RAB
RAB
RAB
1 PRELIMENARY Rp 2,718,006,000.00
2 PEKERJAAN STRUKTUR BAWAH Rp 2,235,646,111.16
3 PEKERJAAN STRUKTUR ATAS Rp 6,574,731,644.25
4 PEKERJAAN ARSITEKTUR Rp 7,895,022,883.86
5 PEKERJAAN MEKANIKAL ELEKTRIKAL PLUMBING Rp 5,705,375,937.00
TOTAL BIAYA PEKERJAAN Rp 25,128,782,576.27
Terbilang : Dua Puluh Lima Milyar Seratus Dua Puluh Delapan Juta Tujuh Ratus Delapan Puluh Dua Ribu Lima Ratus Tujuh Puluh Enam Rupiah.
MARCOS
DIREKTUR UTAMA
PEKERJAAN PEMBANGUNAN HOTEL YAMA RESORT
TONDANO
V. PEKERJAAN PLUMBING
5.1.3.Lantai Tiga
a. Pemipaan Polypropelyne PN.10
- Diameter 3/4" 80.00 m' 26,520.00 2,121,600.00
- Diameter 2" 10.00 m' 145,490.00 1,454,900.00
b. Gate Valve
- Diameter 2" 6.00 bh 459,780.00 2,758,680.00
c. Socket
- Diameter 3/4" 10.00 bh 12,000.00 120,000.00
- Diameter 2" 6.00 bh 25,200.00 151,200.00
d. Elbow
- Diameter 3/4" 12.00 bh 5,200.00 62,400.00
- Diameter 2" 4.00 bh 10,200.00 40,800.00
e. Tee
- Diameter 3/4" 10.00 bh 5,200.00 52,000.00
- Diameter 2" 2.00 bh 16,000.00 32,000.00
f. Material Bantu(Mur-Baut, Flens, Support, Klem, Fitting, dll.) 1.00 ls 61,300.00 61,300.00
JUMLAH 19,901,070.00
5.2. PEKERJAAN AIR KOTOR
5.2.1. Lantai Satu
a. Distribusi Air Kotor ke Biofill
- Pemipaan Air Kotor dan Bekas PVC Tipe AW Kelas 10 kg/ 8.00 m' 117,750.00 942,000.00
- PVC Diameter 4" 8.00 m' 309,560.00 2,476,480.00
- PVC Diameter 6"
- Elbow 2.00 bh 70,800.00 141,600.00
- Diameter 4" 2.00 bh 78,000.00 156,000.00
- Diameter 6"
- Socket 2.00 bh 51,000.00 102,000.00
- Diameter 4" 2.00 bh 60,000.00 120,000.00
- Diameter 6"
b. Distribusi Air Kotor Tiap Lantai
- Pemipaan Air Kotor dan Bekas PVC Tipe AW Kelas 10 kg/cm2
- PVC Diameter 2" 4.00 m' 72,020.00 288,080.00
- PVC Diameter 4" 35.00 m' 117,750.00 4,121,250.00
- Elbow
- Diameter 2" 4.00 bh 15,000.00 60,000.00
- Diameter 4" 4.00 bh 51,000.00 204,000.00
- Socket
- Diameter 2" 6.00 bh 25,200.00 151,200.00
- Diameter 4" 6.00 bh 51,000.00 306,000.00
- Tee-Wye
- Diameter 2" x 4" 6.00 bh 102,000.00 612,000.00
- Diameter 4" x 6" 4.00 bh 150,000.00 600,000.00
5.2.2.Lantai Dua
a. Distribusi Air Kotor
- Pemipaan Air Kotor dan Bekas PVC Tipe AW Kelas 10 kg/ 45.00 m' 72,020.00 3,240,900.00
- PVC Diameter 2" 35.00 m' 117,750.00 4,121,250.00
- PVC Diameter 4"
- Elbow 12.00 bh 15,000.00 180,000.00
- Diameter 4" 12.00 bh 51,000.00 612,000.00
- Diameter 6"
