Application of Digital Relay Protection On APUA.....
Application of Digital Relay Protection On APUA.....
Application of Digital Relay Protection On APUA.....
Presented by: Li Zhengrong Substation Maintenance & Protection Engineer Andre MatthiasDivision Manager
Protection Workstation
1.General information
1.1 Introduction of APUA electric power system
The total installed generation capacity is 64.5MW and the present peak load is 34.8MW;
Eight (8) 69kV transmission lines operating in close-ring are 59.2kM in length;
Twenty-two (22) 11kV feeders radiating and covering entire Island are 539kM in length; Twelve (12) 69/11kV power transformers at seven (7) step-up/-down substations possess a total installed capacity of 160.34MVA.
1.General Information
1.2 . Requirement for relay upgrade
1.2.1 11kv primary feeders: a. Under-frequency protection feature for load-shedding; b. One-shot re-closing
c. fuse-saving scheme
1.General Information
1.2 . Requirement for relay upgrade (continued)
1.General Information
1.3 Relay protection upgrade project
Replacing electromagnetic distance relay protections on 69kv transmission lines with 351 digital relays was done in 2000; Replacing electronic relays on 11kv feeders with DFP-100 and 351/551 digital relays was done in 2001; Replacing differential relays on 69/11kv power transformers with SEL-587 relays is in progress. The entire upgrade project that was from project design, settings calculation to relay programming, installing and testing, was carried out by APUA staff.
2.1.1 Phase-to-phase protection(positive-sequence protection 50P) Instantaneous over-current with time-delay(50PH ) Time-definite over-current (50PL) 2.1.2 Earth fault protection (zero-sequence protection 50N) Time-definite zero-sequence over-current (50N) 2.1.3 Under-frequency protection for load-shedding (81U1,81U1T) 2.1.4 re-closing One-shot re-closing (SH0) is activated only under phase-to-phase fault
A. Phase-to-phase protection(50P)
Instantaneous over-current with time-delay(50PH), protects entire primary feeder and primary side of distribution power transformers; Time-definite over-current (50PL) as backup protection of 50PH and fuse links, protects entire primary feeder and both sides of distribution transformers.
Relay
Solid link Fuse link 1 Fuse link 2 Fuse link 3 50PH 50PL
B. Earth fault protection(50N) Time-definite zero-sequence over-current (50N) as backup protection of fuse links, protects entire primary feeder and primary sides of distribution transformers under earth fault circumstance. Protection zone is shown in Figure 2 .
50NH
Figure 2
earth-fault protection
C. Fuse link protection Fuse link immediately clears faults on both sides of protected distribution transformer; Fuse link clears faults on protected branch of primary line.
Relay
Fuse link 2
Fuse link 3
B. Phase-to-phase protection(50P)
Instantaneous over-current with time-delay(50PH) acts as backup protection for fuse links; Time-definite over-current (50PL) performs as remote backup protection for both 50PH and fuse links.
Instantaneous over-current without time-delay(50PH) will immediately clear fault and then be locked by one-shot re-closing after circuitbreaker tripping.
After 5 seconds, the feeder will be closed by one-shot re-closing successfully if the temporary fault disappears at once; The permanent fault area will be isolated by related fuse link from entire feeder, or time-definite over-current (50PL) trips entire feeder
Date: Cause:
Total tripped Feeders: Total trip times: Phase-to-ground fault: Phase-to-phase fault:
3.1.1 Phase-to-phase protection (positive-sequence protection 50P) Directional instantaneous over-current without time-delay(Zone one 67P1) Directional instantaneous over-current with time-delay (Zone two 67P2) Directional time-definite over-current protection (Zone three 67P3)
3.1.3 re-closing
Synchronize-check (25A) or non-voltage check (27S) to initiate re-closing One-shot re-closing (SH0) is activated only under phase-to-phase fault
TmaxOLD=2.60Seconds TmaxNOW=1.85Seconds
14
12
10
11
13
15
Figure 4 Clockwise in blue starts at # 1 CB and ends at #11/13 C.B Anticlockwise in red starts at #10/12 and ends at #14 C.B
3.4.1 Zero-sequence over-voltage (59N) as a complement at some lines while close-ring of transmission lines is opened at some certain point Case A CB #1 opens (see Figure 5) Case B CB #9 opens (see Figure 6) 3.4.2 distinguish maximum load current ILD from minimum fault current IF at 69kV section breaker # 15 by load-encroachment Logic (see Figures 7&8)
Earth fault 7 9 12 10 11 13 14
15
Y/YO
Y/YO
Y/YO
Y/YO
YO/D
YO/D
YO/D
YO/D
16
1 Opened
O/V
Opened
12
10
11
13
15
14
Y/YO
Y/YO
Y/YO
Y/YO
YO/D
YO/D
YO/D
YO/D
K(1.0)
16 6
O/V
K(1.0) 4
O/V
O/V
ILD=219A
16
fault
Load in
Protection relay
SCADA System
Digital Relay
69kV
circuit-breaker
3.6.1 Interlocking balance current protection on 69kV double lines while single line operates (see Figure 10)
