International Balkans Conference on Challenges of Civil Engineering, BCCCE,
19-21 May 2011, EPOKA University, Tirana, ALBANIA.
Risk assessment from floodings in the rivers of Albania
Agim Selenica1, Mehmet Ardicioglu2 ,Alban Kuriqi2
1
Department of Hydrotechnic, Polytechnic University, Albania
Department of Civil Engineering, Epoka University, Albania
2
ABSTRACT
Flooding is a natural phenomenon in Albania. The floods are flashy and flood – waters occupy the
floodplain; in the biggest rivers, close to the rivermouth area, these waters inundate the floodplain for several
weeks.Attempts have been made to alleviate flood situation in Albania by building protective dykes and
creating upstream storage. Although many of these measures have been beneficial, they also served to
encourage further encroachment upon river floodplains, thereby raising the potential for flood damage.
Actually, more than half of the Albanian population lives very close to the rivermouth areas, where the risk
of flooding is higher. The structural solution is only a partial one; the only long-term solution consists of
keeping flood-vulnerable development and uses out of the floodplain. In order to evaluate the flood potential,
a statistical study in national scale was carried out. The peak discharges for different return periods are
computed using statistical method and a map of the flood potential for the country is designed. Those
constructions had a relevant protective role during the flooding of the winter 1970-71. Non structural
measures consist of measures undertaken for flood warning or flood forecasting or different studies like
flood-mapping, estimation of inundation risk and inundation zones and possible damages etc.
1. MAIN ISSUES FROM FLOODINGS IN THE RIVERS OF ALBANIA
Flooding is a natural phenomenon in Albania, resulting from an increase in streamflow beyond the point
where the normal stream channel can contain the water. When water overspills riverbanks, it spreads out
along the adjoining floodplain [1]. Flood - waters may occupy the floodplain for a matter of hours, as in case
of flash floods, or for several weeks, as sometimes occurs during the winter period, when the period of
rainfall is longer or during the floods of spring period caused by snowmelt.
. In an effort to provide a co-ordinated, cost –effective approach to the problem, there is a need to established
Flood Damage Reduction Program, in order to ensure sustainable development, combining the following
activities:
• Mapping of flood – prone areas
• restricting land use activities in the flood zone
• educating the public
• studying flood – prone areas to suggest mitigation, including structure where warranted
• assisting in the implementation of flood forecasting.
1
International Balkans Conference on Challenges of Civil Engineering, BCCCE,
19-21 May 2011, EPOKA University, Tirana, ALBANIA.
2. HYDROLOGICAL CHARACTERISTICS OF ALBANIA
The climate of Albania, in general, is Mediterranean with some degree of continentality in the mountainous
regions in the northern, central and southern part of the country. The country combines a coastal plain in the
West with fairly high mountains: the highest point reaches 2751 m at the triple border with Yugoslavia and
Macedonia, while many ridges exceed 2000 m in the northern, central and southern parts of the country [2].
The rain comes mainly with south-west winds and falls according to the obstacles encountered. This gives a
variety of climates and rainfall patterns in the different regions of the country, as show the values extracted
for stations with 30 years of continuous observation:
Average annual rainfall is around 1485 mm; the seasonal pattern is very consistent, with July, sometimes
August, as the driest month and November, sometimes December, as the wettest one;
Figure. 1 Hydrographic map of Albania
2
International Balkans Conference on Challenges of Civil Engineering, BCCCE,
19-21 May 2011, EPOKA University, Tirana, ALBANIA.
The wettest area is in the North, in the district of Malesia e Madhe: Boge and Theth receive about 3000 mm
per year; other wet areas with annual rainfall above 2000 mm are found in the mountains of the north-centre
(districts of Puke and Mirdite) and in the south (districts of Tepelene, Skrapar and Gjirokaster);
The precipitation regime in the low part of Albania is in general Mediterranean, characterised by intensive
showers during the winter. The hydrographic basin of the rivers of Albania has a total area of 43,305 km2
from which only 28,748 km2 are situated within the state territory of Albania. The rest, which belongs to the
catchments of the rivers Drini and Vjosa, is situated in Greece, Macedonia and Yugoslavia (figure.1). The
hydrographic catchment of the Drini has a total area of 19.582 km² from which 14.173 km² belong to the
Drini itself and 5.187 km² to the Buna [3]. The Drini is formed by two main tributaries: the Drini Zi, with a
catchment area of 5.885 km², flowing from Macedonia, and the Drini Bardhe, flowing from Yugoslavia
(figure.1).
