104 18120 Mte04418 Eca 440 G 0001 - 0
104 18120 Mte04418 Eca 440 G 0001 - 0
104 18120 Mte04418 Eca 440 G 0001 - 0
MTE04418-RDS-ING440-0001
104-18120-MTE04418-ECA-440-G-0001
ÍNDICE
1. GENERAL ............................................................................................................... 4
1.1 INTRODUCCIÓN ................................................................................................................. 4
1.2 OBJETIVO .............................................................................................................................. 4
1.3 UBICACIÓN ............................................................................................................................. 4
2. DESCRIPCIÓN DEL PROYECTO ........................................................................... 5
2.1 RESUMEN DE LOS TRABAJOS DEL PROYECTO ............................................................................ 5
2.2 DOCUMENTOS DE REFERENCIA................................................................................................ 6
3. CRONOGRAMA DE EJECUCIÓN DE PROYECTO ................................................ 6
3.1 REQUERIMIENTOS PRELIMINARES ................................................................................ 7
4. BASES DEL ESTIMADO Y METODOLOGÍA.......................................................... 8
4.1 PARÁMETROS DE ESTIMACIÓN ................................................................................................ 8
4.2 TIPO DE CAMBIO..................................................................................................................... 9
4.3 ESTRUCTURA GENERAL DE LAS ÁREAS DE TRABAJO - WBS ..................................................... 9
4.3.1 Estructura General por sistemas ................................................................................... 9
4.3.2 Estructura General por commodities ........................................................................... 10
5. COSTOS DIRECTOS ............................................................................................ 12
5.1 COSTO DE LA MANO DE OBRA ............................................................................................... 12
5.2 PRODUCTIVIDAD DE LA MANO DE OBRA ................................................................................. 13
6. COSTOS INDIRECTOS Y OTROS COSTOS DEL PROYECTO ........................... 14
6.1 SERVICIO DE ECM (SIGLAS EN INGLES ENGINEERING AND CONSTRUCTION MANAGEMENT) ..... 14
6.2 COMMISIONAMIENTO............................................................................................................. 15
6.3 COSTOS DEL PROPIETARIO........................................................................................... 15
7. CONTINGENCIA ................................................................................................... 16
7.1 CALCULO DE CONTINGENCIA PROBABILISTICO: ........................................................ 16
7.2 CONTINGENCIA BROWNDFIELD .................................................................................... 17
7.3 CONTINGENCIA POR COVID........................................................................................... 17
8. ESCALAMIENTO .................................................................................................. 18
9. EXCLUSIONES ..................................................................................................... 18
10. SUPOSICIONES.................................................................................................... 19
11. RESUMEN DEL ESTIMADO COSTO DE CAPITAL ............................................. 19
ANEXO A: RESUMEN POR SISTEMA ........................................................................... 21
ANEXO B: RESUMEN POR COMMODITIES ................................................................. 22
ANEXO C: ANÁLISIS DE CONTINGENCIA PROBABILÍSTICO .................................... 23
ANEXO D: JORNAL DE MANO DE OBRA DETALLADO .............................................. 26
ANEXO E: RESUMEN DE COSTO DE CAPITAL POR SISTEMA ................................. 27
ANEXO F: ESTIMADO DE COSTO DE CAPITAL DETALLADO ................................... 28
IMPLEMENTACIÓN DE DIQUE DE PROTECCIÓN
PARA ESTACIONES 3 Y 3B DE AGUA Revisión: 0
Proyecto:18120
ETAPA: INGENIERIA DE DETALLE - 104 Fecha:27-Nov-2020
Page 3 de 28
ESTIMADO DE COSTO - CAPEX
104-18120-MTE04418-ECA-440-G-0001
LISTA DE TABLAS
LISTA DE FIGURAS
Figura 2-1: Arreglo general Dique de protección (Ref. plano 440-C-10114) ............................. 5
Figura 4-1: Clasificación de Estimaciones (DC-480 Sección 4.6.9) .......................................... 8
Figura 6-1: Clasificación de la contingencia (DC-480 Sección 4.6.9) ...................................... 16
IMPLEMENTACIÓN DE DIQUE DE PROTECCIÓN
PARA ESTACIONES 3 Y 3B DE AGUA Revisión: 0
ETAPA: INGENIERIA DE DETALLE - 104 Proyecto:18120
Fecha: 27-Nov-2020
Page 4 de 28
ESTIMADO DE COSTO - CAPEX
104-18120-MTE04418-ECA-440-G-0001
1. GENERAL
1.1 INTRODUCCIÓN
Como parte de los proyectos capital de la Compañía Minera ANTAMINA S.A. (en adelante
ANTAMINA), se contempla el proyecto de reubicación de instalaciones existentes que
puedan ser inundadas con el crecimiento de la presa de relaves. Algunas de las
instalaciones que se prevé se inunden en los próximos años son las Estaciones de Bombeo
3 y 3B, las cuales se encuentran actualmente en las elevaciones 4 130,80 y 4 131,24
m.s.n.m., respectivamente.
Durante el año 2018, SNC-Lavalin Perú S.A. (en adelante SNC-Lavalin) desarrolló la
Ingeniería de detalle del dique de protección de la Estación de bombeo 3 para la elevación
4 131 m.s.n.m., la que actualmente está construido a la elevación 4 130,8 m.s.n.m.
A inicios del año 2019, ANTAMINA decidió extender la vida útil del Dique de protección de
la estación de bombeo 3 hasta el nivel 4 135 m.s.n.m., y prolongarlo para también dar
protección a la Estación de bombeo 3B.
