Building Information Modeling (BIM):
Benefits, Risks and Challenges
Salman Azhar, Michael Hein and Blake Sketo
McWhorter School of Building Science
Auburn University
Auburn, Alabama
Building Information Modeling (BIM) has recently attained widespread attention in the
Architectural, Engineering and Construction (AEC) industry. BIM represents the development
and use of computer-generated n-dimensional (n-D) models to simulate the planning, design,
construction and operation of a facility. It helps architects, engineers and constructors to
visualize what is to be built in simulated environment and to identify potential design,
construction or operational problems. In this paper, the benefits and possible risks of BIM and
future challenges for the construction industry are discussed. First presented is the main concept
of BIM with its advantages and possible applications in construction. Then the role of BIM in
the construction industry and academia is discussed based on the results of three recent
questionnaire surveys. After that, a case study of Hilton Aquarium project in Atlanta is
presented to quantitatively illustrate the cost and time savings realized by developing and using
a building information model. It is followed by data from 10 construction projects to determine
the net BIM savings and BIM return on investment. At the end, BIM risks and future challenges
for the construction industry are discussed.
Key Words: Building Information Model (BIM), Virtual Design and Construction (VDC), nDimensional Modeling, Parametric Modeling, Facilities Management (FM)
Introduction
Building Information Modeling (BIM) represents the process of development and use of a
computer generated model to simulate the planning, design, construction and operation of a
facility as shown in Figure 1. The resulting model, a Building Information Model, is a data-rich,
object-oriented, intelligent and parametric digital representation of the facility, from which views
and data appropriate to various users’ needs can be extracted and analyzed to generate
information that can be used to make decisions and to improve the process of delivering the
facility (AGC, 2005).
The principal difference between BIM and 2D CAD is that the latter describes a building by
independent 2D views such as plans, sections and elevations. Editing one of these views requires
that all other views must be checked and updated, an error-prone process that is one of the major
causes of poor documentation. In addition, data in these 2D drawings are graphical entities only,
such as lines, arcs and circles, in contrast to the intelligent contextual semantic of BIM models,
where objects are defined in terms of building elements and systems such as spaces, walls,
beams and columns (CRC Construction Innovation, 2007).
A BIM carries all information related to the building, including its physical and functional
characteristics and project life cycle information, in a series of “smart objects”. For example, an
air conditioning unit within a BIM would also contain data about its supplier, operation and
maintenance procedures, flow rates and clearance requirements (CRC Construction Innovation,
2007).
(a) 3D Architectural Model
(b) Integrated Sturcutral and MEP Model
(c) Site Logistic Planning Model
(d) Quantiy Estimates
Figure 1: Different Components of a Building Information Model
(Courtsey of: PCL Construction Services, Orlando, FL)
A building information model characterizes the geometry, spatial relationships, geographic
information, quantities and properties of building elements, cost estimates, material inventories
and project schedule. This model can be used to demonstrate the entire building life cycle
(Bazjanac, 2006). As a result, quantities and shared properties of materials can be readily
extracted. Scopes of work can be easily isolated and defined. Systems, assemblies, and
sequences can be shown in a relative scale with the entire facility or group of facilities. The
construction documents such as the drawings, procurement details, submittal processes and other
specifications can be easily interrelated (Khemlani et al., 2006).
BIM Applications
A building information model can be used for the following purposes:
Visualization: 3D renderings can be easily generated in-house with little additional effort.
Fabrication/shop drawings: it is easy to generate shop drawings for various building
systems, for example, the sheet metal ductwork shop drawing can be quickly produced once
the model is complete.
Code reviews: fire departments and other officials may use these models for their review of
building projects.
Forensic analysis: a building information model can easily be adapted to graphically
illustrate potential failures, leaks, evacuation plans, etc.
Facilities management: facilities management departments can use BIM for renovations,
space planning, and maintenance operations.
Cost estimating: BIM software(s) have built-in cost estimating features. Material quantities
are automatically extracted and changed when any changes are made in the model.
Construction sequencing: a building information model can be effectively used to create
material ordering, fabrication, and delivery schedules for all building components.
Conflict, interference and collision detection: because BIM models are created, to scale, in
3D space, all major systems can be visually checked for interferences. This process can
verify that piping does not intersect with steel beams, ducts or walls.
BIM Benefits
The key benefit of BIM is its accurate geometrical representation of the parts of a building in an
integrated data environment (CRC Construction Innovation, 2007). Other related benefits are:
Faster and more effective processes – information is more easily shared, can be value-added
and reused.
