The New 3D Layout for Oil & Gas Offshore Projects: How to ensure success
4.5/5
()
About this ebook
All major oil and gas companies and contractors use 3D software for the design, layout, drawings and procurement of their projects. Each 3D model must be perfect during the detail engineering to be able to extract all the information necessary for the construction. The layout of offshore oil and gas projects start day one of the basic engineering and everything must be fixed before the completion of 50% of your detail engineering to avoid any engineering problems and delay during construction.The layout using 3D software is today an obligation.
Jacques Daubian latest book The New 3D Layout for Oil & Gas Offshore Projects will aid projects struggling with their 3D model layouts as well as those simply looking for a new and more effective approach. The book includes a checklist, listed by discipline, of what must be done to ensure the success of your project. Jacques Daubian draws on personal experience within the engineering and construction industry to provide an informative and helpful guide. For 12 years Jacques Daubian examined the huge degradation of the layout aspect of offshore projects and has since re-evaluated this, as demonstrated in The New 3D Layout for Oil & Gas Offshore Projects.
Jacques Daubian
Jacques Daubian has over 25 years of experience in engineering and construction, specifically for oil and gas offshore projects. He has been working since 1987 on oil and gas projects with major oil and gas companies including Inpex, PTTEP, Total and British Gas.
Related to The New 3D Layout for Oil & Gas Offshore Projects
Related ebooks
Offshore Piping Design: Technical Design Procedures & Mechanical Piping Methods Rating: 0 out of 5 stars0 ratingsCommissioning of Offshore Oil and Gas Projects: The Manager’S Handbook Rating: 4 out of 5 stars4/5The Project Engineer's Toolkit Rating: 0 out of 5 stars0 ratingsAgeing and Life Extension of Offshore Structures: The Challenge of Managing Structural Integrity Rating: 0 out of 5 stars0 ratingsProject Management for Petroleum, Power Generation and General Industry Projects. Rating: 5 out of 5 stars5/5Why Only Two FPSOs in U.S. Gulf of Mexico?: The Late Start and Twenty Year Saga Rating: 0 out of 5 stars0 ratingsIndustrial Megaprojects: Concepts, Strategies, and Practices for Success Rating: 3 out of 5 stars3/5Subsea Rigid Pipelines – Methods of Installation Rating: 5 out of 5 stars5/5Offshore Mechanics: Structural and Fluid Dynamics for Recent Applications Rating: 0 out of 5 stars0 ratingsProcess Plant Lifecycle Information Management Rating: 0 out of 5 stars0 ratingsPetroleum Refinery Relocation Projects: 5-Phases of Project Management Rating: 0 out of 5 stars0 ratingsOffshore installation manager Third Edition Rating: 0 out of 5 stars0 ratingsHydrostatic and Hydro-Testing in the Oil and Gas Field Rating: 3 out of 5 stars3/5Project commissioning Third Edition Rating: 1 out of 5 stars1/5Offshore construction Complete Self-Assessment Guide Rating: 0 out of 5 stars0 ratingsThe Language of Oil & Gas Rating: 5 out of 5 stars5/5Corrosion and Materials in Hydrocarbon Production: A Compendium of Operational and Engineering Aspects Rating: 0 out of 5 stars0 ratingsPiping and Instrumentation Diagram Development Rating: 4 out of 5 stars4/5Offshore Oil and Gas PEOPLE Rating: 4 out of 5 stars4/5Gas Pipeline Hydraulics Rating: 0 out of 5 stars0 ratingsNatural Gas: Operations and Transport: A Handbook for Students of the Natural Gas Industry Rating: 0 out of 5 stars0 ratingsOil & Gas Handbook: A Roughneck's Guide to the Universe Rating: 5 out of 5 stars5/5EPC Contracts A Complete Guide - 2021 Edition Rating: 0 out of 5 stars0 ratingsStress in ASME Pressure Vessels, Boilers, and Nuclear Components Rating: 0 out of 5 stars0 ratingsEPC Contract Strategy A Complete Guide - 2020 Edition Rating: 0 out of 5 stars0 ratingsConstructability A Complete Guide Rating: 0 out of 5 stars0 ratingsPipefitter's Licensing Study Guide Rating: 0 out of 5 stars0 ratings301 Top Tips for Design Engineers: To Help You 'Measure Up' in the World of Engineering Rating: 5 out of 5 stars5/5The TOGAF® Standard, 10th Edition – Architecture Development Method Rating: 0 out of 5 stars0 ratingsCATIA V5-6R2014 for Designers Rating: 3 out of 5 stars3/5
