Design of Syphon Aqueduct
Design of Syphon Aqueduct
Design of Syphon Aqueduct
Chilla Minor drain 0.500 2.950 1.200 2.210 3.130 4.130 4.130 1.400 7.260
Field channel
Chainage Discharge Bed level OFL MFL TBL RTL Bed width Top width Bed fall
Km Cumecs m m m m m m m ----
0.000250
From the above hydraulic particulars,it can be observed that the MFL of Chilla minor drain is above the bed level of field channel.It is proposed to construct Syphon Aqeduct with depressed floor and 1V-RCC barrel of size 2.50mx1.50m for a length of 6m to accommodate the existing village road after the field channel. Further fluming of field channel is not proposed, hence existing width of the channel is not altered. The floor of the aqeduct is proposed to be lowered to a level of +0.485 with vertical drop on upstream side and raising of floor on down stream side in 1V to 5H to ensure clearing of sediments. Wing walls are proposed both upstream&down stream sides of drain along with revetment for slopes and bed protection.Cisterns are also proposed both U/S and D/S as per the requirement.Cut-off walls are proposed both U/S and D/S sides of drain. Similarly,wing walls along with bed and slope protections are proposed for field channel also both U/S and D/S sides. The hydraulic design of syphon aqueduct is carried out as per the guide lines stipulated in IS 7784:Part1--1993.The structural design of the box barrel along with load combinations is carried out as per the guide lines stipulated in IS 7784:Part2--5--1993. In view of the above facts,the box barrel is designed as free flowing vented structure with all possible combinations of loads.Further,the stability of the stucture is also ensured by providing appropriate factors of safety against overturning and sliding.
As,it is not possible propose foundation of box culvert below Max.scour depth,protective works are proposed for the bed of the minor drain as per the guidelines.
er the requirement.Cut-off
Compressive strength of concrete for Box (fck) Yield strength of steel (fy) Cover to reinforcement
= = =
300
PLAN
300
300
ROAD PORTION
CANAL PORTION
600
1545
3100
4500
300 6000
As per IRC:6---2000,the following loadings are to be considered on the box barrel in road portion:1.Dead load 2.Live load 3.Impact load 4.Wind load 5.Water current 6.Tractive,braking effort of vehicles&frictional resistance of bearings 7.Buoyancy 8.Earth pressure 9.Seismic force 10.Water pressure force 11.Static water pressure due to water in canal As per clause 202.3,the increase in permissible stresses is not permissible for the above loading combination.
Further as per IS 7784-Part 1---1993,the structure should be designed for the following forces :12.Uplift pressure due to flowing water 13.Uplift pressure due to subsurface flow
i)Self wieght of the top slab = (3.1*6*0.3*25) = ii)Self wieght of the bottom slab/Raft = (3.1*6*0.3*25) = iii)Self wieght of side walls = (2*1.5*6*0.3*25) = iv)Self weight of haunches = (4*0.5*0.15*0.15*6*25) = v)Self weight of wearing coat = (3.1*6*0.075*25) = vi)Self weight of U/S side brest wall = (1*3.1*0.3*1.545*25) = vii)Self weight of D/S side brest wall = (1*3.1*0.3*1.995*25) = viii)Self weight of middle brest wall = (1*3.1*0.3*1.545*25) = ix)Weight of earth on barrel in Road portion = (18*3.1*4.5*1.545) =
139.50KN
139.50KN
135.00KN
6.75KN
34.88KN
35.92KN
46.38KN
35.92KN
387.95KN 961.80KN
There is no need to consider snow load as per the climatic conditions Taking moments of all loads about upstream end,we get S.No Item Weight Distance of centroid from U/S end 3.00 3.00 3.00 3.00 3.00 0.15 5.85 0.75 3.15 Moment about upstream end in KN-m 418.50 418.50 405.00 20.25 104.64 5.39 271.32 26.94 1222.04 2892.58
1 2 3 4 5 6 7 8 9
Top slab Bottom slab Side walls Haunches Wearing coat U/S brest wall D/S brest wall Mid. brest wall Earth fill
139.50KN 139.50KN 135.00KN 6.75KN 34.88KN 35.92KN 46.38KN 35.92KN 387.95KN 961.80KN
Distance of centroid of above dead load from U/S end = Eccentricity in x- direction = The position of resultant dead load is as shown below:-
3.007m 0.007m
6000
2.Live Load:As per clause 201.1 of IRC:6--2000,the bridges and culverts of medium importance are to be designed for IRC Class A loading. GENERAL IRC Class-A loading Pattern
11.4t
2.7t
1.80
The IRC Class A loading as per the drawing is severe for bearing stresses on soil and the same is to be considered as per clauses 207.1.3&207.4
11.4t
2.7t
3100
6.8t
6.8t
6.8t
6.8t
X
1.10 3.20 1.20 4.30
7 3100
3.00
3.00
3.00
3100
X
1750 2750
11.4t
11.4t
W(mm)
1800
0.45
b
375
The ground contact area of wheels for the above placement,each axle wise is given below:Axle load (Tonnes) 11.4 6.8 2.7 Ground Contact Area
B(mm)
Assuming 0.3m allowance for guide posts and the clear distance of vehicle from the edge of guide post being 0.15m as per clause 207.1,the value of 'f' shown in the figure will be 0.45m
Hence,the width of area to be loaded with 5KN/m2 on left side is (f) = Similarly,the area to be loaded on right side (k) =
The total live load on the top slab composes the following components:1.Wheel loads----Point loads (114+114)=
3.Live load in remaing portion(Left side)----UDL (0.45*3.1*5)= 4.Live load in remaing portion(Right side)----UDL (1.75*3.1*5)=
Resultant live load:Eccentricity of live load w.r.t y-direction(Along the direction of travel of vehicles) Taking moments of all the forces w.r.t y-axis S.No Wheel Load/UDL in KN 57 57 57 57 6.975 27.125 (0.3+0.45 +0.5/2)= (0.3+0.45 +0.5/2) (0.3+0.45 +0.5/2+1.8) (0.3+0.45 +0.5/2+1.8) (0.3+0.45/2)= (0.3+0.45/2 +1.75) = Distance from Y-axis
1 2 3 4 5 6
262.100 Distance of centroid of forces from y-axis (498.57/262.1) = = 1.902m Eccentricity = (1.902-6/2)= 1.098m
Eccentricity of live load w.r.t x-direction(At right angle to the travel of vehicles) Taking moments of all the forces w.r.t x-axis S.No 1 2 3 Load in KN 57 57 57 Distance from X-axis (3.1-0.38) (3.1-0.38) [3.1(0.38+1.2)] = 2.72m 2.72m 1.52m
4 7 8
Distance of centroid of forces from x-axis (536.22/262.1) = = 2.046m Eccentricity = (2.046-3.1/2)= 0.496m
Location of the resultant of live load is as shown in the figure given below:6000
The eccentricty of the line of action of live load wrt centroid in y-direction = The eccentricty of the line of action of live load wrt centroid in x-direction = 3.Impact of vehicles:-
As per Clause 211 of IRC:6--2000,impact allowance shall be made by an increment of live load by a factor 4.5/(6+L) Hence,the factor is [4.5/(6+3.1)]= 0.495
Further as per clause 211.7 of IRC:6--2000,the above impact factor shall be only 50% for calculation of pressure on piers and abutments just below the level of bed block.There is no need to increase the live load below 3m depth. As such,the impact allowance for the top 3m of box culvert will be (0.495/2)=
X
496 1098
3100
Y
0.496m 1.098m
The Wind pressure acting on deck system located at that height is considered for design. As per clause 212.3 and from Table .4 of IRC:6---2000,the wind pressure at that height is (52+1.38*(63-52)/2)= 59.59 Kg/m2. Height of the deck system = Breadth of the deck system =(3.1) = The effective area exposed to wind force =HeightxBreadth = Hence,the wind force acting at centroid of the deck system = (Taking 50% perforations) (0.5*59.59*10.478*10/1000)= Further as per clause 212.4 of IRC:6---2000 ,300 Kg/m wind force is considered to be acting at a hieght of 1.5m from road surface on live load vehicle. Hence,the wind force acting at 1.5m above the road surface = (300*6.0*10/1000)= The location of the wind force from the top of Raft slab of box culvert = (1.5+0.3+1.5+0.075) = 3.380 3.10 10.478
5.Water current force:Water pressure considered on square ended abutments as per clause 213.2 of IRC:6---2000 is P = 52KV = 2 (52*1.5*0.69 )=