Better design – building proposals can be rigorously analyzed, simulations can be performed
quickly and performance benchmarked, enabling improved and innovative solutions.
Controlled whole-life costs and environmental data – environmental performance is more
predictable, lifecycle costs are better understood.
Better production quality – documentation output is flexible and exploits automation.
Automated assembly – digital product data can be exploited in downstream processes and be
used for manufacturing/assembling of structural systems.
Better customer service – proposals are better understood through accurate visualization.
Lifecycle data – requirements, design, construction and operational information can be used
in facilities management.
Stanford University Center for Integrated Facilities Engineering (CIFE) figures based on 32
major projects using BIM indicates benefits such as (CIFE, 2007):
Up to 40% elimination of unbudgeted change.
Cost estimation accuracy within 3%.
Up to 80% reduction in time taken to generate a cost estimate.
A savings of up to 10% of the contract value through clash detections.
Up to 7% reduction in project time.
Role of BIM in the Construction Industry and Academia
In this section, the role of BIM in the US construction industry and academia is discussed based
on the results of three questionnaire surveys. The main findings of these surveys are:
Survey 1: Value from BIM Use
Kunz and Giligan (2007) conducted a questionnaire survey to determine the value from virtual
design and construction (VDC) or BIM use and factors that contribute to success. The main
findings of their study are as follows:
The use of BIM is significantly increased across all phases of design and construction during
the last one year.
BIM users represent all segments of the design and construction industry and they operate
throughout the US.
The major application areas of BIM are, construction document development, conceptual
design support and pre-project planning services.
The use of BIM lowers overall risk distributed with a similar contract structure.
At present, most companies use BIM for 3D/4D clash detections and for planning and
visualization services.
The use of BIM leads to increased productivity, better engagement of project staff and
reduced contingencies.
Currently there is a shortage of competent building information modelers in the construction
industry and their demand will exponentially grow with the passage of time.
Survey 2: Top Criteria for BIM Solutions
This survey was conducted by Khemlani (2007) and the results were published in the October
2007 issue of AECbytes newsletter. The main objective of the survey was to identify the most
important requirements that AEC professionals would like BIM solutions (software) to satisfy.
Based on the compiled results, the 10 most important requirements were found to be:
Full support for producing construction documents so that another drafting application need
not be used.
Smart objects, which maintain associativity, connectivity, and relationships with other
objects.
Availability of object libraries.
Ability to support distributed work processes, with multiple team members working on the
same project.
Quality of help and supporting documentation, tutorials, and other learning resources.
Ability to work on large projects.
Multi-disciplinary capability that serves architecture, structural engineering, and MEP.
Ability to support preliminary conceptual design modeling.
Direct integration with energy analysis, structural analysis and project management
applications.
Industry foundation classes (IFC) compatibility.
She concluded that the AEC industry is still very much reliant on drawings for conducting its
business of designing and constructing buildings as evident from the survey results. At the same
time, AEC professionals also realize the power of BIM for more efficient and intelligent
modeling by placing a high premium on smart objects that maintain associativity, connectivity,
and relationships with other objects and the availability of object libraries. She pointed out that
users want a BIM application that not only leverages the powerful documentation and
visualization capabilities of a CAD platform but also support multiple design and management
operations. BIM as a technology is still in its formative stage and solutions in the market are
continuing to evolve as they respond to user’s specific needs.
Survey 3: BIM: An Education Need?
Dean (2007) carried out a research study to examine if BIM should be taught as a subject to the
construction management students. He conducted two questionnaire surveys targeted at general
contractors and ASC construction management programs in the Southeast. Based on the gathered
data, he concluded in general that construction management programs should teach BIM to their
students. The main reasons behind this conclusion were:
Approximately 70% of the industry participants indicated that they are either using or
considering to use BIM in their companies. This trend indicates that the BIM utilization in
the construction industry is going to increase.
Approximately 75% of survey participants consider employment candidates with BIM skills
to have an advantage over candidates who lack BIM knowledge.
In another study, Woo (2006) pointed out that properly structured BIM courses would provide
industry-required knowledge to prepare students for successful careers in the AEC industry.
Instead of teaching a separate course, he suggested to reconfigure the existing construction
courses to integrate BIM into the course contents.
BIM Benefits: A Case Study
In the above mentioned surveys, the construction industry participants were unanimous that BIM
usage results in time and cost savings. However, no data was provided to quantify these facts.