- Socket 6.00 bh 25,200.00 151,200.00
- Diameter 4" 6.00 bh 51,000.00 306,000.00
- Diameter 6"
- Tee-Wye 6.00 bh 102,000.00 612,000.00
- Diameter 2" x 4" 4.00 bh 150,000.00 600,000.00
- Diameter 4" x 6"
b. Shaft
- Pemipaan Air Kotor dan Bekas PVC Tipe AW Kelas 10 kg/cm2
- PVC Diameter 4" 40.00 m' 117,750.00 4,710,000.00
- PVC Diameter 6" 40.00 m' 309,560.00 12,382,400.00
JUMLAH 37,196,360.00
5.3. PEKERJAAN TALANG AIR HUJAN
1. Pemipaan Tipe AW Kelas 10 kg/cm2
- PVC Diameter 4" 160.00 m' 134,710.00 21,553,600.00
NO URAIAN PEKERJAAN VOLUME SAT HARGA SATUAN SUB JUMLAH HARGA
a b c d Material g = (c x f)
- Material Bantu (Mur-baut, Flens, Support, Klem, Fitting, dll 1.00 ls 431,070.00 431,070.00
2. Roof Drain
- RD Diameter 4" 16.00 bh 365,200.00 5,843,200.00
JUMLAH 27,827,870.00
5.4. PEKERJAAN LAINNYA
- Testing dan Commisioning 1.00 ls 10,000,000.00 10,000,000.00
JUMLAH 10,000,000.00
TOTAL PEKEJERAAN PLUMBING 94,925,300.00
NO URAIAN PEKERJAAN VOLUME SAT HARGA SATUAN SUB JUMLAH HARGA
a b c d Material g = (c x f)
STRUKTUR
II. PEKERJAAN STRUKTUR ATAS
2.1. PEKERJAAN KOLOM
a. KOLOM K1
- Kolom IWF 482.300.11,15 11,680.00 kg 20,700.00 241,776,000.00
- Plat Penyambung t=12 mm 2,134.00 kg 20,700.00 44,173,800.00
- Plat kopel t=15 mm 1,245.00 kg 20,700.00 25,771,500.00
- Baut, Mur dia 16 mm 480.00 bh 18,750.00 9,000,000.00
- Plat Dudukan t = 20 mm 1,278.00 kg 20,700.00 26,454,600.00
- Baut, Angkur dia 25 mm 80.00 bh 41,250.00 3,300,000.00
b. KOLOM K2
- Kolom IWF 450.200.9,14 47,432.00 kg 20,700.00 981,842,400.00
- Plat Penyambung t=12 mm 1,513.00 kg 20,700.00 31,319,100.00
- Plat kopel t=15 mm 1,675.00 kg 20,700.00 34,672,500.00
- Baut, Mur dia 16 mm 2,940.00 bh 18,750.00 55,125,000.00
- Plat Dudukan t = 20 mm 1,214.00 kg 20,700.00 25,129,800.00
- Baut, Angkur dia 25 mm 392.00 bh 41,250.00 16,170,000.00
c. KOLOM K3
- Kolom IWF 400.200.9,14 26,070.00 kg 20,700.00 539,649,000.00
- Plat Penyambung t=12 mm 2,317.00 kg 20,700.00 47,961,900.00
- Plat kopel t=15 mm 2,117.00 kg 20,700.00 43,821,900.00
- Baut, Mur dia 16 mm 3,160.00 bh 18,750.00 59,250,000.00
- Plat Dudukan t = 20 mm 1,145.00 kg 20,700.00 23,701,500.00
- Baut, Angkur dia 25 mm 316.00 bh 41,250.00 13,035,000.00
d. KOLOM K4
- Kolom IWF 350.175.7,11 23,058.00 kg 20,700.00 477,300,600.00
- Plat Penyambung t=12 mm 2,317.00 kg 20,700.00 47,961,900.00
