Cronograma Reprogramado
Cronograma Reprogramado
Cronograma Reprogramado
01 OBRAS PROVISIONALES
01.01 CARTEL DE OBRA 3.60x2.40 und 1.00 1,280.00 1,280.00 1.00 1280.00 100.00% 0.00 0.00% 1.00 1280.00 100.00% 0.00 0.00 0.00%
01.02 HABILITACION DE ACCESO PROVISIONAL est 1.00 8,000.00 8,000.00 1.00 8000.00 100.00% 0.00 0.00% 1.00 8000.00 100.00% 0.00 0.00 0.00%
01.03 INSTALACION DE ACCESO PROVISIONAL est 1.00 4,000.00 4,000.00 1.00 4000.00 100.00% 0.00 0.00% 1.00 4000.00 100.00% 0.00 0.00 0.00%
02 TRABAJOS PRELIMINARES
02.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS est 1.00 5,000.00 5,000.00 1.00 5000.00 100.00% 0.00 0.00% 1.00 5000.00 100.00% 0.00 0.00 0.00%
02.02 DESBROCE Y LIMPIEZA DE TERRENO ha 0.16 1,000.00 160.00 0.16 160.00 100.00% 0.00 0.00% 0.16 160.00 100.00% 0.00 0.00 0.00%
02.03 TRAZO, NIVEL Y REPLANTEO PRELIMINAR m2 308.88 4.00 1,235.52 308.88 1235.52 100.00% 0.00 0.00% 308.88 1235.52 100.00% 0.00 0.00 0.00%
02.04 TRAZO, NIVEL Y REPLANTEO DURANTE LA EJECUCION DE OBRA mes 3.00 2,500.00 7,500.00 3.00 7500.00 100.00% 0.00 0.00% 3.00 7500.00 100.00% 0.00 0.00 0.00%
03 DEMOLICIONES Y DESMONTAJES
03.01 DEMOLICION DE ESTRUCTURAS DE CONCRETO m3 254.01 60.00 15,240.60 254.01 15240.60 100.00% 0.00 0.00% 254.01 15240.60 100.00% 0.00 0.00 0.00%
03.02 TRANSPORTE Y ELIMINACION DE MATERIAL DE DEMOLICIONES m3 381.02 20.00 7,620.40 381.02 7620.40 100.00% 0.00 0.00% 381.02 7620.40 100.00% 0.00 0.00 0.00%
04 MOVIMIENTO DE TIERRAS
04.01 SUB ESTRUCTURA
04.01.01 EXCAVACION PARA ESTRUCTURAS EN MATERIAL COMUN m3 374.66 20.00 7,493.20 374.66 7493.20 100.00% 0.00 0.00% 374.66 7493.20 100.00% 0.00 0.00 0.00%
04.01.02 EXCAVACION PARA ESTRUCTURAS BAJO EL AGUA m3 393.01 15.00 5,895.15 393.01 5895.15 100.00% 0.00 0.00% 393.01 5895.15 100.00% 0.00 0.00 0.00%
04.01.03 DESVIO DE CURSOS DE AGUA m3 226.58 13.00 2,945.54 226.58 2945.54 100.00% 0.00 0.00% 226.58 2945.54 100.00% 0.00 0.00 0.00%
04.01.04 RELLENO DE ESTRUCTURAS CON MATERIAL DE PRESTAMO m3 145.48 90.00 13,093.20 145.48 13093.20 100.00% 0.00 0.00% 145.48 13093.20 100.00% 0.00 0.00 0.00%
04.01.05 RELLENO DE ESTRUCTURAS CON MATERIAL PROPIO m3 256.58 50.00 12,829.00 256.58 12829.00 100.00% 0.00 0.00% 256.58 12829.00 100.00% 0.00 0.00 0.00%
04.01.06 TRANSPORTE Y ELIMINACION DE MATERIAL EXCEDENTE m3 656.77 20.00 13,135.40 656.77 13135.40 100.00% 0.00 0.00% 656.77 13135.40 100.00% 0.00 0.00 0.00%
04.02 CONFORMACION DE BASE PARA FALSO PUENTE
04.02.01 RELLENO DE ESTRUCTURAS CON MATERIAL PROPIO m3 40.84 50.00 2,042.00 40.84 2042.00 100.00% 0.00 0.00% 40.84 2042.00 100.00% 0.00 0.00 0.00%
05 SUB ESTRUCTURA
05.01 SOLADO
05.01.01 CONCRETO f'c=100 kg/cm2 SOLADO E=10 CM 1:12 C:H m2 163.46 30.00 4,903.80 163.46 4903.80 100.00% 0.00 0.00% 163.46 4903.80 100.00% 0.00 0.00 0.00%
05.01.02 ENCOFRADO Y DESENCOFRADO m2 7.67 90.00 690.30 7.67 690.30 100.00% 0.00 0.00% 7.67 690.30 100.00% 0.00 0.00 0.00%
05.02 ESTRIBOS
05.02.01 CIMENTACION
05.02.01.01 CONCRETO f'c=280 kg/cm2 m3 147.11 440.00 64,728.40 147.11 64728.40 100.00% 0.00 0.00% 147.11 64728.40 100.00% 0.00 0.00 0.00%
05.02.01.02 ENCOFRADO Y DESENCOFRADO m2 69.07 90.00 6,216.30 69.07 6216.30 100.00% 0.00 0.00% 69.07 6216.30 100.00% 0.00 0.00 0.00%
05.02.01.03 ACERO fy=4,200 kg/cm2 kg 10,439.50 7.00 73,076.50 10,439.50 73076.50 100.00% 0.00 0.00% 10,439.50 73076.50 100.00% 0.00 0.00 0.00%
05.02.02 PANTALLA
05.02.02.01 CONCRETO f'c=280 kg/cm2 m3 103.63 400.00 41,452.00 103.63 41452.00 100.00% 0.00 0.00% 103.63 41452.00 100.00% 0.00 0.00 0.00%
05.02.02.02 ENCOFRADO Y DESENCOFRADO m2 300.89 90.00 27,080.10 300.89 27080.10 100.00% 0.00 0.00% 300.89 27080.10 100.00% 0.00 0.00 0.00%
05.02.02.03 ACERO fy=4,200 kg/cm2 kg 7,420.67 7.00 51,944.69 7,420.67 51944.69 100.00% 0.00 0.00% 7,420.67 51944.69 100.00% 0.00000 0.00 0.00%
05.02.03 CABEZAL
RESUMEN DE VALORIZACION MENSUAL DE OBRA N° 05 DICIEMBRE
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE MAZAMARI CONTRATO DE OBRA N° N° 001-2023-GM/MDM.
