft is delivered through fit
key, while power transmission between fan shaft and impeller is realized by virtue of fitted bolt.
Bearing description
Bearing block description
Double-row self-aligning spherical roller bearing is installed in horizonally-split bearing, and
cylinder hole is applied to the shaft directly.
Top and bottom bearing boxes are connected through four bolts and riveted through two
taper pins to guarantee correct installation, the end cover of the bearing boxes is a one-piece
structure and is connected through bolts with bearing box, the footing of bearing box is provided
with bolt hole to faciliate the connection with bearing box chassis through bolt, moreover,
alignment hole used for aligning with taper pin is furnished.
Bearing box is especially designed for fixed bearing and floating bearing, so it is
unnecessary to house additional retaining ring in the bearing box. Total axial displacement of
floating bearing approximates to 10mm.
Frame description
Floating bearing block is located on the bearing bracket of straightening guide blade; motor
YKK710-8(29.00) has its own chassis; bracket of fixed bearing box (11.14) is directly mounted
on foundation.
Coupling carries coupling guard to prevent contact with the environment.
Transmitted force of gravity and all possible equilibrant force are taken into consideration
when designing the brackets.
Grid-flexible coupling (25.21,25.22):
The project adopts 5001form14 type grid-flexible coupling, the main shaft connects with the
fan and the motor through coupling respectively. This type of coupling can perform a certain
amount of axial, radial and angular displacements, and can compensate the thermal expansion
during unit operation, various displacements incurred in the process of manufacture and
installation to ensure steady operation.
Cooling fan
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 190 -
Rev. : A
Floating bearing box of the fan is located within straightening guide blade loop, in order to
be free from the influnce of medium temperature, it employs 4-72-11 No 3.2 centrifugal fan,
which is introduced by cooling air duct from the backside of diffuser.
Thermometer
Temperature of the main bearing of the fan is measured through resistance thermometer,
and each bearing block is furnished with three thermal resistance thermometers to measure the
temperature, collected signal will be sent to central control room.
Vibration-measuring detector: each bearing block is provided with a vibration sensor to
measure the vibrating amplitude of bearing block in horizontal direction.
Other spare parts
The fan is also equipped with instrumentation for gauging bearing temperature vibration, oil
level and fan surge, which can provide telemetering, monitoring and interlocking functions to
ensure the operation stability of the fan.The fan is also provided with interface for measuring
gas pressure and temperature for the user to detect air volume and air pressure.
5.3.2.3 Regulating device
Regulation of the fan capacity is achieved by means of the inlet guide regulating device. When
the regulating device is adjusted, the stagger angle of fan inlet guide blade will be adjusted
synchronously. As for a specified fan capacity, optimum prewhirl can be made available to
medium by regulating front guide blade stagger angle of the impeller. The fan can achieve
higher efficiency than throttle governing type under variable working conditions. Because the air
flow directions are almost axial in the simple throttle governing type and bear no relation to the
actual capacity of the fan.
The inlet regulating device adjusting the inlet static blade angle by means of the regulating
mechanism of electric actuator is feasible. Electric actuator operates on the basis of automatic
control provided pulse signal as required by plant capacity. Electric actuator connects with the
position loop of inlet guide blade regulating device by means of steel operating lever. When the
electric actuator acts, position loop rotates together, thereby regualtion can be achieved
through winch, connecting rod and the changing of the inlet guide blade angle.
5.3.3 Parts description
5.3.3.1 Impeller
Welded structure of the impeller can relieve the its rotary inertia, the blade is formed by
uniform steel in line with certain mode line heat moulding. The impeller and the main shaft of
bearing box is jointed togrther through adapter sleeve. In order to ensure the clearance
between the impeller and the casing, outside diameter of the impeller is guaranteed by lathe
and inside diameter of the casing is guaranteed by vertical lathe. Being seen from the air flow
direction, the impeller rotates anticlockwise.
5.3.3.2 Bearing box
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 191 -
Rev. : A
Bearing box adopts split type; bearing is cooled by cooling water. They are safe, reliable
and of compact connection. Each bearing box is equipped with double-row self-aligning
spherical roller bearing to support impelller weight and the axial force incurred by the pressure
rise of the fan.
5.3.3.3 Grid-flexible coupling
The unit employs grid-flexible coupling transmission, which is manufacured by our
company with the imported technology of Germany BSI Corporation and is a coupling that can
achieve actual balance.It can balance various displacements to be generated during the
process of installation and operation of the fan. (including axial displacement, radial
displacement and angural displacement) the coupling is very convinent for alignment. No parts
will suffer friction or fret during the operation of grid-flexible coupling. The flange of such
coupling is made of low alloy steel. Elasticity film with high dimensional tolerance requirement is
made of special high quality steel. Paired configuration of the elasticity film can allow the
connected machine to move in three directions freely. Maintenance is not required for this kind
of coupling. It is unnecessary to lubricate, and it can work without fault below the temperature of
150C.
5.3.3.4 Inlet guide blade regulating device
In the actual cases, fan will meet the situation of various operation requirements. It will
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 192 -
Rev. : A
change the inlet air flow angle through regulating inlet guide blade angle, so that the fan can
answer the boiler to gain better performance under different operating work conditions (loads).
this is the so-called prewhirl.
1.Regulating device shell 2. Regulating position loop3.Roller (radial direction) and bolt
4.Roller (axial direction) and bolt 5.Connecting rod 6.Regulating blade
7.Top regulating shaft bearing 8.Top shaft of root regulating bearing
9.Top shaft 10.Root shaft 11.Joints
5.3.4 Induced Draft Fan Maintenance
Maintenance
Item
Workmanship and Precautions Quality Standard
1. Motor bearing
1. Open the top cover and remove
the oil ring. Open the upper bearing
and measure the top clearance and
side clearance to duely record before
maintenance.
2. Use jack to jack the rotor so to
remove the bottom half bearing and
spray with lead red to grind at the
shaft gland. Check the contact
surface and repeat the grind several
times till the joint satisfies the
1. The top clearance shall be 0.32
0.48mmthe side clearance
shall be one half of the top
clearance, that is 0.16-0.24mm.
2. The clearance between the oil
seal diameter is 0.40-0.60mm
3. The tension of the joint
between the upper bearing and
the bottom bearing shall be
0.00~0.03mm.
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 193 -
Rev. : A
specifications.
3. Clean the bearing seat inside and
check overall the bearing casing.
4. Put down the bottom half bearing
and remove the jack and put the rotor
to the shaft bearing. Measure the
side clearance. Take 3
measurements at each side and use
lead method to gauge the top
clearance.
5. Check and repair internal oil seal
and measure the clearance.
6. Measure the clearance between
the shaft beraing and bearing
casing.7. Check the oil ring and
repair.
8. Check the clearance of external oil
seal and repair. 9. Clean the oil
piping and replace with new flange
gasket.10. Clearly mark the position
before maintenance or find the
original marking. Shaft bearing oil
inlet has to be aligned with the oil
inlet hole on the bearing casing.
1. The front and rear bearing seat oil
inlet has to be installed with throttle
orifice.
4. The contact of the bearing shall
be 2~3contacts/cm
2
.
5. The medium gasket of the
bearing shall not exceed 0.30mm.
6. The clearance between the
bearing and shaft gland shall be
19mm.
7. The rear bearing seat has to be
insulated. The leg has to be on an
insulation plate. The bolts have to
use insulation tube and oil pipe
has to have insulation sleeves
. The oil ring has to be Ok. If it is
worn or deformed, replacement
must be done. The bottom half
has to be immersed in the bearing
seat.
9. The throttle orifice oil inlet
pressure shall be around 49kPa
and the oil filter pressure around
98kPa. There shall be little
difference between the front and
rear pressure.
2. Maintenance
and Service of
Diaphragm type
coupling
1. Check whether diaphragm spring
is Ok.
2. Check whether the bolt connecting
the spring is loose.
3. Check whether the coupling in the
middle of the half coupling is Ok.
1. The spring gasket shall be
complete.
2. The joint shaft and middle
flange shall be complete without
any damage.
3. The bolts connecting the spring
shall be tight.
4. The temperature of the joint
shaft when being heated shall not
exceed 150 . No heating from
fire directly to prevent any
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 194 -
Rev. : A
overheating.
5. Tighten the coupling on the
shaft with a clearance of 0.00
0.04mm.
3. Disassemble
the rotation part
of the fan
1. Remove the bolts on the casing
and the position pin and the casing.
Lift the upper casing according to
TLT rules. Care shall be given to the
lifting and damage to the blade is
prohibited.
2. Cut 0.5-1mm from the front part of
the middle shaft hood and make two
adjustable support to support the
middle shaft. Then remove the flange
bolts between the middle shaft and
coupling and use bolt to tighten the
middle flange in its opposite direction
to press the spring to contract so that
there is clearance between the
middle flange and middle shaft. The
clearance is to be used to lift the
impeller. 3. Loosen the shaft gland
round nut safe and the round nut.
4. Get ready the special tools for
disassembling the impeller. When
disassembling the impeller, first lift
the impeller to prvent damage to the
blade. After disassembling, the
impeller shall be placed to special
support or timber and covered with
waterproof materials to prevent dust.
5. Remove the disaposable bolt
between the bearing seat and casing.
6. Remove the temperature
measurement at the bearing seat
together with oil inlet, return oil piping
and pipe and packed with plastics.
7. Slowly lift the bearing box and
place it on the asessbling support
1. The torque for the disposable
bolt connecting the bearing casing
and casing shall be 250Nm.
2. The torque for impeller lock
bolts (disposable)shall be 300Nm.
3. The maximum and the minimum
clearance between the bearing
rear end cover and casing are
0.80mm and 0.20mm respectively.
They shall be sealed tightly.
4. The added oil shal comply with
specfications made by the
manufacturer.
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 195 -
Rev. : A
and fixed.
8. Loosen the bearing end cover
screw and remove the impeller end
cover9. Put the bearing in an upright
position and extract the rotor.10.
Use a puller to remove containment
shell, and remove bearing end
cover and retaining ring and twin
thrust bearing.11. Check, clean or
replace bearing. 12. Replace all
sealing parts. 13. Check whether the
bearing seat casing and the end
cover is Ok. 14. The order of
sequence for assembling and
disassembling is opposite and clearly
measure the clearances and record.
15. Precautions during
disassembling: mark every part
before disassembing and assemble
according to the marks made. All
high tension bolt shall be tightened
with specified torque. On the bolt
shall sprayed with supramoly. On the
bearing seat end cover shall be
sprayed sealants so that it is oil
leakage free. 16. After placement of
the rotor, no gasket shall be added
between the bearing seat and
casing.17. Impeller shall not be in
any leaning position. Use filler gauge
to measure the clearance at the
bottom of the coupling. The bolts can
only be tightened when the 0.03 filler
gauge can not be inserted.
4. Check the
Main Shaft Gland
and its level
1.When the rotor is positioned, use
level to measure the level of the
coupling shaft gland.
2. Check the key groove and key and
upper tooth and repair
3. The key groove is Ok with no side
1. The shaft gland shall be
smooth, without cracks, curvers,
or burrs. If there is abrasion,
repair needs to be made. The
ovality and concentracity outside
of the shaft gland shall be 0
2.The impeller assembling
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 196 -
Rev. : A
clearance and the tooth is Ok.
position shall shine with bright
yellow colour after copper spray.
There shall not be any black
colour.
3. The level of the shaft shall be
0.06mm/m.
5. Middle Shaft 1. Check the appearance of the
flange, the screw holes on both sides
to see whether there is damage.
2. Use microcalipers to measure the
Out-of-roundness.
3. Meausre the bending on a
specialized motor support.
The flange at both ends shall be
complete without any damage.
The screw hole is Ok. The hollow
shaft shall be no cracks,
damages. The balance weight
shall be fixed and tightened. The
bending shall be , the out of
roundness shall be 0.02mm.
6. Impeller
maintenance
1. Remove the fouling on the
impeller.
2. Before removing the hub, check
whether there is seal on it. If no, first
make seals on the hub.
3. Measure the wear of the induced
draft fan and the blade and record
duely.
4. There shall be no cracks and
deformation from appearance of the
blade.
5. Remove the hub from the main
shaft and place it on a special
support.
1.The blade surface is smooth
and without damage, deformation.
The hub is complete.
2. Inside the hub were no
impurites and foreign matter.
7. Measure the
radial clearance
between the
blade and
casing.
Measure the up, down, left and right.
If the clearance is too small, use
grinder to grind the blade or casing
wall.
The tolerance for the clearance
between the blade and the casing
is 5~7mm.
8. Crosscheck
with the
openness and
closure of the
inactive entry
1. Close the inactive entry 100% and
check whether the trundown ratio is
consistent or not. If not, then adjust
the external articulated parts so that
the turn down ratio is the same. At
When the blade opens +30 or
closes -75, refer to the casing
scale.
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 197 -
Rev. : A
the same time, the casing scale
indication shall read 75. The
position at this time shall be set as
0%.
2. Use the actuator to manually
adjust the entry blade to fully open.
At this time, the scale indication on
the casing shall read 30. The
position at this time shall be set as
100%.
3. Fix the position of stop pad for the
actuator.
9.Alignment of
the fan and the
middle shaft
motor.
1. Use fan as the reference and move
the middle shaft to find the
concentricity. Then move the motor to
find the concentricity between the
motor and middle shaft.2. After
alignment and motor runing without
load, connect the coupling and
remove the temporary support for
the middle shaft and return the
shaft hood and coupling hood.3.
Use Dial Indicators to measure the
center.
1. The radial clearance between
the coupling hood gland seal and
coupling shall be 1~2mm
2. Requirements for the
alignment of diaphragm coupling
at the impeller side and motor
side before the pre-lift of the
motor shaft: radial displacement
r10.15mm; axial displacement
a10.10mm. The requirements of
alignment of diaphragm coupling
after pre-lift of motor shaft: motor
side upper opening and impeller
side downside opening radial
displacement r1=0.20~0.30mm;
left and right opening radial
displacement r10.2mm; up,
down, left and right opening axial
displacement a10.15mm.
3. Alignment requirements after
the coupling is pre-elongated:axial
displacement a1=2.20.15mm,
radial displacement r10.2mm.
10.Casing Inlet
and outlet
compensator
maintenance or
1. Repair the compensator.Replace if
there is serious damage.
2.After repair, check and repair any
1.The compensator shall be
complete, without damage.
2. The tightening plate shall be
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 198 -
Rev. : A
replacement air leakage. complete.
10. Induced draft
fan cooling fan
1.Clean the filter.
2. Check impeller wind duct
3. Reversible deflector maintenance.
4. Motor maintenance together with
its electric supplies. motor.
5.Trial operation
l. The filter, after cleaning, is
complete.
2.Both the impeller and the fume
duct is Ok, without fouling.
3. No vibration and abnormal
noise during trial operation.
12. Induced draft
fan inlet and
outlet fume duct
leakage repair
1. Check the inlet and outlet fume
duct. If there is leakage, repair by
welding with iron plate to remove the
leakage.
1. Replace is the abrasion
reaches 1/2 of the thickness.
13. Induced draft
fan airinlet
chamber and
diffuser
examination and
leakage repair
1. Eliminate manhole air leakages
2. Check the airinlet chamber and
diffuser. If there is leakage, repair by
welding with iron plate to eliminate
the leakage.
1. The manhole is complete,
without air leakage.
2. Replace the inlet chamber,
casing, and diffuser if the
abrasion reaches 1/3 of the
thickness.
14. Outlet guide
vane
examination and
repair by welding
Check and clean the outlet guide
vane. If it is worn, repair by welding.
