Curva S Mes de Octubre

Descargar como xlsx, pdf o txt
Descargar como xlsx, pdf o txt
Está en la página 1de 16

MUNICIPALIDAD DISTRITAL

DE CIUDAD NUEVA
GERENCIA DE INGENIERIA
RESUMEN DE VALORIZACIÓN FÍSICA DE OBRA
JUNIO 2014

OBRA : "MEJORAMIENTO DE LA CALLE HERMANOS ANGULO DE LA AMPLIACION ASENTAMIENTO HUMANO MARGINAL CIUDAD NUEVA, DISTRITO CIUDAD NUEVA –TACNA – TACNA”
RESIDENTE : ING. JESUS GUIDO, CHOQUEGONZA CONDORI
INSPECTOR : ING. ORLANDO JARA ALMONTE VILLAROEL
FECHA : JUNIO 2014

RESUMEN DE VALORIZACIONES
SALDO POR VALORIZAR
ITEM DESCRIPCION PRESUPUESTO ACUMULADO ANTERIOR AVANCE ACTUAL ACUMULADO ACTUAL
FINAL ASIGNADO
MONTO (S/.) % MONTO (S/.) % MONTO (S/.) % MONTO (S/.) %

01 COSTO DIRECTO S/. 2,578,083.71 S/. 50,783.83 S/. 204,176.16 S/. 254,959.99 S/. 2,323,123.72

02 GASTOS GENERALES (7.0%) S/. 180,465.86 S/. 3,554.87 S/. 14,292.33 S/. 17,847.20 S/. 162,618.66

03 COSTO DE OBRA S/. 2,758,549.57 S/. 54,338.70 1.97% S/. 218,468.49 7.92% S/. 272,807.19 9.89% S/. 2,485,742.38 90.11%
2 de 16

VALORIZACIÓN FÍSICA MENSUAL


JUNIO 2014

OBRA : "MEJORAMIENTO DE LA CALLE HERMANOS ANGULO DE LA AMPLIACION ASENTAMIENTO HUMANO MARGINAL CIUDAD NUEVA, DISTRITO CIUDAD NUEVA –TACNA – TACNA”
RESIDENTE : ING. JESUS GUIDO, CHOQUEGONZA CONDORI
INSPECTOR : ING. ORLANDO JARA ALMONTE VILLAROEL
FECHA : JUNIO 2014

PRESUPUESTO PROGRAMADO EJECUTADO


SALDO
ITEM PARTIDAS ANTERIOR ACUMULADO AVANCE : JUNIO 2014 ACUMULADO ACTUAL
UND METRADO P.U. COSTO
METRADO COSTO % METRADO COSTO % METRADO COSTO % METRADO COSTO %

