Finite Capacity Scheduling

This document provides an overview of finite capacity scheduling. It defines finite capacity scheduling as determining the optimal assignment of limited resources to tasks over time while meeting constraints. It discusses types of scheduling problems like job shop, energy, and military logistics scheduling. It also covers representations of schedules and problems, as well as solution algorithms like mixed integer linear programming.

Uploaded by

vague
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPT, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
125 views66 pages

Finite Capacity Scheduling

This document provides an overview of finite capacity scheduling. It defines finite capacity scheduling as determining the optimal assignment of limited resources to tasks over time while meeting constraints. It discusses types of scheduling problems like job shop, energy, and military logistics scheduling. It also covers representations of schedules and problems, as well as solution algorithms like mixed integer linear programming.

Uploaded by

vague
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPT, PDF, TXT or read online on Scribd
You are on page 1/ 66

Finite Capacity Scheduling

6.834J, 16.412J
Overview of Presentation
What is Finite Capacity Scheduling?
Types of Scheduling Problems
Background and History of Work
Representation of Schedules
Representation of Scheduling Problems
Solution Algorithms
Summary
What is Finite Capacity Scheduling?
Informal and Partial Definitions
Determining the best sequence of tasks on a resource
Optimal assignment of limited resources to tasks to
fulfill a set of orders
Elimination of factory bottlenecks

Formal Definition
The allocation of resources over time to perform a set
of tasks
such that task precedence constraints and resource capacity
constraints are not violated, and overall deadline goals are met
to the best extent possible
Example Schedule
Gantt chart
F1
F2
F3
T1
T2
T3
T4
T5
T6
Time
Resources
Types of Scheduling Problems
Energy
Job Shop
Batch Process
Discrete Manufacturing
Servicing of Complex Equipment
Scheduling of a Unique Resource
Military Logistics
Energy Scheduling
Electrical utility generator scheduling to meet anticipated
demand
Ex. Utility with 3 Generators
Generator
1 2 3
Capacity
(kw)
120 120 350
Hourly Cost
($/h)
10 10 10
Incremental
Cost ($/kwh)
0.20 0.30 0.40
Energy Scheduling (cont.)
Demand Profile
Time
KW
1 2 3 4
100
200
300
Energy Scheduling (cont.)
Best Schedule:

Hour
1 2 3 4
Generator 1
100 120 120 100
Generator 2
0 80 120 0
Generator 3
0 0 60 0
Let if generator i is on during time j, 0 otherwise
be the energy generated by generator i during time j
Cost can then be expressed as




From the previous schedule, non-zero values of B and E are:







So cost = 70 + 88 + 60 + 24 = 242
1 =
ij
B
ij
E


= = =
= = =
+ +
+ + + =
4
1
3
4
1
2
4
1
1
4
1
3
4
1
2
4
1
1
40 . 0 30 . 0 20 . 0
10 10 10
j
j
j
j
j
j
j
j
j
j
j
j
E E E
B B B Cost
60
120 80
100 120 120 100
1
1
1
33
23 22
14 13 12 11
33
23 22
14 13 12 11
=
= =
= = = =
=
= =
= = = =
E
E E
E E E E
B
B B
B B B B
Constraints for this problem can be expressed as



Where is demand at time j, and is the capacity of generator i.
Note how this forces Eij to be 0 if Bij is.
This, combined with the constraint that the B variables must be binary, and the
previously defined cost function, yields an optimization problem with
discrete and continuous constraints.

Such problems are often solved by Mixed Integer Linear Programming
algorithms (more on this later).


j
D
i ij ij
j j j j
Cap B E
D E E E
s
= + +
3 2 1
i
Cap
Variations on Problem
Suppose utility has 100 kwh energy storage device (battery
that has no hourly or incremental cost)
Could run generator 2 during 1
st
hour to charge battery
Could then discharge battery to meet demand in 3
rd
hour
Eliminates need to use generator 3
Suppose another consumer would like to buy energy
New consumer has their own demand profile
Utility must evaluate whether it is profitable to sell to this new
customer
This is a function of base demand profile, consumers demand profile,
generation costs, and what the new consumer is willing to pay
- Suppose generator 3 has high hourly cost but low energy
cost
- It may make sense to run it and shut off generators 1 and 2