Replace if the abrasion of the
outlet guide vane reaches 1/2 of
the thickness.
15. Induced draft
fan inlet and
outlet isolating
valve
maintenance
1. Check the whether the damper
switch is correct or not and adjust.
2. Check whether the ram pins are
complete and Ok.
3. Check whether the bearings are
Ok and whether there is lubrication
oil.
1. The baffle is complete and its
opening and closure is flexible.
The turn down ratio on the inside
and outside is consistent.
2. The ram pins are complete,
without damage.
3. No corrosion, falling, or
congestion of the bearings. Inside
the bearings is there lube oil.
16. Trial
operation to
measure the
vibration and
calibrate the
1. After maintenance and in the trial
operation, the fan must satisfy the
following:
1) No impurities within the rotation
1.The vibration value 0.10mm.
2. The bearing operates Ok,
without abnormal noise, and oil
leakage. The bearing temperature
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 199 -
Rev. : A
balance.
parts.
2) Normal oil circulation established.
(3) Remove scaffolding and clean
the site.
(4) People shall stand in the axial
direction in case of accidents.
2. Measure the vibration value during
trial. Check whether is abnormal
noise from the leg screws and the
rotation parts.
3. Calibrate motion balance if
necessary. The balance weight shall
be welded to the rear side of the hub.
shall not exceed 90 .
3. The trial operation shall be 2
hours.
4. The non-static blade can be
adjusted flexibly.
5. After balancing, the thickness
of the balance weight shall be
less than 10mm. The welding
area shall satisfy with the
minimum area on TLT rules. If
tightened with bolts , the size of
the bolt section shall be at less on
half of the welding area. 6.
Regarding the vibration caused
by blade imbalance, the balance
weight has to be marked and
logged so next time it can be
removed when replacing blades.
After removing the rotor blades,
according to TLT rules, it shall be
marked with a bright color
BLADES
5.4 Maintenance of Fume duct and Air duct
Fume Duct, Air Duct and Flange
Maintenance
Item
Workmanship and Precautions Quality Standard
1. Check the air
duct.
1. Check the air leakage of the air duct.
2. Check whether there are defects such
as cracks and deformation.
3. Check whether there are weld
openings, cracks in the air duct
strengthening parts. .
1. No cracks on the air duct
iron plate and strenghthening
parts.
2. The air duct shall be sealed
without air leakage.
2. Air duct and
flange
maintenance
Check whether there is weld openings in
the air duct. 2. Air duct flange packing
seal maintenance.
3. Weld to repiar or remedy the cracks in
the air duct and strengthening parts to
1. No welding defects shall no
noticed on air duct welding.
The joint shall be smooth.
2. No cracks on air duct and
strenghthening bars.
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 200 -
Rev. : A
eliminate the cracks
4. After the air duct maintenance, the
impurities shall be cleared out and the
temporary fixations be removed. 5. Do air
pressure examination and check the seal
quality.6. If there is leakage, it shall be
handled timely. 7. If the air duct vibrate,
analyze the causes and handle them
accordingly.8. Air duct thermal
preservation.
3. No random flame cutting on
the flange bolts. Mechanical
processing shall be adopted.
4. After pipe and equipment
maintenance, immediately
clear all the foreign matters,
dusts and temperary fixations.
5. There shall be seal jacket
between the air duct and the
equipment flange. The jacket
shall not enter either the air
duct or the equipment. Both
sides of the jacket shall be
sprayed with seals.
6. The rear center line
deviation after the air duct
maintenance shall not be
bigger than 30mm.
7. The air pressure experiment
shall comply with regulations.
Fume Duct and its Accessories
Maintenance Item Workmanship and Precautions Quality Standard
1. Baffle and
Plugboard and their
Operatio
Mechanisms
1. Check the new baffle and plugboard
before installation. Do disasembly check
if necessary.
2. Leave heat expansion clearance as
per the drawings.
3. Gland seal maintenance and
replacement to eliminate leakage.
4. Mark on the shaft gland corresponding
positions of the baffle and plugbards as
per the actual positions. Their opening
and closure shall not be limited.
5. Maintenance and check the opening
degrees of combination type baffle.6.
Check the seal of the baffle. If worn,
replace immediately. 7. Check whether
1. The baffle and plugboard shall
comply with the design
requirements.
2.The expansion clearance shall
comply with the design
requirements.
3. The gland seal shall be Ok,
without leakage.
4. The opening and closure of
the baffle and plugboard shall be
accurate and flexible.
5. Regarding the combination
type baffle, the opening shall be
syncronized and the turndown
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 201 -
Rev. : A
the indication in the remote control
equipment is correct; whether the
welding seat opens; whether it is leveled.
8. Check the abrasion level on the
mechanisms with universal joint.
Depending on the level of abrasion, to
decide whether it needs to be repaired or
replaced.9. Check the marking for open
and close and also the limiter for fully
open and fully closure. 10. Clean the
fouling in the fume duct.11. Check the
abrasion level of baffle in the fume duct. If
there is serious abrasion, replace
immediately.
ratio consistent.
6. The operation mechanisms
shall be convenient to use with
correct indications. The seating
plate shall be fixed and leveled.
7. The universal joint shall be
Ok, and the abrasion degree
shall not exceed 1/10. The
rotation degree shall exceed
30.
8. The opening and closure
indication shall be clear and
comply with the turndown ratio
9. The fume duct shall be clean,
without fouling.
2. Extension
maintenance
1. Check the movement of the extension
to ensure free movement. 2. Replace the
fillers each time the extension is
maintenanced. The flange bolt to the filler
shall be flexible.3. Eliminate cracks on
the extension. 4. Check the abrasion
level of the internal tongue in the wavy
extension. If it is serious, either repair by
welding or particially replace. If the
extension as a whole is worn, or the wavy
extension is corrosioned seriously,
replace them as a whole.
1. The movement of the
extension shall be flexible.
2. The fillers in the filling
extension shall comply with
standard.
3. No defects such as cracks on
the extensions.
Support and Hanger
maintenance
1. Check the support and hanger of the
fume duct. If there are cracks,
loosenings, deformations, they shall be
handled immediately.
2. Check the movement and the abrasion
level of the movable support and hanger.
3. Check the spring in the spring hanger
to see whether there are cracks or not.
1. The support and hanger shall
be complete and Ok, without
breakage, cracks, loosening,
and deformation. The load on
the hangers shall be balanced.
2. The movable support, after
being loaded, can still freely
move. Replace the support if the
abrasion exceeds 1/3 of the
walling of the support.
3. The spring on the hanger shall
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 202 -
Rev. : A
comply with design requirments.
No cracks shall be on the
springs.
5.5 Air Heaters and Pipe Maintenance
Air Heaters Maintenance
Maintenance Item Workmanship and Precautions Quality Standard
1. Check the air
heaters
1. After stopping the boiler, water shall be
circulated to check whether is leakage from the
air heaters. Record the leakage position if there
is any.
2. Check the abrasion level of the air heaters.
Replace the worn parts.
3. Check the corrosion degrees of the air
heaters and clearly record them. Replace the
parts which have serious corrision degrees
4. Check the fouling conditions among the
radiators of the air heaters. Clean the fouling
timely to ensure the fume flow area.
1. There shall not be
any leakage from the
air heaters.
2. The abrasion level
of the air heaters
shall not exceed 1/3
of the original
thickness.
3. There shall not be
fouling in the air
heaters. The fume
flow area shall not be
less than 90% of the
design area.
2. Maintenance of
the Air Heaters
1. Replace the damaged air heaters.
2. Hydrotest must be carried out before the air
heaters being installed.
3. When removing the damaged air heaters,
measures have to be taken to prevent damages
to other heaters and to ensure the security and
safety of the site.
4. The welding quality shall pass deficiency free
test by radiation.
5. Hydro test for the whole set shall be carried
out after replacement of the air heaters to
ensure there is no leakage.
6. Hydrotest check shall be executed on each
maintenance and service after the air heaters
are put into operation.
1. New air heaters
have to undergo
hydrotest to ensure
no leakage. The test
pressure is 1.25
times of the work
pressure.
2. After the air
heaters are put into
operation, the
hydrotest pressure
shall be its work
pressure. Normally a
hydrotest with 1.25
times of the work
pressure shall be
carried out around
every 6 years.
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 203 -
Rev. : A
6 ESP
6.1 ESP Technical Specifications
Name Technical specifications parameters
Manufacturer Shanghai Metallurgical & Mining Machine Manufactory
Product type FAA ESP
Nominal flue gas flowing area(m2)
Flue gas flow (m3/s)
Pressure drop of ESP proper (Pa)
Design efficiency (%)
2*269
258.98
<195
99.75%/99.7%
6.2 Structure of ESP
The method utilizing HV electrostatic field to act on dust gas is called electrostatic
precipitation and the equipment is named electrostatic precipitator (ESP). Its operation principle
is that: in HV electrostatic field, gas is ionized by the electric field force into electrons and ions.
These electrons and ions move under the action of electric field force and combine with dust
making dust charged. Dust particles with negative electric charge are collected at anode
(collecting plate), discharged and adhere to the anode. Meanwhile, particles with positive
charge are collected at the cathode. When dust accumulation reaches a certain thickness, dust
particles will be peeled off from the collecting plate by rapping mechanism and drop into ash
bucket. The dust collecting process finishes.
Major features of ESP are: high efficiency; low operation resistance; low operation cost.
However, cost of ESP is high, and its volume is huge requiring a large area. In addition, it has
strict requirements on manufacture, installation and maintenance. Efficiency is easily to be
affected by operation factors. Therefore, operators should have high technical capability.
An ESP is composed of one or more chambers and fields. Devices include discharge
electrode, collecting electrode, rapping unit, ash bucket, ash discharging device. So-called
chamber is a sub branch of transverse flue gas path. There may be single chamber, double
chamber or triple chamber according to flue gas volume. So-called Field is a dust removal unit
along with the direction of gas flow. Each unit has an independent working system.
6.3 Maintenance of ESP
1. Get Equipment Conditions before Maintenance:
Include: operating parameters of electric fields before ESP outage (secondary voltage,
current,ratio of putting into operation, operation hours, etc.); equipment defect and treatment
records; summary of last overhaul and operation maintenance logs since last overhaul (such as
technical improvement and equipment replacement).
2. Prepare Maintenance Schedule:
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 204 -
Rev. : A
Include: progress control schedule; maintenance procedures; labour arrangement and
diciplines coordination; special technical provisions and safety procedures.
3. Material preparation and site arrangement:
Include: preparation of spare parts, maintenance material, construction tools, safety facilities,
lighting tools and protective clothes; division of working area and stack area; management of
site spare parts.
4. Preparation of technical record forms:
Include: measurement record forms of electrode distance, record form for no-load step-up
test of electric field universe point, distributing test of air flow, rapping acceleration test, air
leakage ratio test record forms(if necessary).
Safety Measures and Precautions during ESP Maintenance
1. Maintenance activities inside ESP and at high-altitude should be performed as per
requirements specified in [Working Regulation of Power Safety].
2. Maintenance inside ESP should be carried out after boiler is shut down and cooled by
natural cooling or draft cooling, and the temperature of the electric field is below the safety
value as well as the residual flue gas is exhausted. The safety temperature is 40oC
normally. Properly extend the safety temperature limit as required and strengthen
protective measures. However, the temperature limit should not exceed 45oC.
3. Before enter ESP electric field, shut off the power supply, lay grounding wire and hang
warning sign.
a) Shut off power and hang warning sign: cut off the HV power supply with an obvious
breaking point and hang the warning sign. Cut off the power supplies of the ESP
auxiliary equipment (rapping, ash handling, and electric heater) and hang a warning
sign.
b) Discharge electric field and lay down grounding wire: after verifying the HV power is
shut off, put the HV disconnector to position Power-Grounding and lock it and hang
warning sign. Discharge the electric field with the grounding wire. Then hang a
warning sign written with grounded. Before open b manhole to get in electric field,
discharge the manhole and electric field. Insulation glove should be worn during
discharging and laying grounding wire.
4. Power supplies for electric field maintenance:
a) Voltage of the portable light should not be higher than 12V.
b) If a 220V or 380V maintenance power supply is needed to be routed into the electric
field, a guardian should be appointed outside the electric field manhole to quickly shut
off the power supply equipped with earth leakage protector in case of emergency. The
earth leakage protector should be qualified. Power wires should be well insulated to
avoid any accident.
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 205 -
Rev. : A
c) Welding wires routed into electric field should be well insulated without any damage or
leakage.
5. For maintenance inside electric field, working bags should be used for material
transportation. Count the material and tools before each commence and after each
completion. Remove debris produced by maintenance and do not leave them at electrodes
to prevent them from dropping into ash hopper or left in the electric field.
6. For maintenance inside electric field, there should be at least two personnel with another
for guardian outside the ESP manhole.
7. Special safety measures should be arranged for specific maintenance items:
a) Safety measures during no-load step-up test of electric field: the key points of the
activity are the combination of mechanical and electrical works simultaneously,
power-on test and discharge treatment.
b) Cross working. Parallel installed cable should be supplied on the HV side when double
power supplies are stepped up. Special safety measures include preparation of test
plan or procedures, determination of person-in-charge, guardian from appointed
personnel, reliable communication, guard fence and suspension of warning signs. It
should be approved by the safety supervision department of the factory when entering
the electric field to observe discharge point.
c) For the maintenance of equipment in the HV switch cabinet of the latter stage electric
field maintenance, the damage caused by the drift charge from the former stage
should be avoided.
6.3.1 Maintenance of Cathode Wire and Anode Plate
Maintenance item Workmanship and precautions Quality standard
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 206 -
Rev. : A
Maintenance item Workmanship and precautions Quality standard
Remove ash inside
electric fields
1. Only at least 12 hours after the boiler
flameout can open the manhole for
further cooling so as to avoid the
deformation of parts inside ESP caused
by sudden drop of temperature.
Access can be available only if the
temperature inside electric field drops
below safety value.
2. Check before removing ash: check
the ash accumulation inside electric field
including accumulation position and
degree. Check ash accumulation on
electrode plate and electrode surface.
3. Cleaning of ash accumulation in ash
hopper: before manual ash cleaning in
electric field, start the continuous
cathode/anode rapping and trough plate
rapping for mechanical cleaning.
Discharge ash through normal ash
handling method. For ash removed out
by manual method from ash hopper of
the electric field should be stored in bags
manually for transportation. For cleaning
ash in the ash hopper, personnel should
be dressed with cotton protective
clothing, boot and dust mask to avoid
any injury. Ash releasing port and
maintenance passage should be bright
without barrier. When opening the
manhole, do not face to the front of
manhole.
4. Ash cleaning in electric field: the
cleaning sequence should be manually
performed from upper to lower and from
inlet to outlet by means of compressed
air blowing. Water flushing is prohibited.
Keep original check record
and registration; analyze the
cause of abnormal ash
accumulation to provide
reliable information for
maintenance.
Avoid discharging ash
through manhole.
No ash accumulation, scaling
on the surface of parts after
cleaning ready for the
maintenance.
When cleaning the ash
accumulation on the anode
plate, do not shake it to avoid
deformation of anode plate.
thickness of ash accumulation
should be less than 5mm.
(I)Anode plate
maintenance
1. Check the deformation of a single
anode plate and correct the difference.
2. Check corrosion and electric
1. Flatness error <15mm,
diagonal error <10mm.
2. No burr or sharp corner
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 207 -
Rev. : A
Maintenance item Workmanship and precautions Quality standard
corrosion of a single plate and repair
damaged anode plate as well as grind
the burrs and sharp corner.
on the surface of plate.