“RENOVACION DE PUENTE; EN EL(LA) CAMINO VECINAL R1206241 (PUENTE BALVIN) EN LA
OBRA TRAYECTORIA HACIA EL CENTRO POBLADO RIO DE ORO EN EL DISTRITO DE MAZAMARI, PROVINCIA PLAZO DE EJECUCION 90 DÍAS CALENDARIOS
SATIPO, DEPARTAMENTO JUNIN”
LUGAR CC.PP. RIO DE ORO MAZAMARI SATIPO JUNIN FECHA DE INICIO DE OBRA 8/10/2023
CONTRATISTA CEIA S.A.C FECHA DE TERMINO PROGRAMADO 11/8/2023
RESIDENTE DE OBRA ING. SEGUNDO JUAN LINGAN HERNANDEZ CIP N 68131 FECHA DE SUSPENSIÓN DE OBRA 11/1/2023
SUPERVISOR DE OBRA ING . PONCE AVELLANEDA CESAR MANUEL CIP N 69236 FECHA DE REINICIO DE OBRA 11/29/2023
PERIODO VALORIZADO 01/12/2023 AL 04/12/2023 FECHA DE TERMINO PROGAMADA DE OBR 12/2/2023
05.02.03.01 CONCRETO f'c=280 kg/cm2 m3 7.55 440.00 3,322.00 7.55 3322.00 100.00% 0.00 0.00% 7.55 3322.00 100.00% 0.00 0.00 0.00%
05.02.03.02 ENCOFRADO Y DESENCOFRADO m2 17.27 90.00 1,554.30 17.27 1554.30 100.00% 0.00 0.00% 17.27 1554.30 100.00% 0.00 0.00 0.00%
RESUMEN DE VALORIZACION MENSUAL DE OBRA N° 05 DICIEMBRE
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE MAZAMARI CONTRATO DE OBRA N° N° 001-2023-GM/MDM.
“RENOVACION DE PUENTE; EN EL(LA) CAMINO VECINAL R1206241 (PUENTE BALVIN) EN LA
OBRA TRAYECTORIA HACIA EL CENTRO POBLADO RIO DE ORO EN EL DISTRITO DE MAZAMARI, PROVINCIA PLAZO DE EJECUCION 90 DÍAS CALENDARIOS
SATIPO, DEPARTAMENTO JUNIN”
LUGAR CC.PP. RIO DE ORO MAZAMARI SATIPO JUNIN FECHA DE INICIO DE OBRA 8/10/2023
CONTRATISTA CEIA S.A.C FECHA DE TERMINO PROGRAMADO 11/8/2023
RESIDENTE DE OBRA ING. SEGUNDO JUAN LINGAN HERNANDEZ CIP N 68131 FECHA DE SUSPENSIÓN DE OBRA 11/1/2023
SUPERVISOR DE OBRA ING . PONCE AVELLANEDA CESAR MANUEL CIP N 69236 FECHA DE REINICIO DE OBRA 11/29/2023
PERIODO VALORIZADO 01/12/2023 AL 04/12/2023 FECHA DE TERMINO PROGAMADA DE OBR 12/2/2023
05.02.03.03 ACERO fy=4,200 kg/cm2 kg 206.52 7.00 1,445.64 206.52 1445.64 100.00% 0.00 0.00% 206.52 1445.64 100.00% 0.00 0.00 0.00%
05.02.04 PARAPETOS
05.02.04.01 CONCRETO f'c=280 kg/cm2 m3 5.06 440.00 2,226.40 5.06 2226.40 100.00% 0.00 0.00% 5.06 2226.40 100.00% 0.00 0.00 0.00%
05.02.04.02 ENCOFRADO Y DESENCOFRADO m2 35.18 90.00 3,166.20 35.18 3166.20 100.00% 0.00 0.00% 35.18 3166.20 100.00% 0.00 0.00 0.00%
05.02.04.03 ACERO fy=4,200 kg/cm2 kg 460.20 7.00 3,221.40 460.20 3221.40 100.00% 0.00 0.00% 460.20 3221.40 100.00% 0.00 0.00 0.00%
05.02.04.04 TAPAJUNTA METALICA EN PISOS m 9.80 300.00 2,940.00 9.80 2940.00 100.00% 0.00 0.00% 9.80 2940.00 100.00% 0.00 0.00 0.00%
05.02.04.05 JUNTA DE DILATACION e=1" m 2.00 50.00 100.00 2.00 100.00 100.00% 0.00 0.00% 2.00 100.00 100.00% 0.00 0.00 0.00%
06 SUPER ESTRUCTURA
06.01 TABLERO VIGA - LOSA
06.01.01 CONCRETO f'c=280 kg/cm2 m3 14.04 440.00 6,177.60 14.04 6177.60 100.00% 0.00 0.00% 14.04 6177.60 100.00% 0.00 0.00 0.00%
06.01.02 ENCOFRADO Y DESENCOFRADO m2 59.13 90.00 5,321.70 59.13 5321.70 100.00% 0.00 0.00% 59.13 5321.70 100.00% 0.00 0.00 0.00%
06.01.03 ACERO fy=4,200 kg/cm2 kg 1,563.42 7.00 10,943.94 1,563.42 10943.94 100.00% 0.00 0.00% 1,563.42 10943.94 100.00% 0.00 0.00 0.00%
06.01.04 JUNTA DE DILATACION e=1" m 8.00 50.00 400.00 8.00 400.00 100.00% 0.00 0.00% 8.00 400.00 100.00% 0.00 0.00 0.00%
06.02 VIGAS
06.02.01 CONCRETO f'c=280 kg/cm2 m3 12.79 440.00 5,627.60 12.79 5627.60 100.00% 0.00 0.00% 12.79 5627.60 100.00% 0.00 0.00 0.00%
06.02.02 ENCOFRADOS Y DESENCOFRADOS m2 79.02 100.00 7,902.00 79.02 7902.00 100.00% 0.00 0.00% 79.02 7902.00 100.00% 0.00 0.00 0.00%
06.02.03 ACERO fy=4,200 kg/cm2 kg 1,854.10 7.00 12,978.70 1,854.10 12978.70 100.00% 0.00 0.00% 1,854.10 12978.70 100.00% 0.00 0.00 0.00%
06.03 DIAFRAGMAS
06.03.01 CONCRETO f'c=280 kg/cm2 m3 1.85 440.00 814.00 1.85 814.00 100.00% 0.00 0.00% 1.85 814.00 100.00% 0.00 0.00 0.00%
06.03.02 ENCOFRADO Y DESENCOFRADO m2 17.07 90.00 1,536.30 17.07 1536.30 100.00% 0.00 0.00% 17.07 1536.30 100.00% 0.00 0.00 0.00%
06.03.03 ACERO fy=4,200 kg/cm2 kg 411.46 7.00 2,880.22 411.46 2880.22 100.00% 0.00 0.00% 411.46 2880.22 100.00% 0.00 0.00 0.00%
07 ELEMENTOS COMPLEMENTARIOS
07.01 LOSA DE APROXIMACION
07.01.01 CONCRETO f'c=210 kg/cm2 m3 14.20 380.00 5,396.00 14.20 5396.00 100.00% 0.00 0.00% 14.20 5396.00 100.00% 0.00 0.00 0.00%
07.01.02 ENCOFRADOS Y DESENCOFRADOS m2 13.75 100.00 1,375.00 13.75 1375.00 100.00% 0.00 0.00% 13.75 1375.00 100.00% 0.00 0.00 0.00%
07.01.03 ACERO fy=4,200 kg/cm2 kg 990.55 7.00 6,933.85 990.55 6933.85 100.00% 0.00 0.00% 990.55 6933.85 100.00% 0.00 0.00 0.00%