En enero del 2020 el proyecto es puesto stand-by por Antamina solicitando a SNC-Lavalin
cuantificar el nivel de riesgo durante la operación de los sistemas. Por tal motivo, SNC-
Lavalin elaboró el Análisis del incremento de filtraciones en condiciones de operación al
nivel 4 131 m.s.n.m. y evaluación de riesgos del recrecimiento al nivel 4 135 m.s.n.m. del
dique de protección de las Estaciones de Bombeo 3 y 3B, emitido el 17 de enero del 2020
(N° 15601-18120-40er-0001_0), y reemitido en agosto del 2020 (104-18120-MTE04418-
INF-440-G-0001) para registro como entregable del presente servicio.
1.2 OBJETIVO
El presente documento tiene como objetivo plasmar los alcances para el desarrollo del
Costo de capital del proyecto a nivel de ingeniería de detalle en Clase 2 del documento DC-
480 Control de Estudios (Versión 01) de Antamina.
1.3 UBICACIÓN
En el presente proyecto SNC Lavalin definió las partidas de la obra civil para el Dique de
protección para la estación 3 y 3A que corresponde el Recrecimiento del Dique en una
altura aproximado de 1 metro hasta el nivel EL + 4135. Para la construcción contempla las
siguientes actividades en sitio:
Hitos Fecha
Antes del inicio del programa de construcción del dique protección nivel 4 135 m.s.n.m,
Antamina deberá completar los siguientes trabajos en sitio:
Por lo que estas actividades están fuera del alcance de este documento.
La estimación se efectuó para un rango de precisión esperado de -10% a +15%, con una
probabilidad del 90% correspondiente a una estimación Clase 2 según documento DC-480
Control de Estudios (Versión 01) de Antamina
Los montos de la estimación de costos están expresados en dólares de los Estados Unidos
de Norteamérica (US$). Para los costos que se hayan cotizado en diferente moneda, se
utilizarán los tipos de cambio del tercer trimestre del 2020 que se muestran en la Tabla 4-1.
Código Área/Sub-área
Dique de protección de estación 3 y 3B
1 Actividades preliminares
2 Movimiento de tierras
3 Dique de protección
4 Sistema terramesh
5 Estructuras hidráulicas
6 Canal de coronación
7 Vertedero Estribo izquierdo
8 Vertedero Estribo derecho
9 Estructura de derivación (Estribo Derecho)
10 Poza de bombeo
11 Camino de acceso
Costos Indirectos
12 Soporte de Ingeniería y Procura de la Construcción (E)
13 Gerenciamiento de la construcción (CM)
Código Área/Sub-área
16 Fletes y seguros
17 Comisionamiento y Puesta en Marcha
18 Costos del Propietario
Escalamiento
24 Escalamiento
Contingencia
25 Contingencia
Código Área/Sub-área
AA Controles Medioambientales
AA Facilidades: Oficina, almacén y talleres
Movilización y desmovilización (equipos, herramientas, mano de obra,
AA
facilidades, etc.)
AA Trazo y replanteo
AB Colocación de plancha metálica
AC Geomembrana
AD Geotextil
AF Malla
AG Tubería
AH Colocación de varilla fe
BA Cama de apoyo
BB Cama de arena
BC Capa de rodadura
BE Colocación, compactación de materiales
BF Conformación de berma de seguridad
BG Excavación de suelo para fundación
BG Excavación de suelo y/o relaves
IMPLEMENTACIÓN DE DIQUE DE PROTECCIÓN
PARA ESTACIONES 3 Y 3B DE AGUA Revisión: 0
ETAPA: INGENIERIA DE DETALLE - 104 Proyecto:18120
Fecha: 27-Nov-2020
Page 11 de 28
ESTIMADO DE COSTO - CAPEX
104-18120-MTE04418-ECA-440-G-0001
Código Área/Sub-área
BG Excavación de topsoil
BG Excavación masiva
BG Excavación, carguío y eliminación
BI Preparación y compactación de fundación
BJ Habilitado de roca en cantera para terramesh
BJ Preparación y Homogenización de Materiales
BK Relleno
BK Tubería
BL Transporte, Eliminación, Acarreo
BM Colocación de Piedra
CA Concreto
CB Concreto - Solado
CC Encofrado y desencofrado
CD Estructura de concreto (vertedero)
CE Inserto de tuberías
CG Parrilla
CH Vaceado de concreto ciclópeo
CI Water Stop 6"
Costos Indirectos
12 Soporte de Ingeniería y Procura de la Construcción (EP)
12 Gerenciamiento de la construcción (CM)
12 consultoría de Ingeniería de detalle
12 Alojamiento y Alimentación
12 Fletes y seguros
12 Comisionamiento y Puesta en Marcha
12 Costos del Propietario
Escalamiento
13 Escalamiento
Contingencia
14 Contingencia
IMPLEMENTACIÓN DE DIQUE DE PROTECCIÓN
PARA ESTACIONES 3 Y 3B DE AGUA Revisión: 0
ETAPA: INGENIERIA DE DETALLE - 104 Proyecto:18120
Fecha: 27-Nov-2020
Page 12 de 28
ESTIMADO DE COSTO - CAPEX
104-18120-MTE04418-ECA-440-G-0001
5. COSTOS DIRECTOS
• Equipos permanente
• Costo de instalación:
• Equipos de Construcción
• Sub contrato
Una vez determinado el costo de la Mano de obra en nuestro caso particular por tratarse
de obra civil debe agregarse los costos generales del contratista que están directamente
relacionado con las horas de trabajo en sitio, el costo general del contratista incluye los
siguientes costos:
• Subcontrato
El costo del jornal de la mano de obra se determina según el Anexo D de este documento,
donde incluye todo el beneficio de ley. En la Tabla 5-1 se muestra el costo promedio de la
Mano de Obra.