2
37.14 Kg/m2.
(where the value of 'K' is 1.5 for square endedside walls) For the purpose of calculation of exposed area to water current force,only 1.0m width of box is considered for full hieght upto HFL Hence,the water current force = [37.14*1.0*(2.585-(1.20)*10/1000] = 0.51KN
Point of action of water current force from the top of RCC raft slab = [3.13-(1.20)]/3 =
6.Tractive,braking effort of vehicles&frictional resistance of bearings:The breaking effect of vehicles shall be 20% of live load acting in longitudinal direction at 1.2m above road surface as per the clause 214.2 of IRC:6--2000.
As no bearings are assumed in the present case,50% of the above longitudinal force can be assumed to be transmitted to the supports of simply supported spans resting on stiff foundation with no bearings as per clause 214.5.1.3 of IRC:6---2000
Hence,the longitudinal force due to braking,tractive or frictional resistance of bearings transferred to abutments is (262.1*0.1)= 26.21KN
The location of the tractive force from the top of RCC raft slab = (1.2+0.075+0.3+1.50) = 7.Buoyancy :As per clause 216.4 of IRC:6---2000,for abutments or piers of shallow depth,the dead weight of the box culvert shall be reduced by wieght of equal volume of water upto HFL. The above reduction in self wieght will be considered assuming that the back fill behind the box is scoured. For the preliminary section assumed,the volume of box section is i)Volume of Raft slab section = (186.0/25) = ii)Volume of side walls upto MFL = (180/25) = iii)Volume of haunches = (9/25) = 11.120Cum Reduction in self wieght = (11.12*10)= 8.Earth pressure :As per clause 217.1 of IRC:6---2000,the abutments are to be designed for a surcharge equivalent to a back fill of hieght 1.20m behind the abutment. The coefficient of active earth pressure exerted by the cohesion less back fill on the box as per the Coulomb's theory is given by 111.20KN 0.140Cum 5.400Cum 5.580Cum
Sin(a+Q) = Sin(a-q) = Sina = Sin(Q+q) = Sin(Q-b) = Sin(a+b) = From the above expression,
Ka =
0.3
The hieght of box above GL,as per the preliminary section assumed = Hence,maximum pressure at the base of the wall (0.3*1800*1.80)*10/1000 = The pressure distribution along the height of the wall is as given below:Surcharge load = (0.3*1800*1.2)*10/1000= 6.48 KN/sqm Pa =
6.48
1.800
9.72
6.48
6.48*1.80 = 0.5*9.72*1.8 =
Taking moments of the areas about the toe of the wall S.No 1 2 Description Rectangular Triangular Area 11.66 8.75 20.41 Height from the bottom of the wall = (15.744/20.41) 0.77m Lever arm Moment 0.9 0.6 10.494 5.25 15.744
The active Earth pressure acts on the box culvert is as shown below:-
Pv
P 15 1500
Ph
770
15.00 Deg.
Total earth pressure acting on the wall P = (6.48*1.8+0.5*9.72*1.8)*8 = Horizontal component of the earth pressure Ph = (PCos150 ) Vertical component of the earth pressure Pv = (PSin150 ) Eccentricity of vertical component of earth pressure = (3.1/2-0.0) = 9.Siesmic force :-
122.47KN
As per clause 222.1 of IRC:6---2000,the bridges in siesmic zones I and II need not be designed for siesmic forces.The location of the slab culvert is in Zone-I.Hence,there is no need to design the bridge for siesmic forces.
10.Water pressure force:The water pressure distribution on the sidewall is as given below:-
HFL 3.130m
1.93
LBL 1.200m
19.30kn/sqm
Total horizontal water pressure force = 0.5*19.3*1.93*8 = The above pressure acts at height of H/3 =1.93/3 = Static water pressure force (Vertical) = (1.93+0.16)*10 = 11.Static water pressure due to water in canal Height of water in channel above bed level = The static water pressure on top slab of box barrel = Total load due to static water pressure = Eccentricity of the above load in x-direction =
12.Uplift pressure due to flowing water:Level of bottom of the top slab of box barrel = MFL of the drain = Afflux = Datum head =Height of water above the bottom of top slab of box barrel = Kinetic head = v2/2g = Total head causing uplift on the top slab of box barrel = Hence uplift pressure on the top slab = Total uplift force = +2.29m +3.130m 0.160m
13.Uplift pressure due to subsurface flow Afflux = The difference between subsoil hydraulic gradient line h' = and the bottom of floor just at entry section when the water is held up. Hence,the theoritical max.uplift pressure = yw x h' = Uplift force due to sub surface water = 0.160m 2.090
20.90kn/sqm 194.37KN
IV)Check for stability of Box Barrel:a)Load Envelope-I:-(The drain is dry,back fill intact with live load on span) The following co-ordinates are assumed:a)x-Direction-----At right angle to the movement of vehicles b)y-Direction-----In the direction of movement of vehicles Vertical load acting on the Box barrel (P) composes of the following components S.No Type of load Intensity in KN 961.80KN 391.84KN 31.68KN 1385.32KN Eccentricty about xaxis(m) 0.000 -0.496 1.550
1 2 3
Self wieght of Box culvert Live load with impact factor---(Wheel loads+UDL) [262.1*(1+0.495)] = Vertical component of Active Earth pressure
Horizontal load acting/transferred on the box (H) composes of the following components S.No Type of load Intensity in KN Direction x or y
1 2 3
Wind load Tractive,Braking&Frictional resistance of bearings Horizontal Active Earth pressure force
Check for stability against over turning(Assuming that the earth fill on toe side is scoured):Taking moments of all the overturning forces about toe of the box wrt x-axis, Moment due to tractive,braking&frictional resistance of bearings = (26.21*3.38)=
Moment due to active earth pressure force = (118.3*0.77)= Total overturning moment = Taking moments of all the restoring forces about toe of the box wrt x-axis,, Moment due to self weight of box = [961.8*(3.1/2+0.0)]= Moment due to live load reaction on box = [391.84*(3.1/2-0.496)]= Moment due to vertical component of active earth pressure = [31.68*(3.1/2+1.55)]= Total Restoring moment =