The purpose of this case study is to illustrate the cost and time savings realized by developing
and using a building information model for an actual construction project. The data for this case
study is provided by Holder Construction Company, Atlanta, Georgia. The project details are as
follows:
Project name: Hilton Aquarium, Atlanta, Georgia
Project scope: $46M, 484,000 SF hotel and parking structure
Delivery method: Construction manager at risk
Contract type: Guaranteed maximum price
Design assist: GC and subcontractors on board at design definition phase
BIM scope: Design coordination, clash detection, and work sequencing
File sharing: Navisworks used as common platform
BIM cost to project: $90,000 - 0.2% of project budget ($40,000 paid by owner)
Cost benefit: $600,000 attributed to elimination of clashes
Schedule benefit: 1143 hours saved
Holder Construction created 3D models of the architectural, structural and MEP systems of the
proposed building as shown in Figure 2. These models were created during the design
development phase using detail level information from subcontractors based on drawings from
the designers.
(a) Architectural Model
(b) Structural Model
(c) Plumbing Model
Figure 2: Building Information Modeling for Hilton Aquarium, Atlanta, GA
(Courtesy of: Holder Construction, Atlanta, GA)
This method allowed project team members to perform their work in the comfort of their
traditional 2D, drawing-based delivery process and eliminated the potential risk that is often
associated with open sharing of digital models across stakeholders. Through frequent 3D
coordination sessions, the project team was able to quickly identify and resolve system conflicts,
saving an estimated $600,000 in extras and avoiding months of potential delays as shown in
Table 1.
Table 1: An Illustration of Cost and Time Savings via BIM in Hilton Aquarium Project
(Courtesy of: Holder Construction, Atlanta, GA)
During the construction process, non-BIM-savvy stakeholders made use of Holder’s
visualization models through a free viewer (i.e. Navisworks). The collaborative 3D viewing
sessions also improved communications and trust between stakeholders and enabled rapid
decision making early in the process. Finally, Holder’s commitment to updating the model to
reflect as-built conditions provided the owner, Legacy Pavilion, LLC, a digital 3D model of the
building and its various systems to help aid O&M procedures down the road (CIFE, 2007).
BIM Economics: Net Savings and Return on Investment
Data from 10 selected US based projects is presented in Table 2 to illustrate the net BIM savings
and BIM return on investment (ROI).
Table 2: BIM Economics (CIFE, 2007)
Year
2005
2006
2006
2006
2006
2007
2007
2007
2007
2007
Cost
($M)
30
54
47
16
88
47
58
82
14
32
Project
Ashley Overlook
Progressive Data Center
Raleigh Marriott
GSU Library
Mansion on Peachtree
Aquarium Hilton
1515 Wynkoop
HP Data Center
Savannah State
NAU Sciences Lab
BIM Cost
($)
5,000
120,000
4,288
10,000
1,440
90,000
3,800
20,000
5,000
1,000
Direct BIM
Savings ($)
(135,000)
(395,000)
(500,000)
(74, 120)
(15,000)
(800,000)
(200,000)
(67,500)
(2,000,000)
(330,000)
Net BIM
savings
(130,000)
(232,000)
(495,712)
(64,120)
(6,850)
(710,000)
(196,200)
(47,500)
(1,995,000)
(329,000)
BIM ROI
(%)
2600
140
11560
640
940
780
5160
240
39900
32900
As evident from Table 2, the BIM return on investment (ROI) for different projects varies from
140% to 39900%. Due to the large data spread, it is hard to conclude a specific range for BIM
ROI. The probable reason for this spread is varying scope of BIM in different projects. In some
projects, BIM savings were measured using 'real' construction phase 'direct' collision detection
cost avoidance, and in other projects, savings were computed using 'planning' or 'value analysis'
phase cost avoidance. Also, note that none of these cost figures account for indirect, design,
construction or owner administrative or other 'second wave' cost savings that were realized as a
result of BIM implementation. Hence the actual BIM ROI can be far greater than reported here.
BIM Risks
The first legal risk to determine is ownership of the BIM data and how to protect it through
copyright and other laws. For example, if the owner is paying for the design, then the owner may
feel entitled to own it, but if team members are providing proprietary information for use on the
project, their propriety information needs to be protected as well. Thus, there is no simple answer
to the question of data ownership; it requires a unique response to every project depending on the
participants' needs. The goal is to avoid inhibitions or disincentives that discourage participants
from fully realizing the model's potential (Thompson, 2001).