(II)Anode plate
maintenance
1. Check the fixing pin roll on the
upper cleat of the anode plate, buckle
bushing and fixed-position welding;
check the deformation and abrasion of
the square hanging lug and hanger.
Check for any splitting around electrode
plate tightened by the buckle bushing or
any sinking or displacement of total
anode plates and repair them.
2. Check for any splitting, sealingoff
or deformation on the anode plates and
repair them.
3. Check the fixing pin roll of the
lower cleat of the anode plates, buckle
bushing and fixed-position welding;
check for any splitting around electrode
plate tightened by the buckle bushing.
Check the anode plates for any
deformation or sealingoff.
4. Check the heat expansion
clearance between the lower anode
plates and ash hopper port for any
seizing, expansion or other resisting
sign.
5. There should be no obvious
convex-concave on the whole anode
plate by visual inspection. Replace them
in case of the thickness of the anode
plate is less than 50%.
1. Buckle bushing is not
loose; surrounding electrode
plates are not split; abrasion
of hanger is less than 1/3 of
original thickness. Total
sinking of anode plates is less
than 5mm.
2. No splitting or sealingoff
occurs on the connecting belt.
3. Buckle bushing is not
loose; surrounding electrode
plates are not split; rapping
rod is fixed in the rail with a
transverse clearance of about
4mm.
4. Heat expansion clearance
should be calculated as per
twice of the value when
temperature of the flue
reaches the high limit.
However, it should not be less
than 25mm. the two side of
the comb-shaped port should
be smooth without steps.
5. bending of plane should be
less than 10mm; difference
between two diagonal lines
should be less than 10 mm.
(III) Detection of
the distance
between the same
electrode of the
anode plates
Take the straight electrode plates in the
middle of the electric field as reference,
measure the distance between the same
electrodes. Measurement should be
carried out on three points along the
height of the electrode plate. ,
Measure and record as per
clauses specified in the GB/
T13931-92 [ESP performance
test procedure].
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 208 -
Rev. : A
Maintenance item Workmanship and precautions Quality standard
(IV)Calibration of
the distance
between the same
electrode
When the distance between the same
electrodes exceeds the specified limit,
calibrate the deformed electrode plates.
Do not knock the surface of the
electrode plate if calibration is not
available, replace whole electrode
plates.
Each electrode plate should be tested as
per manufacturer standard test before
replacement. Assemble the plates as per
the former sequence and check their
straightness.
Allowance error of the
distance between the same
electrodes is 10mm. if the
deformation of electrode
plates significantly affects
ESPs efficiency, replace all
plates.
Maintenance item Workmanship and precautions Quality standard
(I) Maintenance of
tube-shaped spine
wires
l. check spine passivation, balling and
dropping off; check spine wires for any
loosing or dropping off; combining the
check of distance of two different
electrodes, check the bending of the spine
wires; tighten, repair, correct or replace
them as required.
2. replace the spine wires :
(1) Visually inspect the new spine wires; it
should be plain without any twist.
Arrangement of spines matches the
electrode wire.
(2) During installation, tighten and weld the
connecting bolt on upper cathode wire.
The blot on the lower part should be loose
a half circle after fully tightening before
welding.
Arrangement of spines
satisfies the requirements of
manufacturer; the space
error between points is no
larger than 1mm; center of
the spine wires should
match the pipe center of
cathode small frame.
(II) Detection and
adjustment of the
distance of two
different electrodes
1detection of distance of two different
electrodes should be carried out after the
maintenance of large/small frame and the
distance between the same electrodes of
the anode plate meets requirements.
2. During detection of distance of two
Error of distance between
the same electrodes is no
greater than 10mm.
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 209 -
Rev. : A
different electrodes, record forms should
be prepared including electric field name,
passage number, detecting points
number, cathode wire number, staff, time
and results.
3 there are two method for detecting
distance of two different electrodes:
(1) Visual observation plus pin gauge. This
method can be performed by experienced
staff. By visual observation , find out
suspect passage and check it with pin
gauge. If the pin gauge passes through,
the distance of two different electrodes
meet requirements.
(2) Standard method. Perform as per GB/T
13931- 92 [ESP performance test
procedure] .
Normally two methods are combined,
ensuring passage distance of two different
electrodes meet requirements. Record the
actual distance of two different electrodes
of the typical passages.
4. Correction of the distance of two
different electrodes: for the electric field
where correction for distance between the
same electrode and large/small frame and
electrode wire as per standards, it can
ensure the distance of two different
electrodes within a standard range.
However, standard may be not fully
satisfied because of large work load, short
work period and lack of maintenance
method and equipment aging. Partial
adjustment should be carried out to ensure
all distance of two different electrodes
within limit. Spine wires can be adjusted by
changing the deflection of spine and
distance between two sharp points. The
number of the adjusted parts should be
less than 5% of total to avoid the changing
of the discharge center, which effect the
Refer to standard GB/T
13931- 92.
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 210 -
Rev. : A
discharge performance of the electric field.
6.3.2 Cathode, anode rapping unit maintenance
Maintenance item Workmanship and precautions Quality standard
(I) Integrity check
of Rapping
mechanism
1. Combining with anode plate ash
accumulation check, check the anode
plates with serious ash accumulation.
2. Check and repair parts based on
the protective action of motor overload
during operation of rapping mechanism
and damage of drive connecting part.
3. Check and treat all fastening parts
in the path of rapping force and retaining
welding.
1. During normal shutdown,
there should be a thin layer of
ash on the electrode plat.
2. Under normal conditions,
rapping mechanism can be
turned manually without
motor overload trip.
(II)Rapping drive
mechanism
maintenance
1. Drive connecting parts
maintenance: check rapping universal
coupling, flange, and spring gasket for
any loose or rupture, and replace and
weld them in case of defects. Pay
attention to the expansion clearance of
the coupling connection.
2. Maintenance of rapping drive shaft:
check shaft sections for any twist and
whether the coaxiality meets the
requirements. For a certain deflection, it
can be adjusted by changing the shim of
the rapping bearing seat.
Replace the shaft with a over abrasion.
3. Maintenance of rapping bearing:
(1) Check and treat the center
variation, sealingoff and displacement of
the 4 rapping bearing supports.
(2) Check abrasion of the sleeve.
Replace it in case of rupture or over
abrasion.
(3) Check the rolling and seizing of the
small roller of the bearing. Replace it
Requirement on the
coaxiality is that the space
tolerance between two
bearings is 1mm, total length
of the shaft is 3m. the
abrasion of the shaft should
be less than 4mm.
Sleeve abrasion is less than
1/3 of the former thickness.
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 211 -
Rev. : A
when repair is not available.
(III) Maintenance of
rapping hammer
and rapping
striking anvil
1. Maintenance of rapping hammer:
(1) Check the connection of the rapping
hammer head jib, hammer beam and
hammerhead; check the fastening parts
for any loose, sealingoff, or damage.
Repair or replace the rapping hammer
shaking seriously.
(2) Check rapping shaft and its
connection. Correct and treat the
deflection based on the deflection of the
hammer point.
(3) Check abrasion and rupture of the
hammer. Replace the hammer with
rupture or over abrasion.
(4). manually turn the hammers and it
should be rotates freely without seizing
or collision. Pay attention to the
direction of the hammer when replacing
hammer with installation direction.
2maintenance of striking anvil:
(1) Check striking anvil for any loose or
sealingoff.
(2) Check striking surface and repair the
depressed part to ensure line contact
between hammer anvils; replace the
striking anvil which can not be repaired.
(3) Check the contacting of the hammer
and anvil. The hammer center value in
hot state can be observed via hammer
marks. For check in cold state, electrode
plate expansion should be taken into
consideration. The hammer strikes the
anvil surface when it drops freely to the
vertical position.
Position error of the actual
hammer point should be less
than 5mm; the contact line
between hammer and anvil
should be longer than 2/3 of
the total length of fully
contacting. Considering the
heat expansion, hammer
point in cold state is 5mm
below the center line. The
distance error to the anvil
surface is 5mm when the
hammerhead freely drops to
vertical position.
(IV) Maintenance
of cycloidal-pin
1. Disconnect the cable of the motor and
clean the reducer casing and seat
platform; dismount the chain cover to
a) Pin roll and pin bush are
free of bending or
deformation, the abrasion
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 212 -
Rev. : A
wheel reducer remove the chain.
2. Disconnect the coupling to remove the
motor and coupling.
3. Mark on the contacting surface of
reducer casing.
4. Make marks when dismounting
connecting rod of the universal joint and
proper contacting surface. Notice the
thickness of the former paper gasket of
the contacting surface. Recover the unit
as per former paper thickness and
marked position.
5. When remove cycloidal gear A
(marked on the gear), the mark A on
the end surface of balance wheel should
match the mark B on the other
cycloidal gear. Recover it as per former
relative position.
6. Collision should be avoided when
remove rings. When remove and install
the roller bearing on the eccentric
locking collar, support the bearing
together with the eccentric locking collar
by hands to remove it along the shaft.
7. When clean runner axle, gear sleeve
and gear casing, check related abrasion
and clearance. Verify the length of
runner axle; seal ring of oil-proof rubber
and its spring are all in proper
conditions. Otherwise, replace them.
Lake-shaped seal ring should be filled
with grease. Fill lube oil into the tank
until required oil level and verify the oil
level gauge is qualified.
8. Maintenance the bearing as per
regular procedures. Bearing is
normally installed in hot state with a
certain stress after installation.
9. When insert input shaft pin into
should be no greater than
0.05mm.
b) Cycloid gear is free of
crackle with an abrasion no
greater than 0.10mm;
pinwheel and pin gear sleeve
should be free of bending with
an abrasion no greater than
0.10mm.
c) Bearing inner and outer
rings and rolling element
should be free of crackle or
pocking mark. Replace it
when the clearance exceeds
limit.
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 213 -
Rev. : A
cycloidal gear, the clearance in relative
holes should be paid attention to. Do not
crash the spacer ring when position with
pin sleeve.
10. After assembly, manually turn the
high speed input shaft to check for any
abrasion.
(V) Test run of
anode rapping
system
1. When rapping system is reset,
manually turning the gear to check
rapping rotation and rapping points.
2. Electrically test run for 1h.
1. Turning gear is free of
seizing, fluctuation and
abnormal noise; the oil mark
is clear and the oil level is
proper.
2. Reducer is free of oil
leakage, temperature rise of
the bearing is less than 50K;
there is no motor overload.
Sound and vibration of the
motor and reducer are
correct.
Cathode rapping system
maintenance item workmanship and precautions Quality standard
(I) Integrity check
of the rapping
mechanism
Integrity check mainly focuses on anode
rapping except ash accumulation check
of the cathode wire.
(II) Maintenance of
rapping drive
mechanism
1. maintenance of the drive connecting
parts:
(1) Check rapping universal coupling or
dowel pin coupling, flange, connecting
bolt, spring washer for any loose or
rupture. Fasten, replace and weld them
if necessary. Pay attention to the
expansion clearance of coupling.
(2) Check engagement of the drive plate
for any over abrasion or damage which
affect the normal turning.
(3) Clean the ash accumulation on
electric porcelain shaft l with a soft cloth.
Check for any crackle and discharge.
Electric porcelain shaft should
have a vertical moving
(expansion ) clearance, which
is 10mm normally.
HV test standard for electric
porcelain shaft is the same as
that for porcelain sleeve.
error between the rotating
shaft and center of the
soldering cup is 5mm
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 214 -
Rev. : A
Replace damaged electric porcelain
shaft. Visual inspection and voltage
withstanding test should be performed
before replacement.
(4) Check the contact sealing between
drive shaft and casing; verify the center
lines of the drive shaft and dust shield
match; check the soldering cup for any
rust and remove it if necessary.
2. Sliding bearing : maintenance content
is the same as that of anode rapping.
(III) Maintenance of
cathode rapping
hammer and
rapping striking
anvil
Maintenance content is the same as that
of anode rapping.
(IV) Cathode
rapping reducer
maintenance
Maintenance content is the same as that
of anode rapping.
(V) Cathode
rapping system test
run
Test run content is the same as that of
anode rapping.
6.3.3 Maintenance of cathode suspension device and large/small frame
Maintenance item Workmanship and precautions Quality standard
(I) bushing
suspension device
1. Visual inspection and maintenance :
(1) Wipe the surface of the support
porcelain sleeve with a soft cloth.
Check surface and support stress
surface for any mechanical damage,
insulation damage or discharge vestige.
(2) Check suspender and locknut, load
bearing parts for any mechanical
damage.
(3) Check corrosion of soldering cup and
the coaxiality of suspender and
soldering cup; remove the dust and rust
inside soldering cup.
1. Concentricity error between
soldering cup and suspender
is no greater than 5mm.
Manhole is airtight and has
been check; inside should be
cleaned.
2. HV test standard of
porcelain sleeve should be
1.5 times of the rated voltage
of the electric field. It should
not be broken through within
1min.
elevation error of the
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 215 -
Rev. : A
(4) Check the electrical connection
between HV suspension device and HV
switch cabinet wall bushing.
(5) Check sealing of the manhole.
2. Replace support porcelain bushing:
replace damaged porcelain bushing.
Before replacement, mark the fixed
position of the suspender bolt. Provide
temporary measures to keep the
balance of four supporting points to
avoid damage to porcelain sleeve new
porcelain sleeve is intact by visual
inspection; HV test is acceptable;
elevation error of the porcelain sleeve
in the same group ( totally four) meets
requirements.
porcelain bushings in the
same group should be
1mm.
(II) Cathode large
frame maintenance
1. Check the levelness and verticality of
the cathode large frame meet the design
requirements or not.
2. Check and repair the partial
deformation, sealingoff or splitting of the
large frame.
3. Check stairs on the large frame for
any loose or sealingoff and repair them.
Flatness error of the frame is
not greater than 15mm,
diagonal error10mm.
cathode large frame should
be vertical to the horizontal
plane with a verticality error
10mm and elevation error
2mm.
(III) Cathode
small frame
maintenance
1. Check the connection of the upper
and lower small frames and fixation of
the small frames on the large frame.
Correct, repair and weld in case of
bending, deformation or sealingoff.
2. Check plainness of the small frame
and correct it as required.
3. Calibration of small frame plainness
should be combined with the distance of
two different electrodes to ensure the
distance of two different electrodes
within specified limit.
Plainness error of the
installed and welded cathode
small frame is 10mm and the
diagonal error is 5mm. all
nuts and bolts for small frame
should be welded for
retaining. There should be no
burr on the welding position.
6.3.4 Maintenance of other auxiliaries of ESP
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 216 -
Rev. : A
maintenance item workmanship and precautions Quality standard
(I) ESP casing
maintenance
1. Check casing for any abrasion and air
leakage. Patching should be carried out
for abrasion and corrosion.
2. Check support pipe and lacing wire in
casing. Replace seriously worn parts.
3. Correct the deformation of the inner
wall of the casing and baffle.
Air leakage ratio of the ESP
is lower than 3%.
(II) Inlet smoke
chamber
maintenance
1 deflector before inlet smoke chamber:
(1) Check abrasion of the deflector and
support parts. Replace the seriously
worn parts. Anti-abrasion measures
should be provided for part used less
than an overhaul period.
(2) Check the arrangement of deflector
is in accordance with the former design;
carry out treatments like adjustment and
repair welding.
2. Inlet smoke chamber :
(1) Check and repair the abrasion and
corrosion of smoke chamber inner wall
and support as well as lacing wire.
Replace seriously worn parts.
Anti-abrasion measures should be
provided for part used less than an
overhaul period
(2) Repair and strengthen the depressed
position of the smoke chamber.