11.6407156
Check for stability against sliding:Total vertical load acting on the base of the box culvert Vb = Total sliding force,ie,horizontal load on the box Hb = Coefficient of friction between concrete surfaces = Factor of safety against sliding Fs = (0.8*1385.32/162.51)= 6.81957361 > 1.5 Hence safe (As per clause 706.3.4 of IRC:78-2000)
b)Load Envelope-II:-(The Canal is running upto HFL with no live load on span) The following co-ordinates are assumed:a)x-Direction-----At right angle to the movement of vehicles b)y-Direction-----In the direction of movement of vehicles Vertical load acting on the box (P) composes of the following components S.No Type of load Intensity in KN 961.80KN -111.20KN 850.60KN -156.75KN 0.000 0.000 Eccentricty about xaxis(m)
2 3
4 5 6 7
Uplift force due to subsurface water Static water force due to water in drain Static water force due to water in channel Vertical component of Active Earth pressure
Horizontal load acting/transferred on the box (H) composes of the following components S.No Type of load Intensity in KN Direction x or y
1 2 3 4
Wind load Tractive,Braking&Frictional resistance of bearings Active Earth pressure force Force due to water pressure Check for stability against over turning:-
Taking moments of all the overturning forces about toe of the box wrt x-axis, Moment due to tractive,braking&frictional resistance of bearings = Moment due to active earth pressure force = (118.3*0.77)= Total overturning moment = Taking moments of all the restoring forces about toe of the box wrt x-axis, Moment due to self weight of box = [850.6*(3.1/2+0.0)]=
Force due to static water pressure need not be considered,as it acts on both side walls in opposite directions
Moment due to vertical component of active earth pressure = [31.68*(3.1/2+1.55)]= Total Restoring moment =
Factor of safety =
15.5238491
Check for stability against sliding:Total vertical load acting on the base of the boxVb = (850.6+31.68) =
Total sliding force,ie,horizontal load on the box Hb = Coefficient of friction between concrete surfaces = Factor of safety against sliding Fs = (0.8*882.28/118.3)= 5.96634219 > 1.5 Hence safe (As per clause 706.3.4 of IRC:78-2000)
V)Check for bearing pressure:a)Load Envelope-I:-(The Canal is dry, back fill intact with live load on span) i)At the bottom of RCC raft slab
The following co-ordinates are assumed:a)x-Direction-----At right angle to the movement of vehicles b)y-Direction-----In the direction of movement of vehicles Vertical load acting on the Box (P) composes of the following components S.No Type of load Intensity in KN 961.80KN 159.84KN 391.84KN 31.68KN Eccentricty about xaxis(m) 0.000 0.00 -0.496 1.550
1 2 3 4
Self weight of box Self weight of levelling concrete =(3.7*6*0.30*24) Live load with impact factor---(Wheel loads+UDL) [262.1*(1+0.495)] = Vertical component of earth pressure
Horizontal load acting/transferred on the abutment (H) composes of the following components S.No Type of load Intensity in KN Direction x or y
1 2 3
Wind load Tractive,Braking&Frictional resistance of bearings Horizontal load due to earth pressure Safe bearing capacity SBC of the soil =
Breadth of footing b = Depth of footing d = Area of the footing = A = Section modulus of bottom footing about x-axis --Zx = (1/6)bd2 =
For RCC Strip footing permissible bearing pressure is 1.5xSBC = No tension is allowed on soil as per clause 706.3.3.1 of IRC 78:2000 S.No Type of load Intensity in KN (P)
113KN/sqm
Eccentricity/Lever arm
1 2 3 4 1 2 3
Vertical loads:-(Stress = P/A(1+6e/b) Self wieght of Box Self weight of levelling concrete Live load with impact factor---(Wheel loads+UDL) [262.1*(1+0.495)] = Vertical component of Earth pressure Horizontal loads:- (Stress = M/Z) Wind load Tractive,Braking&Frictional resistance of bearings Horizontal load due to earth pressure
S.No
Type of load
Intensity in KN (P)
Eccentricity
1 2 3 4 1 2 3
Vertical loads:-(Stress = P/A(1+6e/b) Self wieght of Box Self weight of levelling concrete Live load with impact factor---(Wheel loads+UDL) [262.1*(1+0.495)] = Vertical component of Earth pressure Horizontal loads:- (Stress = M/Z) Wind load Tractive,Braking&Frictional resistance of bearings Horizontal load due to earth pressure
Stress at heel =
P/A(1+6e/b)+M/Z =
53.67 KN/Sqm>0
Hence safe.
About y-axis:-
Breadth of footing b = Depth of footing d = Area of the footing = A = Section modulus of bottom footing about y-axis --Zy = (1/6)bd2 =
For RCC Strip footing permissible bearing pressure is 1.5xSBC = No tension is allowed on soil as per clause 706.3.3.1 of IRC 78:2000 S.No Type of load Intensity in KN (P)
113KN/sqm
Eccentricity/Lever arm
1 2 3 4 1 2 3
Vertical loads:-(Stress = P/A(1+6e/b) Self wieght of Box Self weight of levelling concrete Live load with impact factor---(Wheel loads+UDL) [262.1*(1+0.495)] = Vertical component of Earth pressure Horizontal loads:- (Stress = M/Z) Wind load Tractive,Braking&Frictional resistance of bearings Horizontal load due to earth pressure
S.No
Type of load
Intensity in KN (P)
Eccentricity
1 2 3 4 1 2 3
Vertical loads:-(Stress = P/A(1+6e/b) Self wieght of Box Self weight of levelling concrete Live load with impact factor---(Wheel loads+UDL) [262.1*(1+0.495)] = Vertical component of Earth pressure Horizontal loads:- (Stress = M/Z) Wind load Tractive,Braking&Frictional resistance of bearings Horizontal load due to earth pressure
P/A(1+6e/b)+M/Z =
35.73 KN/Sqm>0
Hence safe. Stress at down stream side edge of abutment = P/A(1+6e/b)+M/Z = 108.77 KN/Sqm<113KN/sqm
Hence safe.