01 OBRAS PROVISIONALES
01.01 CARTEL DE IDENTIFICACION DE LA OBRA DE 2.40 x 3.60 m. und 1.00 1,407.69 S/. 1,407.69 - S/. - - 1.00 S/. 1,407.69 100.00 % 1.00 1,407.69 100.00 % - - -
01.02 CASETA DE ALMACEN Y GUARDIANIA m2 56.00 79.51 S/. 4,452.56 20.00 S/. 1,590.20 35.71 % 36.00 S/. 2,862.36 64.29 % 56.00 4,452.56 100.00 % - - -
01.03 MOVILIZACION Y DESMOVILIZACION DE HERRAMIENTAS Y EQUIPO GLB 1.00 4,334.00 S/. 4,334.00 - S/. - - 0.32 S/. 1,386.88 32.00 % 0.32 1,386.88 32.00 % 0.68 2,947.12 68.00 %
01.04 TRANSPORTE DE MATERIALES PARA LA OBRA GLB 1.00 3,000.00 S/. 3,000.00 0.05 S/. 150.00 5.00 % 0.20 S/. 600.00 20.00 % 0.25 750.00 25.00 % 0.75 2,250.00 75.00 %
01.05 SUMINISTRO PROVISIONAL DE AGUA GLB 1.00 900.00 S/. 900.00 - S/. - - 1.00 S/. 900.00 100.00 % 1.00 900.00 100.00 % - - -
01.06 SUMINISTRO PROVISIONAL ENERGIA ELECTRICA GLB 1.00 600.00 S/. 600.00 - S/. - - 1.00 S/. 600.00 100.00 % 1.00 600.00 100.00 % - - -
01.07 SERVICIOS HIGIENICOS PARA EL PERSONAL DE OBRA mes 6.00 600.00 S/. 3,600.00 - S/. - - 1.00 S/. 600.00 16.67 % 1.00 600.00 16.67 % 5.00 3,000.00 83.33 %
02 SEGURIDAD Y SALUD
02.01 ELABORACION, IMPLEMENTACION Y ADMINISTRACION DEL PLAN DE SEGURIDAD GLB 1.00 3,500.00 S/. 3,500.00 1.00 S/. 3,500.00 100.00 % - S/. - - 1.00 3,500.00 100.00 % - - -
02.02 EQUIPOS DE PROTECCION PERSONAL und 40.00 626.00 S/. 25,040.00 14.00 S/. 8,764.00 35.00 % 22.00 S/. 13,772.00 55.00 % 36.00 22,536.00 90.00 % 4.00 2,504.00 10.00 %
02.03 EQUIPOS DE PROTECCION COLECTIVA und 1.00 1,470.00 S/. 1,470.00 0.05 S/. 73.50 5.00 % 0.95 S/. 1,396.50 95.00 % 1.00 1,470.00 100.00 % - - -
02.04 SEÑALIZACION TEMPORAL DE SEGURIDAD GLB 1.00 1,625.00 S/. 1,625.00 0.01 S/. 16.25 1.00 % 0.99 S/. 1,608.75 99.00 % 1.00 1,625.00 100.00 % - - -
02.05 CAPACITACION SOBRE SALUD Y SEGURIDAD GLB 1.00 3,500.00 S/. 3,500.00 0.03 S/. 105.00 3.00 % 0.12 S/. 420.00 12.00 % 0.15 525.00 15.00 % 0.85 2,975.00 85.00 %
02.06 RECURSOS DE RESPUESTA DE EMERGENCIA GLB 1.00 960.07 S/. 960.07 - S/. - - 1.00 S/. 960.07 100.00 % 1.00 960.07 100.00 % - - -
03 PISOS, VEREDAS Y AREAS VERDES
03.01 OBRAS PRELIMINARES
03.01.01 LIMPIEZA DE TERRENO EN FORMA MANUAL* m2 3,742.21 0.59 S/. 2,207.90 3,081.50 S/. 1,818.08 82.34 % - S/. - - 3,081.50 1,818.08 82.34 % 660.72 389.82 17.66 %
03.01.02 TRAZO Y REPLANTEO EN TERRENO NORMAL CON EQUIPO* m2 3,742.21 1.52 S/. 5,688.16 3,081.49 S/. 4,683.87 82.34 % - S/. - - 3,081.49 4,683.87 82.34 % 660.72 1,004.29 17.66 %
03.01.03 DEMOLICION DE VEREDAS Y BERMAS EXISTENTES C/EQUIPO m2 186.40 23.47 S/. 4,374.81 14.00 S/. 328.58 7.51 % 172.40 S/. 4,046.23 92.49 % 186.40 4,374.81 100.00 % - - -
03.01.04 DEMOLICION DE BANCAS DE CONCRETO m3 8.40 39.73 S/. 333.73 - S/. - - - S/. - - - - - 8.40 333.73 100.00 %
03.01.05 REUBICACION DE POSTES und 10.00 451.62 S/. 4,516.20 - S/. - - - S/. - - - - - 10.00 4,516.20 100.00 %
03.01.06 RETIRO Y REPOSICIÓN DE CAJA DE MEDIDORES DE AGUA und 192.00 89.37 S/. 17,159.04 - S/. - - 79.00 S/. 7,060.23 41.15 % 79.00 7,060.23 41.15 % 113.00 10,098.81 58.85 %
03.01.07 RETIRO Y REPOSICIÓN DE CAJAS DE REGISTRO und 192.00 135.37 S/. 25,991.04 - S/. - - 79.00 S/. 10,694.23 41.15 % 79.00 10,694.23 41.15 % 113.00 15,296.81 58.85 %
03.01.08 ACARREO DE MATERIAL EXCEDENTE D= 40 m. m3 50.90 29.80 S/. 1,516.82 - S/. - - 39.14 S/. 1,166.37 76.90 % 39.14 1,166.37 76.90 % 11.76 350.45 23.10 %
03.01.09 ELIMINACION DE MATERIAL EXCEDENTE C/MAQUINARIA m3 50.90 18.62 S/. 947.76 - S/. - - 39.14 S/. 728.79 76.90 % 39.14 728.79 76.90 % 11.76 218.97 23.10 %
03.02 MOVIMIENTO DE TIERRAS
03.02.01 CORTE SUPERFICIAL DE TERRENO MANUAL HASTA 0.20 M m2 3,742.21 6.67 S/. 24,960.54 418.56 S/. 2,791.80 11.18 % 631.61 S/. 4,212.84 16.88 % 1,050.17 7,004.64 28.06 % 2,692.04 17,955.91 71.94 %
03.02.02 CORTE Y EXCAVACION EN TERRENO SUELTO MANUAL m3 396.16 38.98 S/. 15,442.32 - S/. - - 12.81 S/. 499.33 3.23 % 12.81 499.33 3.23 % 383.35 14,942.98 96.77 %
03.02.03 PERFILADO Y COMPACTADO DE SUBRASANTE C/EQUIPO m2 3,742.21 2.41 S/. 9,018.73 - S/. - - 930.00 S/. 2,241.30 24.85 % 930.00 2,241.30 24.85 % 2,812.21 6,777.43 75.15 %
03.02.04 TERRAPLEN DE VEREDA E=0.10 M m2 3,742.21 13.98 S/. 52,316.10 - S/. - - 577.00 S/. 8,066.46 15.42 % 577.00 8,066.46 15.42 % 3,165.21 44,249.64 84.58 %
03.02.05 ACARREO DE MATERIAL EXCEDENTE D= 40 m. m3 1,487.98 29.80 S/. 44,341.80 - S/. - - 884.40 S/. 26,355.12 59.44 % 884.40 26,355.12 59.44 % 603.58 17,986.68 40.56 %
03.02.06 ELIMINACION DE MATERIAL EXCEDENTE C/MAQUINARIA m3 1,487.98 18.62 S/. 27,706.19 - S/. - - 503.03 S/. 9,366.42 33.81 % 503.03 9,366.42 33.81 % 984.95 18,339.77 66.19 %
03.03 CONCRETO SIMPLE
03.03.01 SOLADO DE 2" CON MEZCLA C:H 1:12 m2 618.21 25.44 S/. 15,727.26 - S/. - - - S/. - - - - - 618.21 15,727.26 100.00 %
03.03.02 CIMIENTOS CORRIDOS MEZCLA 1:10 CEMENTO-HORMIGON 30% P.G. 6" m3 253.49 222.33 S/. 56,358.43 - S/. - - - S/. - - - - - 253.49 56,358.43 100.00 %
03.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 248.39 37.13 S/. 9,222.72 - S/. - - - S/. - - - - - 248.39 9,222.72 100.00 %
03.04 CONCRETO ARMADO
03.04.01 SARDINELES REFORZADOS
03.04.01.01 CONCRETO F'C=175 KG/CM2 EN SARDINELES REFORZADOS m3 251.05 364.15 S/. 91,419.86 - S/. - - - S/. - - - - - 251.05 91,419.86 100.00 %
03.04.01.02 ENCOFRADO Y DESENCOFRADO CARAVISTA EN SARDINELES REFORZADOS m2 2,617.67 55.00 S/. 143,971.85 - S/. - - - S/. - - - - - 2,617.67 143,971.85 100.00 %
03.04.01.03 ACERO CORRUGADO F'Y=4200 KG/CM2 EN SARDINELES REFORZADOS kg 9,135.88 5.63 S/. 51,435.00 - S/. - - - S/. - - - - - 9,135.88 51,435.00 100.00 %
03.05 PISOS Y PAVIMENTOS
03.05.01 VEREDA DE PIEDRA LAVADA C/CEMENTO PULIDO COLOREADO F'C=175 KG/CM2 m2 2,340.49 58.28 S/. 136,403.76 - S/. - - 240.00 S/. 13,987.20 10.25 % 240.00 13,987.20 10.25 % 2,100.49 122,416.56 89.75 %
03.05.02 PISO DE CEMENTO PULIDO COLOREADO F'C=175 KG/CM2 E=0.10M. BRUÑADO m2 403.32 55.88 S/. 22,537.52 - S/. - - - S/. - - - - - 403.32 22,537.52 100.00 %
03.05.03 PISO DE CEMENTO PULIDO COLOREADO F'C=175 KG/CM2 E=0.05M. BRUÑADO m2 257.39 53.46 S/. 13,760.07 - S/. - - - S/. - - - - - 257.39 13,760.07 100.00 %
03.05.04 MARTILLOS DE PIEDRA LAVADA C/CEMENTO PULIDO F'C=175 KG/CM2 E=0.10M. m2 424.92 63.10 S/. 26,812.45 - S/. - - - S/. - - - - - 424.92 26,812.45 100.00 %
03.05.05 RAMPAS DE CEMENTO PULIDO F'C=175 KG/CM2 E=0.10M. BRUÑADO m2 136.88 51.70 S/. 7,076.70 - S/. - - - S/. - - - - - 136.88 7,076.70 100.00 %
03.05.06 GRADA DE PIEDRA LAVADA F'C=175 KG/CM2 E=4" C/DETALLES EN CEMENTO PUL m3 35.84 364.90 S/. 13,078.02 - S/. - - - S/. - - - - - 35.84 13,078.02 100.00 %
03.05.07 SARDINEL SUMERGIDO: CONCRETO F'C=175 KG/CM2 m3 83.18 315.11 S/. 26,210.85 - S/. - - 7.20 S/. 2,268.79 8.66 % 7.20 2,268.79 8.66 % 75.98 23,942.06 91.34 %
03.05.08 ENCOFRADO Y DESENCOFRADO NORMAL EN PISOS Y PAVIMENTOS m2 882.24 52.96 S/. 46,723.43 - S/. - - 110.60 S/. 5,857.38 12.54 % 110.60 5,857.38 12.54 % 771.64 40,866.05 87.46 %
03.06 REVESTIMIENTOS
03.06.01 TARRAJEO EN MUROS Y SARDINELES INC./ESCARIFICADO m2 89.07 38.83 S/. 3,458.59 - S/. - - - S/. - - - - - 89.07 3,458.59 100.00 %
03.07 PINTURA
03.07.01 PINTURA ESMALTE 02 MANOS EN SUPERFICIES DE CONCRETO m2 1,521.33 13.62 S/. 20,720.51 - S/. - - - S/. - - - - - 1,521.33 20,720.51 100.00 %
03.07.02 PINTURA ESMALTE 02 MANOS EN BORDES DE PISOS Y PAVIMENTOS m2 882.24 10.25 S/. 9,042.96 - S/. - - - S/. - - - - - 882.24 9,042.96 100.00 %
03.08 AREAS VERDES
03.08.01 SUMINISTRO Y COLOCACION DE TIERRA DE CHACRA m3 425.24 66.29 S/. 28,189.16 - S/. - - - S/. - - - - - 425.24 28,189.16 100.00 %
3 de 16

VALORIZACIÓN FÍSICA MENSUAL


JUNIO 2014

OBRA : "MEJORAMIENTO DE LA CALLE HERMANOS ANGULO DE LA AMPLIACION ASENTAMIENTO HUMANO MARGINAL CIUDAD NUEVA, DISTRITO CIUDAD NUEVA –TACNA – TACNA”
RESIDENTE : ING. JESUS GUIDO, CHOQUEGONZA CONDORI
INSPECTOR : ING. ORLANDO JARA ALMONTE VILLAROEL
FECHA : JUNIO 2014

