TD2 Solution MPM Pert F
TD2 Solution MPM Pert F
TD2 Solution MPM Pert F
: Solution
1) Les Niveaux :
Niveau 0 : A, B
Niveau 1 : C, D
Niveau 2 : E, F
Niveau 3 : G, H
2) Graphe MPM :
7 3 8
0 3 9 10 13 13 21 21 5
A C E H
26 26
4
9 Z(Fin)
8
3
9 9 4
0 0 D 13 15 21 22
B 4 F G
9 7
Mt(B) = 0- 0 = 0
Mt(C) = 10 – 9 = 1
Mt(D) = 9 – 9 = 0
Mt(E) = 13 – 13 = 0
Mt(F) = 15 – 13 = 2
Mt(G) = 22 – 21 = 1
Mt(H) = 21 – 21 =0
ml = min(ty – tx – dx )
ml(A) = min(9 – 0 – 7 ) = 2
8) Puisque A n’appartient pas au chemin critique le retard de 1 par jours ne va pas changer la
durée de Projet et aussi sur le tâches placé directement après A
PERT
A, B
B
E, F
E
Mt(A) = 10– 0 – 7 = 3
Mt(B) = 9- 0 - 9 = 0
Mt(C) = 13 – 9 – 3 = 1
Mt(D) = 13 – 9 – 4 = 0
Mt(E) = 21 – 13 – 8 = 0
Mt(F) = 22 – 13 – 7 = 2
Mt(G) = 26 – 21 – 4 = 1
Mt(H) = 26 – 21 – 5 = 0
ml = min(tj – ti – dij )
ml(A) = min(9 – 0 – 7 ) = 2
ml(B) = min(9 – 0 – 9) = 0
ml(D) = min(13 – 9 – 4 ) = 0
ml(F) = min(21 – 13 – 7 ) = 1
ml(G) = min(26 – 21 - 4 ) = 1
ml(H) = min(26 – 21 – 5 ) = 0
La Tache Marge Total Marge Libre Marge Certaine
(t*x-tx) (min (ty-tx-dx)) (max (ty-t*x-dx))
A 3-0=3 9-0-7=2 0
B 0-0=0 9-0-9=0 9-0-9=0
C 10-9=1 13-9-3=1 13-10-3=0
D 9-9=0 13-9-4=0 13-9-4=0
E 13-13=0 21-13-8=0 21-13-8=0
F 15-13=2 21-13-7=1 0
G 22-21=1 26-21-4=1 26-22-4=0
H 21-21=0 26-21-5=0 26-21-5=0