Variations on Problem Co-generation
Co-generation introduces a new set of complex
considerations
Ex. Refinery that uses waste heat from process to make
steam to generate electricity
Refinery may schedule production to simultaneously meet
production goals and demand for electricity, thus
maximizing profit
Two kinds of demand
Refinerys main products (gasoline of various grades, etc.)
Electricity (demand profile as shown previously)
Also complicated by the fact that electricity prices vary
based on demand, and on time of day
Contracts between factories, utilities, and customers can be
extremely complicated

Job Shop Scheduling
Schedule n jobs on m machines
Each job requires processing on each
machine in a particular order
This order differs from one job to another
Often formulated as constraint satisfaction
problem with binary temporal constraints
among the mn tasks
Eliminating bottleneck resources is an
important goal
Batch Process Scheduling
Tasks have size that is a continuous and/or
discrete function of the amount of material to be
produced to fulfill an order
Task size can affect task duration, resource
requirements
Resource utilization represented with a
combination of discrete and continuous variables
Often, and important goal is to find ways to
combine similar tasks into larger batches in
order to minimize changeover costs
Example Beer Production
After brewing and aging, beer must be filtered, prior to
packaging.
Filter 1
Filter 2
Holding
Tank
1
From
aging
tanks
Holding
Tank
2
Holding
Tank
3 Holding
Tank
4
To
Packaging
Discrete Manufacturing Scheduling
Semiconductor
Auto assembly
Heavy equipment
Aircraft assembly
Electronic parts assembly

Discrete Manufacturing Scheduling (cont.)
- Characteristics
- Similar, in some ways, to job shop, and to batch
process scheduling
- Process plan instantiated based on order
- Process plans for similar types of orders are similar
- Fewer continuous variables and constraints
- Task sizes are discrete functions of order
- Ex. a car needs 4 tires
- Resource allocations are typically binary
- Resource is utilized or not
- Resources typically allocated to tasks for
individual orders
- Typically, no batching of tasks
Scheduling Service of Complex Equipment
Ex. Space Shuttle Ground Processing
Approximately 40,000 hours of technician labor
between flights.



Space Shuttle Service (cont.)
About 50% same for each flight. Rest is function of
payloads,
maintenance based on age of components
orbiter modifications
Very dynamic environment
Arrival date subject to change (and affected by weather)
Resource requirements parts, supplies, people
State (configuration) of system being repaired is important
State constraints (requirements and effects), very important
Use of changeover tasks to get system into correct state


Scheduling of a Unique Resource
Ex. Hubble Telescope
Scheduling of Hubble Telescope (cont.)
10,000 to 30,000 observations scheduled per year
Primary resource constraint is available observing
time
Affected by orbital position
Required orientation to keep sunlight on solar panels
Many constraints periodic
Disruptions
Targets of opportunity (new supernova)
Spacecraft anomalies
Changes in observing programs
Military Logistics
Transportation of troops and supplies
Resources to be scheduled are transport
vessels and cargo planes
Groups of troops and supplies represent tasks
Resource capacity constraints significant
Deadline constraints significant
Precedence constraints significant
Equipment must be delivered in appropriate
sequence
Background of Work on Scheduling
(a representative, but not exhaustive list)
MRP (Material Requirements Planning), MRP II (1970s)
Demand for end-products expanded into time-phased requirements for
parts
Timing based on operation leadtimes
No accounting of resource loading
Schedules often un-realistic
Mark Fox, CMU, ISIS (1980s)
Each order scheduled one at a time
Constructive approach, incrementally extends partial schedule solution
until complete
Simple best-first search with backtracking
Formulation as CSP, hard and soft constraints, continuous and discrete
Some constraint propagation (forward chaining) capability
Background of Work on Scheduling (cont.)
Monte Zweben, NASA, Gerry (1990s)
Iterative repair algorithm
Modifies complete schedule to repair constraints, or
to make more optimal
Hill-climbing, search states are complete solutions
Pantelides, Imperial College (1990s)
Chemical Process Scheduling
RTN, MILP algorithm
Discrete time formulation
Branch and bound, branch and cut
Areas of Work Related to Scheduling
Assignment Problem
Assign n tasks to n resources (no time rep.)
Specialized algorithm solves this efficiently
Transportation Problem
Transfer material between nodes in a graph
Traveling Salesman Problem
Resource visits n tasks (optimal sequencing of tasks
on a resource)
Graph theory, flow networks (used in TSP)
Long-Range Planning
using Dynamic Programming
Combinatoric Optimization, CSP, A* search,
MILP