PRESUPUESTO PROGRAMADO EJECUTADO


SALDO
ITEM PARTIDAS ANTERIOR ACUMULADO AVANCE : JUNIO 2014 ACUMULADO ACTUAL
UND METRADO P.U. COSTO
METRADO COSTO % METRADO COSTO % METRADO COSTO % METRADO COSTO %
03.08.02 SUMINISTRO Y COLOCACION DE GRASS NATURAL m2 919.23 28.70 S/. 26,381.90 - S/. - - - S/. - - - - - 919.23 26,381.90 100.00 %
03.08.03 SUMINISTRO Y COLOCACION DE ARBOLES und 69.00 45.23 S/. 3,120.87 - S/. - - - S/. - - - - - 69.00 3,120.87 100.00 %
03.09 VARIOS
03.09.01 CURADO DE PISOS Y PAVIMENTOS m2 3,742.21 1.08 S/. 4,041.59 - S/. - - 196.00 S/. 211.68 5.24 % 196.00 211.68 5.24 % 3,546.21 3,829.91 94.76 %
03.09.02 SOLAQUEADO DE VEREDAS, MARTILLOS m2 882.24 6.88 S/. 6,069.81 - S/. - - 51.60 S/. 355.01 5.85 % 51.60 355.01 5.85 % 830.64 5,714.80 94.15 %
03.09.03 IMPERMEABILIZACION ASFALTICA m2 586.86 9.47 S/. 5,557.56 - S/. - - - S/. - - - - - 586.86 5,557.56 100.00 %
03.09.04 JUNTAS DE DILATACION RELLENAS CON MEZCLA ASFALTICA E=1" m 1,053.95 5.44 S/. 5,733.49 - S/. - - - S/. - - - - - 1,053.95 5,733.49 100.00 %
04 MUROS DE CONTENCION
04.01 OBRAS PRELIMINARES
04.01.01 LIMPIEZA DE TERRENO EN FORMA MANUAL m2 119.90 0.59 S/. 70.74 - S/. - - - S/. - - - - - 119.90 70.74 100.00 %
04.01.02 TRAZO Y REPLANTEO EN TERRENO NORMAL CON EQUIPO m2 119.90 1.52 S/. 182.25 - S/. - - - S/. - - - - - 119.90 182.25 100.00 %
04.01.03 CONTROL TOPOGRAFICO C/EQUIPO m2 119.90 0.59 S/. 70.74 - S/. - - - S/. - - - - - 119.90 70.74 100.00 %
04.02 MOVIMIENTO DE TIERRAS
04.02.01 CORTE Y EXCAVACION EN TERRENO SUELTO MANUAL m3 601.18 38.98 S/. 23,434.00 - S/. - - - S/. - - - - - 601.18 23,434.00 100.00 %
04.02.02 RELLENO CON MATERIAL DE PRESTAMO C/EQUIPO m3 509.29 51.66 S/. 26,309.92 - S/. - - - S/. - - - - - 509.29 26,309.92 100.00 %
04.02.03 NIVELACION Y COMPACTADO DE TERRENO P/CIMENTACION C/EQUIPO m2 244.77 6.01 S/. 1,471.07 - S/. - - - S/. - - - - - 244.77 1,471.07 100.00 %
04.02.04 ACARREO DE MATERIAL EXCEDENTE D= 40 m. m3 119.46 29.80 S/. 3,559.91 - S/. - - - S/. - - - - - 119.46 3,559.91 100.00 %
04.02.05 ELIMINACION DE MATERIAL EXCEDENTE C/MAQUINARIA m3 119.46 18.62 S/. 2,224.35 - S/. - - - S/. - - - - - 119.46 2,224.35 100.00 %
04.03 CONCRETO SIMPLE
04.03.01 SOLADO DE E=4" CON MEZCLA C:H 1:12 PARA MUROS DE CONTENCION m2 119.90 57.14 S/. 6,851.09 - S/. - - - S/. - - - - - 119.90 6,851.09 100.00 %
04.03.02 CONCRETO F'C= 140 KG/CM2 + 30% P.G. EN MUROS DE GRAVEDAD m3 139.05 284.65 S/. 39,580.58 - S/. - - - S/. - - - - - 139.05 39,580.58 100.00 %
04.03.03 ENCOFRADO Y DESENCOFRADO NORMAL DE MUROS m2 141.69 63.30 S/. 8,968.98 - S/. - - - S/. - - - - - 141.69 8,968.98 100.00 %
04.03.04 ENCOFRADO Y DESENCOFRADO CARAVISTA EN MUROS DE GRAVEDAD m2 199.93 64.69 S/. 12,933.47 - S/. - - - S/. - - - - - 199.93 12,933.47 100.00 %
04.04 OBRAS DE CONCRETO ARMADO
04.04.01 ZAPATAS
04.04.01.01 CONCRETO F'C= 210 KG/CM2 EN TALONES m3 39.73 361.15 S/. 14,348.49 - S/. - - - S/. - - - - - 39.73 14,348.49 100.00 %
04.04.01.02 ENCOFRADO Y DESENCOFRADO NORMAL EN TALONES m2 45.00 46.96 S/. 2,113.20 - S/. - - - S/. - - - - - 45.00 2,113.20 100.00 %
04.04.01.03 ACERO CORRUGADO FY=4200 KG/CM2 EN TALONES kg 2,407.50 5.63 S/. 13,554.23 - S/. - - - S/. - - - - - 2,407.50 13,554.23 100.00 %
04.04.02 MURO
04.04.02.01 CONCRETO F'C= 210 KG/CM2. EN MURO m3 48.41 419.45 S/. 20,305.57 - S/. - - - S/. - - - - - 48.41 20,305.57 100.00 %
04.04.02.02 ENCOFRADO Y DESENCOFRADO CARAVISTA EN MURO VERTICAL m2 180.72 64.69 S/. 11,690.78 - S/. - - - S/. - - - - - 180.72 11,690.78 100.00 %
04.04.02.03 ENCOFRADO Y DESENCOFRADO NORMAL DE MUROS m2 180.72 63.30 S/. 11,439.58 - S/. - - - S/. - - - - - 180.72 11,439.58 100.00 %
04.04.02.04 ACERO CORRUGADO FY=4200 KG/CM2 EN PANTALLA VERTICAL kg 2,903.33 5.63 S/. 16,345.75 - S/. - - - S/. - - - - - 2,903.33 16,345.75 100.00 %
04.04.03 SARDINEL REFORZADO
04.04.03.01 CONCRETO F'C=175 KG/CM2 EN SARDINEL m3 4.84 350.76 S/. 1,697.68 - S/. - - - S/. - - - - - 4.84 1,697.68 100.00 %
04.04.03.02 ENCOFRADO Y DESENCOFRADO CARAVISTA EN SARDINEL m2 64.55 62.78 S/. 4,052.45 - S/. - - - S/. - - - - - 64.55 4,052.45 100.00 %
04.04.03.03 ACERO GRADO 60 EN SARDINELES kg 260.77 5.69 S/. 1,483.78 - S/. - - - S/. - - - - - 260.77 1,483.78 100.00 %
04.05 VARIOS
04.05.01 SOLAQUEADO DE MUROS m2 445.19 7.18 S/. 3,196.46 - S/. - - - S/. - - - - - 445.19 3,196.46 100.00 %
04.05.02 CURADO DE MUROS DE CONCRETO m2 767.60 3.56 S/. 2,732.66 - S/. - - - S/. - - - - - 767.60 2,732.66 100.00 %
04.05.03 IMPERMEABILIZACION DE MUROS m2 319.13 13.33 S/. 4,254.00 - S/. - - - S/. - - - - - 319.13 4,254.00 100.00 %
04.05.04 JUNTA DE CONSTRUCCION CON TEKNOPORT m 94.54 6.52 S/. 616.40 - S/. - - - S/. - - - - - 94.54 616.40 100.00 %
05 BERMAS LATERALES
05.01 OBRAS PRELIMINARES
05.01.01 LIMPIEZA DE TERRENO EN FORMA MANUAL* m2 1,322.33 0.59 S/. 780.17 1,322.33 S/. 780.17 100.00 % - S/. - - 1,322.33 780.17 100.00 % - - -
05.01.02 TRAZO Y REPLANTEO EN TERRENO NORMAL CON EQUIPO* m2 1,322.33 1.52 S/. 2,009.94 1,322.33 S/. 2,009.94 100.00 % - S/. - - 1,322.33 2,009.94 100.00 % - - -
05.01.03 CONTROL TOPOGRAFICO C/EQUIPO m2 1,322.33 0.59 S/. 780.17 - S/. - - - S/. - - - - - 1,322.33 780.17 100.00 %
05.02 MOVIMIENTO DE TIERRAS
05.02.01 CORTE SUPERFICIAL DE TERRENO MANUAL HASTA 0.20 M m2 330.58 6.67 S/. 2,204.97 - S/. - - 330.58 S/. 2,204.97 100.00 % 330.58 2,204.97 100.00 % - - -
05.02.02 PERFILADO Y COMPACTADO DE SUBRASANTE C/EQUIPO m2 1,322.33 2.41 S/. 3,186.82 - S/. - - - S/. - - - - - 1,322.33 3,186.82 100.00 %
05.02.03 ACARREO DE MATERIAL EXCEDENTE D= 40 m. m3 429.76 29.80 S/. 12,806.85 - S/. - - 150.10 S/. 4,472.98 34.93 % 150.10 4,472.98 34.93 % 279.66 8,333.87 65.07 %
05.02.04 ELIMINACION DE MATERIAL EXCEDENTE C/MAQUINARIA m3 429.76 18.62 S/. 8,002.13 - S/. - - 141.97 S/. 2,643.48 33.03 % 141.97 2,643.48 33.03 % 287.79 5,358.65 66.97 %
05.03 PAVIMENTO FLEXIBLE
05.03.01 BASE GRANULAR E=0.20M. C/EQUIPO m2 1,322.33 18.04 S/. 23,854.83 - S/. - - - S/. - - - - - 1,322.33 23,854.83 100.00 %
05.03.02 LIMPIEZA DE VIAS CON EQUIPO m2 1,322.33 0.70 S/. 925.63 - S/. - - - S/. - - - - - 1,322.33 925.63 100.00 %
05.03.03 IMPRIMACION ASFALTICA m2 1,322.33 7.83 S/. 10,353.84 - S/. - - - S/. - - - - - 1,322.33 10,353.84 100.00 %
05.03.04 CARPETA ASFALTICA E=2" EN FRIO m2 1,322.33 34.21 S/. 45,236.91 - S/. - - - S/. - - - - - 1,322.33 45,236.91 100.00 %
06 PISTAS
06.01 OBRAS PRELIMINARES
4 de 16