IMPLEMENTACIÓN DE DIQUE DE PROTECCIÓN
PARA ESTACIONES 3 Y 3B DE AGUA Revisión: 0
ETAPA: INGENIERIA DE DETALLE - 104 Proyecto:18120
Fecha: 27-Nov-2020
Page 13 de 28
ESTIMADO DE COSTO - CAPEX
104-18120-MTE04418-ECA-440-G-0001
Descripción US$/hora
Operario 11,60
Oficial 9,39
Ayudante 7,80
Total Factor
Condiciones Doble Supervisión Acceso al
Sistemas Altura de
climáticas turno y HSE trabajo
Productividad
Vertedero Estribo
izquierdo 10,96% 10,13% 5,48% 8,94% 5,00% 1,47
Vertedero Estribo
derecho 10,96% 10,13% 5,48% 8,94% 5,00% 1,47
IMPLEMENTACIÓN DE DIQUE DE PROTECCIÓN
PARA ESTACIONES 3 Y 3B DE AGUA Revisión: 0
ETAPA: INGENIERIA DE DETALLE - 104 Proyecto:18120
Fecha: 27-Nov-2020
Page 14 de 28
ESTIMADO DE COSTO - CAPEX
104-18120-MTE04418-ECA-440-G-0001
Total Factor
Condiciones Doble Supervisión Acceso al
Sistemas Altura de
climáticas turno y HSE trabajo
Productividad
Estructura de derivación
(Estribo Derecho) 10,96% 10,13% 5,48% 8,94% 5,00% 1,44
En el presente nivel de desarrollo los costos indirectos han sido calculados con el fin de
mejorar la precisión global del estimado de costos.
Costos Indirectos
12 Procura de la Construcción (P)
12 Gerenciamiento de la construcción (CM)
12 consultoría de Ingeniería de detalle
12 Alojamiento y Alimentación
12 Fletes y seguros
12 Comisionamiento y Puesta en Marcha
12 Costos del Propietario
• Gerencia de proyecto;
• Ingeniería de campo;
• Gerencia de construcción;
• Salud y seguridad;
• Pre-Comisionamiento y Comisionamiento;
6.2 COMMISIONAMIENTO
Los costos del owner se considera en los costos indirectos y son los costos asociados
directamente al propietario del proyecto y al gerenciamiento del mismo, en las etapas de
construcción y pre-operación (gerenciamiento del Cliente, facilidades temporales, seguros,
comisionamiento de puesta en marcha, derechos/permisos, entrenamiento, etc.
IMPLEMENTACIÓN DE DIQUE DE PROTECCIÓN
PARA ESTACIONES 3 Y 3B DE AGUA Revisión: 0
ETAPA: INGENIERIA DE DETALLE - 104 Proyecto:18120
Fecha: 27-Nov-2020
Page 16 de 28
ESTIMADO DE COSTO - CAPEX
104-18120-MTE04418-ECA-440-G-0001
7. CONTINGENCIA
7.1 CALCULO DE CONTINGENCIA PROBABILISTICO:
La contingencia es una parte integral del estimado y se puede definir como una asignación
para elementos o costos indefinidos sobre los que se incurrirá en el marco del alcance del
proyecto aprobado, pero que no se puede prever de manera explícita debido a la falta de
información detallada o precisa en el momento en que se prepara el estimado.
Es un factor que corresponde por la aplicación de medida de seguridad y salud en las obras
para el riesgo de contagio de coronavirus para ello se debe desarrollar un “Plan de
vigilancia, prevención y control de Covid-19 en el trabajo”.
8. ESCALAMIENTO
Es una provisión que cubre el incremento de costos de insumos del proyecto desde la fecha
de estimación de costo de capital hasta la finalización del proyecto, el costo de
escalamiento se estimó un factor del 2.5% del costo directo + costo indirecto
9. EXCLUSIONES
• Capital de trabajo;
• Regalías;
• Fluctuaciones en la moneda;
10. SUPOSICIONES
En la Tabla 4-1 el resumen de costos por sistemas la ingeniería de detalle del dique de
protección de las estaciones de bombeo 3 y 3B (Clase 2). Este monto considera los costos
directos de la ejecución del proyecto, así como los costos indirectos relacionados al diseño,
procura y gerenciamiento de la construcción. Todos los costos están expresados en
dólares americanos de noviembre del 2020.
Total
Código Descripción
(US$)
A Costos Directos
1 Actividades preliminares 359.579,04
2 Movimiento de tierras 160.252,18
3 Dique de protección 1.678.584,01
4 Sistema terramesh 366.059,85
5 Estructuras hidráulicas 37.398,90
6 Canal de coronación 122.394,37
IMPLEMENTACIÓN DE DIQUE DE PROTECCIÓN
PARA ESTACIONES 3 Y 3B DE AGUA Revisión: 0
ETAPA: INGENIERIA DE DETALLE - 104 Proyecto:18120
Fecha: 27-Nov-2020
Page 20 de 28
ESTIMADO DE COSTO - CAPEX
104-18120-MTE04418-ECA-440-G-0001
Total
Código Descripción
(US$)
7 Vertedero Estribo izquierdo 40.754,85
8 Vertedero Estribo derecho 128.196,86
183.267,39
9 Estructura de derivación (Estribo Derecho)
ITEM CÓDIGO COMMODITIES HH MANO OBRA EQUIPOS MATERIALES SUBCONTRATO G.G. UTILIDAD COSTO TOTAL
A AA Movilizacion y desmovilizacion (equipos, herramientas, mano de obra,
1,596.14
facilidades, etc.)