3. FLOOD POTENTIAL BASED ON HISTORICAL RECORDS
The most important cause of floods is excessive rain. Rain may be seasonal occurring over wide areas, or
from localised storms which produce the highest intensity rainfall. Melting snow is another major contributor
to floods.The relief of Albania is mountainous with an altitude of 786 m. The precipitation regime is in
general Mediterranean, characterised by intensive showers in winter and droughts in summer.In the highest
part of the basin the precipitation, in the most part of them come down as snow. During the big floods the
water overflow in the Western Plain of Albania, creating almost one river mouth.During the floods, the
values of the specific discharge in the main rivers oscillate from 0.5 m3/s.km2 (Drini river) to 2 - 5 m3/s.km2
(Ishmi river) and in smaller rivers (A=100-400km2) from 2 to 10 m3/s.km2[4].The floods are flashy and in the
main rivers they traverse the hydrographic network in 8-10 hours.Based on the information of historical
records peak discharges and the volumes of the floods are computed for different return periods, which are
presented for some stations of the low part of river watersheds (figure. 1 Hydrographic map of Albania)
4. AN OVERVIEW OF HISTORICAL FLOODINGS IN ALBANIA
4.1 HISTORICAL FLOODING DURING THE PERIOD 1854 -1962
Archival sources and the data collected from the Institute of Hydrometeorology of the Academy of Sciences
show that big flooding are observed even in the past. From the first centuries before new era roman historians
had given evidences on the flooding of the Buna and Drini Rivers and the movement of their flow direction
one time toward the Shkodra and the other time toward Lezha town [4].
Interesting evidences are given by Turkish chronist M.Sirri on the inundations of Shkodra from the floods of
Drini, Buna, Lake of Shkodra and Kiri River during the period 1854-1871 (see State Archives, document
Nr.1/5605).
In the watershed of the rivers Buna and Drini other floodings have been observed during the years 1937,
1952, 1960 but always with lower river stages than the floods of the winter 1962-63.
4.2 FLOODING OF THE WINTER 1962-63
Amongst all flooding observed until now in the rivers of Albania the biggest are considered those of 1962-63
in relation to the occupation of the territory, duration and damages caused by them. These events occurred
not only in Albania but also in almost all Mediterranean Basin and partly in the Western Europe [7]. More
intensifies they have been in southwestern and eastern part of the Balkan Peninsula and Italy. Because of
intensive showers, wind storms etc. in coastal lagoons a big quantity of water has been entered, causing high
changes in salt, oxygen and sediment regime. In the Lakes of Ohrid, Prespa and Shkodra very high water
levels were observed. Water table of groundwaters in the Western Plain was risen up, joining in some places
the surface waters, particularly in the fields of Myzeqeja of Lushnjes, in Thumane, Maliq [4] etc.
3
International Balkans Conference on Challenges of Civil Engineering, BCCCE,
19-21 May 2011, EPOKA University, Tirana, ALBANIA.
TABLE 2. FLOOD CHARACTERISTICS OF THE PERIOD NOVEMBER 1962 – FEBRUARY 1963
No
River
Station
Discharge
Period
Shkoder
Surface of River
watershed
stage
over“0”
A(km²)
H (cm)
4134
560
1
Buna
( m3/s)
2000
13.1.1963
2
Drini
Vau Dejes
11500
673
5180
13.1.1963
3
Drini
Bahçellek
14173
564
*
4
Drini i Zi
Kukes
4413
531
1080
13.1.1963
5
Kukes
4314
553
1450
13.1.1963
6
Drini
i Bardhe
Lana
Tirane
20
302
159
16.11.1962
7
Erzeni
Ndroq
640
584
794
16.11.1962
8
Erzeni
Sallmonaj
719
971
956
16.11.1962
9
Shkumbini
Murrash
1240
542
945
16.11.1962
10
Shkumbini
Paper
1890
631
1430
16.11.1962
11
Semani
Ura Kuçit
5080
714
*
16.11.1962
12
Osumi
1870
774
1130
16.11.1962
13
Vjosa
Ura
Vajgurore
Dorze
5420
938
3650
3.2.1963
14
Vjosa
Mifol
6680
652
*
18.2.1963
The discharge is not computed because the waters overflowed the riverbanks
TABLE 3. Inundated zones during the floods of November 1962- February 1963.
