Task Type

Task types in project management determine how work, duration, and units are calculated. There are three main task types: fixed units where duration changes if work or units change; fixed duration where work or units change if the other changes; and fixed work where units or duration change if the other changes. The default task type for a project can be set globally, and individual tasks can have their type set independently as needed.

Uploaded by

vickyuniversal
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
0% found this document useful (0 votes)
46 views1 page

Task Type

Task types in project management determine how work, duration, and units are calculated. There are three main task types: fixed units where duration changes if work or units change; fixed duration where work or units change if the other changes; and fixed work where units or duration change if the other changes. The default task type for a project can be set globally, and individual tasks can have their type set independently as needed.

Uploaded by

vickyuniversal
Copyright
© Attribution Non-Commercial (BY-NC)
We take content rights seriously. If you suspect this is your content, claim it here.
Available Formats
Download as DOCX, PDF, TXT or read online on Scribd
You are on page 1/ 1

How task types work

Work, duration, and units (% allocation) are determined by the formula: Work = Duration * Units. In a . . . Fixed units task Fixed work task Fixed duration task If you revise work . . . Duration changes Duration changes Units change If you revise duration . . . Work changes Units change Work changes If you revise units . . . Duration changes Duration changes Work changes

To set a default task type for the entire project, click Options on the Tools menu, and then click the Schedule tab. In the Default task type box, select Fixed Units (the default), Fixed Duration, or Fixed Work.

To change the task type for an individual task, select the task, and then click the Task Information button . Click the Advanced tab, and then in the Task type box, click the task type that you want to create.