13,567.20 0.00 0.00 38,240.00 15,502.36 6,200.94 73,510.51
A AA Facilidades: Oficina, almacen y talleres 5,793.99 57,939.93 0.00 5,800.00 31,350.00 28,453.93 11,381.57 134,925.43
A AA Trazo y replanteo 7,023.02 70,230.22 10,032.00 1,100.00 0.00 24,346.16 9,738.46 115,446.85
A AA Controles Medioambientales 1,536.29 15,362.86 554.40 9,240.00 0.00 7,527.85 3,011.14 35,696.25
A AB Colocacion de plancha metalica 0.00 0.00 0.00 0.00 1,067.34 319.38 127.75 1,514.48
A AC Geomembrana 6,862.14 60,900.34 2,063.69 31,123.55 0.00 28,153.99 11,261.60 133,503.18
A AD Geotextil 7,401.44 67,150.68 7,253.63 19,420.85 22,657.66 34,855.36 13,942.14 165,280.32
A AF Malla 4,208.35 38,476.07 1,361.93 98,745.57 0.00 41,468.61 16,587.44 196,639.62
A AG Tuberia 1,436.94 13,887.48 13,354.19 73,841.99 0.00 30,247.44 12,098.98 143,430.07
A AH Colocacion de varilla fe 189.09 1,671.29 744.02 1,964.84 0.00 1,310.68 524.27 6,215.12
B BA Cama de apoyo 5.36 45.48 27.86 16.86 0.00 26.99 10.80 127.99
B BB Cama de arena 24.76 215.01 110.93 66.35 0.00 117.38 46.95 556.62
B BC Capa de rodadura 349.95 3,053.02 3,287.19 8,103.81 729.34 4,540.35 1,816.14 21,529.87
B BE Colocacion, compactacion de materiales 16,132.68 145,851.01 232,663.45 0.00 79,385.61 137,018.25 54,807.30 649,725.61
B BF Conformación de berma de seguridad 523.54 5,215.70 6,909.33 0.00 0.00 3,628.19 1,451.28 17,204.50
B BG Excavación de suelo para fundacion 141.92 1,254.57 3,163.18 0.00 3,063.26 2,238.56 895.42 10,614.99
B BG Excavación de suelo y/o relaves 1,137.65 10,056.79 25,356.38 0.00 24,555.38 17,944.49 7,177.80 85,090.84
B BG Excavacion de topsoil 5.82 57.23 116.93 0.00 0.00 52.11 20.85 247.12
B BG Excavación masiva 162.80 1,662.18 6,888.30 0.00 5,831.71 4,303.61 1,721.44 20,407.25
B BG Excavación, carguío y eliminación 153.54 1,365.20 1,699.63 0.00 12.60 920.87 368.35 4,366.64
B BI Preparación y compactación de fundacion 641.25 5,869.94 9,764.95 0.00 2,810.15 5,519.34 2,207.74 26,172.13
B BJ Habilitado de roca en cantera para terramesh 423.45 3,874.58 8,432.42 0.00 0.00 3,682.65 1,473.06 17,462.71
B BJ Preparación y Homogenización de Materiales 4,417.64 40,438.86 67,272.08 0.00 19,359.55 38,023.53 15,209.41 180,303.42
B BK Relleno 135.01 1,275.78 2,392.34 221.25 335.56 1,264.23 505.69 5,994.86
B BK Tuberia 25.61 242.00 463.24 41.75 63.31 242.47 96.99 1,149.75
B BL Transporte, Eliminacion, Acarreo 11,783.57 130,591.97 417,352.50 0.00 0.00 163,962.39 65,584.96 777,491.81
B BM Colocacion de Piedra 2,411.61 22,390.37 19,947.30 1,399.86 0.00 13,087.66 5,235.06 62,060.25
C CA Concreto 2,234.01 23,010.27 1,421.89 31,483.10 0.00 16,731.62 6,692.65 79,339.53
C CB Concreto - Solado 42.69 440.16 26.95 355.10 0.00 246.03 98.41 1,166.66
C CC Encofrado y desencofrado 727.01 8,658.64 179.82 888.00 0.00 2,910.47 1,164.19 13,801.12
C CD Estructura de concreto (vertedero) 3,350.32 34,541.79 2,102.46 50,784.00 0.00 26,161.31 10,464.52 124,054.08
C CE Inserto de tuberias 0.00 0.00 0.00 0.00 468.00 140.04 56.02 664.06
C CG Parrilla 0.00 0.00 0.00 0.00 2,973.08 889.64 355.86 4,218.58
C CH Vaceado de concreto ciclópeo 1,095.66 11,504.42 379.50 22,137.50 0.00 10,180.29 4,072.12 48,273.82
C CI Water Stop 6" 24.54 257.64 6.83 217.88 0.00 144.33 57.73 684.41
CIND CIND Gerenciamiento de la construcción (CM) 395,701.00
CIND CIND consultoria de Ingenieria de detalle 287,782.00
CIND CIND Alojamiento y Alimentación 208,197.49
CIND CIND Fletes y seguros 107,918.00
CIND CIND Comisionamiento y Puesta en Marcha 64,751.00
CIND CIND Costos del Propietario 539,592.00
CIND CIND Procura de la Construcción (P) 74,400.00
ESC ESC Escalacion 120,930.30
CONTG CONTG Contingencia 1,169,879.75
Total general 81,997.78 791,058.70 845,329.30 356,952.26 232,902.56 666,162.57 266,465.03 6,128,021.95
IMPLEMENTACIÓN DE DIQUE DE PROTECCIÓN
PARA ESTACIONES 3 Y 3B DE AGUA Revisión: 0
ETAPA: INGENIERIA DE DETALLE - 104 Proyecto:18120
Fecha: 27-Nov-2020
Page 23 de 28
ESTIMADO DE COSTO - CAPEX
104-18120-MTE04418-ECA-440-G-0001
Resultados de la Simulación
TOTALES / Resultados
Minimum 4.966.778,03
Maximum 5.646.182,78
Mean 5.254.065,58
90% CI ± 1.535,02
Mode 5.242.223,92
Median 5.249.912,56
Std Dev 93.313,71
Skewness 0,2181
Kurtosis 2,8417
Values 10000
Errors 0
Filtered 0
Left X 5.105.649,23
Left P 5,00%
Right X 5.414.551,27
Right P 95,00%
Dif. X 308.902,04
Dif. P 90,00%
Percentile Value
1% 5.059.656,08
3% 5.084.081,42
5% 5.105.649,23
10% 5.135.286,51
20% 5.172.248,55
25% 5.188.267,53
50% 5.249.912,56
75% 5.315.968,17
80% 5.333.571,72
90% 5.378.254,11
95% 5.414.551,27
98% 5.445.291,93
99% 5.481.185,83
IMPLEMENTACIÓN DE DIQUE DE PROTECCIÓN
PARA ESTACIONES 3 Y 3B DE AGUA Revisión: 0
ETAPA: INGENIERIA DE DETALLE - 104 Proyecto:18120
Fecha: 27-Nov-2020
Page 25 de 28
ESTIMADO DE COSTO - CAPEX
104-18120-MTE04418-ECA-440-G-0001
Estimación de la Contingencia
Descripción USD CAPEX Total US$ Contingencia %
Estimado Base 4.837.211 - -
P50 5.249.912 412.700 8,53%
P90 5.378.254 541.042 11,19%
La inversión total esperada al nivel de P50 corresponde a USD 4.837.211 la cual contiene un
8,53% ó USD 412.700 de contingencia del valor esperado base que corresponde a USD
5.249.912 resultante del CAPEX en Rev. 0.