52.87 KN/Sqm
b)Load Envelope-III:-(The Canal is running upto HFL with live load on span) i)At the bottom of RCC raft slab
The following co-ordinates are assumed:a)x-Direction-----At right angle to the movement of vehicles b)y-Direction-----In the direction of movement of vehicles Vertical load acting on the Box (P) composes of the following components S.No Type of load Intensity in KN 850.60KN 159.84KN 391.84KN -156.75KN -194.37KN 388.74KN 13.49KN 31.68KN Eccentricty about xaxis(m) 0.000 0.00 -0.496 0.000 0.000 0.000 0.000 1.550
1 2 3 4 5 6 7 8
Self weight of box Self weight of levelling concrete =(5.5*12*0.30*24) Live load with impact factor---(Wheel loads+UDL) [301.5*(1+0.413)] = Uplift force due to flowing water Uplift force due to subsurface water Static water force due to water in drain Static water force due to water in channel Vertical component of earth pressure
Horizontal load acting/transferred on the abutment (H) composes of the following components S.No Type of load Intensity in KN Direction x or y
1 2 3 4
Wind load Tractive,Braking&Frictional resistance of bearings Horizontal load due to earth pressure Force due to water pressure Safe bearing capacity SBC of the soil =
Depth of footing d = Area of the footing = A = Section modulus of bottom footing about x-axis --Zx = (1/6)bd =
2
For RCC Strip footing permissible bearing pressure is 1.5xSBC = No tension is allowed on soil as per clause 706.3.3.1 of IRC 78:2000 S.No Type of load Intensity in KN (P)
113KN/sqm
Eccentricity/Lever arm
1 2 3 4 5 6 7 8 1 2 3 4
Vertical loads:-(Stress = P/A(1+6e/b) Self wieght of Box Self weight of levelling concrete =(5.5*12*0.30*24) Live load with impact factor---(Wheel loads+UDL) [301.5*(1+0.413)] = Uplift force due to flowing water Uplift force due to subsurface water Static water force due to water in drain Static water force due to water in channel Vertical component of Earth pressure Horizontal loads:- (Stress = M/Z) Wind load Tractive,Braking&Frictional resistance of bearings Horizontal load due to earth pressure Force due to water pressure
850.60KN 159.84KN 391.84KN -156.75KN -194.37KN 388.74KN 13.49KN 31.68KN 18.00KN 26.21KN 118.30KN 111.75KN
0.00 0.00 -0.496 0.000 0.000 0.000 0.000 1.55 0.00 3.08 1.07 0.00
S.No
Type of load
Intensity in KN (P)
Eccentricity
1 2 3 4 5 6 7
Vertical loads:-(Stress = P/A(1+6e/b) Self wieght of Box Self weight of levelling concrete =(5.5*12*0.30*24) Live load with impact factor---(Wheel loads+UDL) [301.5*(1+0.413)] = Uplift force due to flowing water Uplift force due to subsurface water Static water force due to water in drain Static water force due to water in channel
8 1 2 3 4
Vertical component of Earth pressure Horizontal loads:- (Stress = M/Z) Wind load Tractive,Braking&Frictional resistance of bearings Horizontal load due to earth pressure Force due to water pressure
Stress at heel =
P/A(1+6e/b)+M/Z =
50.44 KN/Sqm>0
Hence safe.
About y-axis:Breadth of footing b = Depth of footing d = Area of the footing = A = Section modulus of bottom footing about y-axis --Zy = (1/6)bd2 = 3.10m 6.00m 18.6 m2 18.60 m3
For RCC Strip footing permissible bearing pressure is 1.5xSBC = No tension is allowed on soil as per clause 706.3.3.1 of IRC 78:2000 S.No Type of load Intensity in KN (P)
113KN/sqm
Eccentricity/Lever arm
1 2 3 4 5 6 7 8 1
Vertical loads:-(Stress = P/A(1+6e/b) Self wieght of Box Self weight of levelling concrete =(5.5*12*0.30*24) Live load with impact factor---(Wheel loads+UDL) [301.5*(1+0.413)] = Uplift force due to flowing water Uplift force due to subsurface water Static water force due to water in drain Static water force due to water in channel Vertical component of Earth pressure Horizontal loads:- (Stress = M/Z) Wind load
2 3 4
Tractive,Braking&Frictional resistance of bearings Horizontal load due to earth pressure Force due to water pressure
S.No
Type of load
Intensity in KN (P)
Eccentricity
Vertical loads:-(Stress = P/A(1+6e/b) 1 2 3 4 5 6 7 8 Self wieght of Box Self weight of levelling concrete =(5.5*12*0.30*24) Live load with impact factor---(Wheel loads+UDL) [301.5*(1+0.413)] = Uplift force due to flowing water Uplift force due to subsurface water Static water force due to water in drain Static water force due to water in channel Vertical component of Earth pressure Horizontal loads:- (Stress = M/Z) 1 2 3 4 Wind load Tractive,Braking&Frictional resistance of bearings Horizontal load due to earth pressure Force due to water pressure 18.00KN 26.21KN 118.30KN 111.75KN 3.38 0.00 0.00 -0.64 850.60KN 159.84KN 391.84KN -156.75KN -194.37KN 388.74KN 13.49KN 31.68KN -0.01 0.00 1.098 0.000 0.000 0.000 -2.400 0.00
P/A(1+6e/b)+M/Z =
46.17 KN/Sqm>0
Hence safe. Stress at down stream side edge of abutment = P/A(1+6e/b)+M/Z = 98.4 KN/Sqm<113KN/sqm
Hence safe.
103.88 KN/Sqm
103.88 KN/Sqm
VI)Analysis of Box culvert:a)Calculation of equivalent Uniformly Distributed Load(UDL) for IRC live load for Road portion:The position of IRC class A live load for maximum bending moment in top slab in road portion is as given below:-
1750
11.4t
11.4t
1800
2750
500
u
0.45
b
57.00KN
Assuming 1:1 dispersion parallel to Y-axis,the effective width of concentrated load in that direction = [0.25+2(0.075+0.30)]= There is no over lapping of areas of load dispersion in this direction. As per the clause 24.3.2.1 of IS 456:2000, The effective width be = kx[1-x/l]+bw where be = The effective width of slab on which the load acts L = Effective span x = Distance of centre of gravity of load from nearer support bw = Breadth of concentration area of load k = A constant depending on the ratio (B/L),where B is the width of the slab (From Table 14 of IS 456:2000) In the present case,
L = x = bw = B/L = k = Hence be =
Dispersion of Loads
500 1300 500
500 450
745
500
745
From the above figure net effective width of dispersion of loads = For each axle of load,the area of dispersion = (1.0*3.495)= Total load of each axle with impact = [11.4(1+0.495)] Average intensity of load = Add the UDL due to overlapping at certain area = 3.495sqm
3.495m
170.43KN
1.545 0.45
300
300
CANAL PORTION
600
3100
3100
3.00
3.00
6.8t
6.8t
6.8t
X
1750 2750
228.00KN
Moment
498.57KNm
3100
0.2475
3.12KN
18.00KN
3.38m
0.64m
3.08m
1.800m 9.72KN/sqm
ox culvert
1500
770
118.30KN
31.68KN
1.55m
80.73Kn-m
91.26Kn-m
171.98Kn-m
1490.79Kn-m
413.00Kn-m
98.21Kn-m
2002.00Kn-m
e 706.3.4 of IRC:78-2000)
e 706.3.4 of IRC:78-2000)
0.007 0.000
0.00Kn-m 91.26Kn-m
91.26Kn-m
1318.43Kn-m
98.21Kn-m
1416.64Kn-m
e 706.3.4 of IRC:78-2000)
882.28KN
118.30KN 0.80