Representation of Schedules
Task
Start time
Finish time
Duration
Resource assignments
Resource
Renewable (equipment for example)
Non-renewable (material or product, for example)
Useful to think of task as consuming one set of
resources, and producing another set
For equipment, the task consumes the resource at the
start time, and produces it (makes it available again)
at the finish time.
Representation of Schedules (cont.)
Attributes of materials (non-renewable) resources - amount and state
Amount of flour, number of loaves of bread related to task size
State temperature of bread, freshness
Attributes of equipment (renewable) resources state
Oven at input is clean (required state), oven at output is dirty (effect)
Cleaning oven is changeover task
Baker at output is tired (taking a knap might be changeover)
Attributes of tasks related to those of resources

Baking
Task
Bread Baking
Task and Resources
Dough
Cooking
Oil
Oven
Baker
Bread
Oven
Baker
Representation of Schedules:
Discrete vs. Continuous Time Representations
Discrete
Scheduling horizon divided into discrete, equal intervals
Task start, finish times expressed in terms of these increments
Advantageous for certain scheduling algorithms
Easy to check for resource capacity violations
Disadvantage is that if fine time granularity over longer scheduling
horizon is required, then many intervals
Problem size becomes un-manageable
Continuous
Task start, finish times expressed as real numbers
Smaller number of variables
Discrete event vs. discrete time
Disadvantage is that checking resource capacity violations is more
complicated
Rules out use of certain scheduling algorithms
Representation of Schedules
Gantt Chart
F1
F2
F3
T1
T2
T3
T4
T5
T6
Time
Resources
Representation of Scheduling Problems
Resource-Operation Network (RON)
Inspired by Imperial College RTN
Consists of Operations and Resource
Requirements
Operation
Class of task
Duration may be constant, or may be function of other things
Other attributes (amount, type of material to be produced)
Resource Requirement
Renewable and non-renewable resources
Incorporates notion of state (of a material or a resource)
Task is an instantiation of an operation
Resource assignment is an instantiation of a
resource requirement
Representation of Scheduling Problems
(cont.)
- Note similarity to schedule representation
-Attributes of operations and resource requirements similar
to attributes of tasks and resources
Baking
Task
Bread Baking Operations
and Resource Requirements
Dough
Cooking
Oil
Oven
Baker
Bread
Oven
Baker
Kneading
Task
Flour
Water
Baker
Cleaning
Task
Representation of Scheduling Problems:
Constraints
Resource requirements, Operations have attributes
Some general (like duration, start-time, etc.)
Some problem specific (state of a particular resource type)
Attributes can have discrete or continuous values
Combination of algebraic and logical constraints used to
constrain values of attributes
Kneading.finish_time < Baking.start_time
Baking.OvenInput.Status = clean
Baking.Dough.amount = f(Baking.size)
RON architecture is general enough to support just about any
kind of constraint (algebraic, logical, even functions)
However, there are a number of important basic types of constraints that
are often used in scheduling
Representation of Scheduling Problems:
Common Constraint Types
Constraints associated with resources
Resource utilization (how much of a resource a task needs)
Resource capacity (resource utilization should not exceed this)
Resource state
Task may require resource to be in particular state at beginning of task
Task may leave resource in particular state at end of task (effect)
Motivation for changeover tasks
Resource availability (calendar)
Resource (labor for example) may not be available on weekends
Constraints associated with tasks
Duration (may be constant, or may be function of task size)
Start, finish (related by duration)
Precedence (kneading before baking)
Usually not necessary when using RON formulation (falls out)
Due dates (ultimately, the reason for doing scheduling)
Resource Utilization Constraints
Operation usually determines amount of resource
required, and amount produced
May be simple constant:
Baking.Oven_Input.amount = 1 (need one oven)
Baking.Oven_Output.amount = 1 (oven not consumed by process)
May be integer function of task size
Baking.Size = Baking.Break.Loaves (task size = number of loaves)
Baking.Flour.amount = 12 x Baking.Size
May be continuous function of task size
HoldingTank.level = 50 x Filtering.Size
May even be a complex, non-linear function
Lubricant.amount = f(Drilling.Size)
Resource Capacity Constraints
Resource utilization should not exceed maximum
capacity for a resource
Resource utilization becomes function of time over
scheduling horizon
Time
% Utilization
1 2 3 4
50
100
150
5 6
Resource State Constraints
Constraint on state of input resource requirement
Analogous to requirement part of planning operation (Graphplan, etc.)
Baking.Oven_Input.status = clean
Constraint on state of output resource requirement
Analogous to effects part of planning operation
Baking.Oven_Output.status = dirty
Changeover operation used to restore resource to required state
Cleaning operation converts dirty oven to clean one
State requirements, changeover operations, often the key issue in
generating good schedule
Reason: changeover operations take time (setup time)
Goal is often to minimize changeovers
This can be achieved by batching similar tasks
There is a limit to this, however, imposed by limits of inventory (resource
capacity constraints)
Soft Constraints and Cost
It is often advantageous to think of scheduling as a constrained
(or even un-constrained) optimization problem, rather than a
constraint satisfaction problem
Analogous to notion of Lagrange multipliers in non-linear constrained
optimization
Allow some constraints to be relaxed (make them soft)
However, relaxation has a cost penalty
Relaxation of deadline constraint results in lateness penalty
Relaxation of resource capacity constraint results in overtime pay
requirement
Production costs usually directly associated with resource
utilization
Thus, cost function is sum of
Resource utilization costs
Constraint relaxation penalties
Process Plan Instantiation
Instantiate tasks for process plan (operations)
for each order
Ex. 3 orders for bread