De la misma forma evaluando para un escenario más pesimista o más desfavorable, la inversión
total real a un nivel de probabilidad de P90 corresponde USD 5.378.254, monto que contiene un
11,19% ó USD 541.042 de contingencia con respecto al valor esperado base.
IMPLEMENTACIÓN DE DIQUE DE PROTECCIÓN
PARA ESTACIONES 3 Y 3B DE AGUA Revisión: 0
ETAPA: INGENIERIA DE DETALLE - 104 Proyecto:18120
Fecha: 27-Nov-2020
Page 26 de 28
ESTIMADO DE COSTO - CAPEX
104-18120-MTE04418-ECA-440-G-0001
Carpintero
Carpintero
Topografo
Ayudante
Oficial Fierr
Capataz Ob
Equipo Pes
Concreto
Operador
Operario
Mediano
Operado
Operario
Operario
Fierrero
Equipo
Civiles
Oficial
ITEM DESCRIPCIÓN
REMUNERACION BASICA
RB REMUNERACION BASICA SIN LEYES SOCIALES (SB) 84,30 67,40 67,40 67,40 67,40 67,40 53,70 53,70 48,10 67,40
LS LEYES SOCIALES 120,62% 101,68 81,30 81,30 81,30 81,30 81,30 64,77 64,77 58,02 81,30
SUBTOTAL (RB+LS) 185,98 148,70 148,70 148,70 148,70 148,70 118,47 118,47 106,12 148,70
BONIFICACIONES
A BONIFICACION UNIFICADA BUC 26,98 21,57 21,57 21,57 20,22 20,22 16,11 16,11 14,43 21,57
B BONIFICACION DOBLE TURNO 6,32 5,06 5,06 5,06 5,06 5,06 4,03 4,03 3,61 5,06
C BONIFICACION CONTACTO CON EL AGUA 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00
D BONIFICACION POR ALTURA 0,00 0,00 0,00 2,36 2,36 2,36 1,88 1,88 0,00 0,00
E BONIFICACION POR ALTA ESPECIALIZACION BAE 6,74 5,39 0,00 0,00 0,00 0,00 0,00 0,00 6,07
F BONIFICACION TRABAJO BAJO LA COTA CERO S/. 0,00
G DESTAQUE 25% 21,08 16,85 16,85 16,85 16,85 16,85 13,43 13,43 0,00 16,85
H BONIFICACION ESPECIALIDAD EMPRESA 63,23 50,55 50,55 50,55 50,55 50,55 26,85 26,85 12,03 67,40
I BONIFICACION POR DIAS DE DESCANSO 19,05% 16,06 12,84 12,84 12,84 12,84 12,84 10,23 10,23 9,16 12,84
SUBTOTAL BONIFICACION (A+B+C+D+E+F+G+H) 133,66 113,60 112,25 109,22 107,87 107,87 72,52 72,52 39,22 129,78
LEYES SOCIALES BONIFICACION 13,33% 17,82 15,14 14,97 14,56 14,38 14,38 9,67 9,67 5,23 17,30
SUBTOTAL BONIFICACIONES + LEYES SOCIALES 151,47 128,75 127,22 123,78 122,25 122,25 82,19 82,19 44,45 147,08
CONCEPTOS NO REMUNERATIVOS
J BONIFICACION POR ALTITUD S/. 1,80 1,80 1,80 1,80 1,80 1,80 1,80 1,80 1,80 1,80 1,80
K BONIFICACION POR MOVILIDAD S/. 1,50 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 2,25 0,00
SUBTOTAL CONCEPTOS NO REMUNERATIVOS 1,80 1,80 1,80 1,80 1,80 1,80 1,80 1,80 4,05 1,80
SALARIO POR JORNAL DE 8 HORAS/DIA
SALARIO 219,76 182,80 181,45 178,42 177,07 177,07 128,02 128,02 91,37 198,98
SALARIO INCLUYE LLSS 119,50 96,44 96,26 95,86 95,68 95,68 74,44 74,44 63,25 98,60
SUBTOTAL POR JORNAL DE 8 HORAS/DIA 339,25 279,24 277,71 274,28 272,75 272,75 202,46 202,46 154,62 297,57
SALARIO POR HORAS EXTRA SIMPLE
SALARIO 13,17 10,53 10,53 10,53 10,53 10,53 8,39 8,39 6,01 10,53
BONIFICACION POR HORA SOBRETIEMPO 60% 7,90 6,32 6,32 6,32 6,32 6,32 5,03 5,03 3,61 6,32
LLSS Sobre la Hora Normal 28,33% 3,73 2,98 2,98 2,98 2,98 2,98 2,38 2,38 1,70 2,98
LLSS SOBRE LA BONIFICACION POR HORA SOBRETIEMPO 13,33% 1,05 0,84 0,84 0,84 0,84 0,84 0,67 0,67 0,48 0,84
SUBTOTAL HORA EXTRA SIMPLE CON LLSS 25,86 20,68 20,68 20,68 20,68 20,68 16,47 16,47 11,80 20,68
SALARIO POR HORAS EXTRA DOBLE
SALARIO 13,17 10,53 10,53 10,53 10,53 10,53 8,39 8,39 6,01 10,53
BONIFICACION POR HORA SOBRETIEMPO 100% 13,17 10,53 10,53 10,53 10,53 10,53 8,39 8,39 6,01 10,53
LLSS Sobre la Hora Normal 28,33% 3,73 2,98 2,98 2,98 2,98 2,98 2,38 2,38 1,70 2,98
LLSS SOBRE LA BONIFICACION POR HORA SOBRETIEMPO 13,33% 1,76 1,40 1,40 1,40 1,40 1,40 1,12 1,12 0,80 1,40