07.02 BARANDAS
07.02.01 BARANDAS DE FºGº 4" m 31.20 300.00 9,360.00 31.20 9360.00 100.00% 0.00 0.00% 31.20 9360.00 100.00% 0.00 0.00 0.00%
07.02.02 PINTADO DE BARANDAS METALICAS m2 12.00 20.00 240.00 12.00 240.00 100.00% 0.00 0.00% 12.00 240.00 100.00% 0.00 0.00 0.00%
07.03 NEOPRENO Y PAVIMENTOS
07.03.01 CARPETA ASFALTICA EN CALIENTE DE 2" m2 62.40 100.00 6,240.00 62.40 6240.00 100.00% 0.00 0.00% 62.40 6240.00 100.00% 0.00 0.00 0.00%
07.03.02 APOYO DE NEOPRENE DENSIDAD 60 und 4.00 1,000.00 4,000.00 4.00 4000.00 100.00% 0.00 0.00% 4.00 4000.00 100.00% 0.00 0.00 0.00%
07.04 VEREDAS
07.04.01 CONCRETO f'c=280 kg/cm2 m3 4.06 440.00 1,786.40 4.06 1786.40 100.00% 0.00 0.00% 4.06 1786.40 100.00% 0.00 0.00 0.00%
07.04.02 ENCOFRADO Y DESENCOFRADO m2 31.36 90.00 2,822.40 31.36 2822.40 100.00% 0.00 0.00% 31.36 2822.40 100.00% 0.00 0.00 0.00%
07.04.03 ACERO fy=4,200 kg/cm2 kg 542.78 7.00 3,799.46 542.78 3799.46 100.00% 0.00 0.00% 542.78 3799.46 100.00% 0.00 0.00 0.00%
08 OBRAS DE ENCAUSAMIENTO
RESUMEN DE VALORIZACION MENSUAL DE OBRA N° 05 DICIEMBRE
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE MAZAMARI CONTRATO DE OBRA N° N° 001-2023-GM/MDM.
“RENOVACION DE PUENTE; EN EL(LA) CAMINO VECINAL R1206241 (PUENTE BALVIN) EN LA
OBRA TRAYECTORIA HACIA EL CENTRO POBLADO RIO DE ORO EN EL DISTRITO DE MAZAMARI, PROVINCIA PLAZO DE EJECUCION 90 DÍAS CALENDARIOS
SATIPO, DEPARTAMENTO JUNIN”
LUGAR CC.PP. RIO DE ORO MAZAMARI SATIPO JUNIN FECHA DE INICIO DE OBRA 8/10/2023
CONTRATISTA CEIA S.A.C FECHA DE TERMINO PROGRAMADO 11/8/2023
RESIDENTE DE OBRA ING. SEGUNDO JUAN LINGAN HERNANDEZ CIP N 68131 FECHA DE SUSPENSIÓN DE OBRA 11/1/2023
SUPERVISOR DE OBRA ING . PONCE AVELLANEDA CESAR MANUEL CIP N 69236 FECHA DE REINICIO DE OBRA 11/29/2023
PERIODO VALORIZADO 01/12/2023 AL 04/12/2023 FECHA DE TERMINO PROGAMADA DE OBR 12/2/2023
08.01 ENCAUSAMIENTO EN ZONA DE PUENTE m3 418.30 15.00 6,274.50 365.00 5475.00 87.26% 53.30 799.50 12.74% 418.30 6274.50 100.00% 0.00 0.00 0.00%
08.02 TRANSPORTE Y ELIMINACION DE MATERIALES EXCEDENTES m3 501.96 15.00 7,529.40 308.00 4620.00 61.36% 193.96 2909.40 38.64% 501.96 7529.40 100.00% 0.00 0.00 0.00%
09 SEÑALIZACION Y SEGURIDAD VIAL
09.01 SEÑALES INFORMATIVAS (1.25x2.50 m) und 2.00 2,000.00 4,000.00 2.00 4000.00 100.00% 0.00 0.00% 2.00 4000.00 100.00% 0.00 0.00 0.00%
10 VARIOS
10.01 CONCRETO f'c=140 kg/cm2 PARA FALSO PUENTE m3 47.50 350.00 16,625.00 47.50 16625.00 100.00% 0.00 0.00% 47.50 16625.00 100.00% 0.00 0.00 0.00%
10.02 CONSTRUCCION DE FALSO PUENTE m2 85.80 200.00 17,160.00 85.80 17160.00 100.00% 0.00 0.00% 85.80 17160.00 100.00% 0.00 0.00 0.00%
10.03 TUBERIA PVC SAL 3" m 82.04 15.00 1,230.60 82.04 1230.60 100.00% 0.00 0.00% 82.04 1230.60 100.00% 0.00 0.00 0.00%
10.04 ACABADO PULIDO EN VEREDAS CON MORTERO 1:2 x 1.5 CM m2 34.48 20.00 689.60 34.48 689.60 100.00% 0.00 0.00% 34.48 689.60 100.00% 0.00 0.00 0.00%
10.05 PINTURA PARA BORDES DE VEREDAS m 31.20 20.00 624.00 31.20 624.00 100.00% 0.00 0.00% 31.20 624.00 100.00% 0.00 0.00 0.00%
10.06 LIMPIEZA FINAL DE OBRA m2 1,420.00 2.00 2,840.00 0.00 0.00 0.00% 1420.00 2840.00 100.00% 1,420.00 2840.00 100.00% 0.00 0.00 0.00%
10.07 PLACA RECORDATORIA DE BRONCE glb 1.00 900.00 900.00 0.00 0.00 0.00% 1.00 900.00 100.00% 1.00 900.00 100.00% 0.00 0.00 0.00%
11 MITIGACION AMBIENTAL
11.01 MEDIDAS DE PREVENCION Y MITIGACION glb 1.00 1,500.00 1,500.00 1.00 1500.00 100.00% 0.00 0.00% 1.00 1500.00 100.00% 0.00 0.00 0.00%
11.02 SEÑALES INFORMETIVAS AMBIENTALES und 1.00 900.00 900.00 1.00 900.00 100.00% 0.00 0.00% 1.00 900.00 100.00% 0.00 0.00 0.00%
11.03 RESTAURACION DE AREAS AFECTADAS glb 1.00 2,000.00 2,000.00 0.00 0.00 0.00% 1.00 2000.00 100.00% 1.00 2000.00 100.00% 0.00 0.00 0.00%
11.04 PROGRAMA DE MANEJO DE RESIDUOS glb 1.00 2,000.00 2,000.00 1.00 2000.00 100.00% 0.00 0.00% 1.00 2000.00 100.00% 0.00 0.00 0.00%
11.05 PROGRAMA DE MONITOREO AMBIENTAL glb 1.00 9,000.00 9,000.00 1.00 9000.00 100.00% 0.00 0.00% 1.00 9000.00 100.00% 0.00 0.00 0.00%
11.06 PROGRAMA DE ASUNTOS SOCIALES glb 1.00 2,000.00 2,000.00 1.00 2000.00 100.00% 0.00 0.00% 1.00 2000.00 100.00% 0.00 0.00 0.00%
11.07 PLAN DE CONTINGENCIAS glb 1.00 1,000.00 1,000.00 1.00 1000.00 100.00% 0.00 0.00% 1.00 1000.00 100.00% 0.00 0.00 0.00%
12 SEGURIDAD Y SALUD OCUPACIONAL