Order Amount Due Date
1 3 loaves Mon.
2 5 loaves Tues.
3 1 loaf Wed.
Instantiated Tasks (Based on Process Plan)


Task Kneading1 Kneading2 Kneading3 Baking1 Baking2 Baking3
Size 3 5 1 3 5 1
Also, Cleaning1, Cleaning2, and Cleaning3
(size not an issue for these)
Process Plan Instantiation (cont.)
Initial resource assignment based on resource
requirements using very simple dispatch
heuristics
Sequence tasks on resource based on order
Baker Knead1
Clean1
Bake1
Resources
Oven Bake1
Knead2
Clean2
Bake2
Bake2
Mon. Tues.
Process Plan Instantiation (cont.)
This actually is not a bad schedule in some
circumstances
Probably is a good schedule for this example
On the other hand, if the baker doesnt care
about freshness, and wants to take Tues. off
Batch orders together to improve efficiency
Requires inventory capacity
Refrigerated storage space
Tolerance to reduction in quality (quality is a state
variable that decays over time)

Solution of Scheduling Problems
Unlike representation, which is relatively
universal, solution algorithm is problem-
dependent
Most real-world problems also require
heuristics, specialized for the particular type
of problem
Solution Algorithms
Dispatch Algorithms
MILP
Relation to A*, constructive constraint-based
Constructive Constraint-Based
Iterative Repair
Simulated Annealing
How A* heuristics can be used here (relaxation
of deadline constraints)
Genetic Algorithms
Dispatch Algorithms
Process plan instantiated (as described
previously)
Tasks put into queues, one for each order
(Preserves task precedence constraints)
Kneading1 Order 1 Queue Baking1 Cleaning1
Kneading2 Order 2 Queue Baking2 Cleaning2
Kneading3 Order 3 Queue Baking3 Cleaning3
Dispatch Algorithms (cont.)
Tasks released one at a time from queues
Assigned to first available resource
Which queue is popped depends on task
priorities
Queue with highest priority task at top gets
popped
Task priority based on variety of factors
Mainly order importance and urgency
Apex system is a dispatch system
Flight controller assistant, described by Rob
Kochman
Dispatch Algorithms (cont.)
Advantages
Simple to implement
Can easily handle changing requirements by updating
priorities
Disadvantages
When task is popped, it is assigned to first available
resource
If none available, it just waits, and nothing further can
be done
Thus, susceptible to bottlenecks
Doesnt really set schedule times
Cant guarantee when things will get done
No look-ahead, so no optimization
No capability for JIT
Tasks shifted to the left
Dispatch Algorithms (cont.)
However
Much, if not most, real-world scheduling is
done in this way
Manual scheduling is often done in this way
MILP (Mixed Integer Linear
Programming)
Used for energy scheduling
Chemical process scheduling
Pantelides, et. al., Imperial College
Sometimes used in discrete manufacturing
Pekny, Miller, Traveling Salesman Problems
For scheduling, requires discrete time
formulation
MILP Basics
Constraints represented as linear equalities and
inequalities