SUBTOTAL HORA EXTRA SIMPLE CON LLSS 31,83 25,45 25,45 25,45 25,45 25,45 20,28 20,28 14,53 25,45
COSTO DIARIO (US$)
COSTO DIARIO SIN LLSS 72,75 60,14 59,76 58,92 58,55 58,55 43,02 43,02 30,73 64,63
LLSS POR DIA 35,85 28,91 28,86 28,75 28,70 28,70 22,37 22,37 18,78 29,51
SUBTOTAL DIARIO (US$) 108,60 89,05 88,63 87,67 87,25 87,25 65,39 65,39 49,51 94,15
OTROS GASTOS
IMPLEMENTOS DE SEGURIDAD 6,34 6,34 6,34 6,34 6,34 6,34 6,34 6,34 6,34 6,34
ALOJAMIENTO EN OBRA 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00
ALIMENTACIÓN EN OBRA 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00 0,00
TRANSPORTE A OBRA 5,29 5,29 5,29 5,29 5,29 5,29 5,29 5,29 5,29 5,29
TRANSPORTE INTERNO EN OBRA 10,45 10,45 10,45 10,45 10,45 10,45 10,45 10,45 10,45 10,45
EXAMEN MEDICO 1,63 1,63 1,63 1,63 1,63 1,63 1,63 1,63 1,63 1,63
FOTOCHECK 0,11 0,11 0,11 0,11 0,11 0,11 0,11 0,11 0,11 0,11
AGUA PARA BEBER 0,69 0,69 0,69 0,69 0,69 0,69 0,69 0,69 0,69 0,69
CAPACITACION 3,97 3,97 3,97 3,97 3,97 3,97 3,97 3,97 3,97 3,97
SUBTOTAL OTROS GASTOS (US$) 28,47 28,47 28,47 28,47 28,47 28,47 28,47 28,47 28,47 28,47
TOTAL DIARIO (US$) 137,08 117,53 117,10 116,15 115,72 115,72 93,86 93,86 77,98 122,62
TOTAL HORA HOMBRE PROMEDIO (US$/HH) 13,71 11,75 11,71 11,61 11,57 11,57 9,39 9,39 7,80 12,26
IMPLEMENTACIÓN DE DIQUE DE PROTECCIÓN
PARA ESTACIONES 3 Y 3B DE AGUA Revisión: 0
ETAPA: INGENIERIA DE DETALLE - 104 Proyecto:18120
Fecha: 27-Nov-2020
Page 27 de 28
ESTIMADO DE COSTO - CAPEX
104-18120-MTE04418-ECA-440-G-0001
ITEM SISTEMA COMMODITIES HH MANO OBRA EQUIPOS MATERIALES SUBCONTRATO G.G. UTILIDAD COSTO TOTAL
Movilizacion y desmovilizacion (equipos, herramientas, mano de obra, facilidades, etc.) 1,596.14 13,567.20 0.00 0.00 38,240.00 15,502.36 6,200.94 73,510.51
Actividades Facilidades: Oficina, almacen y talleres 5,793.99 57,939.93 0.00 5,800.00 31,350.00 28,453.93 11,381.57 134,925.43
1
preliminares Trazo y replanteo 7,023.02 70,230.22 10,032.00 1,100.00 0.00 24,346.16 9,738.46 115,446.85
Controles Medioambientales 1,536.29 15,362.86 554.40 9,240.00 0.00 7,527.85 3,011.14 35,696.25
Excavación de suelo para fundacion 141.92 1,254.57 3,163.18 0.00 3,063.26 2,238.56 895.42 10,614.99
Excavación de suelo y/o relaves 1,137.65 10,056.79 25,356.38 0.00 24,555.38 17,944.49 7,177.80 85,090.84
Movimiento de
2 Excavacion de topsoil 5.82 57.23 116.93 0.00 0.00 52.11 20.85 247.12
tierras
Preparación y compactación de fundacion 641.25 5,869.94 9,764.95 0.00 2,810.15 5,519.34 2,207.74 26,172.13
Transporte, Eliminacion, Acarreo 576.73 6,433.04 20,437.39 0.00 0.00 8,040.49 3,216.19 38,127.11
Capa de rodadura 232.93 2,032.13 2,188.00 5,292.88 476.36 2,989.14 1,195.65 14,174.16
Colocacion, compactacion de materiales 15,892.00 143,548.44 229,050.45 0.00 78,746.81 135,056.97 54,022.79 640,425.46
Conformación de berma de seguridad 523.54 5,215.70 6,909.33 0.00 0.00 3,628.19 1,451.28 17,204.50
Dique de
3 Geomembrana 5,849.33 51,911.88 1,752.55 26,431.21 0.00 23,967.16 9,586.86 113,649.67
protección
Geotextil 3,920.75 35,571.62 3,752.52 10,047.00 11,721.50 18,280.86 7,312.34 86,685.86
Preparación y Homogenización de Materiales 4,417.64 40,438.86 67,272.08 0.00 19,359.55 38,023.53 15,209.41 180,303.42
Transporte, Eliminacion, Acarreo 9,566.75 106,920.25 334,358.31 0.00 0.00 132,044.56 52,817.82 626,140.94
Colocacion de Piedra 2,364.69 21,850.80 19,506.95 1,336.50 0.00 12,775.47 5,110.19 60,579.91
Geotextil 2,745.94 24,912.92 2,768.22 7,411.64 8,646.91 13,088.30 5,235.32 62,063.31