(3) Check air leakage of contacting
surface between the flange of the casing
and inlet smoke chamber. Replace
packing material if necessary.
(III) Maintenance of
grid plate
1. Check the abrasion of the support
pipe, angel steel and connecting bolts
for supporting and fixing air flow grid
plate. Replace the seriously worn parts.
2. Check abrasion of the air flow grid
When the abrasion volume
reaches 1/4 of the former
opening, or it has obviously
effect the efficiency of
dedusting, replace it.
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 217 -
Rev. : A
plate. Repair seriously worn part. Take
anti-abrasion treatment if necessary.
Find out the cause of over abrasion and
eliminate it, for example, to adjust the
inlet deflector. When abrasion of the
whole unit reaches a certain degree,
replace it.
3. During replacement of the air flow grid
plate, the design requirement should be
satisfied. Determine whether to replace
or how to replace by air flow distribution
test.
Test and criteria as well as
standard refer to
GB/T1393-92 [ESP
Performance Test Procedure].
(IV) Maintenance
of ESP top
1. Check and repair any abrasion,
corrosion or air leakage on the ESP top.
2. Check rainwater collecting annulus
and downcomer.
(V) Outside
insulation and
frame cover
maintenance
1. Check outside insulation and frame
cover for any falling off or damage and
carry out treatment.
2. Check the corrosion and fixation of
the outer frame cover. Measure should
be take for any loose or abrasion.
3. Water flow direction should be taken
into consideration when lap the new
plates to the old plates and the lapping
seams should be straight.
Outer insulation and frame
cover should be plain, firm,
orderly, rain-tight and
anti-gale after maintenance.
(VI) Outlet smoke
chamber
maintenance
1. Maintenance of the outlet smoke
chamber refers to that of inlet smoke
chamber maintenance.
2 maintenance of the trough plate:
1) Check abrasion and deformation of
the trough plate and correct them.
2) Check and reinforce the support,
suspension and arrangement of the
trough plate.
3) Trough plate rapping mechanism
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 218 -
Rev. : A
maintenance refers to anode rapping.
(VII) Maintenance
of manhole
1. The opening and closing of the
manhole is free and airtight without air
leakage (check it based on the air
leakage during equipment operation),
replace disable packing seal and
corrosion, damaged bolt and nut.
2. Check corrosion of the inner wall of
the manhole and carry out rescaling and
repairing.
3. Check safety signs on the manhole,
which should be complete.
The opening and closing of
the manhole is free with
complete safety signs without
air leakage.
6.3.5 ESP ash hopper and slide damper
Maintenance item Workmanship and precautions Quality standard
Maintenance of
ash hopper and
slide damper
1. Check corrosion of flange contacting
surface of the ash hopper based on the
leakage and corrosion during operation.
Repair as required and grind the welding
points with sand grinder.
2. Check the arch plate on ash hopper
for any sealingoff with the side wall. The
surface should be smooth and flat
without scar after repair welding.
3. Check the abrasion and fixation of the
supports in ash hopper and hanging
beam of the air baffle of ash hopper.
Repair, correct and weld any
displacement.
4. Check abrasion, deformation and
loose of the air baffle in ash hopper;
check abrasion of the lug and
suspension ring of the turning parts of air
baffle; repair and replace as required.
5. Maintenance of the slide damper at
the bottom of ash hopper: replace gland
packing at slide damper and ash hopper
flange to eliminate the ash leaking points
at contacting surface. Check the
Inner wall of the ash hopper is
free of leakage and cicatricle,
which may catch ash.
Corners in ash hopper are
smooth without dead angle.
Ash hopper is free of
deformation and the supports
structure is secured.
Air baffle is free of loose and
inclination. Replace the
hanging ring if the abrasion
volume is greater than1/3 of
its body.
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 219 -
Rev. : A
operation of the slide plate mechanism
for any seizing; adjust them and remove
rust as well as add lube oil.
6. Ash hopper gasification unit
maintenance:
(1) Check gasification pipe line and
gasification electric heater.
(2) Check abrasion and blockage of the
ash hopper gasification plate and
replace them when manufacturer limit is
exceeded.
Valves should be opened and
closed freely and can be
reliably isolated without
leakage.
Stairs, platform ,
rail maintenance
1. Check all platforms, passages, stairs
and rails inside and outside ESP; repair
and replace those damaged or not
conform to safety regulations.
2. Remove rust of outdoors steel
structure, such as platform, passage,
stairs, rail, reducer casing and paint.
There should be no crackle or
corrosion; the footpath on
platform is straight and flat.
Strength meets requirements.
6.4 Tests after ESP maintenance
6.4.1 Prerequisite for acceptance test
1. Tests and commissioning on the ESP HV/LP electrical equipment have completed.
2. ESP mechanical maintenance has completed and test of turning equipment have
finished.
6.4.2 Acceptance test items
It is to verify the maintenance quality of ESP mechanical parts and electrical parts and ESP
performance.
Cold state acceptance and test
1. Spot-check of distance of two different electrodes:
(1) Record the distance of two different electrodes detect during maintenance. spot-check
and review 5%~10% of them.
(2) Select 1 or 2 passages which are recorded to detect the distance of two different
electrodes. The result should be in accordance with the requirement on distance of two different
electrodes. Repair and detect the electric field which fails to meet the requirements.
2. Air flow distribution test: for ESP passed model test with a similar condition with tested
equipment, air flow distribution test will not be performed during overhaul. Air flow distribution
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 220 -
Rev. : A
test can be carried out in one of the following cases:
(1) Air flow grid plate is over worn; it is needed to or has significantly adjusted or replaced
the inlet deflector and air flow grid plate.
(2) Dedusting efficiency drops significantly and operation condition of ESP changes
significantly; the air flow uniformity is doubted to meet requirement.
Air flow distribution test refers to GB/T13931-92 [ESP Performance Test Procedure]. If the
test results can not meet the standard, calculate and adjust again until requirements are
satisfied.
3) Rapping acceleration test: when serious ash accumulation exists on the electrode wire
and electrode plate, rapping acceleration test should be considered to be performed. Test
should be carried out as per GB/T 13931-92. When design requirements of manufacturer can
not be satisfied, cause should be found out and treated.
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 221 -
Rev. : A
7. Double screw rod air compressor(zrseries)
7. 1 Double screw rod air compressor technical specifications
ATLAS COPCO fixed type air compressorzr series is a kind of oil spout double screw rod
air compressor. This type of air compressor is of the following advantages ,such as, structure is
simple, can be operated easily, the number of wearing parts is few, changing spare parts is
easy and function is Stable and reliable. Therefore it is widely used in many related industries.
7. 2 Double screw air compressor structure
ZR110 to ZR750 air compressors are oil-jet twin screw stem types with two stages
compressing and driven by motor. They can provide air with stable pressure. Water cooling is
adopted. For this kind of air compressor, their structure and operation principle are nearly the
same although there are some differences in details. Air compressor is installed in a noise
enclosure including the following parts:
air filter
-LP screw stem head
-intermediate cooler
-hpscrew stem head
aftercooler
motor
Driving coupling
Gear box
-Elektronikon. Control system
Safety valve
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 222 -
Rev. : A
Front elevation of ZR series air compressor
AF. Air filter
AO. Air outlet
Ca. Aftercooler
Co. Oil cooler
CM. Elektronikon PC controller
Daa. Automatic condensate blowdown port of aftercooler
Dai. Automatic condensate blowdown port of Intermediate cooler
Dma. Installation port for condensate manual blowdown valve of aftercooler
Dmi. Installation port for condensate manual blowdown valve of intermediate cooler
Dra. Aftercooler condensate blowdown tank
Dri. Intermediate cooler condensate blowdown tank
Eh. Hpscrew stem head
El. Lpscrew stem head
M1. Main motor
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 223 -
Rev. : A
Svh. Hpsafety valve
Svl. Lpsafety valve
TV. Full load/no-load valve
WI. Cooling water inlet
WO. Cooling water outlet
1. Direction of motor rotation
2. Flange
3. Maintenance hole for air filter
4. Regeneration air pipe with non return valve
Side elevation of ZR series air compressor
AF. Air filter
AO. Air outlet
Ca. Aftercooler
Ci. Intermediate cooler
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 224 -
Rev. : A
DP2/5. Blowdown plug screw (painted green)
Dra. Aftercooler condensate blowdown tank
Dri. Intermediate cooler condensate blowdown tank
Eh. HP screw stem head
El. LP screw stem head
M1. Main motor
Svh. HP relieve valve
Svl. LP relieve valve
TV. Full load/no-load valve
WI. Cooling water inlet
WO. Cooling water outlet
Y1. Loading solenoid valve
1. Direction of motor rotation
2. Flange
3. MD dryer joint
4. Cap
1. Drive system: includes main motor, coupling, gear box etc. Normally, the application of
coupling is ignored for minor units. For medium or large units, separable coupling drivers
will be installed for easy assembling and maintenance.
2. Major equipment: in the shape casing, two engaged screw stem rotors are arranged
parallelly, respectively called female and male rotor. Two rotors form a pair of enclosed V
type space with casing. This space will reduce along with the rotation of rotor and the
space will move towards primary port from intake port. This is the whole process of intake-
compress - primary.
3. Control system includes induction system, governor system, minimum pressure valve bank,
safety control system and PC controller. Subsystems all contain associated solenoid
valves, sensors, air-operating piping and related PC programs and orders.
Control system contains the most parts and acts most frequent. Therefore, it is the system
with the most failures. The largest differences and features of different brands are reflected by
this system. In consideration of high reliability, quantity of parts in the ATLAS unit is reduced as
far as possible. Even the governing system is cancelled. Therefore, ATLAS unit has a simple
operation method. In addition, ATLAS combines the load controlling system and discharge
system to the air intake valve. Failure ratio is reduced significantly by adopting piston valve
instead of adjustable butterfly-valve. Its simple operation method makes it difficult for user of
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 225 -
Rev. : A
small amount of air to match demand and supply.
4. Cooling lubrication system: includes special lube oil, heat exchanger, temperature- sensing
valve, oil cut-off valve and cooling fan.
5. Air flow-oil system-cooling system: air is sucked into LP head (E1) through air filter;
after compression, compressed air enters intermediate cooler (Ci) to be cooled. Then
compressed air enters HP head for further compression. Before enters air network, it flows
through silencer (AS) to reduce noise and aftercooler to be cooled. A check valve (CV) is
also installed at the downstream of silencer for ZR110-275 and downstream of aftercooler
for ZR300-750.
6. Condensate blowdown system: two Water separators are installed. One is installed at the
down stream of intermediate cooler (mti) to prevent condensate from entering HP screw
stem head. The other is installed at the down stream of aftercooler to prevent condensate
from entering primary air pipe. Water separator is connected to the condensate blow down
tank. Each blow down tank is equipped with a ball float valve for automatic blowdown and a
manual blowdown valve. For ZR300-750, an extra water separator is installed on the vent
pipe preventing condensate from entering silencer when equipment transfers from loading
to unloading.
7. Lube oil system: lube oil in the oil sink of gear box is pumped by the oil pump (OP) to
bearing and synchronizing gear through cooler (Co) oil filter (OF). Bypass valve (BV) will
open when pressure of lube oil reaches the setting valve.
Cooling system: cooling water flows by cooler (CO) to the cooling water jackets of HP screw
stem head (Eh) and LP screw stem head (El) respectively. For ZR300-750 type, cooling water
is also used to cool the vent pipe of LP screw stem head (E1) and flows by Intermediate cooler
(Ci) and aftercooler (Ca). Cooling system parts failure will directly result in outage of unit.
More than 90% of heat exchanging is carried by cooling system. During hot days, volume of
exchanged heat will increase several times. Any improper maintenance of the cooling system
will result in poor operation, low efficiency, high energy consumption etc. It is important to
perform preventive maintenance before hot days.
7. 3 Maintenance level for Double screw air compressor
The maintenance level of the air system is determined by the oil service life, action times of
parts, bearing service life and abrasion situation of parts..
Normally, the quality and performance of the mineral oil will significantly decrease after 2000
hours operation, and the accumulated carbon will increase. After 2000 hours operation, the
meshes of the filter adopting paper element will be seriously blocked causing the filtering
efficincy decrease, pressure of the lube oil decrease and the inactive power of the unit increase.
The service life of the oil used for filter with glass fibre as element will reach more than 4000
hours. In addition, the service life of the sealing rings of the moving parts in the minimum
pressure valve, load controlling valve of the control system might reach 4000hours because of
iron-oxygen used in the sealing ring. Normally, service life of the air compressor is about 8000
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 226 -
Rev. : A
hours. The maintenance can be divided into three levels: A, B and C corresponding to
2000,4000 and 8000 hours. At the above said time and their times, maintenace should be
carried out to prevent accident. Details include:
Quarterly: level A: oil, oil filter, air filter
Half a year: Level B: Level A plus oil conten as well as maintenance packages of control
system.
Yearly Level C: Level B plus temperature control valve, loading solenoid valve, oil pressure
control valve and operation of motors.
After several yearsoperation, dynamic balance and strength of resonance of the air
compressor should be tested to provide data for overhaul of the main machines and driving
system.
. 4 Level C maintenance for double screw rod air compressor
7.4.1 maintenance preparation:
Start the equpment to run for 15minutes; estamite the operation situation of the equipment via
primary observation so as to determiine the keypoints of maintenance activity and to increase
lube oil temperature and decrease its viscosity.
Verify operating parameters of the unit by PC controller for comparision with data after
maintenance;
Shutdown procedure: close outlet valve, cut off the power supply of the unit and push
emergency shutdown button;
Open manual blowdown valve, vent down the pressure of the primary pipe; verify pressure of
entire unit and close the waterinlet/outlet valve.
Site preparation: level C maintenance will break down all system parts except main machines
and replace all oil. Therefore, the worinf area should be treated to avoid pollution and be good
to clean site.
7.4. 2 Dismantling of unit system parts:
Turn loose by wrench the oil drain hole screws of the oil and gas bucket, oil filter seat, mian
primary pipe,oil cooler, oil cut-off valve and gear box; when completely empty lube oil and vent
the oil cutoff valve and main primary pipe, plain screw driver should be used to drive clockwise
the machine from the motor rod wheel to ensure lube oil in the main machine and gear box is
completely drained out. Waste oil should be treated intensively to avoid pollutions.
Manually take off the set screws (8) at the ends of main primary pipe between the oil and gas
bucket cap and cooler; check two sides of the sealing ring and store them caerfully.
Remove by wrench the connecting hoses of pressure difference transmitter, drain pipe, main
control hoses, oil return hoses, main oil return pipe and HP oil pipe before and after cooler.
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 227 -
Rev. : A
Remove by wrench the set screws (6) of the minimum pressure valve and remove minimum
pressure valve and lower check valve.
Remove set screws on the oil separator cap with wrench, after remove all screws, tighten
screws on the cap side and completely separate the cap from the oil and gas bucket and turn it
in clockwise direction to the final position. Take out oil content element and upper/lower sealing
rings and well store them.
Loose set screws (4) of the oil pressure ontrol valve+temperature control valve with allen
wrench to take off oil pressure regulator; then take pout the disc of temperature control valve
and well store them.
Remove oil filter(3) with chain wrench.
Remove set screws (8)oil cut valve with wrench, and take off oil cut off valve assembly(2).
Remove set screws (8) of air inlet valve wrench and take off air inlet valve assembly(2).
Loose holding screws (2) of the air filter and take out air filter element(2).