VALORIZACIÓN FÍSICA MENSUAL


JUNIO 2014

OBRA : "MEJORAMIENTO DE LA CALLE HERMANOS ANGULO DE LA AMPLIACION ASENTAMIENTO HUMANO MARGINAL CIUDAD NUEVA, DISTRITO CIUDAD NUEVA –TACNA – TACNA”
RESIDENTE : ING. JESUS GUIDO, CHOQUEGONZA CONDORI
INSPECTOR : ING. ORLANDO JARA ALMONTE VILLAROEL
FECHA : JUNIO 2014

PRESUPUESTO PROGRAMADO EJECUTADO


SALDO
ITEM PARTIDAS ANTERIOR ACUMULADO AVANCE : JUNIO 2014 ACUMULADO ACTUAL
UND METRADO P.U. COSTO
METRADO COSTO % METRADO COSTO % METRADO COSTO % METRADO COSTO %
06.01.01 LIMPIEZA DE TERRENO EN FORMA MANUAL* m2 11,456.13 0.59 S/. 6,759.12 11,456.13 S/. 6,759.12 100.00 % - S/. - - 11,456.13 6,759.12 100.00 % - - -
06.01.02 TRAZO Y REPLANTEO EN TERRENO NORMAL CON EQUIPO* m2 11,456.13 1.52 S/. 17,413.32 11,456.13 S/. 17,413.32 100.00 % - S/. - - 11,456.13 17,413.32 100.00 % - - -
06.01.03 CONTROL TOPOGRAFICO C/EQUIPO m2 11,456.13 0.59 S/. 6,759.12 - S/. - - - S/. - - - - - 11,456.13 6,759.12 100.00 %
06.02 MOVIMIENTO DE TIERRAS
06.02.01 CORTE EN TERRENO SUELTO C/MAQUINARIA m3 8,049.64 10.54 S/. 84,843.21 - S/. - - 5,644.45 S/. 59,492.50 70.12 % 5,644.45 59,492.50 70.12 % 2,405.19 25,350.70 29.88 %
06.02.02 RELLENO Y COMPACTADO CON MATERIAL PROPIO SELECCIONADO C/MAQUINARIAm3 209.21 15.76 S/. 3,297.15 - S/. - - - S/. - - - - - 209.21 3,297.15 100.00 %
06.02.03 PERFILADO Y COMPACTADO EN LA SUB RASANTE C/MAQUINARIA m2 11,456.13 3.03 S/. 34,712.07 - S/. - - - S/. - - - - - 11,456.13 34,712.07 100.00 %
06.02.04 ELIMINACION DE MATERIAL EXCEDENTE C/MAQUINARIA m3 9,800.54 18.62 S/. 182,486.05 - S/. - - 630.00 S/. 11,730.60 6.43 % 630.00 11,730.60 6.43 % 9,170.54 170,755.45 93.57 %
06.03 PAVIMENTO FLEXIBLE
06.03.01 BASE GRANULAR E= 0.25 M. m2 11,456.13 16.57 S/. 189,828.07 - S/. - - - S/. - - - - - 11,456.13 189,828.07 100.00 %
06.03.02 LIMPIEZA DE VIAS CON EQUIPO m2 11,456.13 0.70 S/. 8,019.29 - S/. - - - S/. - - - - - 11,456.13 8,019.29 100.00 %
06.03.03 IMPRIMACION ASFALTICA m2 11,456.13 7.83 S/. 89,701.50 - S/. - - - S/. - - - - - 11,456.13 89,701.50 100.00 %
06.03.04 CARPETA ASFALTICA E=2" EN FRIO m2 11,456.13 34.21 S/. 391,914.21 - S/. - - - S/. - - - - - 11,456.13 391,914.21 100.00 %
06.04 SEÑALIZACION DE VIAS
06.04.01 SEÑALIZACION HORIZONTAL
06.04.01.01 PINTADO DE MARCAS EN EL PAVIMENTO m2 745.06 21.50 S/. 16,018.79 - S/. - - - S/. - - - - - 745.06 16,018.79 100.00 %
06.04.01.02 PINTADO LINEAL INTERMITENTE CENTRAL m 510.00 7.87 S/. 4,013.70 - S/. - - - S/. - - - - - 510.00 4,013.70 100.00 %
06.04.01.03 PINTADO LINEAL LATERAL CONTINUO m 3,531.25 7.17 S/. 25,319.06 - S/. - - - S/. - - - - - 3,531.25 25,319.06 100.00 %
06.04.02 SEÑALIZACION VERTICAL
06.04.02.01 EXCAVACION Y COLOCACION DE POSTES DE SEÑALIZACION und 36.00 49.36 S/. 1,776.96 - S/. - - - S/. - - - - - 36.00 1,776.96 100.00 %
06.04.02.02 FABRICACION DE POSTES DE SEÑALES PREVENTIVAS und 36.00 443.87 S/. 15,979.32 - S/. - - - S/. - - - - - 36.00 15,979.32 100.00 %
06.04.02.03 PINTADO DE POSTES DE CONCRETO und 53.00 23.27 S/. 1,233.31 - S/. - - - S/. - - - - - 53.00 1,233.31 100.00 %
07 MOBILIARIO URBANO
07.01 OBRAS PRELIMINARES
07.01.01 LIMPIEZA DE TERRENO EN FORMA MANUAL m2 249.68 0.59 S/. 147.31 - S/. - - - S/. - - - - - 249.68 147.31 100.00 %
07.01.02 TRAZO Y REPLANTEO EN TERRENO NORMAL CON EQUIPO m2 249.68 1.52 S/. 379.51 - S/. - - - S/. - - - - - 249.68 379.51 100.00 %
07.02 MOVIMIENTO DE TIERRAS
07.02.01 EXCAVACION DE ZANJAS PARA CIMIENTACION m3 63.27 38.98 S/. 2,466.26 - S/. - - - S/. - - - - - 63.27 2,466.26 100.00 %
07.02.02 RELLENO CON MATERIAL PROPIO C/EQUIPO LIVIANO m3 26.15 27.08 S/. 708.14 - S/. - - - S/. - - - - - 26.15 708.14 100.00 %
07.02.03 ACARREO DE MATERIAL EXCEDENTE D= 40 m. m3 48.26 29.80 S/. 1,438.15 - S/. - - - S/. - - - - - 48.26 1,438.15 100.00 %
07.02.04 ELIMINACION DE MATERIAL EXCEDENTE C/MAQUINARIA m3 48.26 18.62 S/. 898.60 - S/. - - - S/. - - - - - 48.26 898.60 100.00 %
07.03 CONCRETO SIMPLE
07.03.01 SOLADO DE 2" CON MEZCLA C:H 1:12 m2 55.00 25.44 S/. 1,399.20 - S/. - - - S/. - - - - - 55.00 1,399.20 100.00 %
07.03.02 CIMIENTOS CORRIDOS MEZCLA 1:10 CEMENTO-HORMIGON 30% PIEDRA m3 4.55 222.33 S/. 1,011.60 - S/. - - - S/. - - - - - 4.55 1,011.60 100.00 %
07.04 CONCRETO ARMADO
07.04.01 ZAPATAS
07.04.01.01 CONCRETO EN ZAPATAS F'C= 210 KG/CM2 m3 27.50 372.20 S/. 10,235.50 - S/. - - - S/. - - - - - 27.50 10,235.50 100.00 %
07.04.01.02 ACERO GRADO 60 EN ZAPATAS kg 201.96 5.38 S/. 1,086.54 - S/. - - - S/. - - - - - 201.96 1,086.54 100.00 %
07.04.02 COLUMNAS
07.04.02.01 CONCRETO F'C=210 KG/CM2. PARA COLUMNAS m3 9.79 380.44 S/. 3,724.51 - S/. - - - S/. - - - - - 9.79 3,724.51 100.00 %
07.04.02.02 ENCOFRADO Y DESENCOFRADO CARAVISTA EN COLUMNAS m2 147.40 63.82 S/. 9,407.07 - S/. - - - S/. - - - - - 147.40 9,407.07 100.00 %
07.04.02.03 ACERO GRADO 60 EN COLUMNAS kg 947.08 5.36 S/. 5,076.35 - S/. - - - S/. - - - - - 947.08 5,076.35 100.00 %
07.05 CARPINTERIA DE MADERA
07.05.01 PERGOLA DE MADERA SEGUN DISEÑO TIPO 1 und 11.00 1,171.10 S/. 12,882.10 - S/. - - - S/. - - - - - 11.00 12,882.10 100.00 %
07.05.02 PERGOLA DE MADERA SEGUN DISEÑO TIPO 2 und 11.00 1,839.24 S/. 20,231.64 - S/. - - - S/. - - - - - 11.00 20,231.64 100.00 %
07.06 PINTURA
07.06.01 PINTURA BARNIZ 2 MANOS EN MADERA m2 536.58 15.82 S/. 8,488.70 - S/. - - - S/. - - - - - 536.58 8,488.70 100.00 %
07.07 VARIOS
07.07.01 CURADO DE COLUMNAS DE CONCRETO m2 147.40 3.56 S/. 524.74 - S/. - - - S/. - - - - - 147.40 524.74 100.00 %
07.07.02 SOLAQUEADO DE COLUMNAS m2 147.40 7.18 S/. 1,058.33 - S/. - - - S/. - - - - - 147.40 1,058.33 100.00 %
08 IMPACTO AMBIENTAL
08.01 RIEGO EN LA ZONA DE TRABAJO m2 3,000.00 1.70 S/. 5,100.00 - S/. - - - S/. - - - - - 3,000.00 5,100.00 100.00 %
08.02 CONFORMACION DE MATERIAL DE BOTADEROS m3 1,000.00 4.15 S/. 4,150.00 - S/. - - - S/. - - - - - 1,000.00 4,150.00 100.00 %