e 706.3.4 of IRC:78-2000)
KN/Sqm>113KN/sqm
KN/Sqm<113KN/sqm
Eccentricty about yaxis(m) 0.007 0.00 1.098 0.000 0.000 0.000 2.400 0.000
e following components Location(Ht.from the section considered).(m) 3.38 3.08 1.07 0.64
45.73 8.59 10.62 -8.43 -10.45 20.9 0.73 4.34 0 -8.40 -13.19 0 50.44
KN/Sqm>113KN/sqm
KN/Sqm<113KN/sqm
1750
2750
1.00m
745
b)Loading on the Box culvert:Effective span of the culvert = Effective height of the culvert = 2.80m 1.80m
Case-I---Drain is running full,with live load on span and approaches are intact Load on Top slab :Self weight of top slab = Self weight of wearing coat = Weight of earth filling in Road portion = Average intensity of load due to IRC Class-A live load =
Load on bottom slab :Upward bearing pressure on raft = Upward bearing pressure due to weight of water = Downward static pressure due static water pressure = Add uplift pressure due to water in Channel =
Load on side walls from out side :At top:Earth pressure on side wall = At bottom:Earth pressure on side wall = Load on side walls from in side :At top:Hydro static pressure from inside wall = At bottom:Hydro static pressure from inside wall =
The loading on slab culvert is shown below for the above case of loading
1800
19.3 KN/sqm
1800
19.3 KN/sqm
C
16.20 KN/sqm 19.30KN/sqm 144.08 KN/sqm
D
16.20 KN/sqm
c)Calculation of internal forces:i) Calculation of fixed end moments:Span AB:MFAB = wl2/12 = MFBA = -wl /12 = Span BD:For Earth pressure from outside:For UDL part MFBD = wl2/12 = MFDB = -wl /12 = For Triangular part MFBD = wl2/20 = MFDB = -wl /30 = For Water pressure from inside:MFBD = -wl2/20 = MFDB = wl2/30 = Total :MFBD = MFDB = Span CD:Net Upward pressure = MFCD = -wl2/12 = MFDC = wl2/12 = Span AC:124.78 KN-m -81.52 KN-m 81.52 KN-m -3.13 KN-m 2.08 KN-m
2 2 2
For Earth pressure from outside:For UDL part MFAC = wl2/12 = MFCA = -wl2/12 = For Triangular part MFAC = wl2/20 = MFCA = -wl /30 = For Water pressure from inside:MFAC = MFCA = Total :MFAC = MFCA =
2
A AC 0.391 -0.190 -23.159 24.604 -16.672 8.336 -8.336 4.168 -4.168 2.084 -2.084 1.042 AB 0.609 59.420 -36.071 18.036 -25.967 12.984 -12.984 6.492 -6.492 3.246 -3.246 1.623 BA 0.609 -59.420 36.071 -18.036 25.967 -12.984 12.984 -6.492 6.492 -3.246 3.246 -1.623
B BD 0.391 0.190 23.159 -24.604 16.672 -8.336 8.336 -4.168 4.168 -2.084 2.084 -1.042 CA 0.609 0.720 49.207 -11.579 16.672 -8.336 8.336 -4.168 4.168 -2.084 2.084 -1.042
C CD 0.391 -81.520 31.593 -15.796 10.704 -5.352 5.352 -2.676 2.676 -1.338 1.338 -0.669 DC 0.391 81.520 -31.593 15.796 -10.704 5.352 -5.352 2.676 -2.676 1.338 -1.338 0.669
D DB 0.609 -0.720 -49.207 11.579 -16.672 8.336 -8.336 4.168 -4.168 2.084 -2.084 1.042
-1.042 -15.417
-1.623 15.417
1.623 -15.417
1.042 15.417
1.042 55.020
0.669 -55.020
-0.669 55.020
-1.042 -55.020
Span AB:Max.moment for simply supported condition = wl2/8 = Span BD:Due to earth pressure from out side For UDL:Max.moment for simply supported condition = wl2/8 = For Triangular load:Max.moment for simply supported condition = wl2/(9*30.5) = Due to water pressure from in side Max.moment for simply supported condition = (Assuming that the max.moments occur at mid span(On safe side) Max.moment at mid span 89.13 KN-m
2.62 KN-m
2.02 KN-m
-2.08 KN-m
2.56 KN-m
Span AC:Due to earth pressure from out side For UDL:Max.moment for simply supported condition = wl2/8 = For Triangular load:Max.moment for simply supported condition = wl2/(9*30.5) = Due to water pressure from in side Max.moment for simply supported condition = (Assuming that the max.moments occur at mid span(On safe side) Max.moment at mid span
2.62 KN-m
2.02 KN-m
-2.08 KN-m
2.56 KN-m
Span AB:The max.span moment = 89.13-(15.42+15.42)/2 = Span BD:The max.span moment = 2.56-(15.42+55.02)/2 = There is no sagging moment -32.66 KN-m 73.71 KN-m
Span AC:The max.span moment = 2.56-(15.42+55.02)/2 = There is no sagging moment Span CD:The max.span moment = 122.28-(55.02+55.02)/2 = The bending moment diagram for the box culvert is as shown below:87.06 KN-m -32.66 KN-m
15.42 15.42
15.42
15.42
A
73.71
32.66 87.06
32.66
C
55.02 55.02
D
55.02 55.02
v) Calculation of shear force for the box culvert:Span AB:Shear force at A = (90.95*2.8/2)+((15.42-15.42)/2.8) = Shear force at B = (90.95*2.8/2)+((15.42-15.42)/2.8) = 127.33 127.33
The Shear force diagram for the box culvert is as shown below:-
vi) Computation of axial forces for the box culvert:Top slab:Axial force in top slab = Shear force at A or B for the spans BD&AC = Bottom slab:Axial force in bottom slab = Shear force at C or D for the spans BD&AC = Side walls:Axial force in side walls = Shear force at A or C for the spans AB&CD = 174.69 33.67 30.75
b)Loading on the Box culvert:Effective span of the culvert = Effective height of the culvert = 2.80m 1.80m
Case-I---Drain is running full,with live load on span and approaches are intact Load on Top slab :Self weight of top slab = Self weight of wearing coat = Weight of earth filling in Road portion = Average intensity of load due to IRC Class-A live load =
Load on bottom slab :Upward bearing pressure on raft = Upward bearing pressure due to weight of water = Downward static pressure due static water pressure = Add uplift pressure due to water in Channel =
Load on side walls from out side :At top:Earth pressure on side wall = At bottom:Earth pressure on side wall = Load on side walls from in side :At top:Hydro static pressure from inside wall = At bottom:Hydro static pressure from inside wall =
The loading on slab culvert is shown below for the above case of loading
2800
90.95 KN/sqm 6.48 KN/sqm 6.48 KN/sqm
1800
1800
C
16.20 KN/sqm 124.78 KN/sqm
D
16.20 KN/sqm
c)Calculation of internal forces:i) Calculation of fixed end moments:Span AB:MFAB = wl2/12 = MFBA = -wl2/12 = Span BD:For Earth pressure from outside:For UDL part MFBD = wl2/12 = MFDB = -wl2/12 = For Triangular part MFBD = wl2/20 = MFDB = -wl /30 = For Water pressure from inside:MFBD = -wl2/20 = MFDB = wl /30 = Total :MFBD = MFDB = Span CD:2 2
Net Upward pressure = MFCD = -wl2/12 = MFDC = wl2/12 = Span AC:For Earth pressure from outside:For UDL part MFAC = wl2/12 = MFCA = -wl2/12 = For Triangular part MFAC = wl2/20 = MFCA = -wl /30 = For Water pressure from inside:MFAC = MFCA = Total :MFAC = MFCA =
2
A AC 0.391 -3.320 -21.935 23.970 -16.052 8.026 -8.026 4.013 -4.013 2.006 AB 0.609 59.420 -34.165 17.082 -25.001 12.501 -12.501 6.250 -6.250 3.125 BA 0.609 -59.420 34.165 -17.082 25.001 -12.501 12.501 -6.250 6.250 -3.125