7.4.3 Dismantling of minimum pressure valve, oil cutoff valve, air inlet valve and oil pressure
regulator
1. Dismantle minimum pressure valve assembly: loose set screws of the minimum pressure
valve cap, and take out reset spring; slightly knock the piston from outside to inside to let it
fall down automatically. Pry out sealing ring with plain screw driver. Remove set screws (3 )
of the check valve packing seal and take off packing seal and triangle gasket. All parts
should be well stored
Dismantle oil cutoff valve assembly: remove inner snap ring with inner snap ring pliers. Take out
piston and reset spring. Remove set screws (4) of the lower end cover with wrench and take
off the end cover. Take out piston. All parts should be well stored.
Dismantle oil pressure valve regulator assembly: loose the seat and set screws of the oil
pressure regulator with allen wrench to take out piston
Dismantle air inlet valve assembly: remove set screws (4) of the end cover of air inlet valve with
wrench to take out reset spring. Knovk the piston from outside to inside until it drops naturally
pry out the sealing ring of piston and take out the snap ring of the end cover of load controlling
valve with inner snap ring pliers. Clamp the end of the end cover with lock wrench. Pull out
end cover by slightly turning it. Then take out reset spring. Pull out load controlling piston with
vise.
Dismantling of all parts are completed up till now.
7.4.4 Check, verify, repair, replace system parts
In turn check sealing ring of parts.
In turn check operation of pistons of parts.
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 228 -
Rev. : A
In turn check abrasion of wearing auxiliary parts.
In turn check aging of all hoses
Verify the above check activities. Replace the entire maintenance package containing parts
needed to be replaced and record the results.
7.4.5 washaftercooler:
Remove holding screws of the water inlet and outlet chuck of the aftercooler with wrench. Take
out chuck. Lift the entire aftercooler to a specified location.
Marinate the water pipes and oil pipes with scale washing agent and carbon washing agent for
6 hours, nd flush with clean water. Determine whether to marinate the pipe based on the
washing result.
7.4.6 Check sensors
Check all wire connecting terminals inside the electric cabinet and the strength of the
connecting wires.
Check ablation of main contactor.
7.4.7 Recover
Recover chucks of cooler and water pipe.
Recover the system parts according to the turns of parts, assembly and system which is
opposite to the dismantling of the system
7.4.8 Startup commissioning:
Check and verify all hosesconnection, tightness of all holding screws;
Open outlet valve to test pressure; the minimum pressure valve is free of leakage;
Open cooling water valve and no leakage is detected;
All screws of the oil drain holes, fill cooling oil to the specified level and then tighten the oil filling
screw;
The unit and reset all maintenance parameters;
Unit without abnormal condition; load the unit without abnormal condition;
Unit, fill oil to the level of oil filling port and tighten the oil filling screw;
The unit and load; verify all operataing parameters meet the requirements
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 229 -
Rev. : A
8 Oil Free Screw Air Compressor
8.1 Technical Specifications
To supply clean compressed air, the motors supply no lubrication and cooling to the
compressing part of the main rotor. The motors adopt two stage compressions, two stage
cooling and two stage gas water separation to lower the work temperature to an acceptable
level. The rotors are made of special materials with advanced technology to lower the motor
load. All the above is to make the air compressor adapt to harsh work conditions. However, the
parts with no compressed air contact, including gear box and bearings, are still oil lubricated
and cooled.
8.2 Oil Free Screw Air Compressor Configuration
The compressor consists of driving system, two stage air intake valve, low pressure motor,
high pressure motor, gas water separator, cooling system, lubrication system and electronic
control system.
As the compressor has twin motors, the driving system and working principle is different
from those with single motor.
When the compressor starts, it drives the specialized gear box through coupling, which at
the same time drives the twin motors and oil pump to pump the oil from the gear box. In order to
prevent oil leak to the rotor from the motor casing when the pressure is high, the oil system has
a by-pass valve, which opens automatically to release the pressure. When the compressor
reaches the nominal speed, the solenoid valve is triggered. The primary airintake valve
gradually opens under the system pressure to start the primary motor. The primary motor works
and the compressed air enters the middle cooler. With pressure increasing, the high pressure
air overpowers pressure relief valve to completely open the airintake valve, followed by
pressure increase and primary gas water separator to enter the secondary air intake valve
silencer to open the minimum pressure valve to go to the secondary motor for further
compression. The high temperature and pressure gas is supplied after secondary oil gas
separator and cooling. When the secondary pressure reaches relief pressure, the loading
solenoid valve is cut off and turned off to release the valve and the pressure is released with
primary airintake valve closed and secondary airintake valve returned, the motor starts
unloading. Simultaneously, the oil from the oil pump is supplied to the dual motors and gears
after filtering and the oil returned is collected by the gear box after oil cooler and the balanced
between the oil and the atmosphere is maintained through breather.
If the unloading is too long, the controller will stop the compressor until the pressure drops
to loading pressure to initiate another cycle.
8.3 Maintenance and Service
1. It shall be carried out by professionals.
2. Daily monitors the operational parameters.
3. Weekly cleans the motors.
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 230 -
Rev. : A
4. Monthly monitoring of the oil consumption.
5. Cleans or replaces the air filter and oil filter every 2000 hours.
6. Cleans middle cooler, rear cooler, oil cooler, oil breather, gas oil separator every 4000
hours and carry out motor lubrication.
7. Replaces lubrication oil every 8000 hours.
8. Overhual the motors every 16000 to 20000 hours.
Content:
1) Above 1 to 7.
2) Examine and replace main motor bearings.
3) Examine and replace motor bearings of fan.
4) Replace gear box bearing.
5) Observe oil pump and by pass valve.
6) Examine main motor.
8.4 Commissioning
1. Check all the pipes are well connected, nuts tightened.
2. Open the outlet valve to test the pressure and make sure there is no leakage from the
minimum pressure valve.
3. Power supply to the motors and reset all the service parameters;
4. Start the compressor with no abnormities noticed and loading goes well;
5. Restart the compressor and load to ensure all the parameters are in compliance to the
requirements.
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 231 -
Rev. : A
9 Refrigerated Air Dryer
9.1 RSL Type Refrigerated Air Dryer Technical Specifications
9.1.1 Working Principle Description
RSL Type refrigerated air dryer lowers the air temperature so that the water vapor in the
compressed air become over-saturated and turns into water droplets, which will be separated
and discharged, so that the compressed air can be dried. The dew point of the compressed air
in the RSL dryer can be lowered to 2~10 under pressure.
RSL Type refrigerated air dryer product is as a result of several new technical innovations
and patents, characterized by its stability, efficiency, cost-effectiveness and automation.
9.1.2 Refer to Figure 1 for the work procedure of the refrigerated air dryer.
Y
S
3
PT PT
Y
S
1
YS2
R
S1
R3
Y
S
1
R
KP15
12
5
6
8
3
2
10
9
11
1
R5
DN15
DN15
T
R5
T
T
T
YS2
D
N
1
5
D
N
1
5
X1
7
D2
4
D1
Figure 1 Work Principle of the Refrigerated Air Dryer
1. Pre-cooler 2. Evaporator
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 232 -
Rev. : A
3. Cyclone Separator 4 Automatic Water Capacity Adjustment Valve Discharge
Equipment
5. Refrigeration Compressor 6. Condenser
7. Water Regulating Valve 8. Drying and Filtering Device
9. Stop Valve 10. Expansion Valve
11. Capacity Adjustment Valve 12. High/Low Pressure Controller
9.1.3 Process Description
Air Compression
1. Air compression consists of pre cooler, evaporator, cyclone separator, and automatic
water discharge equipment.
2. The humid compressed air from the air compressor enters the pre cooler of the
refrigerated air dryer, where it conducts heat exchange with the low temperature
compressed air from the cyclone separator and becomes cooler. As a result, it is
condensed due to over saturation together with oil and dust particles.
3. The pre-cooled compressed air enters the evaporator to carry out a further strong heat
exchange, when the temperature is dramatically dropped to the dew point to produce
large quantity of water, which will then be drained together with that in the pre cooler
by the automatic water discharge system.
4. Then, the low temperature compressed air enters the cyclone separator, where the
condensed water particles is separated by enforced cyclone and discharged. By now,
the compressed air reaches the drying requirements.
5. The dried low temperature compressed air returns to the pre cooler to heat exchange
with the humid high temperature air, which is then to be conveyed downstream for
use.
Refrigeration System
1. The refrigeration system mainly consists of air compressor, condenser, expansion
valve and evaporator with other auxiliary parts.
2. The refrigerant is compressed by the refrigeration compressor into high temperature
and pressure gas and output into condenser, where it is cooled into liquid with normal
temperature and pressure. Then it goes to expansion valve and expands and changes
into low temperature and pressure gas liquid mixture and enters the evaporator to
heat exchange with the compressed air. The refrigerant mixture absorbs the heat from
the incoming compressed air and evaporates and is sucked into the refrigeration
compressor to reinitiate the cycle.
3. The hot air bypass valve is to control the amount of refrigerant to be recycled based on
the load change of the compressed air so that refrigeration system matches to the
load of the compressed air to ensure the quality of the air. The valve requires manual
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 233 -
Rev. : A
adjustment when the load varies greatly.
4. The high/low pressure controller is to ensure the refrigeration compressor work within
the specified scope. The condensation controller is to ensure the condensation
pressure not lower than specifications. Both the scope and the condensation pressure
have been factory pre-set.
5. The drying and filtering device plays the role of cleaner, to remove the water,
impurities, and acid matters in the refrigerant.
6. The water regulating valve is to control the water supply based on the primary
pressure of the refrigeration compressor to maintain the normal condensation
pressure. The valve requires manual adjustment when the compressed air load varies
greatly or the temperature and pressure of the cooling water varies dramatically.
7. Refrigerant valve is to fill in refrigerant when the dryer is being assembled or serviced.
8. The solenoid valve is to cut off the high and low pressure parts of the refrigeration
system when the dryer stops, so a balance between them can be gradually achieved.
9. The stop valve is for maintenance and service.
9.2 Maintenance and Service
9.2.1 Principles
1. The dryer has to be enlisted for company assets management, and the maintenance,
service and operation log regulations need to be set up based on the characteristics of
the dryer and to be strictly implemented.
2. The operation, maintenance and service of the dryer shall be conducted by trained
personnel.
3. The dryer in operation needs to be checked regularly, every 1 to 2 hours, and logged.
9.2.2 Content
1. Periodically check the conditions of the dryer to ensure the its good performance.
Recommended once weekly.
2. Cleans the automatic water discharge system periodically to remove the accumulated
oil and impurities that might affect its normal operation. Recommended once weekly.
3. Clean the blades of the fan condenser once every two weeks to remove the dust and
impurities. The procedures is as follows as indicated:
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 234 -
Rev. : A
Note: Care shall be taken in operation not to damage the blades and heat exchanger. Striking
from hard objects is prohibited.
9.2.3 RSL Air Dryer Troubleshooting
Table 5 Air Dryer Troubleshooting
Conditions Possible Causes Solutions
Power supply or power fault Check the power switch or the lines
low voltage
Check voltage to make sure it complies
with requirement
Loose power connection to
the electronic control
system
Reconnection
Electric trip
Check the breaker and thermorelay and
reset. Also examine the voltage and
power lines
Delayed start after high/low
pressure protection initiates
Wait after the delay to start
Refrigeration compressor
damage
*replace compressor
Refrigerant leakage
*Check, and repair the refrigeration
system and refill in refrigerant
The dryer
does not
start.
Refrigeration compressor
start up capacitor damage
Replace capacitor
Clogged water drain system Clean, repair or replace
Installation error in automatic
water drain system
Reinstallation
Humid air
from the
dryer outlet
Air by-pass valve not turned
off
Turn off the by-pass valve
Condenser cleaning of the air-cooled air dryer
IN OUT
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 235 -
Rev. : A
Conditions Possible Causes Solutions
The air dryer does not work Check the air dryer system
The front service valve of the
automatic drain system is not
turned on
Turn on the front service valve
Refrigeration system faulty *Check or repair the refrigeration system
Poor condensation capacity Clean or dust condenser
Air compressor
overload(exceed the rated
capacity)
Reduce the capacity or replace air dryer
Compressed airintake
temperature too high
Lower airintake temperature or replace air
dryer
Compressed airintake
pressure too low
Increase airintake pressure or replace air
dryer
Cooling water temperature
too high
Lower cooling water temperature
Amount of cooling water not
enough
Adjust water regulating valve or increase
water supply
Ambient temperature too
high(Wind-cooling type)
Improve site ventilation or replace with a
water-cooling air dryer
Hot air by-pass valve opened
too wide
Reduce the opening
Heat expansion valve
opened too small
*Increase the heat expansion valve
Refrigerant not enough *Add refrigerant
Refrigerant leakage *Service the refrigeration system
Abnormal
dewpoint
Clogged drying and filtering
device
*Replacement
Clogged or damaged Cleaning or replacing
Service valve not open Open service valve
Float Type
Automatic
Water
Discharge
system
faulty
Installation error Reinstall
Solenoid valve no power Check the cables to supply power
Solenoid coil burnt Replace solenoid coil
Electronic
Automatic
Discharge
System
Faulty
Clogged valve Cleaning
Air Dryer
Poor condensation Clean condenser
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 236 -
Rev. : A
Conditions Possible Causes Solutions
Air dryer overload
Check whether the flowrate, temperature
and pressure of the compressed air are
within the rated values
Cooling water too hot Lower the temperature of cooling water
Cooling water not enough
Adjust water regulating valve to increase
water
Ambient temperature too
high(air cooling type air
dryer)
Improve ventilation or replace with water
cooling type air dryer
Condensation motor faulty *replace motor
Clogged cooling system
*Check the drying and filtering device and
heat expansion valve, either replace or
repair
Thermo-sensor of the heat
expansion valve faulty
*Replace the expansion valve
stops after
operation or
frequently
trips during
operation
Air existing in the
refrigeration system
*Re-vacuumize and refill in the refrigerant
The voltage exceeds the
rated voltage scope
Check the power voltage
Electronic
protective
switch
tripping
Refrigeration compressor
overloaded
Adjust the air drying system
Poor condensation Clean the condenser
The air dryer overloaded
Check whether the flowrate, temperature,
temperature and pressure of the
compressed air are within the rated scope
Cooling water too hot Lower cooling water temperature
Cooling water not enough
Adjust water regulating valve and increase
water amount
Ambient temperature too
high(air-cooling type air
dryer)
Improve ventilation or replace with water
cooling type air dryer
Refrigeratio
n
compressor
temperature
too high
Refrigerant too little Fill in refrigerant
Frost at the
surface of
refrigeration
compressor
The air dryer was less
loaded
Adjust hot gas by-pass valve or adjust
water regulating valve or to adjust the load
of the air dryer
The air inlet and outlet
valves are not fully open
Fully open the valves
Pressure
difference
too high
between the
air inlet and
The amount of compressed
air exceeds the rated amount
Reduce compressed air amount
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 237 -
Rev. : A
Conditions Possible Causes Solutions
air outlet of
the air dryer
Evaporator clogged by ice Adjust refrigeration system
Note: the items with asteroid means they shall be handled by professionals by the
equipment supplier.
Warning: Specified procedures have to be followed in case of faults to prevent further
damage.
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 238 -
Rev. : A
10 Gasification Blower
10.1 Technical Specifications
Type of the blower: SRD-100; Intake flow rate: 11.7m
3
/min; Inlet pressure : 101.3Kpaoutlet
pressure: 199.3Kpa; rotation speed: 1450rpm; motor type: Y225S-4; power: 37KW
10.1.1 Working Principle
SRD-100 Roots blower is a volume type power machine with two impellers rotating in
opposite directions driven by a pair of synchronized gears. Through the two impellers gearing
with each other (clearance between impellers without contact), the inlet and the primary outlet
is divided and the air is transferred to the primary outlet without compression. The air when
reaching the primary outlet is compressed to transfer to the system due to the compressed air
at the outlet side.
