0% found this document useful (0 votes)
31 views24 pages

Activity Networks Example 3

The document describes constructing an activity network from a table of tasks, durations, and predecessors to determine the critical path and minimum project duration. It shows adding each task as a node and arrow, calculating early and late event times by working forward and backward, and identifying that the critical path and minimum project duration is 15 days, with critical tasks being B, C, D, E, and G along two critical paths of BCE and BDH.

Uploaded by

mizmell
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPT, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
31 views24 pages

Activity Networks Example 3

The document describes constructing an activity network from a table of tasks, durations, and predecessors to determine the critical path and minimum project duration. It shows adding each task as a node and arrow, calculating early and late event times by working forward and backward, and identifying that the critical path and minimum project duration is 15 days, with critical tasks being B, C, D, E, and G along two critical paths of BCE and BDH.

Uploaded by

mizmell
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as PPT, PDF, TXT or read online on Scribd
You are on page 1/ 24

Activity networks Example 3

The table below shows the tasks involved in a project, with their durations and immediate predecessors.
Task A Duration (days) 2 Immediate predecessors -

B
C D E F G

4
5 3 6 3 8

A, B B C C D

D, F

Draw an activity network and use it to find the critical activities and the minimum duration of the project.

Activity networks Example 3

A(2)
1

B(4)

Begin with a start node, labelled 1.

Activities A and B have no preceding activities, so can both begin at the start node.

Activity networks Example 3


3

A(2)
1

B(4) 2 Activity C depends on both A and B, but activity D depends on B only. We can deal with this by adding a dummy activity.

Activity networks Example 3


C(5)
3

A(2)
1

B(4) 2

D(3)
Now add activity C, which depends on both A and B ... and activity D, which depends on B only.

Activity networks Example 3


C(5)
3 4 F(3) E(6)

A(2)
1

B(4) 2 5 G(8)

D(3)
Activities E and F depend on C only and activity G depends on D only.

Activity networks Example 3


C(5)
3 4 F(3) H(2) E(6)

A(2)
1

6
B(4) 2 5 G(8)

D(3)
Activity H depends on activities D and F. To deal with this, we need a dummy activity from event 5. Now activity H can be added.

Activity networks Example 3


C(5)
3 4 F(3) H(2) E(6)

A(2)
1

E(6)

6
B(4) G(8) 2 5 G(8)

D(3)
A finish node is now needed.

Activity networks Example 3


C(5)
3 4

A(2)
1

E(6)
F(3) H(2)

6
B(4) G(8) 2 5

D(3) The next step is to find the early event times (EETs).

Activity networks Example 3


C(5)
3 4

A(2)
1

E(6)
F(3) H(2)

6
0 B(4) G(8) 2 5

D(3) Event 1 occurs at time zero.

Activity networks Example 3


C(5)
3 4

A(2)
1

E(6)
F(3) H(2)

6
0 B(4) G(8) 2 5

D(3)
4

Event 2 cannot occur until B has finished, so the earliest time for event 2 is 4.

Activity networks Example 3


4

C(5)
3 4

A(2)
1

E(6)
F(3) H(2)

6
0 B(4) G(8) 2 5

D(3)
4

Event 3 cannot occur until both A and B have finished, so the earliest time for event 3 is 4.

Activity networks Example 3


4

C(5)
3 4 F(3)

A(2)
1

E(6)

H(2)

6
0 B(4) G(8) 2 5

D(3)
4

Event 4 cannot occur until C has finished, so the earliest time for event 4 is 4 + 5 = 9.

Activity networks Example 3


4

C(5)
3 4 F(3)

A(2)
1

E(6)

H(2)

6
0 B(4) G(8) 2 5

D(3)
4 7

Event 5 cannot occur until D has finished, so the earliest time for event 5 is 4 + 3 = 7.

Activity networks Example 3


4

C(5)
3 4 F(3)

A(2)
1 0 B(4)

E(6)

H(2) 12

G(8) 2 5

D(3)
4 7

Event 6 cannot occur until both D and F have finished. The earliest time that D can finish is 7, and the earliest time that F can finish is 9 + 3 = 12, so the earliest time for event 6 is 12.

Activity networks Example 3


4

C(5)
3 4 F(3)

A(2)
1 0 B(4)

E(6)

H(2) 12

7
15 G(8)

D(3)
4 7

Event 7 cannot occur until E, G and H have all finished. The earliest time that E can finish is 9 + 6 = 15, the earliest time that G can finish is 7 + 8 = 15, and the earliest time that H can finish is 12 + 2 = 14, so the earliest time for event 7 is 15.

Activity networks Example 3


4

C(5)
3 4 F(3)

A(2)
1 0 B(4)

E(6)

H(2) 12

7
15 G(8)

D(3)
4 7

The next step is to find the late event times (LETs), working backwards through the network.

Activity networks Example 3


4

C(5)
3 4 F(3)

A(2)
1 0 B(4)

E(6)

H(2) 12

7
15 15 G(8)

D(3)
4 7

The latest time that event 7 can occur without delaying the project is 15.

Activity networks Example 3


4

C(5)
3 4 F(3)

A(2)
1 0 B(4)

E(6)

H(2) 12 13

7
15 15 G(8)

D(3)
4 7

The latest time that activity H can start is 13, so the latest time for event 6 is 13.

Activity networks Example 3


4

C(5)
3 4 F(3)

A(2)
1 0 B(4)

E(6)

H(2) 12 13

7
15 15 G(8)

D(3)
4 7 7

Activity G and a dummy activity both lead out of event 5. The latest time that activity G can start is 7, and the latest time that the dummy activity can start is 13, so the latest time for event 5 is 7.

Activity networks Example 3


4

C(5)
3 4 F(3)

A(2)
1 0 B(4)

E(6)

H(2) 12 13

7
15 15 G(8)

D(3)
4 7 7

Activities E and F both lead out of event 4. The latest time that activity E can start is 9, and the latest time that activity F can start is 9, so the latest time for event 4 is 9.

Activity networks Example 3


4 4

C(5)
3 4 F(3)

A(2)
1 0 B(4)

E(6)

H(2) 12 13

7
15 15 G(8)

D(3)
4 7 7

The latest time that activity C can start is 4, so the latest time for event 3 is 4.

Activity networks Example 3


4 4

C(5)
3 4 F(3)

A(2)
1 0 B(4)

E(6)

H(2) 12 13

7
15 15 G(8)

D(3)
4 4 7 7

Activity D and a dummy activity both lead out of event 2. The latest time that activity D can start is 6, and the latest time that the dummy activity can start is 4, so the latest time for event 2 is 4.

Activity networks Example 3


4 4

C(5)
3 4 F(3)

A(2)
1 0 0 B(4)

E(6)

H(2) 12 13

7
15 15 G(8)

D(3)
4 4 7 7

Finally, the latest time for event 1 is zero.

Activity networks Example 3


4 4

C(5)
3 4 F(3)

A(2)
1 0 0 B(4)

E(6)

H(2) 12 13

7
15 15 G(8)

D(3)
4 4 7 7 The float in this example is analysed in the Notes and Examples.

The minimum duration of the project is 15 days. The critical activities are B, C, D, E and G.
Notice that there are two critical paths: BCE and BDH.

You might also like