12.01 SEGURIDAD Y SALUD glb 1.00 9,000.00 9,000.00 1.00 9000.00 100.00% 0.00 0.00% 1.00 9000.00 100.00% 0.00 0.00 0.00%
12.02 VIGILANCIA, PREVENCION Y CONTROL DE COVID - 19 glb 1.00 13,127.69 13,127.69 1.00 13127.69 100.00% 0.00 0.00% 1.00 13127.69 100.00% 0.00 0.00 0.00%
13 FLETE TERRESTRE
13.01 FLETE TERRESTRE glb 1.00 9,526.00 9,526.00 1.00 9526.00 100.00% 0.00 0.00% 1.00 9526.00 100.00% 0.00 0.00 0.00%
100.00%
98.43%
1.57%
0.00%
IGV 18.00% 0.00 0.00 0.00 0.00 0.00
01 OBRAS PROVISIONALES
01.01 CARTEL DE OBRA 3.60x2.40 und 1.00 1,280.00 1,280.00 1.00 1280.00 100.00% 0.00 0.00% 1.00 1280.00 100.00% 0.00 0.00 0.00%
01.02 HABILITACION DE ACCESO PROVISIONAL est 1.00 8,000.00 8,000.00 1.00 8000.00 100.00% 0.00 0.00% 1.00 8000.00 100.00% 0.00 0.00 0.00%
01.03 INSTALACION DE ACCESO PROVISIONAL est 1.00 4,000.00 4,000.00 1.00 4000.00 100.00% 0.00 0.00% 1.00 4000.00 100.00% 0.00 0.00 0.00%
02 TRABAJOS PRELIMINARES
02.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS est 1.00 5,000.00 5,000.00 1.00 5000.00 100.00% 0.00 0.00% 1.00 5000.00 100.00% 0.00 0.00 0.00%
02.02 DESBROCE Y LIMPIEZA DE TERRENO ha 0.16 1,000.00 160.00 0.16 160.00 100.00% 0.00 0.00% 0.16 160.00 100.00% 0.00 0.00 0.00%
02.03 TRAZO, NIVEL Y REPLANTEO PRELIMINAR m2 308.88 4.00 1,235.52 308.88 1235.52 100.00% 0.00 0.00% 308.88 1235.52 100.00% 0.00 0.00 0.00%
02.04 TRAZO, NIVEL Y REPLANTEO DURANTE LA EJECUCION DE OBRA mes 3.00 2,500.00 7,500.00 3.00 7500.00 100.00% 0.00 0.00% 3.00 7500.00 100.00% 0.00 0.00 0.00%
03 DEMOLICIONES Y DESMONTAJES
03.01 DEMOLICION DE ESTRUCTURAS DE CONCRETO m3 254.01 60.00 15,240.60 254.01 15240.60 100.00% 0.00 0.00% 254.01 15240.60 100.00% 0.00 0.00 0.00%
03.02 TRANSPORTE Y ELIMINACION DE MATERIAL DE DEMOLICIONES m3 381.02 20.00 7,620.40 381.02 7620.40 100.00% 0.00 0.00% 381.02 7620.40 100.00% 0.00 0.00 0.00%
04 MOVIMIENTO DE TIERRAS
04.01 SUB ESTRUCTURA
04.01.01 EXCAVACION PARA ESTRUCTURAS EN MATERIAL COMUN m3 374.66 20.00 7,493.20 374.66 7493.20 100.00% 0.00 0.00% 374.66 7493.20 100.00% 0.00 0.00 0.00%
04.01.02 EXCAVACION PARA ESTRUCTURAS BAJO EL AGUA m3 393.01 15.00 5,895.15 393.01 5895.15 100.00% 0.00 0.00% 393.01 5895.15 100.00% 0.00 0.00 0.00%
04.01.03 DESVIO DE CURSOS DE AGUA m3 226.58 13.00 2,945.54 226.58 2945.54 100.00% 0.00 0.00% 226.58 2945.54 100.00% 0.00 0.00 0.00%
04.01.04 RELLENO DE ESTRUCTURAS CON MATERIAL DE PRESTAMO m3 145.48 90.00 13,093.20 145.48 13093.20 100.00% 0.00 0.00% 145.48 13093.20 100.00% 0.00 0.00 0.00%
04.01.05 RELLENO DE ESTRUCTURAS CON MATERIAL PROPIO m3 256.58 50.00 12,829.00 256.58 12829.00 100.00% 0.00 0.00% 256.58 12829.00 100.00% 0.00 0.00 0.00%
04.01.06 TRANSPORTE Y ELIMINACION DE MATERIAL EXCEDENTE m3 656.77 20.00 13,135.40 656.77 13135.40 100.00% 0.00 0.00% 656.77 13135.40 100.00% 0.00 0.00 0.00%
04.02 CONFORMACION DE BASE PARA FALSO PUENTE
04.02.01 RELLENO DE ESTRUCTURAS CON MATERIAL PROPIO m3 40.84 50.00 2,042.00 40.84 2042.00 100.00% 0.00 0.00% 40.84 2042.00 100.00% 0.00 0.00 0.00%
05 SUB ESTRUCTURA
05.01 SOLADO
05.01.01 CONCRETO f'c=100 kg/cm2 SOLADO E=10 CM 1:12 C:H m2 163.46 30.00 4,903.80 163.46 4903.80 100.00% 0.00 0.00% 163.46 4903.80 100.00% 0.00 0.00 0.00%
05.01.02 ENCOFRADO Y DESENCOFRADO m2 7.67 90.00 690.30 7.67 690.30 100.00% 0.00 0.00% 7.67 690.30 100.00% 0.00 0.00 0.00%
05.02 ESTRIBOS
05.02.01 CIMENTACION
05.02.01.01 CONCRETO f'c=280 kg/cm2 m3 147.11 440.00 64,728.40 147.11 64728.40 100.00% 0.00 0.00% 147.11 64728.40 100.00% 0.00 0.00 0.00%
05.02.01.02 ENCOFRADO Y DESENCOFRADO m2 69.07 90.00 6,216.30 69.07 6216.30 100.00% 0.00 0.00% 69.07 6216.30 100.00% 0.00 0.00 0.00%
05.02.01.03 ACERO fy=4,200 kg/cm2 kg 10,439.50 7.00 73,076.50 10,439.50 73076.50 100.00% 0.00 0.00% 10,439.50 73076.50 100.00% 0.00 0.00 0.00%
05.02.02 PANTALLA
05.02.02.01 CONCRETO f'c=280 kg/cm2 m3 103.63 400.00 41,452.00 103.63 41452.00 100.00% 0.00 0.00% 103.63 41452.00 100.00% 0.00 0.00 0.00%
05.02.02.02 ENCOFRADO Y DESENCOFRADO m2 300.89 90.00 27,080.10 300.89 27080.10 100.00% 0.00 0.00% 300.89 27080.10 100.00% 0.00 0.00 0.00%
05.02.02.03 ACERO fy=4,200 kg/cm2 kg 7,420.67 7.00 51,944.69 7,420.67 51944.69 100.00% 0.00 0.00% 7,420.67 51944.69 100.00% 0.00000 0.00 0.00%
05.02.03 CABEZAL
RESUMEN DE VALORIZACION MENSUAL DE OBRA N° 05 DICIEMBRE
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE MAZAMARI CONTRATO DE OBRA N° N° 001-2023-GM/MDM.