Work Principle Illustration
Chinese English
Inlet
Exhaust
10.1.2 Motor Configuration Diagram
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 239 -
Rev. : A
10.1.2.1 Casing and walling
The casing and walling of the blower is an integrated structure made of high strength cast
iron and the casing is horizontal with external side strengthened with bars.
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 240 -
Rev. : A
The walling (with side plates) is installed at both sides of the casing. The side plates
functions to position the walling, and with walling and casing together, they form a sealed
cylinder.
10.1.2.2 Impellers
The impellers are made of quality cast iron with cycloidal profile. The top of the impellers
have wide arch boss, made by specialized lathe. The impellers are fitted to the shaft using heat
expansion methods and through dynamic poise to reach an accuracy of G5.6 in the balance.
10.1.2.3 Gears
Gears are one of the most important parts in roots blower, made of quality chrome
molybdenum steel, and ground by grinder after carburizing and quenching, with a grade 5 in
GB10095.2-2001.
The gears have wide tooth width with good meshing inside the gear box. The deviation
caused by wear can be eliminated by the adjustable gear. Please note that the adjustable gear
and the hub shall not be separated when dismantling but not in adjustment.
10.1.2.4 Bearings
All bearings are E grade with 4 bearings installed on the bearing seat of the walling, among
which the inlet side two bearings performs the role of adjustment and fixing the axial clearance
of impellers.
10.1.2.5 Shaft Sealing
The sealing of the shaft adopts labyrinth seal and at the bottom of the 4 bearing seats is
fixed with V type seal to further separate the oil and gas. In the shaft gland, the seal adopts
rubber structure to prevent oil leakage and dust.
10.1.2.6 Lubrication
The lubrication of the blower integrates splash lubrication and forced circulation lubrication.
The gear box and oil box have all got oil gauge with the correct oil level indicated when the
machine is not operation. In operation, the oil level shall be within the correct level. If the oil
level is too high, the temperature might rise and if too low, the lubrication is not good.
If the blower is used for general purpose, the lubrication oil is mineral oil, such as machine
oil, gear oil, hydraulic oil, or anti-rust turbine oil. There shall be no water, carbonate, resin or bar
contained in the oil. The oil volume in the gear box shall be 2.4 L and in the standby oil box 1.1
L.
10.1.2.7 Cooling system
Cooling water rate: 8~10l/min; Water pressure: 196~294kPa; Inlet water temperature:
Less than 33 .
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 241 -
Rev. : A
10.2 Maintenance and service of the blower can be as per the table below.
No. Period
of
Inspection
Items
Before
Operation
Daily
Three
Months
Annually
Two
Years
Four
Years
Remark
1 Clean the
foreign
objects in the
piping
2 Check every
connection
part
Blower,
piping
3 Valve
operation
4 Inverted
Valve
operation
5 Electric circuit
6 Gear oil
volume
Oil gauge
7 Oil leakage
8 Rotation
direction
As indicated
9 Pressure Pressure
gauge,
vacuum
gauge
10 Safety Valve
11 Current and
Voltage
Ammeter,
Voltmeter
12 Flowrate
13 Noise Gear
abnormal
noise, rotor
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 242 -
Rev. : A
collision
noise
14 Vibration
15 Temperature Ambient,
blower, and
motor
16 Tension and
wear of
V-belt
Adjust if
loose and
replace if
worn
17 Gear and
bearing
operation
Beware of
abnormal
noise
18 Gear oil
replacement
Replace
all(first
replacement
after 500
operation
hours)
19 V-belt
replacement
20 Filter cleaning
21 Oil seal
replacement
22 Rotor and
casing inside
cleaning
23 Gear
checking
10.2.1 Dismantling
1.1 Cautions
1. All the connections and couplings shall be marked.
2. No damage shall be done to the parts especially to the joint surface.
3. All gaskets shall be measured when dismantling.
4. The parts after dismantling shall be kept dust free.
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 243 -
Rev. : A
5. Appropriate dismantling tools shall be used.
1.2 Dismantling Procedure
All the accessories dismantled; discharge the oil in the gear box and standby oil box;
dismantle the wheel; dismantle standby oil box; dismantle gear box and gears; dismantle
walling.
NOTE: In the operation, care shall be taken to protect the seal and bearing internals.
10.2.2 Assembling
2.1 Cautions
1. Check whether the dismantled parts are damaged. Care shall be taken to the joint
surface. When there is damage, repair it or replace.
2. The bearing shall be cleaned first, then greased. When installing, the tools and hand
shall be cleaned first.
3. The joint surface shall be cleaned first before greasing.
4. In case of damage of sealant, then the gasket with the same thickness and quality
material shall be used.
2.2 Assembling Procedure
1. Install the walling (with side plates) of the motor side to the casing.
2. Install the impellers from the gear side.
3. Install walling (with side plates) at the gear side to the casing. Care shall be taken to
the axial clearance. When there is not enough, then, a casing seal can be chosen.
4. Assemble the seal jacket, V shape seal, bearing seat and front and rear bearings. Use
the bearing seat gasket to control the axial clearance.
5. Assemble gears. On both sides of the key sprayed molybdenum disulfide (not on the
gearing face), use the adjustable gear to adjust the impellers and then tighten them
with locknuts.
6. Assemble gear box.
7. Assemble standby oil box. If necessary, the location pin for the standby oil box and
walling shall be remade and implemented.
8. Assemble the wheel and other accessories.
2.3 Clearance Adjustment
The key to the blower assembling is to ensure the working clearance within the specified
scope so its quality and performance is guaranteed. The clearance scope is as follows:
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 244 -
Rev. : A
Clearance as illustrated
Blower Clearance(Reference Value) Unit of Measurement: mm
impellers-casing Impeller-Impeller
Impeller-Front
wall
Impeller-Rear
Wall
Value
Type
a(a1,a2,a3) b(b1,b2) c d
SRD-100 0.16~0.45 0.15~0.27 0.20~0.25 0.20~0.25
1. The adjustment of the casing-impeller clearance(a1,a2,a3) is guaranteed by the
accuracy of the joint accuracy of the casing and walling. No damage shall be done to
the casing and walling.
2. The adjustment of the impeller-impeller clearance (b1,b2): rotate the impellers to the
position as indicated in c. Make sure the driven gear is aligned to the driving gear and
mark it on the shaft. Then install according to order of the gear retaining ring, retaining
gasket, locknut and slightly tighten the nut. Loosen the gear ring to tighten the bolts
and adjust the ring so the impeller-impeller clearance is within the scope. Then tighten
the bolts.
3. The adjustment of the impeller-side walling axial clearance(cd): before installing the
walling, the axial total clearance C+D (through the adjustment of the casing
gasket)need to be ensured. Then through the adjustment of the front bearing gasket to
ensure the c and d distribution.
2.4 Installation of the Transmission Parts
!
Warning: Use appropriate tools to install the wheel on the shaft and motor.
Hammer is prohibited when installing the wheel or coupling.
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 245 -
Rev. : A
2.4.1 Belt Installation
The belt for the blower is narrow V shaped belt. The correction installation of the wheel and
belt will directly affect the life span of the belt and the equipment performance. Following items
needs to be taken care of:
1. Before belt installation, loosen the motor tightening bolts and track adjustable screw to
shorten the central distance. No prying force shall be used.
2. The belt and grooves shall be free from impurities.
3. In consideration of the preliminary elongation rate, after adjustment, the blower can be
operated for 2 hours to ensure the tension. The tension is to ensure no slipping and no
tightness. The tension can be measured by the sagging distance when there is a
weight. Refer to the following illustration.
The fixed force W vertically works onto the central of the belt, when the sagging satisfies
S=0.016a (mm), it indicates the tension is proper. The W is valued in the scope 76.4~101.9N,
with median value as the appropriate.
!
Warning: If the belt is too tight, the lifespan of the belt and bearing will be
shortened. If too loose, slipping and vibration will be caused.
4. Use ruler or lines to check the position of the wheels. As the following diagram
indicates, the axial lines shall be parallel after adjustment. The symmetrical plane of
the corresponding grooves shall be overlapped, with deviation of 20l1.6a/1000.
5. After adjustment, the coupling bolts and track adjustable screw must have been
tightened.
6. When replacing belt, belts of the same specifications must be used and old and new
ones shall not be mixed. Upon wheel replacement, the wheel shall be the same as the
previous specifications.
7. Loosen the belts if they are not used for a long time.
!
Warning: In order to ensure safety and security, belt hood shall be installed.
2.5 Safety Valve and Check Valve
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 246 -
Rev. : A
2.5.1 Introduction
1. Cautions
1) The safety valve for the blower is metal sealing type with the seat and core
assembled together after grinding; therefore, it is not affected by ambient humidity
and temperature. If there are foreign objects attached to the seat, when the core
works, it will go to the contact surface, causing leakage. In addition, when moving
the valves, it shall be handled carefully as collision will cause leakage.
2) The safety valve must be installed on an horizontal pipe through a tee to ensure
the axis of it is vertical to the ground.
3) During operation, if the sensitivity of the safety valve is lowered, then it means
immediate cleaning to the valve seat and core. The method is to remove the cap
and spring and use diesel or petrol to clean it. (The following diagram indicates
the structure of the valve.)
A27TW-2Q SVF Type Safety Valve(Thread Type)
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 247 -
Rev. : A
1. Adjusting Bolt 2. Locknut 3. Cap 4. Valve seat
4) All the parts shall be periodically cleaned in order to ensure the life span and its
sensitivity.
2. Principle: When the load exceeds the set pressure of the safety valve, the valve opens
to prevent blower faults.
!
Warning: When the blower is in operation, do not stay around the primary hole of
the safety valve to prevent getting burnt.
2.5.2 Check valve
The check valve has to be installed onto a horizontal pipe. During installation, the valve
rotation shaft shall be horizontal and pay attention to the flow direction (refer to the diagram
below).
H74W-1C Type Check Valve
Reminder: There shall be plenty of space to ensure the opening and closing of the
valve.
2.6 Troubleshooting
Troubleshooting Table
Faults Causes Solutions
Insufficient air
volume
1. piping leakage
2.Clearance increase
3.inlet clogged
4.belt slipping
1.Check the connections and repair if
there are leakages
2. Adjust gap or replace rotor
3.clean filter
4. Adjust the tension or replace belt.
Motor
overload
1. Inlet resistance too much
2. Pressure increase enlarged
3. Friction between the cylinder and
impellers
4. Speed too high
1.Clean filter
2. Check primary pressure and load
3. Adjust clearance
4. Replace belt wheels
Overheating
1. Pressure increase enlarged
2. Friction between the cylinder and
blades
1. Check the inlet and primary pressure
and load
2. Adjust clearance
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 248 -
Rev. : A
Faults Causes Solutions
3. Lubricants too much or too less
4. Lubricant oil quality not good
3. Check the oil gauge
4. Replace oil
Noise
1. Mislocation of the synchronized
gears and rotors
2.Bearings worn
3.Pressure rise fluctuate widely
4.Gears damaged
5.Safety valve closes and restarts
automatically
5. Check valve damaged
1.Correct the position and get them
tightened.
2.Replace bearing
3.Check the piping and load
4.Replace gears
5.Check whether there is pressure
overload or adjust the safety valve
6.replace check valve
Refuse to
start
1.Primary outlet clogged or valve
refuses to open
2. Power connection wrong or other
electric problems
1. Remove the blockage or open the
valve
2. Check the connection or other
electrics
Lubricant
leakage
1. Oil level too high
2. Seal damaged
1. Lower the oil level
2. Replace seal
Vibration
1. Foundation unfixed
2. Bearing worn
1. Fix the foundation
2. Replace bearing
Reminder: Refer to the manual provided by the motor manufacture for the maintenance
and service of the motor.
10.3 Main Parts and Consumables
10.3.1 List of Main Parts
10.3.1.1 Main Parts List
Driving Impeller
Driven Impeller Sealing Jacket
Name
Type
No. Qty No. Qty No.
Qty
SRD-100 SRD100.1.1 1 SRD100.1.2 1
RD.1-17( )
ARD.1-17( )
2
2
Side Plates Bearing Gear Components
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 249 -
Rev. : A
Name
Type
No. Qty No. Qty No. Qty
SRD-100 RD.1-04 4
NU311/P6
21312
2
2
RD.1-05
RD.1-07
RD.1-08
1
1
1
10.3.2 Consumables
No. Name No. Qty
1 Lock washer 45 GB858-88 2
2 Lock washer 60 GB858-88 2
3 Locknut M45X1.5 RD.1-29 2
4 Round nut M60X2 GB812-88 2
5 Front bearing seat seal gasket RD.1-49 2 sets
6 Rear bearing seat seal gasket RD.1-48 2
7 Casing seal gasket RD.1-40 2
8 Oil box seal gasket RD.1-41 2
9 Structure oil seal B55X78X12 GB9877.1-88 2
10 V belt(with coupling) 5V-1000 3
11
V shaped rubber oil retaining
ring 72X90X5 T08.1 4
12 O ring 55X3.1 GB1235-76 1
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 250 -
Rev. : A
11 Slag Removal System
11.1 Slag Hopper Maintenance and Service
11.1.1 Slag Hopper and Slag Gate Structure
The slag hopper is to temporarily store the furnace slag. The slag from the furnace falls
into the hopper and releases great amount of heat and explodes to many small pieces to
get stored in the hopper. After a period of time, the slag will be flushed out of the hopper by
water through the slag gate and crusher. The water level in the hopper has to be
maintained; therefore there are two 6 inch water inlet pipe and drain pipe in the hopper.
The structure of the hopper is bottom support. The up water trough is located below the
header under the water-cooling wall. The water sealing plate of the header under the
water-cooling wall is connected to the water trough to seal the furnace and ensures the
water wall expansion and contraction to maintain the stability of the water level.
Surrounded the water trough are 10 pieces of 2 inch low pressure water pipe and one
overflow pipe to ensure the water level. The 4 corners of the water trough have 4 discharge
valves which are used when the furnace is being serviced to drain the water and slag in the
water trough. The slag hopper has two halves on the left and right connecting with each
other. At the bottom, it is fitted with slag gate and slag crusher.
Slag Gate Structure
The slag gate consists of gate, seat, guiding track, wheel, wheel shaft and cylinder.
11.1.2 Slag Hopper and Maintenance and Service
Item Working Methods and Cautions Quality Standard
1.
Preparation
1. Open the drain valve to drain the water.
2. Open the slag gate manhole so it is fully
open.
3. Remove the slag on the hopper wall and turn
on the slag crusher to discharge the slag
through manhole.
Cautions: Do not damage the hopper walls
whiling removing the slag. When the slag
crusher turns on, there shall be nobody or tools
in the hopper.
2. Internal
Examination
1. Check on the concrete surface on the
internal wall of the hopper. Repair the broken
part or crack part. Remove the crack before
repair.
2. Slag hopper concrete sleeve replacement
1 Smooth concrete surface
without cracks, breakage
or arching.
2 The concrete surface
after relaying shall
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 251 -
Rev. : A
Item Working Methods and Cautions Quality Standard
shall be after complete removal of the original
concrete walling and the strengthening nails.
3. Flush the water nozzle in the slag hopper
(including observation lens nozzle) and clear
away the slag around the nozzles.
4. Clear and flush the slag in the overflow
outlet and overflow water container.
comply with the
specifications.
3 The nozzles shall be free
from blockage and
ejection distance is
normal.
