QUANTITE DE BRIQUE


H L Surface briques briques 8 trous
S/SOL 2.46 270.73 666.00 13,187 591.46
RDC 4.08 374.88 1,529.51 30,284 1,280.02
1 3.00 316.74 950.22 18,814 529.14
2 3.00 253.42 760.26 15,053 415.86
3 3.00 253.42 760.26 15,053 415.86
4 3.00 253.42 760.26 15,053 415.86
5 3.00 124.26 372.78 7,381 275.88
terrasse 3.00 121.35
5,799.29 114,826 3,924.08

qtité de briq 77,697

niveau surface
enduits exterieurs 613.75 2,488.96 16.59
S/SOL 1,205.21 8.03
RDC 2,560.04 17.07
1 1,058.28 7.06
2 831.72 5.54
3 831.72 5.54
4 831.72 5.54
5 551.76 3.68
terrasse 121.35 0.81
TOTAL 10,480.75
U m² U
Briques 12 Trous
11,711 74.54 1,476
25,344 249.49 4,940
10,477 421.08 8,337
8,234 344.40 6,819
8,234 344.40 6,819
8,234 344.40 6,819
5,462 96.90 1,919
121.35
77,697 1,875.21 37,129

37,129

5,799.29
1,159.86
57,992.86
niveau surface % jours
26.93 145M²
+24,04 487.00 31.72 15.86
+20,44 255.40 16.64 8.32
+16,84 84.00 5.47 2.74
+13,24 71.50 4.66 2.33
+9,64 71.50 4.66 2.33
+6,04 113.30 7.38 3.69
+1,36 452.50 29.47 14.74 455.75
TOTAL 1,535.20 100.00 50.00
QUANTITATIF DE REVETEMENT DE S

NIVEAUX travertin
0.468 S/SOL 24.60
0.504 RDC 866.70
1er 570.00
2eme 638.50
3eme 638.50
4eme 617.25
5eme 561.01
terrasse 108.06
TOTAL 4024.62

QUANTITATIF DE REVETEMENT DE M

NIVEAUX ascenseur
S/SOL 6.56
RDC 6.56
1er 6.56
2eme 6.56
3eme 6.56
4eme 6.56
5eme 6.56
terrasse
TOTAL 45,92M²
TIF DE REVETEMENT DE SOL

EPOXY compacto dalle


MARCHES
sur plot CONTRE MARCHE
915.50 0 7.072
52.3088 24.424
76.80 19.44 8.64
### 19.44 8.64
### 19.44 8.64
### 19.44 8.64
### 19.44 8.64
10.08 4.16
915.50 76.80
### 660.96 78.86

TIF DE REVETEMENT DE MUR

sanitaires PLINTHE Colonne2


25.872 200 32.432
102.62 300 109.176
80.10 700 86.664
64.67 700 71.232
64.67 700 71.232
64.67 700 71.232
68.27 300 74.832
60 0
470,88M² 3562###
ml
SURFACE DE PEINTURE INTERIEURE/EXTERIEURE

NIVEAUX HAUTEUR PERIMETRE ouvertures


S/SOL 2.80 454.8 64.596
RDC 3.80 502.95 182.724
1er 2.80 602.35 175.316
2eme 2.80 697.05 593.71
3eme 2.80 697.05 593.71
4eme 2.80 677.15 524.138
5eme 2.80 550.69 291.42
terrasse 2.80 117.81 53.388
TOTAL 4299.85

EXTERIEURE
EURE/EXTERIEURE

SURFACE
1,208.84 2.42 8.00
1,728.49 3.46 9.00
1,511.26 3.02 9.00
1,358.03 2.72 8.00
1,358.03 2.72 8.00
1,371.88 2.74 8.00
1,250.51 2.50 8.00
276.48 0.55 6.00
10,063.53 20.13 26.00
- 5.00
- 5.00
3,790.35 7.58 13.00
cloison seche

H L Surface
S/SOL 2.46 -
RDC 4.08 54.03 220.44 4.59
1 3.00 92.20 276.60 5.76
2 3.00 98.72 296.16 6.17
3 3.00 98.72 296.16 6.17
4 3.00 98.72 296.16 6.17
5 3.00 90.96 272.88 5.69
terrasse 3.00 0.00 -
1,658.40
CLOISONS VITREES

H Q Surface
S/SOL 0 -
RDC 2 -
1 5 -
2 19 -
3 19 -
4 18 -
5 10 -
terrasse -

216
168
menuiserie

niveau portes fenetres


S/SOL 13 2
RDC 34 7
1 22 11
2 24 18
3 24 18
4 25 22
5 25 9
Terrasse 9 10
TOTAL 176 97
chemin de cable courant fort

Longueur
S/SOL 107
RDC 66.5
1 50.5
2 59.5
3 59.5
4 59.5
5 38.7
Terrasse 10
pour l' attestation de besoin en ciment

m3 kg
chappe 5005 200,200.00
maçonnerie 5,799.29 57,992.86
beton 120 48,000.00
forme de pente 181.5 45,375.00

351,567.86

TOTAL 400 tonnes de ciment