3.6.2 Speed-up tripping of Zone two (67P2) while re-closing onto permanent faulted line (see Figure 11)
3.6.3 Anti-pump of circuit-breaker (see Figures 12)
G2
G1
Output 1 Output 2
52A1
52A2
Output1output contact of #1 351 relay (=67P2) Output2output contact of #2 351 relay (=67P2) 52A1 auxiliary contact of #1 circuit-breaker 52A2 auxiliary contact of #2 circuit-breaker B/C balance current protection B/C triptrip contact of balance current protection
67P1
Relay #2
G
67P2
Trip logic: Trip= 67P1T+67P2T+67P3T+67P2*\SH0 Where: 67P1Ttimer of zone one (67P1) 67P2Ttimer of zone two (67P2) 67P3Ttimer of zone three (67P3) \SH0 declining edge of one-shot reclosing
67P3
Figure 11 Speed-up tripping of Zone two (67P2) while re-closing onto permanent faulted line
TLDO T67P1T
TOP
TOPinherent open time of circuit-breaker TCLinherent close time of circuit-breaker T67P1Ttimer of relay zone one (67P1) TLDOdrop-off timer of logic-controlled contact (TCL +T67P1T+ TOP> TLDO> TCL) Figures 12 Anti-pump of circuit-breaker under permanent faulty condition
a. The magnitude and phase angle of three-phase current and voltage; b. Dual-directional single/three-phase active/reactive power and energy;
CRB-CAS #1 69KV LINE Date: 05/29/02 Time: 11:13:55.618 CRABBS SUBSTATION A B C N G I MAG (A) 77.534 74.927 78.517 0.387 0.424 I ANG (DEG) -35.34 -153.68 87.31 134.14 123.30 A B C S V MAG (KV) 41.222 40.328 40.812 40.583 V ANG (DEG) 0.00 -119.97 117.52 -0.57 A B C 3P MW 2.607 2.514 2.769 7.890 MVAR 1.849 1.677 1.612 5.138 PF 0.816 0.832 0.864 0.838 LAG LAG LAG LAG I1 3I2 3I0 V1 V2 3V0 MAG 76.978 6.342 0.424 40.779 0.334 2.551 ANG (DEG) -33.90 -105.67 123.30 -0.82 150.90 29.60 FREQ (Hz) 59.92 VDC (V) 114.8 IA DEMAND 77.5 PEAK 146.4 IB 74.6 133.7 IC 78.4 150.0 IN 0.4 35.2 IG 3I2 0.4 6.7 35.3 35.3
MWA MWB MWC MW3P MVARA MVARB MVARC MVAR3P 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.0 0.2 0.2 0.4 0.6 0.2 0.2 1.2 1.2 2.6 2.5 2.8 7.9 1.8 1.7 1.6 5.1 4.6 4.3 5.2 14.1 3.8 3.2 3.1 10.1
MWhA MWhB MWhC MWh3P MVARhA MVARhB MVARhC MVARh3P IN 0.2 0.2 0.2 0.5 1.0 1.1 1.2 3.3 OUT 28278.4 26797.4 31523.3 86599.1 21038.4 17781.7 17006.4 55826.5
PT voltage memory polarization unit secures reliable operation of relay employed on short line while a three-phase fault occurs close to busbar. units secure reliability and selectivity of relay under earth fault condition.
2030
MODEM
PHONE
(PAGING)
LOCAL PC
351
551
587
321
DFP-100
Figure 13
communication configuration
4.3.2 5010 Setting assistance software The most complex work on 351 relay is programming due to 512 settings in one of six groups.
This software can: make relay programming facilitated; synchronize date and time on relays.
It can: periodically or automatically retrieve the latest event reports from designated digital relays; save event reports in database of workstation for viewing in oscillography.
5. A Captured Event
IAF=552A INF=701A IAF=1642A IAS=378A 0.5S IAF=1911A IAS=1407A 0S INF=2054A INS=2016A 0S
12
10
11
13
15
14 IA(1.0)
L=1.62KM
Y/ Yo
Y/ Yo
Yo/Y
Yo/Y
Crabbs
IAF=699A IAS=675A 0S
16
1 1
INF=700A INS=531A 0S
Y/ Yo
Y/ Yo
Y/ Yo
Y/ Yo
Union Road
Belmont
Swetes
Lavington
# 4 42 41 40 39 38 37 36 35 34 33 32 31 26 21
DATE TIME EVENT LOCAT CURR FREQ GRP SHOT TARGETS 05/05/02 06:21:26.909 AG T 1.62 1911 60.06 1 0 INST 50 05/05/02 05/05/02 05/05/02 05/05/02 05/05/02 05/05/02 05/05/02 05/05/02 05/05/02 05/05/02 05/05/02 05/05/02 05/05/02 05/05/02 06:21:26.901 06:21:26.905 06:21:26.905 06:21:26.909 06:21:26.909 06:21:26.917 06:21:26.917 06:21:26.917 06:21:26.917 06:21:26.917 06:21:26.917 06:21:26.917 06:21:26.963 06:21:26.972 67N4 67N3 67P3 67N2 67P2 67N1 67P1 67N1T 67P1T TRIP OUT202 OUT201 IN101 52A Asserted Asserted Asserted Asserted Asserted Asserted Asserted Asserted Asserted Asserted Asserted Asserted Deasserted Deasserted
67N3 67N2 67P3 67N1 67N1T TRIP OUT201 67P1 67P1T IN101 52A
6. Conclusion
1. About two year operating experience shows that: a. the digital relay protections secure 69kV transmission lines and 11kV primary feeders operating under safe, reliable condition; b. the micro-processed directional over-current protection can be applied to the close-ring transmission network, especially, to the short lines connected to small power system.
6. Conclusion
2. The established workstation makes daily inspection of relays and fault analysis easier. All event reports recorded in related relays can be immediately downloaded by 5040 software within few minutes once an event occurs. In accordance with the event reports listed in table, the event sequence and cause, conclusion can be easily obtained to guide system improvement.
6. Conclusion
3.
Based on application of 2030 communication relays and 5040 and other related software, the established workstation performs functions as mini-SCADA system on protection, monitoring, metering and control.