“RENOVACION DE PUENTE; EN EL(LA) CAMINO VECINAL R1206241 (PUENTE BALVIN) EN LA
OBRA TRAYECTORIA HACIA EL CENTRO POBLADO RIO DE ORO EN EL DISTRITO DE MAZAMARI, PROVINCIA PLAZO DE EJECUCION 90 DÍAS CALENDARIOS
SATIPO, DEPARTAMENTO JUNIN”
LUGAR CC.PP. RIO DE ORO MAZAMARI SATIPO JUNIN FECHA DE INICIO DE OBRA 8/10/2023
CONTRATISTA CEIA S.A.C FECHA DE TERMINO PROGRAMADO 11/8/2023
RESIDENTE DE OBRA ING. SEGUNDO JUAN LINGAN HERNANDEZ CIP N 68131 FECHA DE SUSPENSIÓN DE OBRA 11/1/2023
SUPERVISOR DE OBRA ING . PONCE AVELLANEDA CESAR MANUEL CIP N 69236 FECHA DE REINICIO DE OBRA 11/29/2023
PERIODO VALORIZADO 01/12/2023 AL 04/12/2023 FECHA DE TERMINO PROGAMADA DE OBR 12/6/2023
05.02.03.01 CONCRETO f'c=280 kg/cm2 m3 7.55 440.00 3,322.00 7.55 3322.00 100.00% 0.00 0.00% 7.55 3322.00 100.00% 0.00 0.00 0.00%
05.02.03.02 ENCOFRADO Y DESENCOFRADO m2 17.27 90.00 1,554.30 17.27 1554.30 100.00% 0.00 0.00% 17.27 1554.30 100.00% 0.00 0.00 0.00%
RESUMEN DE VALORIZACION MENSUAL DE OBRA N° 05 DICIEMBRE
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE MAZAMARI CONTRATO DE OBRA N° N° 001-2023-GM/MDM.
“RENOVACION DE PUENTE; EN EL(LA) CAMINO VECINAL R1206241 (PUENTE BALVIN) EN LA
OBRA TRAYECTORIA HACIA EL CENTRO POBLADO RIO DE ORO EN EL DISTRITO DE MAZAMARI, PROVINCIA PLAZO DE EJECUCION 90 DÍAS CALENDARIOS
SATIPO, DEPARTAMENTO JUNIN”
LUGAR CC.PP. RIO DE ORO MAZAMARI SATIPO JUNIN FECHA DE INICIO DE OBRA 8/10/2023
CONTRATISTA CEIA S.A.C FECHA DE TERMINO PROGRAMADO 11/8/2023
RESIDENTE DE OBRA ING. SEGUNDO JUAN LINGAN HERNANDEZ CIP N 68131 FECHA DE SUSPENSIÓN DE OBRA 11/1/2023
SUPERVISOR DE OBRA ING . PONCE AVELLANEDA CESAR MANUEL CIP N 69236 FECHA DE REINICIO DE OBRA 11/29/2023
PERIODO VALORIZADO 01/12/2023 AL 04/12/2023 FECHA DE TERMINO PROGAMADA DE OBR 12/6/2023
05.02.03.03 ACERO fy=4,200 kg/cm2 kg 206.52 7.00 1,445.64 206.52 1445.64 100.00% 0.00 0.00% 206.52 1445.64 100.00% 0.00 0.00 0.00%
05.02.04 PARAPETOS
05.02.04.01 CONCRETO f'c=280 kg/cm2 m3 5.06 440.00 2,226.40 5.06 2226.40 100.00% 0.00 0.00% 5.06 2226.40 100.00% 0.00 0.00 0.00%
05.02.04.02 ENCOFRADO Y DESENCOFRADO m2 35.18 90.00 3,166.20 35.18 3166.20 100.00% 0.00 0.00% 35.18 3166.20 100.00% 0.00 0.00 0.00%
05.02.04.03 ACERO fy=4,200 kg/cm2 kg 460.20 7.00 3,221.40 460.20 3221.40 100.00% 0.00 0.00% 460.20 3221.40 100.00% 0.00 0.00 0.00%
05.02.04.04 TAPAJUNTA METALICA EN PISOS m 9.80 300.00 2,940.00 9.80 2940.00 100.00% 0.00 0.00% 9.80 2940.00 100.00% 0.00 0.00 0.00%
05.02.04.05 JUNTA DE DILATACION e=1" m 2.00 50.00 100.00 2.00 100.00 100.00% 0.00 0.00% 2.00 100.00 100.00% 0.00 0.00 0.00%
06 SUPER ESTRUCTURA
06.01 TABLERO VIGA - LOSA
06.01.01 CONCRETO f'c=280 kg/cm2 m3 14.04 440.00 6,177.60 14.04 6177.60 100.00% 0.00 0.00% 14.04 6177.60 100.00% 0.00 0.00 0.00%
06.01.02 ENCOFRADO Y DESENCOFRADO m2 59.13 90.00 5,321.70 59.13 5321.70 100.00% 0.00 0.00% 59.13 5321.70 100.00% 0.00 0.00 0.00%
06.01.03 ACERO fy=4,200 kg/cm2 kg 1,563.42 7.00 10,943.94 1,563.42 10943.94 100.00% 0.00 0.00% 1,563.42 10943.94 100.00% 0.00 0.00 0.00%
06.01.04 JUNTA DE DILATACION e=1" m 8.00 50.00 400.00 8.00 400.00 100.00% 0.00 0.00% 8.00 400.00 100.00% 0.00 0.00 0.00%
06.02 VIGAS
06.02.01 CONCRETO f'c=280 kg/cm2 m3 12.79 440.00 5,627.60 12.79 5627.60 100.00% 0.00 0.00% 12.79 5627.60 100.00% 0.00 0.00 0.00%
06.02.02 ENCOFRADOS Y DESENCOFRADOS m2 79.02 100.00 7,902.00 79.02 7902.00 100.00% 0.00 0.00% 79.02 7902.00 100.00% 0.00 0.00 0.00%
06.02.03 ACERO fy=4,200 kg/cm2 kg 1,854.10 7.00 12,978.70 1,854.10 12978.70 100.00% 0.00 0.00% 1,854.10 12978.70 100.00% 0.00 0.00 0.00%
06.03 DIAFRAGMAS
06.03.01 CONCRETO f'c=280 kg/cm2 m3 1.85 440.00 814.00 1.85 814.00 100.00% 0.00 0.00% 1.85 814.00 100.00% 0.00 0.00 0.00%