- Plat kopel t=15 mm 2,117.00 kg 20,700.00 43,821,900.00
- Baut, Mur dia 16 mm 3,660.00 bh 18,750.00 68,625,000.00
- Plat Dudukan t = 20 mm 1,145.00 kg 20,700.00 23,701,500.00
- Baut, Angkur dia 25 mm 488.00 bh 41,250.00 20,130,000.00
e. KOLOM K6
- Kolom IWF 250.125.6,9 2,380.00 kg 20,700.00 49,266,000.00
- Plat Penyambung t=12 mm 2,317.00 kg 20,700.00 47,961,900.00
- Plat kopel t=15 mm 2,117.00 kg 20,700.00 43,821,900.00
- Baut, Mur dia 16 mm 630.00 bh 18,750.00 11,812,500.00
- Plat Dudukan t = 20 mm 1,145.00 kg 20,700.00 23,701,500.00
- Baut, Angkur dia 25 mm 32.00 bh 41,250.00 1,320,000.00
JUMLAH 3,081,578,700.00
2.2. PEKERJAAN SAMBUNGAN KOLOM
a. PEKERJAAN BADAN WF 482 - WF 450
- Plat Penyambung t=12 mm 3,245.00 kg 20,700.00 67,171,500.00
- Plat Pengsi t=16 mm 2,235.00 kg 20,700.00 46,264,500.00
- Baut, Mur dia 19 mm 125.00 bh 18,750.00 2,343,750.00
PEKERJAAN FLENS WF 482 - WF 450
- Plat Penyambung t=12 mm 2,314.00 kg 20,700.00 47,899,800.00
- Baut, Mur dia 19 mm 85.00 bh 18,750.00 1,593,750.00
b. PEKERJAAN BADAN WF 450 - WF 350
- Plat Penyambung t=12 mm 2,314.00 kg 20,700.00 47,899,800.00
- Plat Pengisi t=25 mm 2,314.00 kg 20,700.00 47,899,800.00
- Baut, Mur dia 19 mm 46.00 bh 18,750.00 862,500.00
PEKERJAAN FLENS WF 482 - WF 450
- Plat Penyambung t=12 mm 2,314.00 kg 20,700.00 47,899,800.00
- Baut, Mur dia 19 mm 46.00 bh 18,750.00 862,500.00
JUMLAH 310,697,700.00
2.3. PEKERJAAN BALOK
BALOK INDUK
a. BALOK B1
- Balok HC 600.200.8.13 11,731.00 kg 20,700.00 242,831,700.00
- Plat Penyambung t=10 mm 1,246.00 kg 20,700.00 25,792,200.00
- Plat Pengaku t=10 mm 1,146.00 kg 20,700.00 23,722,200.00
- Baut, Mur dia 22 mm 75.00 bh 18,750.00 1,406,250.00
b. BALOK B2
- Balok HC 525.175.7.11 3,251.00 kg 20,700.00 67,295,700.00
- Plat Penyambung t=10 mm 1,246.00 kg 20,700.00 25,792,200.00
- Plat Pengaku t=10 mm 1,146.00 kg 20,700.00 23,722,200.00
- Baut, Mur dia 19 mm 75.00 bh 18,750.00 1,406,250.00
c. BALOK B3
- Balok HC 450.150.6.5,9 3,251.00 kg 20,700.00 67,295,700.00
- Plat Penyambung t=10 mm 1,246.00 kg 20,700.00 25,792,200.00
- Plat Pengaku t=10 mm 1,146.00 kg 20,700.00 23,722,200.00
- Baut, Mur dia 16 mm 75.00 bh 18,750.00 1,406,250.00
d. BALOK B4
- Balok HC 5375.125.6.9 3,251.00 kg 20,700.00 67,295,700.00
- Plat Penyambung t=10 mm 1,246.00 kg 20,700.00 25,792,200.00
NO URAIAN PEKERJAAN VOLUME SAT HARGA SATUAN SUB JUMLAH HARGA