COSTO DIRECTO S/. 2,578,083.71 S/. 50,783.83 1.97% S/. 204,176.16 7.92% S/. 254,959.99 9.89% S/. 2,323,123.71 90.11%
GASTOS GENERALES (7.0%) 7.00% S/. 180,465.86 S/. 3,554.87 S/. 14,292.33 S/. 17,847.20 S/. 162,618.66
COSTO DE OBRA S/. 2,758,549.57 S/. 54,338.70 1.97% S/. 218,468.49 7.92% S/. 272,807.19 9.89% S/. 2,485,742.37 90.11%
5 de 16

MUNICIPALIDAD DISTRITAL
DE CIUDAD NUEVA
GERENCIA DE INGENIERIA
CUADRO COMPARATIVO DE METRADOS EJECUTADOS
JUNIO 2014

OBRA : "MEJORAMIENTO DE LA CALLE HERMANOS ANGULO DE LA AMPLIACION ASENTAMIENTO HUMANO MARGINAL CIUDAD NUEVA, DISTRITO CIUDAD NUEVA –TACNA – TACNA”
RESIDENTE : ING. JESUS GUIDO, CHOQUEGONZA CONDORI
INSPECTOR : ING. ORLANDO JARA ALMONTE VILLAROEL
FECHA : JUNIO 2014

UND METRADO
ITEM PARTIDAS METRADO SEPTIEMBRE ACUMULADO
SALDO
JULIO 2014 AGOSTO 2014 OCTUBRE 2014
2014

01 OBRAS PROVISIONALES
01.01 CARTEL DE IDENTIFICACION DE LA OBRA DE 2.40 x 3.60 m. und 1.00 - - - - - 1.00
01.02 CASETA DE ALMACEN Y GUARDIANIA m2 56.00 - - - - - 56.00
01.03 MOVILIZACION Y DESMOVILIZACION DE HERRAMIENTAS Y EQUIPO GLB 1.00 - - - - - 1.00
01.04 TRANSPORTE DE MATERIALES PARA LA OBRA GLB 1.00 - - - - - 1.00
01.05 SUMINISTRO PROVISIONAL DE AGUA GLB 1.00 - - - - - 1.00
01.06 SUMINISTRO PROVISIONAL ENERGIA ELECTRICA GLB 1.00 - - - - - 1.00
01.07 SERVICIOS HIGIENICOS PARA EL PERSONAL DE OBRA mes 6.00 - - - - - 6.00
02 SEGURIDAD Y SALUD
02.01 ELABORACION, IMPLEMENTACION Y ADMINISTRACION DEL PLAN DE SEGURIDAD EN EL TRABAJO GLB 1.00 - - - - - 1.00
02.02 EQUIPOS DE PROTECCION PERSONAL und 40.00 - - - - - 40.00
02.03 EQUIPOS DE PROTECCION COLECTIVA und 1.00 - - - - - 1.00
02.04 SEÑALIZACION TEMPORAL DE SEGURIDAD GLB 1.00 - - - - - 1.00
02.05 CAPACITACION SOBRE SALUD Y SEGURIDAD GLB 1.00 - - - - - 1.00
02.06 RECURSOS DE RESPUESTA DE EMERGENCIA GLB 1.00 - - - - - 1.00
03 PISOS, VEREDAS Y AREAS VERDES
03.01 OBRAS PRELIMINARES
03.01.01 LIMPIEZA DE TERRENO EN FORMA MANUAL* m2 3,742.21 - - - - - 3,742.21
03.01.02 TRAZO Y REPLANTEO EN TERRENO NORMAL CON EQUIPO* m2 3,742.21 - - - - - 3,742.21
03.01.03 DEMOLICION DE VEREDAS Y BERMAS EXISTENTES C/EQUIPO m2 186.40 - - - - - 186.40
03.01.04 DEMOLICION DE BANCAS DE CONCRETO m3 8.40 - - - - - 8.40
03.01.05 REUBICACION DE POSTES und 10.00 - - - - - 10.00
03.01.06 RETIRO Y REPOSICIÓN DE CAJA DE MEDIDORES DE AGUA und 192.00 - - - - - 192.00
03.01.07 RETIRO Y REPOSICIÓN DE CAJAS DE REGISTRO und 192.00 - - - - - 192.00
03.01.08 ACARREO DE MATERIAL EXCEDENTE D= 40 m. m3 50.90 - - - - - 50.90
03.01.09 ELIMINACION DE MATERIAL EXCEDENTE C/MAQUINARIA m3 50.90 - - - - - 50.90
03.02 MOVIMIENTO DE TIERRAS
03.02.01 CORTE SUPERFICIAL DE TERRENO MANUAL HASTA 0.20 M m2 3,742.21 - - - - - 3,742.21
03.02.02 CORTE Y EXCAVACION EN TERRENO SUELTO MANUAL m3 396.16 - - - - - 396.16
03.02.03 PERFILADO Y COMPACTADO DE SUBRASANTE C/EQUIPO m2 3,742.21 - - - - - 3,742.21
03.02.04 TERRAPLEN DE VEREDA E=0.10 M m2 3,742.21 - - - - - 3,742.21
03.02.05 ACARREO DE MATERIAL EXCEDENTE D= 40 m. m3 1,487.98 - - - - - 1,487.98
03.02.06 ELIMINACION DE MATERIAL EXCEDENTE C/MAQUINARIA m3 1,487.98 - - - - - 1,487.98
03.03 CONCRETO SIMPLE
03.03.01 SOLADO DE 2" CON MEZCLA C:H 1:12 m2 618.21 - - - - - 618.21
03.03.02 CIMIENTOS CORRIDOS MEZCLA 1:10 CEMENTO-HORMIGON 30% P.G. 6" m3 253.49 - - - - - 253.49
03.03.03 ENCOFRADO Y DESENCOFRADO NORMAL m2 248.39 - - - - - 248.39
03.04 CONCRETO ARMADO
03.04.01 SARDINELES REFORZADOS
03.04.01.01 CONCRETO F'C=175 KG/CM2 EN SARDINELES REFORZADOS m3 251.05 - - - - - 251.05
03.04.01.02 ENCOFRADO Y DESENCOFRADO CARAVISTA EN SARDINELES REFORZADOS m2 2,617.67 - - - - - 2,617.67
03.04.01.03 ACERO CORRUGADO F'Y=4200 KG/CM2 EN SARDINELES REFORZADOS kg 9,135.88 - - - - - 9,135.88
03.05 PISOS Y PAVIMENTOS
03.05.01 VEREDA DE PIEDRA LAVADA C/CEMENTO PULIDO COLOREADO F'C=175 KG/CM2 E=0.10M. BRUÑ m2 2,340.49 - - - - - 2,340.49
03.05.02 PISO DE CEMENTO PULIDO COLOREADO F'C=175 KG/CM2 E=0.10M. BRUÑADO m2 403.32 - - - - - 403.32
03.05.03 PISO DE CEMENTO PULIDO COLOREADO F'C=175 KG/CM2 E=0.05M. BRUÑADO m2 257.39 - - - - - 257.39
6 de 16

MUNICIPALIDAD DISTRITAL
DE CIUDAD NUEVA
GERENCIA DE INGENIERIA
CUADRO COMPARATIVO DE METRADOS EJECUTADOS
JUNIO 2014

OBRA : "MEJORAMIENTO DE LA CALLE HERMANOS ANGULO DE LA AMPLIACION ASENTAMIENTO HUMANO MARGINAL CIUDAD NUEVA, DISTRITO CIUDAD NUEVA –TACNA – TACNA”
RESIDENTE : ING. JESUS GUIDO, CHOQUEGONZA CONDORI
INSPECTOR : ING. ORLANDO JARA ALMONTE VILLAROEL
FECHA : JUNIO 2014