B BD 0.391 3.320 21.935 -23.970 16.052 -8.026 8.026 -4.013 4.013 -2.006 CA 0.609 2.800 47.940 -10.968 16.052 -8.026 8.026 -4.013 4.013 -2.006
C CD 0.391 -81.520 30.780 -15.390 10.306 -5.153 5.153 -2.576 2.576 -1.288 DC 0.391 81.520 -30.780 15.390 -10.306 5.153 -5.153 2.576 -2.576 1.288
D DB 0.609 -2.800 -47.940 10.968 -16.052 8.026 -8.026 4.013 -4.013 2.006
Span AB:Max.moment for simply supported condition = wl2/8 = Span BD:Due to earth pressure from out side For UDL:Max.moment for simply supported condition = wl2/8 = For Triangular load:Max.moment for simply supported condition = wl2/(9*30.5) = Due to water pressure from in side Max.moment for simply supported condition = (Assuming that the max.moments occur at mid span(On safe side) Max.moment at mid span 89.13 KN-m
2.62 KN-m
2.02 KN-m
0.00 KN-m
4.64 KN-m
Span AC:Due to earth pressure from out side For UDL:Max.moment for simply supported condition = wl2/8 = For Triangular load:Max.moment for simply supported condition = wl2/(9*30.5) = Due to water pressure from in side Max.moment for simply supported condition = (Assuming that the max.moments occur at mid span(On safe side) Max.moment at mid span
2.62 KN-m
2.02 KN-m
0 KN-m
4.64 KN-m
iv) Calculation of Max.span moments for the box culvert:Span AB:The max.span moment = 89.13-(17.34+17.34)/2 = Span BD:The max.span moment = 4.64-(17.34+55.83)/2 = There is no sagging moment -31.94 KN-m 71.79 KN-m
Span AC:The max.span moment = 4.64-(17.34+55.83)/2 = There is no sagging moment Span CD:The max.span moment = 122.28-(55.83+55.83)/2 = The bending moment diagram for the box culvert is as shown below:85.7 KN-m -31.94 KN-m
17.34 17.34
17.34
17.34
A
71.79
31.94 85.70
31.94
C
55.02 55.83
D
55.83 55.83
55.02 55.83
55.83 55.83
v) Calculation of shear force for the box culvert:Span AB:Shear force at A = (90.95*2.8/2)+((17.34-17.34)/2.8) = Shear force at B = (90.95*2.8/2)+((17.34-17.34)/2.8) = 127.33 127.33
The Shear force diagram for the box culvert is as shown below:-
vi) Computation of axial forces for the box culvert:Top slab:Axial force in top slab = Shear force at A or B for the spans BD&AC = Bottom slab:Axial force in bottom slab = Shear force at C or D for the spans BD&AC = Side walls:Axial force in side walls = Shear force at A or C for the spans AB&CD = 174.69 33.05 30.13
f)Design of Members:Compressive strength of concrete for Box (fck) Yield strength of steel (fy) Cover to reinforcement Limiting stress in steel for axial tension i) Design of top slab:Factored critical bending moment(Sagging) = (1.5*73.71) Factored critical bending moment(Hogging) (1.5*15.42) Factored axial force = (1.5*30.75) Factored shear force = (1.5*127.33) Effective depth required d =
6
= = = =
Mu/0.138fckb =
0.5
200.15mm
[110.57x10 /(0.138*20*1000)]
The over all depth required(Assuming 16mm dia bars) = [200.15+50+8] = However provide overall depth of =
258.15mm
300.00mm
242.00mm
0.641
Area of steel required for bending tension = [0.641*242*1000/100]= Area of steel required for axial force = (46.13*1000/2*150) = Total area of steel required =
1551.2sqmm
153.8sqmm
1705.0sqmm
Hence provide 16mm dia bars at 110mm c/c at bottom,the area of reinforcement comes to =(1000/110)*(3.14/4)*162 = Top steel:Mu/bd2 = 0.395 0.114 0.15 363.0sqmm 1826.9sqmm
From table 2 of SP 16,percentage of steel required = (Minimum steel as per IS 456-2000 = Area of steel required for bending tension = [0.15*242*1000/100]= Area of steel required for axial force = (46.13*1000/2*150) = Total area of steel required =
153.8sqmm
516.8sqmm
Hence provide 10mm dia bars at 125mm c/c at top,the area of reinforcement comes to =(1000/125)*(3.14/4)*102 = Distribution steel:Provide distribution reinforcement of 0.15% of cross sectional area of footing Hence,the distribution reinforcement required = (0.15*300*1000/100) = Adopting 10mm dia bars,the spacing required = 1000/[450/(3.14/4)*102]= 450.00sqmm 174.00mm 628.0sqmm
However provide 10mm dia bars at 150mm c/c spacing,as distribution reinforcement
Check for one way shear:The critical section for beam shear is at distance of 'd' from the face of the support Hence,the factored design shear force VFd = at a distance D from the face of the support [191-(191/1400)*(150+242)] = Nominal shear stress Tv = [137.52x1000/(1000*242)] = 137.52KN
0.75%
The design shear strength of concrete for the above steel percentage from Table 19 of IS 456 is 0.56 Hence Vuc = 135.52KN Considering the enhanced shear strength at supports as 1.5 times the shear strength, 0.84>0.6 Hence,no shear reinforcement is required
ii) Design of bottom slab:Factored critical bending moment(Sagging) = (1.5*87.06) Factored critical bending moment(Hogging) (1.5*55.83) Factored axial force = (1.5*33.67) Factored shear force = (1.5*174.69) Effective depth required d =
6
Mu/0.138fckb =
0.5
217.52mm
[130.59x10 /(0.138*20*1000)]
The over all depth required(Assuming 16mm dia bars) = [217.52+50+8] = However provide overall depth of = Hence,effective depth =
275.52mm
300.00mm 242.00mm
Area of steel required for bending tension = [0.707*242*1000/100]= Area of steel required for axial force = (50.51*1000/2*150) = Total area of steel required =
1710.9sqmm
168.4sqmm
1879.3sqmm
Hence provide 16mm dia bars at 100mm c/c at TOP,the area of reinforcement comes to =(1000/100)*(3.14/4)*162 = Bottom steel:Mu/bd2 = 1.43 0.457 1105.9sqmm 2009.6sqmm
From table 2 of SP 16,percentage of steel required = Area of steel required for bending tension = [0.457*242*1000/100]= Area of steel required for axial force = (50.51*1000/2*150) = Total area of steel required =
168.4sqmm
1274.3sqmm
Hence provide 16mm dia bars at 150mm c/c at BOTTOM ,the area of reinforcement comes to =(1000/150)*(3.14/4)*162 = Distribution steel:Provide distribution reinforcement of 0.15% of cross sectional area of footing Hence,the distribution reinforcement required = (0.15*300*1000/100) = Adopting 10mm dia bars,the spacing required = 1000/[450/(3.14/4)*102]= 450.00sqmm 174.00mm 1339.7sqmm
However provide 10mm dia bars at 150mm c/c spacing,as distribution reinforcement
Check for one way shear:The critical section for beam shear is at distance of 'd' from the face of the support Hence,the factored design shear force VFd = at a distance D from the face of the support 262.04-(262.04/1400)*(150+242)] = Nominal shear stress Tv = [188.67x1000/(1000*242)] = 188.67KN
0.83%
The design shear strength of concrete for the above steel percentage from Table 19 of IS 456 is [0.56+{0.08*(0.62-0.56}/0.25] = 0.579 Hence Vuc = 140.12KN Considering the enhanced shear strength at supports as 1.5 times the shear strength, 0.87>0.80 Hence,no shear reinforcement is required