When project team members, other than the owner and A/E, contribute data that is integrated
into the BIM, licensing issues can arise. For example, equipment and material vendors offer
designs associated with their products for the convenience of the lead designer in hopes of
inducing the designer to specify the vendor's equipment. While this practice might be good for
business, licensing issues can nevertheless arise if the vendor's design was produced by a
designer not licensed in the location of the project (Thompson and Miner, 2007).
Another issue to address is who will control the entry of data into the model and be responsible
for any inaccuracies in it. Taking responsibility for updating BIM data and ensuring its accuracy
entails a great deal of risk. Requests for complicated indemnities by BIM users and the offer of
limited warranties and disclaimers of liability by designers will be essential negotiation points
that need to be resolved before BIM technology is utilized. It also requires more time spent
imputing and reviewing BIM data, which is a new cost in the design and project administration
process. Although these new costs may be more than offset by efficiency and schedule gains,
they are still a cost that someone on the project team will have to bear. Thus, before BIM
technology can be fully utilized, the risks of its use must not only be identified and allocated, but
the cost of its implementation must be paid for as well (Thompson and Miner, 2007).
The integrated concept of BIM blurs the level of responsibility so much that risk and liability
will likely be enhanced. Consider the scenario where the owner of the building files suit over a
perceived design error. The architect, engineers and other contributors of the BIM process look
to each other in an effort to try to determine who had responsibility for the matter raised. If
disagreement ensues, the lead professional will not only be responsible as a matter of law to the
claimant but may have difficulty proving fault with others such as the engineers (Rosenburg,
2007).
As the dimensions of cost and schedule are layered onto the 3D model, responsibility for the
proper technological interface among various programs becomes an issue. Many sophisticated
contracting teams require subcontractors to submit detailed CPM schedules and cost breakdowns
itemized by line items of work prior to the start of the project. The general contractor then
compiles that data, creating a master schedule and cost breakdown for the entire project. When
the subcontractors and prime contractor use the same software, the integration can be fluid. In
cases where the data is incomplete or is submitted in a variety of scheduling and costing
programs, a team member - usually a general contractor or construction manager must re-enter
and update a master scheduling and costing program. That program may be a BIM module or
another program that will be integrated with the 3-D model. At present, most of these project
management tools and the 3-D models have been developed in isolation. Responsibility for the
accuracy and coordination of cost and scheduling data must be contractually addressed
(Thompson and Miner, 2007).
BIM Future Challenges
The productivity and economic benefits of BIM to the AEC industry are widely acknowledged
and increasingly well understood. Further, the technology to implement BIM is readily available
and rapidly maturing. Yet, BIM adoption is much slower than anticipated (Fischer and Kunz,
2006). There are two main reasons, technical and managerial.
The technical reasons can be broadly classified into three categories (Bernstein and Pittman,
2005):
1. the need for well-defined transactional construction process models to eliminate data
interoperability issues,
2. the requirements that digital design data be computable, and
3. the need for well-developed practical strategies for the purposeful exchange and integration
of meaningful information among the BIM model components.
The management issues cluster around the implementation and use of BIM. Right now there is
no clear consensus as how to implement or use BIM. Unlike many other construction practices,
there is no single document or treatise on BIM that instructs on its application or usage (AGC,
2005). Several software firms are cashing in on the “buzz” of BIM, and have programs to
address certain quantitative aspects of it, but they do not treat the process as a whole. There is a
need to standardize the BIM process and to define the guidelines for its implementation. Another
contentious issue among the AEC industry stakeholders (i.e. owners, designers and constructors)
is who should develop and operate the building information models and how should the
developmental and operational costs be distributed?
The researchers and practitioners have to develop suitable solutions to overcome these
challenges and other associated risks. As a number of researchers, practitioners, software
vendors and professional organizations are working hard to resolve these challenges, it is
expected that the use of BIM will continue to increase in the AEC industry.
In the past facilities managers have been included in the building planning process in a very
limited way, implemented maintenance strategies based on the as-built condition at the time the
owner takes possession. BIM modeling may allow facilities managers to enter the picture in the
future at a much earlier stage, where they can influence the design and construction. The visual
nature of the BIM allows all stakeholders to get important information before the building is
completed. This includes tenants, service agents as well as maintenance personnel. Finding the
right time to include these people will undoubtedly be a challenge for owners.
Conclusions
Building Information Modeling (BIM) is emerging as an innovative way to manage projects.