UND METRADO
ITEM PARTIDAS METRADO SEPTIEMBRE ACUMULADO
SALDO
JULIO 2014 AGOSTO 2014 OCTUBRE 2014
2014

03.05.04 MARTILLOS DE PIEDRA LAVADA C/CEMENTO PULIDO F'C=175 KG/CM2 E=0.10M. BRUÑADO m2 424.92 - - - - - 424.92
03.05.05 RAMPAS DE CEMENTO PULIDO F'C=175 KG/CM2 E=0.10M. BRUÑADO m2 136.88 - - - - - 136.88
03.05.06 GRADA DE PIEDRA LAVADA F'C=175 KG/CM2 E=4" C/DETALLES EN CEMENTO PULIDO m3 35.84 - - - - - 35.84
03.05.07 SARDINEL SUMERGIDO: CONCRETO F'C=175 KG/CM2 m3 83.18 - - - - - 83.18
03.05.08 ENCOFRADO Y DESENCOFRADO NORMAL EN PISOS Y PAVIMENTOS m2 882.24 - - - - - 882.24
03.06 REVESTIMIENTOS
03.06.01 TARRAJEO EN MUROS Y SARDINELES INC./ESCARIFICADO m2 89.07 - - - - - 89.07
03.07 PINTURA
03.07.01 PINTURA ESMALTE 02 MANOS EN SUPERFICIES DE CONCRETO m2 1,521.33 - - - - - 1,521.33
03.07.02 PINTURA ESMALTE 02 MANOS EN BORDES DE PISOS Y PAVIMENTOS m2 882.24 - - - - - 882.24
03.08 AREAS VERDES
03.08.01 SUMINISTRO Y COLOCACION DE TIERRA DE CHACRA m3 425.24 - - - - - 425.24
03.08.02 SUMINISTRO Y COLOCACION DE GRASS NATURAL m2 919.23 - - - - - 919.23
03.08.03 SUMINISTRO Y COLOCACION DE ARBOLES und 69.00 - - - - - 69.00
03.09 VARIOS
03.09.01 CURADO DE PISOS Y PAVIMENTOS m2 3,742.21 - - - - - 3,742.21
03.09.02 SOLAQUEADO DE VEREDAS, MARTILLOS m2 882.24 - - - - - 882.24
03.09.03 IMPERMEABILIZACION ASFALTICA m2 586.86 - - - - - 586.86
03.09.04 JUNTAS DE DILATACION RELLENAS CON MEZCLA ASFALTICA E=1" m 1,053.95 - - - - - 1,053.95
04 MUROS DE CONTENCION
04.01 OBRAS PRELIMINARES
04.01.01 LIMPIEZA DE TERRENO EN FORMA MANUAL m2 119.90 - - - - - 119.90
04.01.02 TRAZO Y REPLANTEO EN TERRENO NORMAL CON EQUIPO m2 119.90 - - - - - 119.90
04.01.03 CONTROL TOPOGRAFICO C/EQUIPO m2 119.90 - - - - - 119.90
04.02 MOVIMIENTO DE TIERRAS
04.02.01 CORTE Y EXCAVACION EN TERRENO SUELTO MANUAL m3 601.18 - - - - - 601.18
04.02.02 RELLENO CON MATERIAL DE PRESTAMO C/EQUIPO m3 509.29 - - - - - 509.29
04.02.03 NIVELACION Y COMPACTADO DE TERRENO P/CIMENTACION C/EQUIPO m2 244.77 - - - - - 244.77
04.02.04 ACARREO DE MATERIAL EXCEDENTE D= 40 m. m3 119.46 - - - - - 119.46
04.02.05 ELIMINACION DE MATERIAL EXCEDENTE C/MAQUINARIA m3 119.46 - - - - - 119.46
04.03 CONCRETO SIMPLE
04.03.01 SOLADO DE E=4" CON MEZCLA C:H 1:12 PARA MUROS DE CONTENCION m2 119.90 - - - - - 119.90
04.03.02 CONCRETO F'C= 140 KG/CM2 + 30% P.G. EN MUROS DE GRAVEDAD m3 139.05 - - - - - 139.05
04.03.03 ENCOFRADO Y DESENCOFRADO NORMAL DE MUROS m2 141.69 - - - - - 141.69
04.03.04 ENCOFRADO Y DESENCOFRADO CARAVISTA EN MUROS DE GRAVEDAD m2 199.93 - - - - - 199.93
04.04 OBRAS DE CONCRETO ARMADO
04.04.01 ZAPATAS
04.04.01.01 CONCRETO F'C= 210 KG/CM2 EN TALONES m3 39.73 - - - - - 39.73
04.04.01.02 ENCOFRADO Y DESENCOFRADO NORMAL EN TALONES m2 45.00 - - - - - 45.00
04.04.01.03 ACERO CORRUGADO FY=4200 KG/CM2 EN TALONES kg 2,407.50 - - - - - 2,407.50
04.04.02 MURO
04.04.02.01 CONCRETO F'C= 210 KG/CM2. EN MURO m3 48.41 - - - - - 48.41
04.04.02.02 ENCOFRADO Y DESENCOFRADO CARAVISTA EN MURO VERTICAL m2 180.72 - - - - - 180.72
04.04.02.03 ENCOFRADO Y DESENCOFRADO NORMAL DE MUROS m2 180.72 - - - - - 180.72
04.04.02.04 ACERO CORRUGADO FY=4200 KG/CM2 EN PANTALLA VERTICAL kg 2,903.33 - - - - - 2,903.33
04.04.03 SARDINEL REFORZADO
04.04.03.01 CONCRETO F'C=175 KG/CM2 EN SARDINEL m3 4.84 - - - - - 4.84
04.04.03.02 ENCOFRADO Y DESENCOFRADO CARAVISTA EN SARDINEL m2 64.55 - - - - - 64.55
7 de 16

MUNICIPALIDAD DISTRITAL
DE CIUDAD NUEVA
GERENCIA DE INGENIERIA
CUADRO COMPARATIVO DE METRADOS EJECUTADOS
JUNIO 2014

OBRA : "MEJORAMIENTO DE LA CALLE HERMANOS ANGULO DE LA AMPLIACION ASENTAMIENTO HUMANO MARGINAL CIUDAD NUEVA, DISTRITO CIUDAD NUEVA –TACNA – TACNA”
RESIDENTE : ING. JESUS GUIDO, CHOQUEGONZA CONDORI
INSPECTOR : ING. ORLANDO JARA ALMONTE VILLAROEL
FECHA : JUNIO 2014

UND METRADO
ITEM PARTIDAS METRADO SEPTIEMBRE ACUMULADO
SALDO
JULIO 2014 AGOSTO 2014 OCTUBRE 2014
2014

04.04.03.03 ACERO GRADO 60 EN SARDINELES kg 260.77 - - - - - 260.77


04.05 VARIOS
04.05.01 SOLAQUEADO DE MUROS m2 445.19 - - - - - 445.19
04.05.02 CURADO DE MUROS DE CONCRETO m2 767.60 - - - - - 767.60
04.05.03 IMPERMEABILIZACION DE MUROS m2 319.13 - - - - - 319.13
04.05.04 JUNTA DE CONSTRUCCION CON TEKNOPORT m 94.54 - - - - - 94.54
05 BERMAS LATERALES
05.01 OBRAS PRELIMINARES
05.01.01 LIMPIEZA DE TERRENO EN FORMA MANUAL* m2 1,322.33 - - - - - 1,322.33
05.01.02 TRAZO Y REPLANTEO EN TERRENO NORMAL CON EQUIPO* m2 1,322.33 - - - - - 1,322.33
05.01.03 CONTROL TOPOGRAFICO C/EQUIPO m2 1,322.33 - - - - - 1,322.33
05.02 MOVIMIENTO DE TIERRAS
05.02.01 CORTE SUPERFICIAL DE TERRENO MANUAL HASTA 0.20 M m2 330.58 - - - - - 330.58
05.02.02 PERFILADO Y COMPACTADO DE SUBRASANTE C/EQUIPO m2 1,322.33 - - - - - 1,322.33
05.02.03 ACARREO DE MATERIAL EXCEDENTE D= 40 m. m3 429.76 - - - - - 429.76
05.02.04 ELIMINACION DE MATERIAL EXCEDENTE C/MAQUINARIA m3 429.76 - - - - - 429.76
05.03 PAVIMENTO FLEXIBLE
05.03.01 BASE GRANULAR E=0.20M. C/EQUIPO m2 1,322.33 - - - - - 1,322.33
05.03.02 LIMPIEZA DE VIAS CON EQUIPO m2 1,322.33 - - - - - 1,322.33
05.03.03 IMPRIMACION ASFALTICA m2 1,322.33 - - - - - 1,322.33
05.03.04 CARPETA ASFALTICA E=2" EN FRIO m2 1,322.33 - - - - - 1,322.33
06 PISTAS
06.01 OBRAS PRELIMINARES
06.01.01 LIMPIEZA DE TERRENO EN FORMA MANUAL* m2 11,456.13 - - - - - 11,456.13
06.01.02 TRAZO Y REPLANTEO EN TERRENO NORMAL CON EQUIPO* m2 11,456.13 - - - - - 11,456.13
06.01.03 CONTROL TOPOGRAFICO C/EQUIPO m2 11,456.13 - - - - - 11,456.13
06.02 MOVIMIENTO DE TIERRAS
06.02.01 CORTE EN TERRENO SUELTO C/MAQUINARIA m3 8,049.64 - - - - - 8,049.64
RELLENO Y COMPACTADO CON MATERIAL PROPIO SELECCIONADO C/MAQUINARIA_x000D_
06.02.02 m3 209.21 - - - - - 209.21
06.02.03 PERFILADO Y COMPACTADO EN LA SUB RASANTE C/MAQUINARIA m2 11,456.13 - - - - - 11,456.13
06.02.04 ELIMINACION DE MATERIAL EXCEDENTE C/MAQUINARIA m3 9,800.54 - - - - - 9,800.54
06.03 PAVIMENTO FLEXIBLE
06.03.01 BASE GRANULAR E= 0.25 M. m2 11,456.13 - - - - - 11,456.13
06.03.02 LIMPIEZA DE VIAS CON EQUIPO m2 11,456.13 - - - - - 11,456.13
06.03.03 IMPRIMACION ASFALTICA m2 11,456.13 - - - - - 11,456.13
06.03.04 CARPETA ASFALTICA E=2" EN FRIO m2 11,456.13 - - - - - 11,456.13
06.04 SEÑALIZACION DE VIAS
06.04.01 SEÑALIZACION HORIZONTAL
06.04.01.01 PINTADO DE MARCAS EN EL PAVIMENTO m2 745.06 - - - - - 745.06
06.04.01.02 PINTADO LINEAL INTERMITENTE CENTRAL m 510.00 - - - - - 510.00
06.04.01.03 PINTADO LINEAL LATERAL CONTINUO m 3,531.25 - - - - - 3,531.25
06.04.02 SEÑALIZACION VERTICAL
06.04.02.01 EXCAVACION Y COLOCACION DE POSTES DE SEÑALIZACION und 36.00 - - - - - 36.00
06.04.02.02 FABRICACION DE POSTES DE SEÑALES PREVENTIVAS und 36.00 - - - - - 36.00
06.04.02.03 PINTADO DE POSTES DE CONCRETO und 53.00 - - - - - 53.00
07 MOBILIARIO URBANO
07.01 OBRAS PRELIMINARES
07.01.01 LIMPIEZA DE TERRENO EN FORMA MANUAL m2 249.68 - - - - - 249.68
8 de 16