A is constant matrix, b is constant vector, x is
vector of variables
X vector has lower and upper bounds
X consists of real and integer variables


Cost represented as weighted sum of x
u x l
b Ax
s s
=
(

=
I
R
x

=
i
i i tot
x c c
MILP Basics
Energy scheduling example presented previously
is an example of an MILP


+ =
s s
=
j i
ij ij
j i
ij ij
i ij ij
j
i
ij
E Ce B Cb C
Cap B E
D E
, ,
0
MILP Basics (cont.)
This formulation is relatively easy to solve if x has
just real variables, no integers (if it is an LP)
Simplex algorithm, commercial solvers (CPLEX) can
easily handle problems with > 100,000 variables
Integer constraint adds significant complexity
Requires search where for each integer variable,
Pick an integer
Propagate by solving LP
If feasible, go on to next variable and repeat
If not feasible, pick different integer
Bad news depth-first search
Good news there is a very good heuristic to
guide the search

MILP Basics (cont.)
The linear relaxation often gives good guidance about what
integer values to pick
Ex.
Suppose that LP relaxation results in value of 7.3 for
variable x1, which is constrained to be an integer
variable.
MILP solver tries x1 = 7 as one search branch, and x1 =
8 as the other
This algorithm is called branch and bound
Note that the LP relaxation is a best-case heuristic
Therefore, branch and bound is a kind of A*
search
If the LP relaxation yields a solution that is worse than
the best one found so far, that entire branch of the tree
is pruned

MILP Basics (cont.)
Ex. x1, x2 are integer, other variables real
X1=3
1
Relaxation: x1 = 3.6
cost = 5.0
2 5
3 4
X1=4
Relaxation: x2 = 2.1
cost = 10.0
Relaxation: x2 = 7.5
cost = 20.0
X2=2 X2=3
cost = 14.0
RTN Formulation
Let

if resource i is assigned to task j at time k,
0 otherwise. Suppose task j has duration n. Let

if task j starts at time k, 0 otherwise. Then



Note that if ST is set to integer (1 or 0), all other variables have integer
values, even in LP relaxation! Example of branch and cut.
Resource capacity constraint is easy to express:


1 =
ijk
R
1 =
jk
ST
1
...
1
= +
= + + + +
+ +
jk jk
jk n ijk ijk ijk
ST SLK
n SLK n R R R
1 s

j
ijk
R
RTN Formulation (cont.)
Material production is formulated as follows:

here, j refers to tasks that produce material Mi.
Then, deadline constraint is simply

(is enough of the material ready at the due time).

Advantages
- Rigorous formulation, all constraints propagated
- Easy to try all sorts of what-if scenarios
- Resource capacity constraints, material production easily checked
Disadvantages
- Requires discrete-time formulation, so formulation can become large
- Formulation tricky
- Important that constraints significantly reduce search space
- Should be set up so that relaxation produces integer results
- Compilers can mitigate this disadvantage




+ =
+ +
j
jk j n ik n ik
ST K M M
1
i kfinal i
Mgoal M >
Constructive Constraint-Based
- Fox, et. al., ISIS
- Best-first search with backtracking
- Tasks for orders scheduled one at a time
- Incrementally adds to partial schedule at each node in the search
- If infeasibility is reached (constraint violation)
- Backtrack to resolve constraint
- Advantages
- Relatively simple, can make use of standard algorithms like A*
- Use of A* allows for incorporation of heuristics
- Such heuristics are often used by human schedulers
- Disadvantages
- Re-scheduling is difficult
- May not find a complete schedule in the required time
- Changeover constraints, task switching is difficult
- Constraint relaxation is difficult





Constructive Constraint-Based (cont.)
- Important disadvantage (often a show-stopper)
- A simple swap of ordering of two tasks on a resource (something that
human schedulers often do) may require significant backtracking
- Ex.