06.03.02 ENCOFRADO Y DESENCOFRADO m2 17.07 90.00 1,536.30 17.07 1536.30 100.00% 0.00 0.00% 17.07 1536.30 100.00% 0.00 0.00 0.00%
06.03.03 ACERO fy=4,200 kg/cm2 kg 411.46 7.00 2,880.22 411.46 2880.22 100.00% 0.00 0.00% 411.46 2880.22 100.00% 0.00 0.00 0.00%
07 ELEMENTOS COMPLEMENTARIOS
07.01 LOSA DE APROXIMACION
07.01.01 CONCRETO f'c=210 kg/cm2 m3 14.20 380.00 5,396.00 14.20 5396.00 100.00% 0.00 0.00% 14.20 5396.00 100.00% 0.00 0.00 0.00%
07.01.02 ENCOFRADOS Y DESENCOFRADOS m2 13.75 100.00 1,375.00 13.75 1375.00 100.00% 0.00 0.00% 13.75 1375.00 100.00% 0.00 0.00 0.00%
07.01.03 ACERO fy=4,200 kg/cm2 kg 990.55 7.00 6,933.85 990.55 6933.85 100.00% 0.00 0.00% 990.55 6933.85 100.00% 0.00 0.00 0.00%
07.02 BARANDAS
07.02.01 BARANDAS DE FºGº 4" m 31.20 300.00 9,360.00 31.20 9360.00 100.00% 0.00 0.00% 31.20 9360.00 100.00% 0.00 0.00 0.00%
07.02.02 PINTADO DE BARANDAS METALICAS m2 12.00 20.00 240.00 0.00 0.00 0.00% 12.00 240.00 100.00% 12.00 240.00 100.00% 0.00 0.00 0.00%
07.03 NEOPRENO Y PAVIMENTOS
07.03.01 CARPETA ASFALTICA EN CALIENTE DE 2" m2 62.40 100.00 6,240.00 0.00 0.00 0.00% 62.40 6240.00 100.00% 62.40 6240.00 100.00% 0.00 0.00 0.00%
07.03.02 APOYO DE NEOPRENE DENSIDAD 60 und 4.00 1,000.00 4,000.00 4.00 4000.00 100.00% 0.00 0.00% 4.00 4000.00 100.00% 0.00 0.00 0.00%
07.04 VEREDAS
07.04.01 CONCRETO f'c=280 kg/cm2 m3 4.06 440.00 1,786.40 4.06 1786.40 100.00% 0.00 0.00% 4.06 1786.40 100.00% 0.00 0.00 0.00%
07.04.02 ENCOFRADO Y DESENCOFRADO m2 31.36 90.00 2,822.40 31.36 2822.40 100.00% 0.00 0.00% 31.36 2822.40 100.00% 0.00 0.00 0.00%
07.04.03 ACERO fy=4,200 kg/cm2 kg 542.78 7.00 3,799.46 542.78 3799.46 100.00% 0.00 0.00% 542.78 3799.46 100.00% 0.00 0.00 0.00%
08 OBRAS DE ENCAUSAMIENTO
RESUMEN DE VALORIZACION MENSUAL DE OBRA N° 05 DICIEMBRE
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE MAZAMARI CONTRATO DE OBRA N° N° 001-2023-GM/MDM.
“RENOVACION DE PUENTE; EN EL(LA) CAMINO VECINAL R1206241 (PUENTE BALVIN) EN LA
OBRA TRAYECTORIA HACIA EL CENTRO POBLADO RIO DE ORO EN EL DISTRITO DE MAZAMARI, PROVINCIA PLAZO DE EJECUCION 90 DÍAS CALENDARIOS
SATIPO, DEPARTAMENTO JUNIN”
LUGAR CC.PP. RIO DE ORO MAZAMARI SATIPO JUNIN FECHA DE INICIO DE OBRA 8/10/2023
CONTRATISTA CEIA S.A.C FECHA DE TERMINO PROGRAMADO 11/8/2023
RESIDENTE DE OBRA ING. SEGUNDO JUAN LINGAN HERNANDEZ CIP N 68131 FECHA DE SUSPENSIÓN DE OBRA 11/1/2023
SUPERVISOR DE OBRA ING . PONCE AVELLANEDA CESAR MANUEL CIP N 69236 FECHA DE REINICIO DE OBRA 11/29/2023
PERIODO VALORIZADO 01/12/2023 AL 04/12/2023 FECHA DE TERMINO PROGAMADA DE OBR 12/6/2023
08.01 ENCAUSAMIENTO EN ZONA DE PUENTE m3 418.30 15.00 6,274.50 0.00 0.00 0.00% 365.00 5475.00 87.26% 365.00 5475.00 87.26% 53.30 799.50 12.74%
08.02 TRANSPORTE Y ELIMINACION DE MATERIALES EXCEDENTES m3 501.96 15.00 7,529.40 0.00 0.00 0.00% 308.00 4620.00 61.36% 308.00 4620.00 61.36% 193.96 2909.40 38.64%
09 SEÑALIZACION Y SEGURIDAD VIAL
09.01 SEÑALES INFORMATIVAS (1.25x2.50 m) und 2.00 2,000.00 4,000.00 2.00 4000.00 100.00% 0.00 0.00% 2.00 4000.00 100.00% 0.00 0.00 0.00%
10 VARIOS
10.01 CONCRETO f'c=140 kg/cm2 PARA FALSO PUENTE m3 47.50 350.00 16,625.00 47.50 16625.00 100.00% 0.00 0.00% 47.50 16625.00 100.00% 0.00 0.00 0.00%
10.02 CONSTRUCCION DE FALSO PUENTE m2 85.80 200.00 17,160.00 85.80 17160.00 100.00% 0.00 0.00% 85.80 17160.00 100.00% 0.00 0.00 0.00%
10.03 TUBERIA PVC SAL 3" m 82.04 15.00 1,230.60 82.04 1230.60 100.00% 0.00 0.00% 82.04 1230.60 100.00% 0.00 0.00 0.00%
10.04 ACABADO PULIDO EN VEREDAS CON MORTERO 1:2 x 1.5 CM m2 34.48 20.00 689.60 34.48 689.60 100.00% 0.00 0.00% 34.48 689.60 100.00% 0.00 0.00 0.00%
10.05 PINTURA PARA BORDES DE VEREDAS m 31.20 20.00 624.00 0.00 0.00 0.00% 31.20 624.00 100.00% 31.20 624.00 100.00% 0.00 0.00 0.00%
10.06 LIMPIEZA FINAL DE OBRA m2 1,420.00 2.00 2,840.00 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1,420.00 2840.00 100.00%