MUNICIPALIDAD DISTRITAL
DE CIUDAD NUEVA
GERENCIA DE INGENIERIA
CUADRO COMPARATIVO DE METRADOS EJECUTADOS
JUNIO 2014

OBRA : "MEJORAMIENTO DE LA CALLE HERMANOS ANGULO DE LA AMPLIACION ASENTAMIENTO HUMANO MARGINAL CIUDAD NUEVA, DISTRITO CIUDAD NUEVA –TACNA – TACNA”
RESIDENTE : ING. JESUS GUIDO, CHOQUEGONZA CONDORI
INSPECTOR : ING. ORLANDO JARA ALMONTE VILLAROEL
FECHA : JUNIO 2014

UND METRADO
ITEM PARTIDAS METRADO SEPTIEMBRE ACUMULADO
SALDO
JULIO 2014 AGOSTO 2014 OCTUBRE 2014
2014

07.01.02 TRAZO Y REPLANTEO EN TERRENO NORMAL CON EQUIPO m2 249.68 - - - - - 249.68


07.02 MOVIMIENTO DE TIERRAS
07.02.01 EXCAVACION DE ZANJAS PARA CIMIENTACION m3 63.27 - - - - - 63.27
07.02.02 RELLENO CON MATERIAL PROPIO C/EQUIPO LIVIANO m3 26.15 - - - - - 26.15
07.02.03 ACARREO DE MATERIAL EXCEDENTE D= 40 m. m3 48.26 - - - - - 48.26
07.02.04 ELIMINACION DE MATERIAL EXCEDENTE C/MAQUINARIA m3 48.26 - - - - - 48.26
07.03 CONCRETO SIMPLE
07.03.01 SOLADO DE 2" CON MEZCLA C:H 1:12 m2 55.00 - - - - - 55.00
07.03.02 CIMIENTOS CORRIDOS MEZCLA 1:10 CEMENTO-HORMIGON 30% PIEDRA m3 4.55 - - - - - 4.55
07.04 CONCRETO ARMADO
07.04.01 ZAPATAS
07.04.01.01 CONCRETO EN ZAPATAS F'C= 210 KG/CM2 m3 27.50 - - - - - 27.50
07.04.01.02 ACERO GRADO 60 EN ZAPATAS kg 201.96 - - - - - 201.96
07.04.02 COLUMNAS
07.04.02.01 CONCRETO F'C=210 KG/CM2. PARA COLUMNAS m3 9.79 - - - - - 9.79
07.04.02.02 ENCOFRADO Y DESENCOFRADO CARAVISTA EN COLUMNAS m2 147.40 - - - - - 147.40
07.04.02.03 ACERO GRADO 60 EN COLUMNAS kg 947.08 - - - - - 947.08
07.05 CARPINTERIA DE MADERA
07.05.01 PERGOLA DE MADERA SEGUN DISEÑO TIPO 1 und 11.00 - - - - - 11.00
07.05.02 PERGOLA DE MADERA SEGUN DISEÑO TIPO 2 und 11.00 - - - - - 11.00
07.06 PINTURA
07.06.01 PINTURA BARNIZ 2 MANOS EN MADERA m2 536.58 - - - - - 536.58
07.07 VARIOS
07.07.01 CURADO DE COLUMNAS DE CONCRETO m2 147.40 - - - - - 147.40
07.07.02 SOLAQUEADO DE COLUMNAS m2 147.40 - - - - - 147.40
08 IMPACTO AMBIENTAL
08.01 RIEGO EN LA ZONA DE TRABAJO m2 3,000.00 - - - - - 3,000.00
08.02 CONFORMACION DE MATERIAL DE BOTADEROS m3 1,000.00 - - - - - 1,000.00
CONTROL DE AVANCE DE OBRA - CURVA "S"
Oct-17

ENTIDAD :MUNICIPALIDAD PROVINCIAL DE CANDARAVE MODALIDAD ADMINISTRACION DIRECTA

OBRA :MEJORAMIENTO DEL CAMINO VECINAL EN EL SECTOR CALIENTES-VILACOTA(JARUMA FECHA :OCTUBRE 2017
RESIDENTE :ADRIAN ALEJANDRO COPA QUISPE
SUPERVISOR :ARQ. WILSON RUFINO MORALES SANTI

AVANCE DE OBRA EXPEDIENTE TECNICO

100.00%
100%
94.37%
% DE AVANCE ACUMULADO

80%
72.83%
72.83%
60%
54.86%

40% 35.13%

20%

0%
Aug-2017

Sep-2017

Oct-2017
AVANCE FISICO PROGRAMADO EXP. TECNICO
AVANCE FISICO EJECUTADO MESES VALORIZADOS
CONTROL DE AVANCE DE OBRA - CURVA "S"
Oct-17

ENTIDAD :MUNICIPALIDAD PROVINCIAL DE CANDARAVE MODALIDAD ADMINISTRACION DIRECTA

OBRA :MEJORAMIENTO DEL CAMINO VECINAL EN EL SECTOR CALIENTES-VILACOTA(JARUMA FECHA :OCTUBRE 2017
RESIDENTE :ADRIAN ALEJANDRO COPA QUISPE
SUPERVISOR :ARQ. WILSON RUFINO MORALES SANTI

GRÁFICO 1- CURVA DE CONTROL "S" PROGRAMADO SEGUN EXP. TECNICO

105% 100.00%

95%
94.37%
% DE AVANCE ACUMUADO

85%

75% 72.83%
72.83%
65%

55%
54.86%
45%

35%
35.13%
25%

15%

5% 0.00%

-5% 0.00%

FISICO EJECUTADO FISICO PROGRAMADO


CONTROL DE AVANCE DE OBRA - CURVA "S"
Oct-17

ENTIDAD :MUNICIPALIDAD PROVINCIAL DE CANDARAVE MODALIDAD ADMINISTRACION DIRECTA

OBRA :MEJORAMIENTO DEL CAMINO VECINAL EN EL SECTOR CALIENTES-VILACOTA(JARUMA FECHA :OCTUBRE 2017
RESIDENTE :ADRIAN ALEJANDRO COPA QUISPE
SUPERVISOR :ARQ. WILSON RUFINO MORALES SANTI

GRÁFICO 2- CURVA DE CONTROL "S"

105%

95%
94.37%
% DE AVANCE ACUMUADO

85%

75%
72.83% 65.62%
65%

55%
54.86%
45%

35%
25.33%
25%
17.82%
15%

5% 0.00%

-5% 0.00%

AVANCE FISICO EJECUTADO


FINANCIERO EJECUTADO ANIVEL DEVENGADO
CONTROL DE AVANCE DE OBRA - CURVA "S" REPROGRAMADO
Oct-17

ENTIDAD :MUNICIPALIDAD PROVINCIAL DE CANDARAVE MODALIDAD ADMINISTRACION DIRECTA

OBRA :MEJORAMIENTO DEL CAMINO VECINAL EN EL SECTOR CALIENTES-VILACOTA(JARUMA FECHA :OCTUBRE 2017
RESIDENTE :ADRIAN ALEJANDRO COPA QUISPE
SUPERVISOR :ARQ. WILSON RUFINO MORALES SANTI

