0% found this document useful (0 votes)
163 views

CPM

The document provides an overview of the critical path method (CPM) for project scheduling. It discusses that CPM was developed in the 1950s by the US Navy to model the logical dependencies between project activities. The document outlines that CPM calculates the longest path of activities to determine the critical path, which is the shortest time to complete the project. It also describes how CPM is used to determine the earliest and latest start and finish dates for activities, and how float can be used to prioritize and crash activities to shorten the project duration. An example CPM network and definitions are provided to demonstrate how CPM can be applied.

Uploaded by

atifmd1
Copyright
© Attribution Non-Commercial (BY-NC)
Available Formats
Download as PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
163 views

CPM

The document provides an overview of the critical path method (CPM) for project scheduling. It discusses that CPM was developed in the 1950s by the US Navy to model the logical dependencies between project activities. The document outlines that CPM calculates the longest path of activities to determine the critical path, which is the shortest time to complete the project. It also describes how CPM is used to determine the earliest and latest start and finish dates for activities, and how float can be used to prioritize and crash activities to shorten the project duration. An example CPM network and definitions are provided to demonstrate how CPM can be applied.

Uploaded by

atifmd1
Copyright
© Attribution Non-Commercial (BY-NC)
Available Formats
Download as PDF, TXT or read online on Scribd
You are on page 1/ 19

CRITICAL PATH METHOD

(CEE 320 VDC SEMINAR) 4 February 2009

Jesse Santiago & Desirae Magallon

Overview
Background & History CPM Defined The CPM approach Definitions Class Exercise

Background & History


Developed in the 1950s by the US Navy Originally, the critical path method considered only logical dependencies between terminal elements Since then, it has been expanded to allow for the inclusion of resources related to each activity, through processes called activity-based resource assignments and resource leveling. Critical Path Method for the construction industry
Non-computer approach John Fondahl

John Fondahl
Stanford CE Professor Emeritus 35 years Passed away last September 13th, 2008 US Marine Corps Sergeant in Iwo Jima
His father was USMC LtCol

Co-founder of the CEM program 1961 Paper for the US Navy "Non-Computer Approach to the Critical Path Method for the Construction Industry"

What is CPM?
The Critical Path Method or Critical Path Analysis, is a mathematically based algorithm for scheduling a set of project activities It is an important tool for effective project management Commonly used with all forms of projects, including construction, software development, research projects, product development, engineering, and plant maintenance, among others Any project with interdependent activities can apply this method of scheduling

What is CPM?
The essential technique for using CPM is to construct a model of the project that includes the following:
A list of all activities required to complete the project (also known as Work Breakdown Structure) The time (duration) that each activity will take to completion The dependencies between the activities.

What is CPM?
CPM calculates
The longest path of planned activities to the end of the project The earliest and latest that each activity can start and finish without making the project longer

Determines critical activities (on the longest path) Prioritize activities for the effective management and to shorten the planned critical path of a project by:
Pruning critical path activities Fast tracking" (performing more activities in parallel) Crashing the critical path" (shortening the durations of critical path activities by adding resources)

The CPM Approach


Phase I
Break project into operations necessary for completion Determine sequential relationship of operations
Every operation must have event to mark commencement i.e. completion of preceding operation Can operations overlap?

The CPM Approach


Phase II
Create time estimates for each operation Determine earliest possible start date, earliest possible finish date , latest start & finish
Determine free float and total float

Revised after completion of Phase III

The CPM Approach


Phase III
Establish time-cost relationship Establish scheduling variations
Determine most favorable balance between time-cost

Normal Start normal time, least cost All-Crash Start least time, higher cost

The CPM Approach

Definitions
Float (slack) - amount of time that a task can be delayed without causing a delay to: subsequent tasks (free float) project completion date (total float) Critical path is the sequence of activities which add up to the longest overall duration. It is the shortest time possible to complete the project. Any delay of an activity on the critical path directly impacts the planned project completion date (there is no float on the critical path). A project can have several, parallel, near critical paths. An additional parallel path through the network with the total durations shorter than the critical path is called a sub-critical or non-critical path. Critical activity activity with zero float Resource leveling iterative process of assigning crews to activities in order to calculate their duration

Definitions
Activity Identity box
Early Start (ES) Early Finish (EF)

Activity ID
Late Start (LS) Late Finish (LF)

Duration

Class Exercise
A STAR T C G H B D F
Activity ID A B C D E F G H Duration 7 3 6 3 3 2 3 2 A B D,F B C E,G Dependency

Class Exercise
0 A 0 7 7 7 7 7 C 6 13 13 13 13 G 3 16 16 H 16 0 B 7 3 10 10 3 3 D 3 13 13 6 6 E 3 16 9 2 18 18 16

3 F 11

5 2 13

Class Exercise
Gantt Chart

Summary
Critical Path Analysis is an effective and powerful method of assessing: Tasks which must be carried out Where parallel activity can be carried out The shortest time in which a project can be completed Resources needed to achieve a project The sequence of activities, scheduling, and timings involved Task priorities

References
Fondahl, John W., Non-Computer Approach to the Critical Path Method for the Construction Industry, Report #9, Stanford University, 1961 Fondahl, John W. The History of Modern Project Management Precedence Diagramming Methods: Origins and Early Development. Project Management Journal. Volume XVIII. No. 2. June 1987. Hendrickson, Chris & Au, Tung, Project Management for Construction, Prentice Hall, 1989 Weber, Sandra C., Scheduling Construction Projects: Principles and Practices, Prentice Hall, 2005

Questions???

You might also like