4 No Slag in the water drain
outlet
3. Water
sealing
Equipment
Examination
and
Clearance
1.Use high pressure water gun to clear away
the slag accumulated in the water trough.
2. Remove the water nozzle in the trough and
turn on the flushing valve to examine and
flush the trough and nozzle and then
re-install.
3. Check the water sealing plate and the bolts
connecting the plate and water cooling walls.
Replace any warped or broken bolts.
4. Check the surface and welding seam of the
tooth shaped dam plate in the water trough
and check the slag metal mesh and the
welding seam with the fixed parts.
5. Measure the clearance between water seal
plate and the bottom of the water trough.
1. No slag, dirt or sand in the
trough. No hindrance in the
expansion of the water
cooling wall.
2. Sealing quality, no leaking
and sealing water level
constant. No blockage in the
flush pipe and nozzle in the
trough.
3. No corrosion, deformation
of the water sealing plate and
the bolts is free from
deformation or breakage.
4. No corrosion from the
tooth shaped overflow plate.
The welding is well done. The
slag metal mesh is free from
deformation, corrosion.
5. The clearance between the
water sealing plate and water
trough complies with the
design requirements.
Slag Gate Maintenance and Service
Items Procedure and Cautions Quality Standards
1.
Dismantling
1. Remove the bolts connecting the slag gate
panel and room and remove the panel.
2. Open the slag gate and to its maximum
opening and turn off the gas/hydraulic
1. The base antifriction plate
shall be worn less than 2mm.
When being replaced, the
head of the bolts shall be
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 252 -
Rev. : A
Items Procedure and Cautions Quality Standards
controller.
3. Remove the nuts for the guiding wheel and
get the wheel out and loosen the bolts for the
wheel shaft to get it out.
4. Remove O shaped ring and clean its
groove.
5. Close the slag gate and in an off position.
6. Remove the nuts between the piston rod
and slag gate and bolts between guiding rod
and slag gate. Separate the piston rod and
slag gate using gas/hydraulic controller.
Then, turn off the controller and cut the power
off.
7. Tighten the piston cylinder using steel wire
and chain lift and then remove the bolts
between the cylinder and piping and cylinder
and slag gate. Remove and separate the
cylinder and slag gate from the equipment.
Cautions: The exposed part of the piston rod
shall be packed and when being lifted, no
striking or collision.
8. Remove the slag gate wedge and put a
jack under the gate so to get the slag gate out
of the guiding track. Tighten the gate and
chain lift with metal wire and get the guiding
track removed.
9. Move the slag gate out of the base slowly
by operating the chain lift.
aligned with the surface.
2. The slag gate is smooth
and without deformation. The
wear shall be less than 30%.
3. The guiding track is
smooth and free from
deformation.
4. No corrosion on the rod
surface and no deformation.
The bolts shall be free from
damage. The sealing quality
of the cylinder is good.
5. The indicating guiding rod
shall be smooth and the
indication is correct.
6. After the wheel being
reinstalled, it is still smooth.
7. After installation of the
gate, it is freely open or close
and the clearance between
the gate and the track shall
be smaller than 0.8mm.
8. The room and the panel
joint surface is smooth. When
the panel is closed, there
shall be no leakage.
2. Installation
1. Clean the slag gate with clean water and
check the surface or use clean water to clean
the gate base and anti-friction plate. If the
friction is too much, replace the plate.
2. Replace those deformed seriously.
3. Clean the gate frame and track with clean
water and check the smoothness of the track.
Replace if deformed and then install it on the
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 253 -
Rev. : A
Items Procedure and Cautions Quality Standards
frame and tighten with bolts.
4. Lift the gate to the frame and install it
based on the guiding track and put back the
positioning wedge.
5. Clean the threads of the piston rod with
diesel and check the threads. For minor
defects such as burr, use file to correct and
try with a nut. Replace with a new piston rod if
threads are damaged. The seal for the rod
shall also be replaced.
6. Lift the cylinder to the gate and get
connected. Caution: During the installation,
the piston rod shall be backed with the
exposed part and threads protected.
7. Reconnect the controlling piping and turn
on the gas/hydraulic controller to get the rod
and gate connected and fixed with nuts. Then
connect the gate with indication rod and
adjust the rod to a close position.
8. Open the gas/hydraulic controller so that
the gate opens fully and adjust the indication
rod correspondingly and adjust the indication
section so that it is correct.
9. Clean the guiding shaft and base with
diesel and replace O shaped ring and then
guide the eccentric part of the shaft to the
hole and tighten with bolt and put the sleeve
on and tighten with nuts. Note: Grease the
wheel and shaft before installation.
10. Turn the gas/hydraulic controller so that
the gate is located in an off position and use a
jack to jack the gate to the top of the frame.
Caution: Do not overuse force. Measure the
clearance between the slag gate and frame.
Before adjustment, the bolt shall be loosened
and rotate the shaft so that the guiding wheel
and the gate wedge is well contacted. Then
tighten the bolt and get the jack out. Measure
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 254 -
Rev. : A
Items Procedure and Cautions Quality Standards
again the gap and turn on the controller to
move the gate till it can move freely.
11. Use blade to clean the remnant on the
joint between the panel and slag room and
then close the panel.
11.2 Slag Crusher Maintenance and Service
Item Procedure and Cautions Quality Standard
1. Dismantling
1. Cut the motor power off.
2. Remove the bolts on the coupling hood and
remove the hood and the bolts on the couplings.
3. Remove the chain guard bolts and the guard
and remove the chain pin to get the chain off and
into the diesel.
4. Remove the shaft seal water pipe and water
outlet of the slag crusher.
5. Remove the connecting flange bolts between
the casing and the bottom of the slag hopper.
6. Heat the gears and chain wheels and remove
the gears and chain wheels with a puller.
Caution: before dismantling chain wheels, first
use steel wire to connect them to the moving
crane and tighten the wire a bit. When heating, it
shall be done evenly.
7. Remove the bearing seat at both sides of the
roller and use flame to heat the bearings internal
rings respectively and separate the bearing with
the roller.
Caution: Heating the rings evenly.
8. Remove the shaft seal filler cover bolts and
remove the cove and the filler.
9. Remove the bolts on the side plates of the
casing and remove the anti-friction ring and
separate the casing and side plates.
10. Lift the roller onto a wood and heat the sleeve
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 255 -
Rev. : A
Item Procedure and Cautions Quality Standard
and separate the sleeve from the roller with a
puller.
2. Service parts
1. Clean the chain wheel and gears in diesel and
check the gearing face. Use sand paper to grind
the shaft hole and chain grooves.
Caution: Grease the sand paper first before
application.
2. Use diesel to clean the bearing seat and
bearings. Check the joint of the seat and bearing.
Check the internal and external rings and rollers
of the bearings. Measure the bearing clearance.
If too large, replace bearings.
3. Clean the shaft sleeve and bearing jacket in
diesel and check the inside and outside. Use
sand paper to grind the sleeves and jacket.
Caution: Grease the sand paper first before
application.
4. Clean the casing and anti-friction ring with
clean water. Replace the ring if it is damaged.
5. Clean the roller teeth with clean water and
check the gearing face.
6. Clean the roller with diesel and check the shaft
surface. Replace if damage is there.
1. The chain wheel
and gear gearing face
shall be smooth, free
from corrosion,
breakage,
deformation. The
shaft chain groove
shall be free from
burr and deformation.
2. No corrosion in the
bearing seat and no
cracks. The bearing
roller shall be no
friction and the
bearing clearance
shall be 0.08-0.1lmm.
3. The wear of the
anti-friction ring shall
be less than 50%.
4. The wear of the
roller teeth shall be
less than 7 mm.
5. The roller shaft
shall be smooth and
free from corrosion
and the chain groove
shall be free from
burr and deformation.
6. There shall be no
corrosion or friction in
the sleeves.
3. Installation
1. Put the filler cover and water retaining ring
onto the roller shaft. The bearing to be heated in
oil and put on the shaft.
2. Use blade to clean the remnant on the joint
1. The joint face
between the casing
and slag hopper is
smooth with good
sealing quality. No
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 256 -
Rev. : A
Item Procedure and Cautions Quality Standard
face between casing and slag hopper and on the
side plates and then wipe clean with blade cloth.
3. Flush the casing inside with clean water and
install the anti-friction plate.
4. Install the side plate on one side of the casing.
Caution: Sealant shall be applied to the joint
surface and bolts.
5. Fix the bottom of the bearing seat and support.
6. Lift the roller and components to the casing
and install the other side plate.
7. Rotate the shaft so that the axial teeth of one
roller is located in the middle of that of another.
8. Heat the driving gear of the roller into the oil to
get heated and then put into the shaft and get to
the gearing location. The gear installation shall
be according to diagram 7-4.
Caution: When reinstalling the gears, the relative
position of the two shafts shall be temporarily
fixed.
9. Use a tommy bar to move the roller so that it is
in the middle of the casing.
10. Loosen the bolts between the bearing seat
and support, and add a gasket to the bearing seat
and support till the two shafts can rotate freely.
Then use filler gauge to measure the clearance
between the sleeve and casing shaft bore. If the
clearance is bigger than 0.05mm, then readjust
the gasket till it is smaller and ensure the shafts
can rotate freely.
11.Install the bearing seat position pin and
tighten the bottom position bolts of the bearing
seat and grease the bearing seat and install the
bearing seat cover.
Caution: Use blade cloth to clean the bearings
and the bearing seat before the cover is put on.
impurities in the
casing.
2. Good sealing
quality of the casing.
3. Installation tension
for the gear and chain
wheel is 0-O. 03mm.
4. Even clearance
between the roller
shaft and the side
plates. The roller
shaft could rotate
flexibly.
5. The shaft has good
shaft seal quality.
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 257 -
Rev. : A
Item Procedure and Cautions Quality Standard
12. Install the shaft seal filler, cover and water
retaining ring.
Caution: During the installation of the filler, the
filler direction shall be 90 degrees from each
other.
13. Use sand paper to grind the shaft gland
groove and key at the chain wheel side and then
heat the chain wheel shaft bore. Strike the chain
wheel with copper bar as cushion so that the
wheel goes to shaft and to the shaft shoulder.
Install the chain wheel position pin.
14. Move the slag crusher to under the slag
hopper and like the slag hopper and the crusher
with bolts, tightened.
Caution: The joint flange bolts between the
crusher and the slag hopper shall be applied
sealant.
4. Disintegrate the
reducer
1. Remove the bolts between the reducer and
coupling and bolts at the bottom of the reducer
2. Heat with a flame the wheel of the small chain
wheel and remove it from the reducer with a
puller.
Caution: Before removal, mark the position on
the shaft.
3. Turn on the oil drain of the reducer to get the
lubricant out and check the quality. If too bad,
replace the lubricant.
4. Open the side cover of the reducer and remove
the oil seal. Use copper tools to strike the gear
and bearing internal ring to get it separated from
the shaft.
5. Use diesel to clean the reducer box and
transmission gear and bearing and check the
shaft surface, gearing face and bearing.
6. Use diesel to clean the small chain wheel and
1. Lubricant no
quality change, no
emulsification.
2. Gearing face no
deformation, cracks,
wear, and corrosion.
3. Transmission shaft
surface smooth with
no wear.
4. Side cover of the
reducer no cracks
and box no cracks.
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 258 -
Rev. : A
Item Procedure and Cautions Quality Standard
the shaft bore.
5. Reducer
Installation
1. Use blade cloth to clean the reducer and clean
the joint surface of the casing.
2. Put the bearing and gear into the oil to get
heated and put onto the shaft.
3. When the transmission shaft components are
put into the reducer, fix them and rotate them to
check the flexibility.
4Install the side covers.
Caution: the joint surface shall be greased.
5. Fill in lubricant till the specified level.
6. Install the chain wheel to the marked position
and tighten it using bolts.
1. Inside the reducer
is clean and dry.
2. The tension of the
internal ring of the
bearing is
0.010.03mm and
for the gear is
0.030.05mm.
6. Assembling
1. Firmly fix the reducer to the foundation
platform and restore the chain. Adjust the bottom
position bolts to adjust the parralellity and
sagging amount.
2 Connect the reducer together with the
coupling and find the coupling center.
3Install the coupler and the chain guard.
4. Install the shaft seal water pipe and slag
crusher outlet.
1. The chain
parallelism deviation
shall be less than 2
mm. The free sagging
shall be smaller than
40mm.
2. The coupling
center deviation
smaller than 0.10mm.
3. No deformation
and leakage of the
chain guard.
4. The shaft seal
water pipe has no
leakage.
11.3 Slurry Pump Maintenance and Service
11.3.1 Technical Specifications
High pressure pumps are horizontal, single impeller, suction and centrifugal pump
with double casing. The casing has replaceable internal sleeves including impeller,
sleeve, plates, pump and cover. The pump is made of ductile cast iron. The front and the
back of the impellers have back blades to reduce leakage and to improve the life span
and efficiency. The inlet of the pump is horizontal and sealed with fillers and it is
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 259 -
Rev. : A
equipped with specialized shaft seal pump to provide enough water.
The bearing is single layer heavy duty cone bearing, capable of bearing maximum
axial and horizontal load. The bearing is oil lubricated and on both sides of the bearing
box, it all has sealing covers, labyrinth sleeves and rings to prevent any invasion of
foreign materials.
11.3.2 Slurry Pump Maintenance
Items Procedures and Cautions Quality Standard
1. Service
Preparation
1. Turn off the power for the slurry pump.
2. Close the inlet and outlet valves for the
slurry pump. Close the shaft seal water inlet
valve.
Caution: As the inlet and outlet valves are
closed, inside the pump and the inlet and
outlet piping there is still water and pressure;
therefore, the piping connections shall be
loosened to drain the remaining water and
pressure and then, dismantle the outlet pipe.
3. Remove the bolts for the coupling hood and
the hood and the bolts for the couplings.
2. Dismantling 1. Remove the connecting pin between the
pump and the motor.
2. Remove the inlet and outlet piping
connectors, and then remove the flange
bolts to get the piping out.
3. Remove the pump cover bolts with a
spanner and lift the cover to a designated
place. Caution: The cover shall be placed on
top of a wood or rubber.
4. Remove the 2 position iron plates for the
pump jacket and lift the jacket out.
5. Insert a steel pipe or bar into the impeller
chamber with another end on the ground.
Use special tube on the shaft gland and turn
anti-clockwise to get the impeller out of the
shaft.
Caution: Use steel wire to connect the
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 260 -
Rev. : A
Items Procedures and Cautions Quality Standard
impeller with the traveling crane, tightened.
a. Remove the filler cover bolts and the
cover and pull out all the fillers.
6. Strike the sleeve with hammer and copper
bar so that it gradually comes out. Remove
the 4 hold-down bolts between the bearing
components and the support, and the
adjustment bolts in the axial direction. Then
remove the bearing components and water
sealing ring.
7. Remove the locknut for the bearing
components with a hook wrench and the pins
at the front and back of the cover. Use an
iron bar to pry open the cover and pull the
labyrinth sleeve and cover out.
8. Use copper bar as a cushion to strike the
pump shaft so that it retreats till the bearing
comes out from the bearing box and then
remove the pump shaft from the bearing box.
9. Use heating methods evenly heat the
bearing and lubricant retainer ring on the
pump shaft to get them out of the shaft.
10. Get the positioning wedge for the front
plate of the pump cover out and place the
cover inlet side upwards on the ground. Use
copper bar as a cushion to separate the front
cover with the pump cover. Then remove the
nuts of the rear plate and strike the bolt ends
till the rear plate separate.
11. Mark the position of the filler box on the
pump and use copper bar as a cushion to
strike the filler box cover till it gets
separated with the pump.