a b c d Material g = (c x f)
- Plat Pengaku t=10 mm 1,146.00 kg 20,700.00 23,722,200.00
- Baut, Mur dia 16 mm 75.00 bh 18,750.00 1,406,250.00
e. BALOK B5
- Balok HC 300.100.5,5.8 3,251.00 kg 20,700.00 67,295,700.00
- Plat Penyambung t=10 mm 1,246.00 kg 20,700.00 25,792,200.00
- Plat Pengaku t=10 mm 1,146.00 kg 20,700.00 23,722,200.00
- Baut, Mur dia 12 mm 75.00 bh 18,750.00 1,406,250.00
BALOK ANAK
BALOK B2
- Balok HC 525.175.7.11 3,251.00 kg 20,700.00 67,295,700.00
- Plat Penyambung t=10 mm 1,246.00 kg 20,700.00 25,792,200.00
- Plat Pengaku t=10 mm 1,146.00 kg 20,700.00 23,722,200.00
- Baut, Mur dia 19 mm 75.00 bh 18,750.00 1,406,250.00
BALOK B3
- Balok HC 450.150.6.5,9 3,251.00 kg 20,700.00 67,295,700.00
- Plat Penyambung t=10 mm 1,246.00 kg 20,700.00 25,792,200.00
- Plat Pengaku t=10 mm 1,146.00 kg 20,700.00 23,722,200.00
- Baut, Mur dia 16 mm 75.00 bh 18,750.00 1,406,250.00
BALOK B4
- Balok HC 5375.125.6.9 3,251.00 kg 20,700.00 67,295,700.00
- Plat Penyambung t=10 mm 1,246.00 kg 20,700.00 25,792,200.00
- Plat Pengaku t=10 mm 1,146.00 kg 20,700.00 23,722,200.00
- Baut, Mur dia 16 mm 75.00 bh 18,750.00 1,406,250.00
BALOK B5
- Balok HC 300.100.5,5.8 3,251.00 kg 20,700.00 67,295,700.00
- Plat Penyambung t=10 mm 1,246.00 kg 20,700.00 25,792,200.00
- Plat Pengaku t=10 mm 1,146.00 kg 20,700.00 23,722,200.00
- Baut, Mur dia 12 mm 75.00 bh 18,750.00 1,406,250.00
BALOK B6
- Balok HC 255.75.5.7 3,251.00 kg 20,700.00 67,295,700.00
- Plat Penyambung t=10 mm 1,246.00 kg 20,700.00 25,792,200.00
- Plat Pengaku t=10 mm 1,146.00 kg 20,700.00 23,722,200.00
- Baut, Mur dia 12 mm 75.00 bh 18,750.00 1,406,250.00
JUMLAH 1,357,699,500.00
2.4. PEKERJAAN PLAT BETON
a. PEKERJAAN SHEAR CONNECTOR
- Besi D 13 3,594.00 kg 12,762.75 45,869,323.50
b. PEKERJAAN PLAT LANTAI BETON
- Pembesian 3,214.00 kg 12,762.75 41,019,478.50
- Bekisting Bondage 2,341.00 m2 67,500.00 158,017,500.00
- Beton K-300 312.00 m3 1,238,154.75 386,304,282.00
c. PEKERJAAN TANGGA
- Pembesian 2,135.00 kg 12,762.75 27,248,471.25
- Bekisting Bondage 578.00 m2 67,500.00 39,015,000.00
- Beton K-300 67.00 m3 1,238,154.75 82,956,368.25
JUMLAH 780,430,423.50
III. PEKERJAAN STRUKTUR ATAP
a. PEKERJAAN TALANG BETON & DUDUKAN ANGKUR
- Pembesian 1,925.00 kg 12,762.75 24,568,293.75
- Bekisting Plywood 211.00 m2 180,096.00 38,000,256.00
- Beton K-300 36.00 m3 1,238,154.75 44,573,571.00