Power Resources For You
Electronics All-in-One For Dummies Rating: 4 out of 5 stars4/5OFF-GRID PROJECTS: Essential Guide to Enhance DIY Skills for Self-Reliance Preppers Rating: 0 out of 5 stars0 ratingsSolar Power Demystified: The Beginners Guide To Solar Power, Energy Independence And Lower Bills Rating: 5 out of 5 stars5/5The Homeowner's DIY Guide to Electrical Wiring Rating: 5 out of 5 stars5/5The Grid: The Fraying Wires Between Americans and Our Energy Future Rating: 4 out of 5 stars4/5Emergency Preparedness and Off-Grid Communication Rating: 3 out of 5 stars3/5The Boy Who Harnessed the Wind: Creating Currents of Electricity and Hope Rating: 4 out of 5 stars4/5Idaho Falls: The Untold Story of America's First Nuclear Accident Rating: 4 out of 5 stars4/5DIY Lithium Battery Rating: 3 out of 5 stars3/5Wind Power Basics: A Green Energy Guide Rating: 4 out of 5 stars4/5Solar Electricity Basics: Powering Your Home or Office with Solar Energy Rating: 5 out of 5 stars5/5The Illustrated Tesla Rating: 5 out of 5 stars5/5The Illustrated Tesla (Rediscovered Books): With linked Table of Contents Rating: 5 out of 5 stars5/5The Way Home: Tales from a life without technology Rating: 4 out of 5 stars4/5OFF-GRID PROJECTS: A Comprehensive Beginner's Guide to Learn All about OffGrid Living from A-Z and Live a Life of Self-Sufficiency Rating: 0 out of 5 stars0 ratingsSolar Power Your Home For Dummies Rating: 4 out of 5 stars4/5Station Blackout: Inside the Fukushima Nuclear Disaster and Recovery Rating: 3 out of 5 stars3/5The Ultimate Solar Power Design Guide Less Theory More Practice Rating: 4 out of 5 stars4/5How Do Electric Motors Work? Physics Books for Kids | Children's Physics Books Rating: 0 out of 5 stars0 ratingsBuild Your Own Electric Vehicle, Third Edition Rating: 3 out of 5 stars3/5Electric Power Transmission: Lecture Notes of Electric Power Transmission Course Rating: 5 out of 5 stars5/5Nuclear War Survival Skills Rating: 0 out of 5 stars0 ratingsOff Grid And Mobile Solar Power For Everyone: Your Smart Solar Guide Rating: 0 out of 5 stars0 ratingsGeo Power: Stay Warm, Keep Cool and Save Money with Geothermal Heating & Cooling Rating: 5 out of 5 stars5/5Pulse-Width Modulated DC-DC Power Converters Rating: 0 out of 5 stars0 ratings
Reviews for The New 3D Layout for Oil & Gas Offshore Projects
3 ratings1 review
- Rating: 4 out of 5 stars4/5Very nice book covering to the point 3D model issues and knowledge about 3D modeling
Book preview
The New 3D Layout for Oil & Gas Offshore Projects - Jacques Daubian
Glossary
Introduction
The layout is probably one of the more essential parts of offshore oil & gas (O&G) projects and can impact everything and all disciplines during engineering and construction as well as the CPY field operations (OPS) during offshore operations. The principal reason is the very tight space available on offshore oil & gas (O&G) projects.
The objective of the company (CPY) during the engineering and the construction (CTR) phases is to deliver the project on time and safely to the field operators (OPS) and ensure they will be able to maintain everything safely during the life of the offshore operations.
The layout has schedules, rules and steps and if you start too late to review the layout you will have major risks during all of your engineering and construction phases. There may also be problems for the CPY field operations (OPS) and high cost for the company (CPY) and the contractor (CTR).
The layout of offshore oil & gas (O&G) project(s) starts on day one of the basic engineering and everything must be fixed before the completion of 50% of your detail engineering to avoid any engineering problems and delay during construction.