- Swapping to eliminate large changeover (asymetric TSP) requires
backtracking
- Unravels everything done between order 1 and n





Task for order 1 Large Changeover Task for order n
Iterative Repair
- Zweben, et. al., GERRY, Red Pepper Software
- Scheduling of space shuttle ground operations
- Johnston and Minton
- Scheduling of Hubble space telescope

- Begin with complete but possibly flawed schedule
- Generate initial schedule quickly using simple dispatching
- Iteratively modify to repair constraint violations, and to make more optimal
- Each step in search is a repair step (single modification to complete schedule)
- Results in either better or worse schedule
- Hill-climbing (best-first) search
- Searches space of possible complete assignments





Iterative Repair (cont.)
- Disadvantage
- May get stuck in local optimum (as with all local search techniques)
- Can be mitigated using simulated annealing approach
- Allow repair step that increases cost with some non-zero probability
- Advantages
- Inherently provides for rescheduling
- Current schedule is initial (flawed) schedule for new requirements
- Assumes new requirements not that different from old
- Complete schedule available at all times
- Though it may not be such a great schedule
- Constraint relaxation is easy (a repair step)
- Swapping tasks to reduce changeovers is easy (repair step)
- A complete assignment is often more informative in guiding search than a partial
assignment (Johnston and Minton)






Iterative Repair (cont.)
- Potentially many kinds of repair steps
- Using a few assumptions, problem can be reduced to very small number of kinds of
repair steps
- Assume that a discrete-event simulator exists such that
- Given an assignment of tasks to resources, and an ordering of tasks on resources
- Simulator propagates timing and resource constraints so that no resource is overloaded, state
constraints are met, resource calendar constraints are met
- Note that order deadlines may not be met (soft constraint)
- Effectively simulates what would happen in real plant
- Continuous time representation
- Such a simulator is relatively easy to implement, and is fast
- Such a simulator can operate as the constraint propagation kernel of an iterative repair
algorithm
- Given such a simulator, the only decisions to make are
- Which resources to assign tasks to
- Sorting of tasks on a resource
- Repair steps are thus
- Move task on a resource to a different sort position on that resource
- Move task to a different resource (insert somewhere in the new resources sort sequence)





Iterative Repair Example Beer Scheduling
- Filtering of alcoholic vs. non-alcoholic beer prior to packaging




Filter 1
Holding
Tank
1
Holding
Tank
2
Holding
Tank
3 Holding
Tank
4
To
Packaging
Alcoholic
Non-
Alcoholic
Iterative Repair Example Beer Scheduling
- RON




Packaging
Filtered
Beer
Holding
Tank
Packaged
Beer
Filtering Aged Beer
Holding
Tank
Filter
Backwash
Filter
Iterative Repair Example Beer Scheduling
- Assume holding tank capacity is 100 gallons
- 3 orders each for 80 gallons alcoholic, non-alcoholic beer, interspersed as
follows
- (packaging tasks fixed)






Filter
Time
Resources
Tank1
1 2
Tank2
Tank3
Tank4
Packaging NA A
3
A NA A NA
Iterative Repair Example Beer Scheduling
- Simple dispatching produces following (flawed) schedule





Filter
Time
Resources
Tank1
1 2
Tank2
Tank3
Tank4
Packaging NA A
3
A NA A NA
A
A
A NA
NA
A A
A
NA
NA
A A A
A
Iterative Repair Example Beer Scheduling
- Iterative repair batches second A, NA tasks with first












- Note that further batching is not possible (would need more tanks)





Filter
Time
Resources
Tank1
1 2
Tank2
Tank3
Tank4
Packaging NA A
3
A NA A NA
A
A
A NA
NA
A A
A
NA
NA
A A A
A
Summary
Focus of this lecture was on generally useful
techniques
Solution of real-world scheduling problems can
make use of these techniques, but also, often
requires use of problem specific heuristics
As with other problems, scheduling becomes
easier as computers get faster (less need for
problem-specific heuristics)