- Baut, Angkur dia 25 mm 52.00 bh 41,250.00 2,145,000.00
b. STRUKTUR ATAP HOTEL
- RAFTER HC 375.125.6,9 11,459.00 kg 20,700.00 237,201,300.00
- Plat Penyambung t = 10 mm 1,745.00 kg 20,700.00 36,121,500.00
- Baut, Mur dia 16 mm 276.00 bh 18,750.00 5,175,000.00
- Besi Siku 60.60 3,890.00 kg 20,700.00 80,523,000.00
b. STRUKTUR ATAP BALLROOM
- RAFTER HC 450.150.6.5,9 16,882.00 kg 20,700.00 349,457,400.00
- IWF 150.75 573.00 kg 20,700.00 11,861,100.00
- Plat Penyambung t = 10 mm 1,045.00 kg 20,700.00 21,631,500.00
- Baut, Mur dia 12 mm 75.00 bh 18,750.00 1,406,250.00
- Baut, Mur dia 16 mm 85.00 bh 18,750.00 1,593,750.00
- Besi Siku 60.60 1,989.00 kg 20,700.00 41,172,300.00
- Besi Canal 125.50.20 6,449.00 kg 20,700.00 133,494,300.00
- Trekstang D 10 mm 744.00 kg 20,700.00 15,400,800.00
JUMLAH 1,044,325,320.75
TOTAL PEKERJAAN STRUKTUR ATAS 6,574,731,644.25
PEKERJAAN PEMBANGUNAN HOTEL YAMA RESORT - TONDANO
STRUKTUR
I. PEKERJAAN STRUKTUR BAWAH
1.1. PEMASANGAN TIANG PANCANG 25 X 25
a. Tiang Pancang P1 98.00 titik 2,490,000.00 244,020,000.00
b. Tiang Pancang P2 154.00 titik 2,490,000.00 383,460,000.00
c. Tiang Pancang P3 42.00 titik 2,490,000.00 104,580,000.00
JUMLAH 732,060,000.00
1.2. PEMOTONGAN TIANG PANCANG 25 X 25
a. Tiang Pancang P1 98.00 titik 138,750.00 13,597,500.00
b. Tiang Pancang P2 154.00 titik 138,750.00 21,367,500.00
c. Tiang Pancang P3 42.00 titik 138,750.00 5,827,500.00
JUMLAH 40,792,500.00
1.3. PEKERJAAN PILECAP
a. Pile Cap P1
- Galian Tanah 26.46 m3 53,437.50 1,413,956.25
- Urugan Pasir 3.53 m3 343,162.50 1,211,363.63
- Lantai Kerja 1.76 m3 1,062,708.00 1,870,366.08
- Pembesian 6,056.73 Kg 12,762.75 77,300,530.81
- Bekisting Batako 141.12 m2 125,216.25 17,670,517.20
- Beton K-300 21.17 m3 1,238,154.75 26,211,736.06
b. Pile Cap P2
- Galian Tanah 41.58 m3 53,437.50 2,221,931.25
- Urugan Pasir 5.54 m3 343,162.50 1,901,120.25
- Lantai Kerja 2.77 m3 1,062,708.00 2,943,701.16
- Pembesian 7,257.71 Kg 12,762.75 92,628,338.30
- Bekisting Batako 166.32 m2 125,216.25 20,825,966.70
- Beton K-300 33.26 m3 1,238,154.75 41,181,026.99
c. Pile Cap P3
- Galian Tanah 45.36 m3 53,437.50 2,423,925.00
- Urugan Pasir 6.05 m3 343,162.50 2,076,133.13
- Lantai Kerja 3.02 m3 1,062,708.00 3,209,378.16
- Pembesian 6,209.85 Kg 12,762.75 79,254,763.09
- Bekisting Batako 120.96 m2 125,216.25 15,146,157.60