iii) Design of side walls:Factored critical bending moment(Sagging) = Factored critical bending moment(Hogging) (1.5*55.83) Factored axial force = (1.5*174.69) Factored shear force = (1.5*33.67) Effective depth required d =
6
Mu/0.138fckb =
0.5
174.19mm
[83.75x10 /(0.138*20*1000)]
The over all depth required(Assuming 12mm dia bars) = [174.19+50+8] = However provide overall depth of = Hence,effective depth = [300-50-8]= Steel on outer face :-
230.19mm
300.00mm 242.00mm
Mu/bd2 =
1.43 0.457
Area of steel required for bending tension = [0.457*242*1000/100]= Area of steel required for axial force = (262.04*1000/2*150) = Total area of steel required =
1105.9sqmm
873.5sqmm
1979.4sqmm
Hence provide 16mm dia bars at 100mm c/c on outer face,the area of reinforcement comes to =(1000/100)*(3.14/4)*162 = Steel on inner face :Area of steel required for bending tension = 0.0sqmm 2009.6sqmm
Area of steel required for axial force = (262.04*1000/2*150) = Total area of steel required =
873.5sqmm
873.5sqmm
Hence provide 12mm dia bars at 125mm c/c on inner face,the area of reinforcement comes to =(1000/125)*(3.14/4)*122 = Distribution steel:Provide distribution reinforcement of 0.15% of cross sectional area of footing Hence,the distribution reinforcement required = (0.15*300*1000/100) = Adopting 10mm dia bars,the spacing required = 1000/[450/(3.14/4)*102]= 450.00sqmm 174.00mm 904.3sqmm
However provide 10mm dia bars at 150mm c/c spacing,as distribution reinforcement
Check for one way shear:The critical section for beam shear is at distance of 'd' from the face of the support Hence,the factored design shear force VFd = at a distance 'd' from the face of the support 50.51-(50.51/1400)*(150+242)] = 36.36KN
0.83%
The design shear strength of concrete for the above steel percentage from Table 19 of IS 456 is [0.56+{0.08*(0.62-0.56}/0.25] = 0.579 Hence Vuc = 140.12KN 0.579>0.2 Hence,no shear reinforcement is required
6.48 KN/sqm
1800
1800
16.20 KN/sqm
0.3571 0.555556
0.912698 0.391304 -1
Joint Member Distribution Factor Fixed end moment Distribution Carry over Distribution Carry over Distribution Carry over Distribution Carry over Distribution Carry over
15.42
55.02
KN KN
KN KN
KN KN
KN KN
KN
KN
KN
6.48 KN/sqm
1800
6.48 KN/sqm
1800
16.20 KN/sqm
Joint Member Distribution Factor Fixed end moment Distribution Carry over Distribution Carry over Distribution Carry over Distribution Carry over
7.34
5.83
5.83
KN KN
KN KN
KN KN
KN KN
KN
KN
KN
nt comes to
nt comes to
Coefficient of active earth pressure by Coulomb's theory Ka = sina sin(a-q) Sin(a+Q) sin(Q+q)sin(Q-b) sin(a+b)
Sin(a+Q) = Sin(a-q) = Sina = Sin(Q+q) = Sin(Q-b) = Sin(a+b) = From the above expression, Ka =
0.32
Dimensions of the brest wall(Assumed for preliminary design):Thickness of stem at bottom = Thickness of stem at top =
1995
300
Earth pressure at top including surcharge = Kays = (0.32*1800*0.6) = Earth pressure at bottom including surcharge = Kay(s+h) = [0.32*1800*(1.995+0.6)] = Pressure distribution is as shown below:345.6
1.995m
Taking moments of the areas about the toe of the wall S.No 1 2 Description Rectangular Triangular Area 689.47 1146.25 1835.72 Lever arm 0.9975 0.665 Moment 687.746 762.256 1450
0.79m
0.20
17.83
1.995m 0.79m
87.17
0.30m 0.04 Total earth pressure acting on the wall per 1m length P = (345.6*1.995+0.5*1149.1*1.995)*1 = Horizontal component of the earth pressure Ph = (PCos20.150 ) Vertical component of the earth pressure Pv = (PSin20.150 ) Eccentricity of vertical component of earth pressure = (0.3/2-0.04) =
2180.46Kg
Total earth pressure = It acts at a hieght of from the base Moment due to horizontal component of earth pressure =
Design of wall or stem:Factored bending moment Mu = (1.5*1639.67) = Effective depth required d = Over all depth provided = Mu/0.138fckb = 300.00mm 242.00mm 2459.51Kgm
94.40mm
From table 2 of SP 16,percentage of steel required = (Minimum percentage of steel as per IS 456:2000) =
Area of steel required = Hence provide 10mm dia HYSD bars@ 150mm c/c spacing Hence Ast provided = Check for shear:523.33sqmm
363.00sqmm
The critical section for beam shear is at distance of 'd' from the face of the support Hence,the factored design shear force VFd = at a distance 'd' from the face of the support 11.11KN
0.22%
The design shear strength of concrete for the above steel percentage from Table 19 of IS 456 is [0.28+0.07*(0.36-0.28)/0.10] = 0.336 0.336>0.02
Hence,no shear reinforcement is required. Provide temperature re inforcement @ 0.15% Area required = 375.00sqmm 125.00sqmm
Provide 1/3rd of above reinforcement on earthen side = Provide 8mm dia @ 300mm c/c on earthen side Provide 2/3rd of above reinforcement on other side = Provide 8mm dia @ 200mm c/c on other side
250.00sqmm
BREST WALL
1.995m 1.995m 0.00m 1800Kg/Cum M20 Fe415 30 87.17 0 15 0Kg/sqm 7500Kg/sqm 0.60m 20N/sqmm 415N/sqmm 2500Kg/Cum 2400Kg/Cum
0.30m 0.20m
345.6Kg/sqm
1494.7Kg/sqm
2075.84Kg
667.32Kg
0.11m
2180.5Kg/m 0.79m
1639.67Kg/m
Hydraulic design
a)Hydraulic Particulars of drain:1.Maximum Flood Level 2.Ordinary Flood level 3.Lowest Bed level 4.Average bed slope (Calculated from the profile of drain) 5.Rugosity Coefficient(n) (As per table 5 of IRC:SP 13) 6.Top of bund level b)Hydraulic Particulars of field channel:7.Maximum Flood Level 8.Ordinary Flood level 9.Lowest Bed level 10.Average bed slope (Calculated from the profile of drain) 11.Rugosity Coefficient(n) (As per table 5 of IRC:SP 13) 12.Top of bund level c)Hydraulic Particulars of the proposed box barrel:13.Bed level 14.Bottom level of the top slab 15.Top level of the top slab (Bed level of the field channel) 16.No.of vents provided 17.Breadth of the vent 18.Depth of the vent 19.Width of box barrel 0.785 2.285 2.585 3.210 2.910 2.585 0.000250 3.130 2.210 1.200 0.000250
0.033
4.130
0.033
3.510
Discharge Calculations:-
MFL
1:1
slo pe
1:1 p slo e
MFL
1:1
slo p
1:1 slo pe
b
LBL
1.930m
1.40m 5.260m
Assuming side slopes 1 :1 in clayey soils,top width at HFL (b+2h) = Wetted Area(A) = 1.93*(1.4+5.26)/2 Wetted perimetre(P) = 1.4+2*[(1.4)2+(1.4)2]0.5 Hydraulic Radius Velocity V = Discharge Q = R= 6.43sqm
6.86m
1/nX(R2/3XS1/2) = AXV =
Discharge as per the record = Higher of the above two values is adopted for design of CD Work Design Discharge = Design Velocity =
2.950Cumecs
2.960Cumecs 0.46m/sec
Ventway Calculations(H.F.L Condition):Assuming the minor drain to be truly alluvial,the regime width is equal to linear waterway required for the drain.