No
Zone
1
Zadrima of Shkodres and Lezha, Bregu Bunes
2
Fields between Drini of Lezha and Mati
Inundated
surface in ha
Duration in
days
18575
22
4
International Balkans Conference on Challenges of Civil Engineering, BCCCE,
19-21 May 2011, EPOKA University, Tirana, ALBANIA.
3
4
5
6
7
3122
10
5825
7
6896
7
26738
35
Fields in both river banks of Vjosa downward
Ura of Mifoli
3538
20
Total
64694
Fields between Mati and Ishmi
(Thumane etc)
Fields downward Rogozhina in both river
banks of Shkumbini
Fields in both river banks of Semani
5. MEASURES FOR FLOOD MITIGATION IN THE RIVESR OF ALBANIA
The measures undertaken for preventing the lowlands from flooding can be classified in two types: structural
and non-structural measures
5.1 STRUCTURAL MEASURES IN THE WESTERN PLAIN OF ALBANIA.
After the catastrophic inundation of the years 1962-63 the Albanian government decided to reconstruct the
destroyed embankments and to construct new dykes in other rivers.
As for the structural measures, huge investments are carried out after the inundations of the winter 1962 – 63,
for the construction of embankments in the lower part of the rivers Drini, Buna. Mati, Ishmi, Erzeni,
Shkumbini, Semani, Vjosa etc.
Those constructions had a relevant role during the flooding of the winter 1970-71.
In addition, the artificial reservoirs in Drini and Mati represent important structural measures, which apart
from their use for hydro-energetical purpose, play an important role for the flood regulation [4].
By taking these measures, the floods with a return period of less than 50 years do not cause the inundations
of the lowlands in the Western Plain, on condition that the dykes remain undamaged during these floods and
that the pumping stations operate normally.
DYKES ON THE RIVERS BUNA, DRINI AND KIRI
From the village of Zus until the village of Dajc the embankments on the river Buna are constructed on both
sides of riverbanks. From the village of Dajci until the rivermouth of Buna the dykes of the left side are
situated in the Albanian territory. These dykes, in general, have worked normally, except during the flooding
of 1962-63, when the waters overspilled the river banks in the village of Muriqan and inundated the fields.
Embankments are built also along the river Drini, downward Vau Deja, as well as a part of the Kiri River.
Nevertheless, during big floods, as those of 1962-63, the waters inundate the city of Shkodra.
DYKES ON MATI RIVER
The dykes in the Mati River are built downward URA e Milotit until the rivermouth. In general, these dykes
protect the fields from the inundation, except of a part close to the rivermouth, where river waters recharge
the swamp of Potoku.
DYKES ON THE RIVERS OF ISHEM AND ERZEN
The dykes on Ishmi River are built downward the city of Fushkruja until its rivermouth, and they are still in
good conditions. The dykes in Erzeni River exist in the lower part of the river and are also in good
conditions.
5
International Balkans Conference on Challenges of Civil Engineering, BCCCE,
19-21 May 2011, EPOKA University, Tirana, ALBANIA.
6.2 NON STRUCTURAL MEASURES
Non structural measures consist of measures undertaken for flood warning or flood forecasting or different
studies like flood-mapping, estimation of inundation risk and inundation zones and possible damages etc
Two types of maps could be produces under the Flood Damage Reduction Program: public information maps
and working maps. Public information maps cover the flood risk area, are usually printed in colour, and serve
to provide the public with general knowledge of the areas threatened by flooding [5]. These maps are handed
out freely during information sessions and are readily available from appropriate government agencies.
Working maps are large-scale, detailed, and generally, monochromatic maps. They are available to that
needing comprehensive site information such as engineers, planners, property owners, developers, and
government agencies.
7. FLOODPLAIN MAPPING IN THE WESTERN PLAIN OF ALBANIA
The purpose of floodplain mapping is to delineate the area affected by a flood of a specified magnitude.
Under the national Flood Damage Reduction Program, the flood hazard area should be subdivided into the
floodway and the flood fringe.
The first step in floodplain mapping involves the production of topographic maps for the basin under
consideration. The typical production schedule for the maps consist of ground control surveys to establish the
vertical and horizontal positions of targets interspersed throughout the basin. Aerial photography is then
taken of the area in which the surveyed targets appear in the imagery. In order to avoid in some way these
problems, the following procedure was followed [6]. First, the river stages and the corresponding absolute
quotas, with different return periods, were computed. Analysing and comparing these quotas with those of
the flood of 1962-63, was noted that the highest river stages of this flood actually have a return period of
around 100 years. Concerning the minimal scenario, it is presented by inundated zones, inside the space of
the dykes, on both sides of the river. For this scenario an indicative map on the scale 1: 100 000 has been
elaborated as showen in (figure.2).