Sistema
4 Habilitado de roca en cantera para terramesh 423.45 3,874.58 8,432.42 0.00 0.00 3,682.65 1,473.06 17,462.71
terramesh
Malla 3,826.74 34,987.10 1,244.14 94,864.77 0.00 39,228.09 15,691.24 186,015.33
Transporte, Eliminacion, Acarreo 563.24 5,906.12 22,240.97 0.00 0.00 8,422.50 3,369.00 39,938.60
Cama de arena 1.73 15.06 7.96 4.76 0.00 8.32 3.33 39.43
Colocacion, compactacion de materiales 223.34 2,140.53 3,353.94 0.00 547.62 1,807.99 723.19 8,573.27
Concreto 58.31 600.62 38.15 844.80 0.00 443.93 177.57 2,105.08
Concreto - Solado 2.51 25.83 1.64 21.60 0.00 14.68 5.87 69.63
Encofrado y desencofrado 91.11 1,085.16 23.33 115.20 0.00 366.17 146.47 1,736.33
Estructuras
5 Excavación, carguío y eliminación 153.54 1,365.20 1,699.63 0.00 12.60 920.87 368.35 4,366.64
hidráulicas
Geotextil 565.78 5,133.15 570.37 1,527.12 1,781.64 2,696.76 1,078.70 12,787.75
Inserto de tuberias 0.00 0.00 0.00 0.00 192.00 57.45 22.98 272.43
Parrilla 0.00 0.00 0.00 0.00 190.08 56.88 22.75 269.71
Tuberia 78.32 759.56 594.25 3,541.99 0.00 1,464.98 585.99 6,946.76
Water Stop 6" 8.23 86.37 2.34 74.70 0.00 48.90 19.56 231.86
Cama de apoyo 2.68 22.78 14.06 8.51 0.00 13.57 5.43 64.37
Colocacion de varilla fe 189.09 1,671.29 744.02 1,964.84 0.00 1,310.68 524.27 6,215.12
Colocacion, compactacion de materiales 5.64 51.79 85.57 0.00 35.32 51.67 20.67 245.01
Concreto 1,882.54 19,390.17 1,199.77 26,565.00 0.00 14,110.26 5,644.10 66,909.30
Concreto - Solado 9.59 98.84 6.11 80.50 0.00 55.49 22.20 263.14
Canal de Encofrado y desencofrado 89.64 1,067.67 22.36 110.40 0.00 359.21 143.68 1,703.31
6
coronación Excavación masiva 91.72 936.46 3,906.98 0.00 3,307.69 2,439.08 975.63 11,565.83
Geomembrana 970.61 8,614.03 298.36 4,499.75 0.00 4,013.34 1,605.33 19,030.81
Inserto de tuberias 0.00 0.00 0.00 0.00 92.00 27.53 11.01 130.54
Parrilla 0.00 0.00 0.00 0.00 885.50 264.97 105.99 1,256.46
Tuberia 86.20 838.65 655.48 8,925.84 0.00 3,117.99 1,247.19 14,785.15
Water Stop 6" 8.09 84.98 2.24 71.59 0.00 47.52 19.01 225.33
Cama de apoyo 2.67 22.70 13.80 8.35 0.00 13.42 5.37 63.63
Colocacion de plancha metalica 0.00 0.00 0.00 0.00 711.56 212.92 85.17 1,009.65
Concreto 293.15 3,019.48 183.97 4,073.30 0.00 2,177.43 870.97 10,325.15
Concreto - Solado 21.84 225.14 13.70 180.55 0.00 125.50 50.20 595.09
Encofrado y desencofrado 546.25 6,505.81 134.14 662.40 0.00 2,185.09 874.04 10,361.48
Vertedero Estribo Excavación masiva 49.58 506.25 2,079.71 0.00 1,760.71 1,300.66 520.26 6,167.60
7
izquierdo Geomembrana 42.19 374.44 12.77 192.60 0.00 173.50 69.40 822.70
Geotextil 75.56 685.57 73.06 195.62 228.22 353.83 141.53 1,677.82
Inserto de tuberias 0.00 0.00 0.00 0.00 184.00 55.06 22.02 261.08
Parrilla 0.00 0.00 0.00 0.00 1,897.50 567.79 227.12 2,692.41
Relleno 67.01 633.19 1,193.44 79.35 120.35 606.34 242.54 2,875.20
Tuberia 35.98 348.57 195.47 2,206.67 0.00 823.10 329.24 3,903.04
1 de 1
DETALLE DE COSTO DE CAPITAL POR SISTEMAS
ITEM SISTEMA COMMODITIES HH MANO OBRA EQUIPOS MATERIALES SUBCONTRATO G.G. UTILIDAD COSTO TOTAL
Colocacion de plancha metalica 0.00 0.00 0.00 0.00 355.78 106.46 42.58 504.83
Colocacion, compactacion de materiales 9.53 90.35 141.43 0.00 42.64 82.11 32.85 389.38
Concreto 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
Vertedero Estribo Concreto - Solado 8.76 90.34 5.50 72.45 0.00 50.36 20.14 238.79
8
derecho Estructura de concreto (vertedero) 3,350.32 34,541.79 2,102.46 50,784.00 0.00 26,161.31 10,464.52 124,054.08
Excavación masiva 21.50 219.47 901.61 0.00 763.31 563.87 225.55 2,673.81