AVANCE DE OBRA EXPEDIENTE TECNICO

100.00%
100%
100.00%
% DE AVANCE ACUMULADO

80%

60%

40%

20%

0%

Oct-2017

AVANCE FISICO REPROGRAMADO


MESES VALORIZADOS AVANCE FISICO EJECUTADO DEL ADICIONAL N°01
CONTROL DE AVANCE DE OBRA - CURVA "S" REPROGRAMADO
Oct-17

ENTIDAD :MUNICIPALIDAD PROVINCIAL DE CANDARAVE MODALIDAD ADMINISTRACION DIRECTA

OBRA :MEJORAMIENTO DEL CAMINO VECINAL EN EL SECTOR CALIENTES-VILACOTA(JARUMA FECHA :OCTUBRE 2017
RESIDENTE :ADRIAN ALEJANDRO COPA QUISPE
SUPERVISOR :ARQ. WILSON RUFINO MORALES SANTI

GRÁFICO 1- CURVA DE CONTROL "S" REPROGRAMADO VS EJECUTADO ADICIONAL N°01

105%

95% 100.00%
100.00%
% DE AVANCE ACUMUADO

85%

75%

65%

55%

45%

35%

25%

15%

5% 0.00%

-5% 0.00%

FISICO EJECUTADO ADICIONAL N°01


FISICO REPROGRAMADO
CUADRO DE CONTROL
OBRA
: "MEJORAMIENTO DE LA CALLE HERMANOS ANGULO DE LA AMPLIACION ASENTAMIENTO HUMANO MARGINAL CIUDAD NUEVA, DISTRITO CIUDAD NUEVA –TACNA – TACNA”

RESIDENTE :ING. JESUS CARLOS IBAÑEZ VALDEZ INICIO DE OBRA : 23/07/2014

INSPECTOR :ING. VANESSA PLATERO AVENDAÑO PLAZ. EJECUCIÓN : 90 D.C.

FECHA :AGOSTO DEL 2014 CULMINACION DE OBRA : 20/10/2014

170,529.22

INCREMENTO PRESUPUESTAL: S/. - AVANCE FÍSICO (S/.)

TOTAL
TOTAL JUL 2014 AGO 2014 SET 2014 OCT 2014 SALDO
ACUMULADO
MONTO 579,029.32 26,339.00 144,190.22 333,597.81 74,902.29 579,029.32 -

PROGRAMADO % PARCIAL 4.55% 24.90% 57.61% 12.94% 100.00% 0.00%

% ACUM. 4.55% 29.45% 87.06% 100.00% 100.00% 0.00%

MONTO 579,029.32 17,783.68 127,834.60 - - 145,618.28 433,411.04

EJECUTADO % PARCIAL 3.07% 22.08% 0.00% 0.00% 25.15% 74.85%

% ACUM. 3.07% 25.15% 25.15% 25.15% 25.15% 74.85%

AVANCE FÍSICO (S/.) AVANCE FÍSICO (%)


S/. 400,000.00

S/. 300,000.00
145,618.28
25.15%
SOLES

S/. 200,000.00

S/. 100,000.00

S/. 0.00
4 4 4
433,411.04
01 14 01 01 74.85%
L2 20 T2 T2
JU A GO SE OC
MESES

PROGRAMADO EJECUTADO TOTAL ACUMULADO SALDO

NOTA
*** EN EL GRÁFICO MOSTRADO SOLO FIGURA EL MONTO CORRESPONDIENTE A COSTO DIRECTO + GASTOS GENERALES
CUADRO DE CONTROL
OBRA
: "MEJORAMIENTO DE LA CALLE HERMANOS ANGULO DE LA AMPLIACION ASENTAMIENTO HUMANO MARGINAL CIUDAD NUEVA, DISTRITO CIUDAD NUEVA –TACNA – TACNA”

RESIDENTE :ING. JESUS CARLOS IBAÑEZ VALDEZ INICIO DE OBRA : 23/07/2014

INSPECTOR :ING. VANESSA PLATERO AVENDAÑO PLAZ. EJECUCIÓN : 90 D.C.

FECHA :AGOSTO DEL 2014 CULMINACION DE OBRA : 20/10/2014

AVANCE FINANCIERO (S/.)


2.30% 6.89% 20.10% 28.13% 57.42%
13,317.67 39,895.12 116,384.89 162,880.95

TOTAL
TOTAL JUL 2014 AGO 2014 SET 2014 OCT 2014 SALDO
ACUMULADO
MONTO 579,029.32 26,345.83 144,178.30 333,578.79 74,926.39 579,029.32 -

PROGRAMADO % PARCIAL 4.55% 24.90% 57.61% 12.94% 100.00% 0.00%

% ACUM. 4.55% 29.45% 87.06% 100.00% 100.00% 0.00%

MONTO 579,029.32 33,369.25 116,478.46 - - 149,847.71 429,181.61

EJECUTADO % PARCIAL 5.76% 20.12% 25.88% 74.12%

% ACUM. 5.76% 25.88% 25.88% 25.88% 25.88% 74.12%

AVANCE FINANCIERO (S/.) AVANCE FINANCIERO (%)


S/. 900,000.00

S/. 800,000.00

S/. 700,000.00
149,847.71
S/. 600,000.00 25.88%

S/. 500,000.00
SOLES

S/. 400,000.00

S/. 300,000.00

S/. 200,000.00
429,181.61
S/. 100,000.00 74.12%

S/. 0.00
4 14 4 4
01 20 01 01
L2 O T2 T2
JU AG SE OC
TOTAL ACUMULADO SALDO
MENSUAL

PROGRAMADO EJECUTADO

OBSERVACIONES :

*SE INFORMA QUE EN EL AVANCE FINANCIERO QUE SE INDICA CORRESPONDE A LOS GASTOS TOTALES AFECTADOS A LA OBRA.
*SE INCLUYE EL GASTO DE PLANILLAS DEL MES DE AGOSTO - 2014
16 de 16

VALORIZACIÓN FÍSICA MENSUAL


MAYO 2014

OBRA : "MEJORAMIENTO DE LA INFRAESTRUCTURA VIAL EN LA ASOCIACION DE VIVIENDA, SANTA CRUZ DE BELEN, DISTRITO DE CIUDAD NUEVA - TACNA - TACNA”
RESIDENTE : ING. JESUS GUIDO, CHOQUEGONZA CONDORI
INSPECTOR : ING. ORLANDO JARA ALMONTE VILLAROEL
FECHA : MAYO 2014

MAYO 2014
ITEM PARTIDAS UND METRADO
METRADO PARCIAL % AVANCE
MAYO 2014 MENSUAL

01.02 CASETA DE ALMACEN Y GUARDIANIA m2 56.00 20.00 35.71%


01.04 TRANSPORTE DE MATERIALES PARA LA OBRA GLB 1.00 0.05 5.00%
02.01 ELABORACION, IMPLEMENTACION Y ADMINISTRACION DEL PLAN DE SEGURIDA GLB 1.00 1.00 100.00%
02.02 EQUIPOS DE PROTECCION PERSONAL und 40.00 14.00 35.00%
02.03 EQUIPOS DE PROTECCION COLECTIVA und 1.00 0.05 5.00%
02.04 SEÑALIZACION TEMPORAL DE SEGURIDAD GLB 1.00 0.01 1.00%
02.05 CAPACITACION SOBRE SALUD Y SEGURIDAD GLB 1.00 0.03 3.00%
03.01.01 LIMPIEZA DE TERRENO EN FORMA MANUAL* m2 3,742.21 3,081.50 82.34%
03.01.02 TRAZO Y REPLANTEO EN TERRENO NORMAL CON EQUIPO* m2 3,742.21 3,081.50 82.34%
03.01.03 DEMOLICION DE VEREDAS Y BERMAS EXISTENTES C/EQUIPO m2 186.40 14.00 7.51%
03.02.01 CORTE SUPERFICIAL DE TERRENO MANUAL HASTA 0.20 M m2 3,742.21 418.56 11.18%
05.01.01 LIMPIEZA DE TERRENO EN FORMA MANUAL* m2 1,322.33 1,322.33 100.00%
05.01.02 TRAZO Y REPLANTEO EN TERRENO NORMAL CON EQUIPO* m2 1,322.33 1,322.33 100.00%
06.01.01 LIMPIEZA DE TERRENO EN FORMA MANUAL* m2 11,456.13 11,456.13 100.00%
06.01.02 TRAZO Y REPLANTEO EN TERRENO NORMAL CON EQUIPO* m2 11,456.13 11,456.13 100.00%