Building performance and predictability of outcomes are greatly improved by adopting BIM. As
the use of BIM accelerates, collaboration within project teams should increase, which will lead to
improved profitability, reduced costs, better time management and improved customer/client
relationships. As shown in this paper, average BIM return on investment is 9486%, which clearly
depicts its lucrative economic benefits. On the other hand, teams implementing BIM should be
very careful about the legal pitfalls such as data ownership and associated propriety issues and
risk sharing. Such issues must be addressed upfront in the contract documents. BIM represents a
new paradigm within AEC, one that encourages integration of the roles of all stakeholders on a
project. This has the potential to bring about great efficiency as well as harmony among players
who all too often in the past saw themselves as adversaries. As in most paradigm shifts there will
undoubtedly be risks associated with this change. Perhaps one of the greatest risk is the potential
elimination of an important checks and balance mechanism inherent in the current paradigm. An
adversarial stance often brings a more critical review of the project in a kind of mutual guarding
of their own interests among the participants. In the early stages of BIM, constructors worked
from architectural plans since digital models were not shared by architects with contractors. The
construction modelers inevitably discovered errors and inconsistencies in the plans as they
created the BIM. This brought about a natural redundancy as the construction model put the
design to this virtual building test. With a more trustful sharing of architectural drawings, which
can be easily be imported and serve as the basis for the BIM model, there may be a loss of this
critical checking phase. In other words when all players see themselves on the same team they
may cease to look for and find mistakes in each other’s work. In the past, a lack of critical review
has been at least one of the component ingredients of building failure.
Disclaimer
The opinions and recommendations expressed in this paper are the authors' personal opinions
and do not necessarily represent the official position of any participating organization.
Acknowledgements
The authors would like to express their gratitude to Mr. Paul Hedgepath, Holder Construction
Company, Atlanta, GA and Mr. Christopher Ritter, PCL Construction Services, Orlando, FL for
providing necessary data and feedback. This study is supported by the Faculty Mentoring Grant
provided by the Office of the Vice-President for Research at Auburn University, Alabama.
References
Associated General Contractors of America. (2005). The Contractor’s Guide to BIM, 1st ed.
AGC Research Foundation, Las Vegas, NV.
Bazjanac, V. (October 23, 2006). Virtual Building Environments (VBE) – Applying Information
Modeling to Buildings [WWW document]. URL http://repositories.cdlib.org/lbnl/LBNL56072
Bernstein, P.G., and Pittman, J.H. (2005). “Barriers to the Adoption of Building Information
Modeling in the Building Industry”. Autodesk Building Solutions Whitepaper, Autodesk
Inc., CA.
CIFE. (November 22, 2007). CIFE Technical Reports [WWW document] URL
http://cife.stanford.edu/Publications/index.html
CRC Construction Innovation. (2007). Adopting BIM for Facilities Management: Solutions for
Managing the Sydney Opera House, Cooperative Research Center for Construction
Innovation, Brisbane, Australia.
Dean, R. (2007). Building Information Modeling (BIM): Should Auburn University Teach BIM to
Building Science Students? Graduate Capstone, Department of Building Science, Auburn
University.
Fischer, M., and Kunz, J. (November 12, 2006). The Scope and Role of Information Technology
in Construction [WWW document]. URL
http://cife.stanford.edu/online.publications/TR156.pdf
Khemlani, L. (November 22, 2007). “Top Criteria for BIM Solutions”, AECbytes, October issue
[WWW document] URL http://www.aecbytes.com.
Khemlani, L.; Papamichael, K.; and Harfmann, A. (November 02, 2006). The Potential of
Digital Building Modeling [WWW document]. URL
http://www.aia.org/SiteObjects/files/potentialofdigital.pdf
Kunz, J., and Gilligan, B. (October 23, 2007). Values from VDC/BIM Use [WWW document].
URL http://cife.stanford.edu/VDCsurvey.pdf
Rosenburg, T.L. (2007). “Building Information Modeling.” [WWW document] URL
http://www.ralaw.com/resources/documents/Building%20Information%20Modeling%20%20Rosenberg.pdf
Thompson, D.,B. (2001). “e-Construction: Don’t Get Soaked by the Next wave.” The
Construction Law Briefing Paper [WWW document] URL
http://www.minnlaw.com/Articles/68553.pdf
Thompson, D.B., and Miner, R.G. (November 23, 2007). “Building Information Modeling BIM: Contractual Risks are Changing with Technology” [WWW document] URL
http://www.aepronet.org/ge/no35.html
Woo, J. H. (2006). “BIM (Building Information Modeling) and Pedagogical Challenges”.
Proceedings of the 43rd ASC National Annual Conference, Flagstaff, AZ, April 12-14.