Geotextil 4.90 44.43 4.74 12.68 14.79 22.93 9.17 108.75
Water Stop 6" 8.22 86.30 2.24 71.59 0.00 47.92 19.17 227.21
Estructura de Cama de arena 23.03 199.95 102.96 61.58 0.00 109.07 43.63 517.19
derivación Transporte, Eliminacion, Acarreo 239.12 2,732.01 8,213.97 0.00 0.00 3,275.38 1,310.15 15,531.51
9
(Estribo Tuberia 1,262.05 12,182.71 12,372.22 59,209.25 63.31 25,083.85 10,033.54 118,944.87
Derecho) Vaceado de concreto ciclópeo 1,095.66 11,504.42 379.50 22,137.50 0.00 10,180.29 4,072.12 48,273.82
Colocacion de Piedra 46.92 539.57 440.35 63.36 0.00 312.18 124.87 1,480.34
Colocacion, compactacion de materiales 2.17 19.90 32.05 0.00 13.23 19.51 7.80 92.49
Geotextil 88.51 802.99 84.71 226.80 264.60 412.67 165.07 1,956.84
10 Poza de bombeo
Malla 381.61 3,488.97 117.79 3,880.80 0.00 2,240.52 896.21 10,624.28
Relleno 14.50 137.04 255.67 14.40 21.84 128.35 51.34 608.64
Transporte, Eliminacion, Acarreo 5.71 58.34 219.83 0.00 0.00 83.23 33.29 394.69
Capa de rodadura 117.02 1,020.89 1,099.19 2,810.94 252.98 1,551.22 620.49 7,355.71
Camino de
11 Relleno 53.50 505.56 943.23 127.50 193.38 529.54 211.82 2,511.01
acceso
Transporte, Eliminacion, Acarreo 832.02 8,542.21 31,882.04 0.00 0.00 12,096.22 4,838.49 57,358.96
Gerenciamiento de la construcción (CM) 395,701.00
consultoria de Ingenieria de detalle 287,782.00
Alojamiento y Alimentación 208,197.49
INDIRECTOS
12 Fletes y seguros 107,918.00
PROYECTO
Comisionamiento y Puesta en Marcha 64,751.00
Costos del Propietario 539,592.00
Procura de la Construcción (P) 74,400.00
ESCALAMIENT
13 Escalacion 120,930.30
O
CONTINGENCI
14 Contingencia 1,169,879.75
A
Grand Total 81,997.78 791,058.70 845,329.30 356,952.26 232,902.56 666,162.57 266,465.03 6,128,021.95
2 de 2
IMPLEMENTACIÓN DE DIQUE DE PROTECCIÓN
PARA ESTACIONES 3 Y 3B DE AGUA Revisión: 0
ETAPA: INGENIERIA DE DETALLE - 104 Proyecto:18120
Fecha: 27-Nov-2020
Page 28 de 28
ESTIMADO DE COSTO - CAPEX
104-18120-MTE04418-ECA-440-G-0001
153 A COSTOS DIRECTOS COSTOS DIRECTOS 81,998 81,998 791,059 845,329 356,952 232,903 2,226,243 666,163 - 266,465 - 3,158,870
154
155
156 B INDIRECTOS PROYECTO INDIRECTOS PROYECTO 1,678,341
157 12 INDIRECTOS PROYECTO Procura de la Construcción (P) Procura de la Construcción (P) % Costo Directo 2.36% 74,400
158 12 INDIRECTOS PROYECTO Gerenciamiento de la construcción (CM) Gerenciamiento de la construcción (CM) % Costo Directo 12.53% 395,701
159 12 INDIRECTOS PROYECTO consultoria de Ingenieria de detalle consultoria de Ingenieria de detalle % Costo Directo 9.11% 287,782
160 12 INDIRECTOS PROYECTO Alojamiento y Alimentación Alojamiento y Alimentación % Costo Directo 6.59% 208,197
161 12 INDIRECTOS PROYECTO Fletes y seguros Fletes y seguros % Costo Directo 3.42% 107,918
162 12 INDIRECTOS PROYECTO Comisionamiento y Puesta en Marcha Comisionamiento y Puesta en Marcha % Costo Directo 2.05% 64,751
163 12 INDIRECTOS PROYECTO Costos del Propietario Costos del Propietario % Costo Directo 17.08% 539,592
164
165 C ESCALAMIENTO ESCALAMIENTO 120,930
166 13 ESCALAMIENTO Escalacion ESCALAMIENTO % Costo Directo 2.5% 120,930
167
168 D CONTINGENCIA CONTINGENCIA 1,169,880
169 14 CONTINGENCIA Contingencia CONTINGENCIA CAPEX % Costo Directo 11.19% 541,042
170 14 CONTINGENCIA Contingencia CONTINGENCIA BROWNDFIELD % Costo Directo 3.00% 145,116
171 14 CONTINGENCIA Contingencia CONTINGENCIA POR COVID % Costo Directo 10.00% 483,721
172 E TOTAL CAPEX (A + B + C + D) TOTAL CAPEX (A + B + C + D) 6,128,022
173
174