- Beton K-300 36.29 m3 1,238,154.75 44,932,635.88
JUMLAH 434,423,547.52
1.4. PEKERJAAN KOLOM PEDESTAL (KAKI KOLOM)
a. Kolom K1
- Pembesian 923.20 Kg 14,262.75 13,167,370.80
- Bekisting Plywood 24.00 m2 180,096.00 4,322,304.00
- Beton K-300 2.88 m3 1,238,154.75 3,565,885.68
b. Kolom K2
- Pembesian 2,562.00 Kg 14,262.75 36,541,165.50
- Bekisting Plywood 99.96 m2 180,096.00 18,002,396.16
- Beton K-300 9.70 m3 1,238,154.75 12,010,101.08
c. Kolom K3
- Pembesian 1,175.36 Kg 14,262.75 16,763,865.84
- Bekisting Plywood 75.84 m2 180,096.00 13,658,480.64
- Beton K-300 7.11 m3 1,238,154.75 8,803,280.27
d. Kolom K4
- Pembesian 3,217.00 Kg 14,262.75 45,883,266.75
- Bekisting Plywood 107.10 m2 180,096.00 19,288,281.60
- Beton K-300 9.13 m3 1,238,154.75 11,304,352.87
e. Kolom K6
- Pembesian 1,098.00 Kg 14,262.75 15,660,499.50
- Bekisting Plywood 29.98 m2 180,096.00 5,399,278.08
- Beton K-300 1.98 m3 1,238,154.75 2,451,546.41
JUMLAH 226,822,075.17
1.5. PEKERJAAN TIE BEAM
a. Tie Beam B1
- Galian Tanah 47.00 m3 53,437.50 2,511,562.50
- Urugan Pasir Bawah Pondasi 35.00 m3 343,162.50 12,010,687.50
- Lantai Kerja 20.00 m3 1,062,708.00 21,254,160.00
- Pembesian 9,505.00 Kg 12,762.75 121,309,938.75
- Bekisting Batako 419.00 m2 125,216.25 52,465,608.75
- Beton K-300 45.00 m3 1,238,154.75 55,716,963.75
b. Tie Beam B3
NO URAIAN PEKERJAAN VOLUME SAT HARGA SATUAN SUB JUMLAH HARGA
a b c d Material g = (c x f)
- Galian Tanah 63.44 m3 53,437.50 3,390,075.00
- Urugan Pasir Bawah Pondasi 79.30 m3 343,162.50 27,212,786.25
- Lantai Kerja 39.65 m3 1,062,708.00 42,136,372.20
- Pembesian 10,965.00 Kg 12,762.75 139,943,553.75
- Bekisting Batako 793.00 m2 125,216.25 99,296,486.25
- Beton K-300 93.30 m3 1,238,154.75 115,519,838.18
c. Tie Beam B4
- Galian Tanah 11.28 m3 53,437.50 602,775.00
- Urugan Pasir Bawah Pondasi 18.80 m3 343,162.50 6,451,455.00
- Lantai Kerja 12.00 m3 1,062,708.00 12,752,496.00
- Pembesian 1,992.00 Kg 12,762.75 25,423,398.00
- Bekisting Batako 112.00 m2 125,216.25 14,024,220.00
- Beton K-300 11.28 m3 1,238,154.75 13,966,385.58
JUMLAH 765,988,762.46
1.6. PEKERJAAN PONDASI BATU KALI
- Galian Tanah 40.00 m3 53,437.50 2,137,500.00
- Urugan Pasir Bawah Pondasi 9.80 m3 343,162.50 3,362,992.50
- Pasangan Batu Kali 1 : 4 37.28 m3 806,296.50 30,058,733.52
JUMLAH 35,559,226.02
TOTAL PEKERJAAN STRUKTUR BAWAH 2,235,646,111.16