Fig.5 Flooding with e return period of 100 year
Buna River
Albania
Figure.2 Flooding map for Buna
6
International Balkans Conference on Challenges of Civil Engineering, BCCCE,
19-21 May 2011, EPOKA University, Tirana, ALBANIA.
BAJRAM
CURRI
BAJRAM
CURRI
CURRI
BAJRAM CURRI
BAJRAM
BAJRAM
CURRI
CURRI
SHKODRA
SHKODRA
SHKODRA
SHKODRA
SHKODRA
SHKODRA
KUKES
KUKES
KUKES
KUKES
KUKES
KUKES
PESHKOPI
PESHKOPI
PESHKOPI
PESHKOPI
PESHKOPI
PESHKOPI
BULQIZA
BULQIZA
BULQIZA
BULQIZA
BULQIZA
BULQIZA
DURRES
DURRES
DURRES
DURRES
DURRES
TIRA
TIRANA
NA
NA
TIRA
ELBASAN
ELBASAN
ELBASAN
ELBASAN
ELBASAN
POGRADEC
POGRADEC
POGRADEC
POGRADEC
POGRADEC
POGRADEC
FIER
FIER
FIER
FIER
FIER
FIER
BERAT
BERAT
BERAT
BERAT
BERAT
KORCA
KORCA
KORCA
KORCA
VLORA
VLORA
VLORA
VLORA
VLORA
GIROKASTRO
GIROKASTRO
GIROKASTRO
GIROKASTRO
GIROKASTRO
GIROKASTRO
River
s
Lakes
SARANDA
SARANDA
SARANDA
SARANDA
SARANDA
Flooded Area
Fig. 3 Flood Risk Map
100 Years Return Period
8. CONCLUSIONS RELATED TO SOME FLOODING MITIGATION MEASURES
As it is mentioned in the above paragraphs, the flood is a natural phenomenon in Albania. In these conditions
only flooding mitigation measures could be taken in order to reduce the damages caused by flooding.
These measures can be classified into two types: short-term measures and long-term measures.
SHORT – TERM MEASURES
These measures consist of local works, generally of low cost, that could be undertaken in one season or year.
They include maintenance works and organizative measures, aiming to warn as soon as possible the state
institutions and population. These measures could be summarized as follows:
• Measures for the improvement of the drainage systems and the channels of high water, especially the work
of the pumping stations.
• Organization of the Flood Warning Service in the Institute of Hydrometeorology, which will have the
responsibility to warn regularly the emergency institutions and populations on the situation of the rainfall
regime and river, stages in rivers.
7
International Balkans Conference on Challenges of Civil Engineering, BCCCE,
19-21 May 2011, EPOKA University, Tirana, ALBANIA.
LONG-TERM MEASURES
The establishment of a National Flood Damage Reduction Program is a priority. This program will be based
on the actual Law on Emergencies, which charge the institutions to establish national or regional Flooding
Mitigation Planes.
Some measures of technical character are mentioned as follows:
• Identification of the state of dykes and necessary measures for rehabilitation and eventually, building of
new structures on both riverbanks (partly in Drini and Buna, Shkumbini, Semani and Vjosa).
• Analyzing the current standards of the hydro-module of drainage of agricultural fields aiming to recomputation of these standards and increasing the pumping station’s capacity.
• Rehabilitation of existing dams in small irrigation reservoirs and eventually building of new reservoirs,
which could increase the capacity of the flood control.
• Reducing the high erosion rates by means of reforestation, building of small dams in the upper part of
mountain torrents etc., especially in the rivers Devolli, Erzeni, Osumi, Drino etc.
REFERENCES
[1] Hydrologjia inxhirike (kontrolli I plotave), Agim Selenica
[2] Studime gjeografike (klima e shqiperise).
[3] Pasurite ujore Te shqiperise (lumejte kryesore ne shqiperi), Niko Pano
[4] Pasurite ujore Te shqiperise (rrjedhja maksimale ne shqiperi), Niko Pano
[5] Proceedings of the 3rd international symposium on flood defence, Nijmegen, The
Netherlands, 2527May 2005. Lavoiser.
[6] Cui, P., Han, Y. S. and Ge, Y. G. (2007) China strategy of flood mitigation: from control to management.
[7] Hydrologjia inxhirike (vecorite e plotave), Agim Selenica
8