10.07 PLACA RECORDATORIA DE BRONCE glb 1.00 900.00 900.00 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 900.00 100.00%
11 MITIGACION AMBIENTAL
11.01 MEDIDAS DE PREVENCION Y MITIGACION glb 1.00 1,500.00 1,500.00 1.00 1500.00 100.00% 0.00 0.00% 1.00 1500.00 100.00% 0.00 0.00 0.00%
11.02 SEÑALES INFORMETIVAS AMBIENTALES und 1.00 900.00 900.00 1.00 900.00 100.00% 0.00 0.00% 1.00 900.00 100.00% 0.00 0.00 0.00%
11.03 RESTAURACION DE AREAS AFECTADAS glb 1.00 2,000.00 2,000.00 0.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 1.00 2000.00 100.00%
11.04 PROGRAMA DE MANEJO DE RESIDUOS glb 1.00 2,000.00 2,000.00 1.00 2000.00 100.00% 0.00 0.00% 1.00 2000.00 100.00% 0.00 0.00 0.00%
11.05 PROGRAMA DE MONITOREO AMBIENTAL glb 1.00 9,000.00 9,000.00 1.00 9000.00 100.00% 0.00 0.00% 1.00 9000.00 100.00% 0.00 0.00 0.00%
11.06 PROGRAMA DE ASUNTOS SOCIALES glb 1.00 2,000.00 2,000.00 1.00 2000.00 100.00% 0.00 0.00% 1.00 2000.00 100.00% 0.00 0.00 0.00%
11.07 PLAN DE CONTINGENCIAS glb 1.00 1,000.00 1,000.00 1.00 1000.00 100.00% 0.00 0.00% 1.00 1000.00 100.00% 0.00 0.00 0.00%
12 SEGURIDAD Y SALUD OCUPACIONAL
12.01 SEGURIDAD Y SALUD glb 1.00 9,000.00 9,000.00 1.00 9000.00 100.00% 0.00 0.00% 1.00 9000.00 100.00% 0.00 0.00 0.00%
12.02 VIGILANCIA, PREVENCION Y CONTROL DE COVID - 19 glb 1.00 13,127.69 13,127.69 1.00 13127.69 100.00% 0.00 0.00% 1.00 13127.69 100.00% 0.00 0.00 0.00%
13 FLETE TERRESTRE
13.01 FLETE TERRESTRE glb 1.00 9,526.00 9,526.00 1.00 9526.00 100.00% 0.00 0.00% 1.00 9526.00 100.00% 0.00 0.00 0.00%
98.43%
2.87%
1.57%
IGV 18.00% 0.00 0.00 0.00 0.00 0.00
SUPERVISOR DE OBRA ING . PONCE AVELLANEDA CESAR MANUEL CIP N 69236 FECHA DE REINICIO DE OBRA
01 OBRAS PROVISIONALES
01.01 CARTEL DE OBRA 3.60x2.40 und 1.00 1,280.00 1,280.00 1.00 1280.00 100.00% 0.00 0.00% 1.00 1280.00 100.00% 0.00 0.00 0.00%
01.02 HABILITACION DE ACCESO PROVISIONAL est 1.00 8,000.00 8,000.00 1.00 8000.00 100.00% 0.00 0.00% 1.00 8000.00 100.00% 0.00 0.00 0.00%
01.03 INSTALACION DE ACCESO PROVISIONAL est 1.00 4,000.00 4,000.00 1.00 4000.00 100.00% 0.00 0.00% 1.00 4000.00 100.00% 0.00 0.00 0.00%
02 TRABAJOS PRELIMINARES
02.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS est 1.00 5,000.00 5,000.00 0.50 2500.00 50.00% 0.50 2500.00 50.00% 1.00 5000.00 100.00% 0.00 0.00 0.00%
02.02 DESBROCE Y LIMPIEZA DE TERRENO ha 0.16 1,000.00 160.00 0.16 160.00 100.00% 0.00 0.00% 0.16 160.00 100.00% 0.00 0.00 0.00%
02.03 TRAZO, NIVEL Y REPLANTEO PRELIMINAR m2 308.88 4.00 1,235.52 308.88 1235.52 100.00% 0.00 0.00% 308.88 1235.52 100.00% 0.00 0.00 0.00%
02.04 TRAZO, NIVEL Y REPLANTEO DURANTE LA EJECUCION DE OBRA mes 3.00 2,500.00 7,500.00 2.00 5000.00 66.67% 1.00 2500.00 33.33% 3.00 7500.00 100.00% 0.00 0.00 0.00%
03 DEMOLICIONES Y DESMONTAJES
03.01 DEMOLICION DE ESTRUCTURAS DE CONCRETO m3 254.01 60.00 15,240.60 254.01 15240.60 100.00% 0.00 0.00% 254.01 15240.60 100.00% 0.00 0.00 0.00%
03.02 TRANSPORTE Y ELIMINACION DE MATERIAL DE DEMOLICIONES m3 381.02 20.00 7,620.40 381.02 7620.40 100.00% 0.00 0.00% 381.02 7620.40 100.00% 0.00 0.00 0.00%
04 MOVIMIENTO DE TIERRAS
04.01 SUB ESTRUCTURA
04.01.01 EXCAVACION PARA ESTRUCTURAS EN MATERIAL COMUN m3 374.66 20.00 7,493.20 374.66 7493.20 100.00% 0.00 0.00% 374.66 7493.20 100.00% 0.00 0.00 0.00%
04.01.02 EXCAVACION PARA ESTRUCTURAS BAJO EL AGUA m3 393.01 15.00 5,895.15 393.01 5895.15 100.00% 0.00 0.00% 393.01 5895.15 100.00% 0.00 0.00 0.00%
04.01.03 DESVIO DE CURSOS DE AGUA m3 226.58 13.00 2,945.54 226.58 2945.54 100.00% 0.00 0.00% 226.58 2945.54 100.00% 0.00 0.00 0.00%
04.01.04 RELLENO DE ESTRUCTURAS CON MATERIAL DE PRESTAMO m3 145.48 90.00 13,093.20 120.00 10800.00 82.49% 25.48 2293.20 17.51% 145.48 13093.20 100.00% 0.00 0.00 0.00%