Hence,as per Lacey's silt theory,the regime width W = 4.8Q 1/2 = 4.8*2.960.5 =
8.26m
But the actual top width is much less than the above regime width.Hence,the stream is no truly alluvial in nature. It is quasi-alluvial.As per IRC:SP--13,the ventway calculations for quasi-alluvial streams are as given below:The linear water way required = Actual width of the drain at HFL (W) = 5.260m
As per the clause 8.1.2.2 of IS 7784-Part1--1993,for the works with rigid floors,the waterway can be further flumed
within the permissible limits of velocity for the particular type of floor. The limiting velocity for the floor with concrete below M30 is = The area of cross section required = Q/A = 4.00m/s 0.74sqm
Assuming 1V--box barrel, vent being 2.50mX1.50m,the area of cross-section provided = Hence,the flow velocity in the box barrel will be within the limits.
3.75sqm
Calculation of Afflux at HFL condition:The area of un obstructed cross section A = The area of cross section provided a = Depth of flow on down stream side Dd = Linear water way of the Box barrel (L) = Adopting,orifice formula for discharge Q = C0 (2g)1/2 LDd[h+(1+e)v2/2g]1/2 = For the ratio a/A = 0.58 0.87 1 6.43sqm 3.75sqm 0.650m 2.500m 2.960Cumecs
where, C0 = Coefficient of discharge = h = afflux in m e = factor accounting for recovery of some velocity head as = potential head v = average velocity in approach section h+0.102v2 =
0.223373029
Further, as per discharge formula ,Q =W x (Dd+h) x v,hence v x (0.65+h) = substituting h = (0.56/v)-0.65 and re-arranging the terms we get 0.56-0.87v+0.102v3 = 0 solving for v,we get v = Hence,afflux h =
0.56
0.69m/s 0.160m
Scour Depth Calculations:As per the clause 101.1.2 of IRC:5--1985,the design discharge should be increased by 30% to ensure adequate margin of safety for foundations and protection works Hence,the discharge for design of foundations = 1.30XDesign Discharge = Qdf = (1.3*2.96) Lacey's Silt factor for standard silt ' f ' = 1.76Xm1/2= = (Value taken from table 4 of SP13) =
Discharge per metre width of foundations = q = (3.94/2.5) Normal scour depth D = 1.34(q2/f)1/3 = [1.34*(1.5762/1.0)0.33] For quasi-alluvial streams,linear water way required is natural width of the channel at HFL . = Linear water way provided = As per clause 12.1 of IRC SP:13,Increased scour depth due to contraction of linear water way D' = D(W/L) 0.61 = 1.81(5.26/2.5)0.61 =
Maximum scour depth Dm = 1.5XD = (For design of foundations,as per clause 110.1.4.2 of IRC:5--1985) (1.5*2.85) Depth of foundation = Dm + Max.of 1.2m or 1/3 Dm = (4.28+1.2) Bottom level of foundation = (3.13-5.48) =
Depth of foundation below low bed level = [1.2-(-2.35)] = The Minimum Safe Bearing capacity of the soil is considered as 7.5 KN/m2 Box barrel of size 1v-2.00mx2.35m is proposed at a level of Hence,cut-off walls and aprons are required to protect the foundation&floor bed
Design of cut-off walls:a)From scour depth criteria:It is sufficient to take the D/S side cut-off upto 1.27 times the normal scour depth as per caluse 703.2.3.2 of IRC 78-1983 considering that the reach is straight. 1.27XNormal scour depth from HFL = (1.27*2.85) = Depth of bottom of Cut-off wall from HFL = Bottom level of cut-off wall = (3.13-3.62)= Depth of bottom of D/S side Cut-off wall from LBL [1.2-(-0.49)]= 3.62m
3.62m -0.49
1.69m
According to Khosla's theory for two dimensional flow,the exit gradient G E = (H/d) x 1 The value of B/d = For the above value,1 = 3.550 0.07
The exit gradient for clayey soil = Static head including afflux = Hence,the depth of cut-off required = However, provide 2.40 depth cut-off wall
Design of LAUNCHING APRONS:Size of stones as per clause 5.3.7.2 of IRC 89-1985 Diametre (d) = (Vmax/4.893)2 = (0.92/4.893)2 = Say 0.23m 0.020m
Weight of each stone considering the specific gravity of stone as 2.65 Weight of stone = 4/3x x(d/2)3 x 2.65 x 1000 = Say Weight of each stone shall not be less than 20 Kg. 15.81Kg 20Kg
Dimensions of apron as per clause 5.3.5.2 of IRC 89-1985 ( T ) = 0.06 x (Qdf)1/3 = 0.06*(3.48)
1/3
0.095
Thickness of apron at inner edge(near raft) = 1.5 x T = Say Thickness of apron at outer edge = 2.25 x T = Say
Hence provide a thickness of 0.30m at near end and 0.6m at the outer end
MFL
MFL
LBL
an be further flumed
0.003385
-0.00679
3.94Cumecs
1.00
1.576
1.81m
5.26m 2.50m
2.85m
4.28m
5.48m
-2.35m
3.55m
0.485m