The layout using 3D software is today an obligation. Oil & gas (O&G) major companies (CPY) and the contractors (CTR) are all using 3D software for the design, layout, drawings and procurement.
The 3D model of the project must be perfect during the detail engineering to be able to extract all the information necessary for the construction and must be approved by the company (CPY) in the same manner as official documents. The 3D model is deliverable from the contractor (CTR).
Implemented in the information you will find in my book in the company (CPY) specifications and in the contractor (CTR) are the internal 3D procedure(s) that will help your projects. You will have a checklist by disciplines for what you must do and must not forget for the layout of your projects.
I consider the CONTRACTOR as the ENGINEERING Company in this book.
The layout is a long job that needs to be followed closely during the detail engineering by the company/contractor (CPY/CTR) and where all must be methodical.
Chapter 1
CPY Contract, CPY Specifications and CPY & CTR Organisation
1.1 – CPY Contract
I am not a contract specialist, but I advise you to add or to be sure that you have the points below in your contract with your CTR.
1.1.1 – Basic Engineering
The CTR will use the 3D software requested contractually by the CPY (PDS, PDMS or SM3D).
The software NavisWorks will be used for all 3D model reviews official or specifics and without exception.
3D model review every week with the CTR and the CPY including comments and closeout will be managed using the software NavisWorks.
3D model for internal CPY reviews (NavisWorks file) will be given to the CPY every week by the CTR and more often if necessary the first week after the CTR starts the 3D model.
Mechanical handling (MH) will be modelled in the 3D model and show all volumes like access ways, turning radius, handling equipment for the major valves and equipment or skids or packages.
Clear and comprehensive management of change (MOC) must be used from day one and be able to keep the history.
1.1.2 – Detail Engineering
The CTR will use the 3D software requested contractually by the CPY (PDS, PDMS or SM3D).
The software NavisWorks will be used for all 3D model reviews, official or specifics and without exception.
Permanent 3D model review with the CTR and the CPY and during the full detail engineering if necessary including comments and close out will be managed using the software NavisWorks.
The 3D model for internal reviews (NavisWorks file) will be given to the CPY every week by the CTR and more often if necessary the first week after the CTR starts the 3D model.
The CTR should use one unique and same database for engineering and construction (sometimes, it is impossible depending on the CTR, eg., Samsung Heavy Industry in South Korea. They use two databases and different software between the engineering and construction. You can understand that without perfect control of these different systems it can be a major risk for the project).
MH will be modelled in the 3D model and show all volumes like access ways, turning radius, equipment, valves, handling equipment, etc.
All necessary volumes will be modelled in the 3D model, like doors opening, gas detection between receptors, cones for sprinklers (deluge system for equipment, skids or packages), all access ways (primary, secondary, operation), etc.
Clear and comprehensive MOC must be used from day one and able to keep the history.
1.2 – The CPY Specifications
VERY IMPORTANT AND THE CPY NEEDS TO BE VIGILANT. If you specify in the CPY specifications a minimum access way with a value, please remove this information from your specifications.
I saw in different specifications a minimum access way of 700mm used generally for the CPY OPS. This information does not mean ANYTHING, and the CTR will use this specification to make everywhere 700mm clearance and it will not work!
If you want to write in your specifications the minimum distance for an access way, you should follow my advice and definition:
A minimum distance in between items for an access way is the clearance the CPY will need for the mechanical or valve handling (MH or VH) of the bigger item in this way, including 150mm clearance for items equal to or less than five tonnes and 300mm clearance for items more than five tonnes in each side of the handling equipment will need the CPY to transport this item (you can modify the clearance 150mm for items maximum 5T and 300mm clearance for items more than 5T but try to keep these distances and weights).
If the CPY does not have any MH or VH in this way, the minimum distance in between items will be 800mm clearance (this is an example for the distance but try to keep this value. Remember that for oil & gas offshore projects an access without MH or VH does not exist; you always have something).
Example:
Two piping lines parallel where the bigger item is ESDVs with actuators and less than five tonnes. The minimum distance in between these piping lines will be the size of the trolley OPS will need to remove the larger ESDV + 150mm each side (considering you will use a permanent monorail(s) above the ESDV to pull down this valve on the