3. Parts
Maintenance
and Service
1. Check the degree of wear on the pressure
enlarge outlet pipe of the slurry pipe. If
serious, replace.
2. Check the wedge shaped connecting
1. The pressure enlargement
outlet pipe wear shall be
smaller than 2mm. The
wedge seal ring shall be free
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 261 -
Rev. : A
Items Procedures and Cautions Quality Standard
rubber seal ring. If worn, replace.
3. Clean the front and back plates of the
pump cover and the cover with diesel and
check the level of wear of the back plate. If
serious, replace the back plate. If there is
crack on the pump cover, replace.
4. Clean the impeller jacket and check the
degree of wear. If the wear is serious at the
internal wall ant the outlet, replace it.
5. Clean the impeller and check the blades
and its working surface and if they are worn,
replace them.
6. Use diesel to clean the shaft sleeve and
water seal ring and check their surfaces.
7. Use diesel to clean the bearing and
labyrinth seal ring and check the bearings
rollers, internal and external rings and
labyrinth ring.
8. Clean the sealing filler box with diesel and
check the circumvent surface.
9. Clean the rear pump casing and check the
surface whether there are cracks. If there
are, replace.
10. Check the center straightness of the
support trough and check the trough surface
and support.
11. Clean the pump shaft with diesel and
check the bearings, oil retaining parts and
key way. Use fine greased sand paper to
grind the shaft and key way surface. Check
the threads of the shaft gland.
12. Periodically check oil level and quality of
the liquid coupler.
from worn and deformation.
2. The wear to the front and
back plates shall be less than
5mm. There shall be no
cracks on the pump cover.
The sealing gasket shall not
be worn.
3. No serious wear on the
internal wall and the outlet of
the jacket.
4. The wear to the impeller
front diameter and the front
and rear back blades shall
not be more than 3mm. The
blades shall be free from
corrosion and cracks. The
threads of the impeller shall
be damage free.
5. The sleeve surface shall
be smooth. Replace if the
wear is more than 1mm. The
clearance between the bore
of the sleeve and shaft shall
be 0.04mm-0.06mm. The
water seal ring shall be
complete. The surface shall
be not rusted or scaled.
6.The internal and external
ring of the bearing and rollers
shall be wear free, corrosion
free and no color change.
The tension is similar. The
clearance between the
internal ring and shaft shall
be -+0.01mm. The clearance
between the external ring
and bearing seat bore is
0.06mm-0.10mm, and the
same to the bearing box
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 262 -
Rev. : A
Items Procedures and Cautions Quality Standard
bore. No damage to the
labyrinth ring.
7. The filler box shall be free
from cracks with smooth
surface.
8. The bottom pump casing
shall be free from cracks.
9.The support trough center
straightness deviation shall
be less than 0.02 mm and the
trough surface shall be
smooth and wear free. The
support shall be wear free
and crack free.
10. The pump shaft surface
shall be smooth and free
from friction. The shaft
gland threads shall be free
from damage.
4. Assembling 1. Put the filler box into the pump to the
marked position and use copper bar as a
cushion to strike till the position is correct.
2. Put the back plate seal ring into the groove
and when it is smooth, then put the back plate
on to the pump with bolts.
Caution: Bolts shall be tightened with equal
strength.
3. Use blade cloth to clean the shaft surface
and then grease the surface.
4. Check and clean the joint surface and use
steel wire to lift the pump to connection place to
get connected with bolts.
Caution: Replace the sealing gasket for the
joint surface and the surface and the bolts shall
be sprayed with sealants.
5. Connect the pressure enlarging pipe with
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 263 -
Rev. : A
Items Procedures and Cautions Quality Standard
outlet pipe using connector.
Caution: Replace the rubber gasket.
6. Connect the inlet and water pipe with flange
and tightened with bolts equally.
Caution: The sealing gasket of the joint shall
be replaced.
11.4 Dehydration Granary Maintenance and Service
11.4.1 Brief introduction
The dehydration granary is a continuous dehydration equipment for the wet slag. A set of
the dehydration equipment consists of two granaries. When one of them is filled with slag,
dehydration process will initiate. The wet slag mixture will be switched to another granary. After
dehydration, the water content in the slag will be greatly reduced and the slag will be dry and
falling apart. Then through the slag gate to fill in a tipper to be transported. The two granaries
alternate to dehydrate.
The dehydration granary is shaped cylinder like on the top and cone like at the bottom. The
top has income slag gate and at the bottom, there is outgoing slag gate. The accessories
include: vibrators, water removal elements, diffusion grids, water flushing piping, and valves.
11.4.2 Procedure and Quality Standards
Item Maintenance Quality Standard
1.
Preparation
1. Check the equipment
maintenance and service logbook.
2. Prepare all the spare parts and
tools.
3. Process a maintenance and
service pass.
1. The slag incoming gate and water
flushing valve can be closed firmly
without leakage.
2. Turn off the power for the vibrators and
slag outgoing gate.
2.
Dehydration
granary and
accessories
Maintenance
1. Check whether there are cracks
or leakage from the dehydration
granary.
2. Check whether the columns and
support for the granary are firm.
3. Check the downflow weir is
leveled.
4. Check the diffusion grid and
1. The granary is firm and free from
cracks and leakage.
2. The columns and support are reliable.
3. If the distribution grooves are worn, it
shall be repaired by welding.
4. The downflow level (tooth bottom
level) difference shall be within 2mm.
5. The water removal elements shall be
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 264 -
Rev. : A
Item Maintenance Quality Standard
distribution grooves are worn.
5. Check whether the water removal
elements are scaled or clogged.
free from scales or clogging.
3. outgoing
slag gate
maintenance
1. The maintenance for the cylinder
shall be carried out according to the
appendix.
2. Examine and replace the
inflatable seal ring.
1) Remove the side plates at the
slag outgoing gate.
2) Open the slag outgoing gate
and remove the inflatable seal ring
positioning.
3) Remove the damaged
inflatable seal ring.
4) Clean the gate seat and inflate
the new inflatable ring together with
soap water sprayed and install it.
5) Install the positioning and bolts.
6) Install the slag outgoing gate
plates and close the gate.
3. Check the wearing level of the
gate.
4. Check the rollers, roller bearings
and lubrication.
5. The clearance examination and
adjustment for the gate and gate
seat
1) Use filler gauge to check the
clearance between the gate and the
gate seat. If the clearance is not
equal, then adjust..
2) The method: Adjust the
positioning bars at the gate corners
1. Cylinder sealing Ok without leakage.
2. The inflatable work pressure between
0.3~0.5MPa.
3. Replace damaged rings and worn
rings.
4. The rollers are complete and contacts
well with the track.
5. The roller bearing is Ok with enough
lubrication.
6. The clearance between the gate and
the seat is equal with a distance between
1.5 to 4mm.
7. The slag outgoing gate works well.
8. If the wall to the slag outgoing granary
is damaged, repair or replace it.
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 265 -
Rev. : A
Item Maintenance Quality Standard
to move it upwards or downwards
and measure the clearance with
filler gauge.
4. Flushing
water valve
overhaul
1. Check the valve property to
ensure it can be closed firmly.
2. Check the lead screw, valve seat,
valve and hand wheel to see
whether there is crack or damage
3. Check the support to the piping.
Weld any broken pipes.
4. Replace valve packing gland
1. The valve is free from leakage and
works well.
2. The piping is free from clogging and
with firm support.
3. Replace or repair damaged valves.
5. Trial Run
1. Try water experiment to the
dehydration granary to check the
gate property and sealing property.
2. Clear the work site.
1. The gates work well.
2. The inflatable sealing ring works well.
3. Ensure the site is clean with
equipments clearly labeled.
11.5 Maintenance of Concentration Tank and Buffer Tank
11.5.1 Maintenance Period: As per the system overhaul.
11.5.2 Maintenance Items
1. Check the slag removal of the concentration tank.
2. Check the slag removal of the buffer tank.
11.5.3 Maintenance procedure and quality standards.
Concentration tank clearance
1. Stop the slurry pump, and slag flushing pump. Close the slag incoming gate, water
removal gate and flushing gate of the dehydration granary.
2. First, use dredge to pump the slag water of the concentration tank to the ash slurry
pond, and then with mortar pump, pump to the disposal site.
3. When the slag water is lowered to a certain level, high pressure water flushing shall be
carried out to remove the slag at the bottom.
4. When it reaches the bottom, and the dredge pump refuses to work then a diving pump
shall be used.
5. Manually clears any clogs at the bottom until the bottom is clean.
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 266 -
Rev. : A
Buffer Tank Clearance
Ditto above.
11.6 Maintenance of Pumps in the Slurry System
11.6.1 High, Medium, and Low pressure pumps
High, medium, and low pressure pumps are horizontal, single impeller, suction and
centrifugal pump with double casing. The casing has replaceable internal sleeves
including impeller, sleeve, plates, pump and cover. The pump is made of ductile cast iron.
The front and the back of the impellers has back blades to reduce leakage and to improve
the life span and efficiency. The inlet of the pump is horizontal and sealed with fillers and
it is equipped with specialized shaft seal pump to provide enough water. The
maintenance to the three pumps is similar. The following takes slurry pump for example.
11.6.1.1 High Pressure Pump Maintenance
Items Procedures and Cautions Quality Standard
1. Service
Preparation
1. Turn off the power for the slurry pump.
2. Close the inlet and outlet valves for the
slurry pump. Close the shaft seal water inlet
valve.
Caution: As the inlet and outlet valves are
closed, inside the pump and the inlet and
outlet piping there is still water and pressure;
therefore, the piping connections shall be
loosened to drain the remaining water and
pressure and then, dismantle the outlet pipe.
3. Remove the bolts for the coupling hood and
the hood and the bolts for the couplings.
2. Dismantling 1. Remove the connecting pin between the
pump and the motor.
2. Remove the inlet and outlet piping
connectors, and then remove the flange bolts
to get the piping out.
3. Remove the pump cover bolts with a
spanner and lift the cover to a designated
place. Caution: The cover shall be placed on
top of a wood or rubber.
4. Remove the 2 position iron plates for the
pump jacket and lift the jacket out.
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 267 -
Rev. : A
5. Insert a steel pipe or bar into the impeller
chamber with another end on the ground. Use
special tube on the shaft gland and turn
anti-clockwise to get the impeller out of the
shaft.
Caution: Use steel wire to connect the
impeller with the traveling crane, tightened.
a. Remove the filler cover bolts and the cover
and pull out all the fillers.
6. Strike the sleeve with hammer and copper
bar so that it gradually comes out. Remove
the 4 hold-down bolts between the bearing
components and the support, and the
adjustment bolts in the axial direction. Then
remove the bearing components and water
sealing ring.
7. Remove the locknut for the bearing
components with a hook wrench and the pins
at the front and back of the cover. Use an iron
bar to pry open the cover and pull the labyrinth
sleeve and cover out.
8. Use copper bar as a cushion to strike the
pump shaft so that it retreats till the bearing
comes out from the bearing box and then
remove the pump shaft from the bearing box.
9. Use heating methods evenly heat the
bearing and lubricant retainer ring on the
pump shaft to get them out of the shaft.
10. Get the positioning wedge for the front
plate of the pump cover out and place the
cover inlet side upwards on the ground. Use
copper bar as a cushion to separate the front
cover with the pump cover. Then remove the
nuts of the rear plate and strike the bolt ends
till the rear plate separate.
11. Mark the position of the filler box on the
pump and use copper bar as a cushion to
strike the filler box cover till it gets separated
with the pump.
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 268 -
Rev. : A
3. Parts
Maintenance
and Service
1. Check the degree of wear on the pressure
enlarge outlet pipe of the slurry pipe. If
serious, replace.
2. Check the wedge shaped connecting
rubber seal ring. If worn, replace.
3. Clean the front and back plates of the pump
cover and the cover with diesel and check the
level of wear of the back plate. If serious,
replace the back plate. If there is crack on the
pump cover, replace.
4. Clean the impeller jacket and check the
degree of wear. If the wear is serious at the
internal wall ant the outlet, replace it.
5. Clean the impeller and check the blades
and its working surface and if they are worn,
replace them.
6. Use diesel to clean the shaft sleeve and
water seal ring and check their surfaces.
7. Use diesel to clean the bearing and
labyrinth seal ring and check the bearings
rollers, internal and external rings and
labyrinth ring.
8. Clean the sealing filler box with diesel and
check the circumvent surface.
9. Clean the rear pump casing and check the
surface whether there are cracks. If there are,
replace.
10. Check the center straightness of the
support trough and check the trough surface
and support.
11. Clean the pump shaft with diesel and
check the bearings, oil retaining parts and key
way. Use fine greased sand paper to grind the
shaft and key way surface. Check the threads
of the shaft gland.
12. Periodically check oil level and quality of
the liquid coupler.
1. The pressure enlargement
outlet pipe wear shall be
smaller than 2mm. The
wedge seal ring shall be free
from worn and deformation.
2. The wear to the front and
back plates shall be less than
5mm. There shall be no
cracks on the pump cover.
The sealing gasket shall not
be worn.
3. No serious wear on the
internal wall and the outlet of
the jacket.
4. The wear to the impeller
front diameter and the front
and rear back blades shall
not be more than 3mm. The
blades shall be free from
corrosion and cracks. The
threads of the impeller shall
be damage free.
5. The sleeve surface shall be
smooth. Replace if the wear
is more than 1mm. The
clearance between the bore
of the sleeve and shaft shall
be 0.04mm-0.06mm. The
water seal ring shall be
complete. The surface shall
be not rusted or scaled.
6.The internal and external
ring of the bearing and rollers
shall be wear free, corrosion
free and no color change.
The tension is similar. The
clearance between the
internal ring and shaft shall be
-+0.01mm. The clearance
between the external ring and
bearing seat bore is
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 269 -
Rev. : A
0.06mm-0.10mm, and the
same to the bearing box bore.
No damage to the labyrinth
ring.
7. The filler box shall be free
from cracks with smooth
surface.
8. The bottom pump casing
shall be free from cracks.
9.The support trough center
straightness deviation shall
be less than 0.02 mm and the
trough surface shall be
smooth and wear free. The
support shall be wear free
and crack free.
10. The pump shaft surface
shall be smooth and free from
friction. The shaft gland
threads shall be free from
damage.
4. Assembling 1. Put the filler box into the pump to the
marked position and use copper bar as a
cushion to strike till the position is correct.
2. Put the back plate seal ring into the groove
and when it is smooth, then put the back plate
on to the pump with bolts.
Caution: Bolts shall be tightened with equal
strength.
3. Use blade cloth to clean the shaft surface
and then grease the surface.
4. Check and clean the joint surface and use
steel wire to lift the pump to connection place
to get connected with bolts.
Caution: Replace the sealing gasket for the
joint surface and the surface and the bolts
shall be sprayed with sealants.
5. Connect the pressure enlarging pipe with
SEC
QUANG NI NH THERMAL POWER J OI NT STOCK COMPANY
2300 MW
BOI LER & AUXI LI ARI ES MAI NTENANCE MANUAL
Date: 2008-10-20 No.:QN1-SEC-G-04-TP-009 - 270 -
Rev. : A
outlet pipe using connector.
Caution: Replace the rubber gasket.
6. Connect the inlet and water pipe with flange
and tightened with bolts equally.
Caution: The sealing gasket of the joint shall
be replaced.
11.6.2 Backwashing Pump
Refer to the maintenance period, items and quality standards of the slurry pump.
11.6.3 Dredge Pump
Refer to the maintenance period, items and quality standards of the slurry pump.
11.6.4 Lift Pump
Refer to the maintenance period, items and quality standards of the slurry pump.