04.01.05 RELLENO DE ESTRUCTURAS CON MATERIAL PROPIO m3 256.58 50.00 12,829.00 218.29 10914.50 85.08% 38.29 1914.50 14.92% 256.58 12829.00 100.00% 0.00 0.00 0.00%
04.01.06 TRANSPORTE Y ELIMINACION DE MATERIAL EXCEDENTE m3 656.77 20.00 13,135.40 0.00 0.00 0.00% 656.77 13135.40 100.00% 656.77 13135.40 100.00% 0.00 0.00 0.00%
04.02 CONFORMACION DE BASE PARA FALSO PUENTE
04.02.01 RELLENO DE ESTRUCTURAS CON MATERIAL PROPIO m3 40.84 50.00 2,042.00 40.84 2042.00 100.00% 0.00 0.00% 40.84 2042.00 100.00% 0.00 0.00 0.00%
05 SUB ESTRUCTURA
05.01 SOLADO
05.01.01 CONCRETO f'c=100 kg/cm2 SOLADO E=10 CM 1:12 C:H m2 163.46 30.00 4,903.80 163.46 4903.80 100.00% 0.00 0.00% 163.46 4903.80 100.00% 0.00 0.00 0.00%
05.01.02 ENCOFRADO Y DESENCOFRADO m2 7.67 90.00 690.30 7.67 690.30 100.00% 0.00 0.00% 7.67 690.30 100.00% 0.00 0.00 0.00%
05.02 ESTRIBOS
05.02.01 CIMENTACION
05.02.01.01 CONCRETO f'c=280 kg/cm2 m3 147.11 440.00 64,728.40 147.11 64728.40 100.00% 0.00 0.00% 147.11 64728.40 100.00% 0.00 0.00 0.00%
05.02.01.02 ENCOFRADO Y DESENCOFRADO m2 69.07 90.00 6,216.30 69.07 6216.30 100.00% 0.00 0.00% 69.07 6216.30 100.00% 0.00 0.00 0.00%
05.02.01.03 ACERO fy=4,200 kg/cm2 kg 10,439.50 7.00 73,076.50 10,439.50 73076.50 100.00% 0.00 0.00% 10,439.50 73076.50 100.00% 0.00 0.00 0.00%
05.02.02 PANTALLA
05.02.02.01 CONCRETO f'c=280 kg/cm2 m3 103.63 400.00 41,452.00 103.63 41452.00 100.00% 0.00 0.00% 103.63 41452.00 100.00% 0.00 0.00 0.00%
05.02.02.02 ENCOFRADO Y DESENCOFRADO m2 300.89 90.00 27,080.10 300.89 27080.10 100.00% 0.00 0.00% 300.89 27080.10 100.00% 0.00 0.00 0.00%
05.02.02.03 ACERO fy=4,200 kg/cm2 kg 7,420.67 7.00 51,944.69 7,420.67 51944.69 100.00% 0.00 0.00% 7,420.67 51944.69 100.00% 0.00000 0.00 0.00%
05.02.03 CABEZAL
RESUMEN DE VALORIZACION MENSUAL DE OBRA N° 03 OCTUBRE
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE MAZAMARI CONTRATO DE OBRA N° N° 001-2023-GM/MDM.
“RENOVACION DE PUENTE; EN EL(LA) CAMINO VECINAL R1206241 (PUENTE BALVIN) EN LA
OBRA TRAYECTORIA HACIA EL CENTRO POBLADO RIO DE ORO EN EL DISTRITO DE MAZAMARI, PROVINCIA PLAZO DE EJECUCION 90 DÍAS CALENDARIOS
SATIPO, DEPARTAMENTO JUNIN”
LUGAR CC.PP. RIO DE ORO MAZAMARI SATIPO JUNIN FECHA DE INICIO DE OBRA 8/10/2023
CONTRATISTA CEIA S.A.C FECHA DE TERMINO PROGRAMADO 11/8/2023
RESIDENTE DE OBRA ING. SEGUNDO JUAN LINGAN HERNANDEZ CIP N 68131 FECHA DE SUSPENSIÓN DE OBRA
SUPERVISOR DE OBRA ING . PONCE AVELLANEDA CESAR MANUEL CIP N 69236 FECHA DE REINICIO DE OBRA
05.02.03.01 CONCRETO f'c=280 kg/cm2 m3 7.55 440.00 3,322.00 7.55 3322.00 100.00% 0.00 0.00% 7.55 3322.00 100.00% 0.00 0.00 0.00%
05.02.03.02 ENCOFRADO Y DESENCOFRADO m2 17.27 90.00 1,554.30 17.27 1554.30 100.00% 0.00 0.00% 17.27 1554.30 100.00% 0.00 0.00 0.00%
RESUMEN DE VALORIZACION MENSUAL DE OBRA N° 03 OCTUBRE
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE MAZAMARI CONTRATO DE OBRA N° N° 001-2023-GM/MDM.
“RENOVACION DE PUENTE; EN EL(LA) CAMINO VECINAL R1206241 (PUENTE BALVIN) EN LA
OBRA TRAYECTORIA HACIA EL CENTRO POBLADO RIO DE ORO EN EL DISTRITO DE MAZAMARI, PROVINCIA PLAZO DE EJECUCION 90 DÍAS CALENDARIOS
SATIPO, DEPARTAMENTO JUNIN”
LUGAR CC.PP. RIO DE ORO MAZAMARI SATIPO JUNIN FECHA DE INICIO DE OBRA 8/10/2023
CONTRATISTA CEIA S.A.C FECHA DE TERMINO PROGRAMADO 11/8/2023
RESIDENTE DE OBRA ING. SEGUNDO JUAN LINGAN HERNANDEZ CIP N 68131 FECHA DE SUSPENSIÓN DE OBRA
SUPERVISOR DE OBRA ING . PONCE AVELLANEDA CESAR MANUEL CIP N 69236 FECHA DE REINICIO DE OBRA
05.02.03.03 ACERO fy=4,200 kg/cm2 kg 206.52 7.00 1,445.64 206.52 1445.64 100.00% 0.00 0.00% 206.52 1445.64 100.00% 0.00 0.00 0.00%
05.02.04 PARAPETOS
05.02.04.01 CONCRETO f'c=280 kg/cm2 m3 5.06 440.00 2,226.40 5.06 2226.40 100.00% 0.00 0.00% 5.06 2226.40 100.00% 0.00 0.00 0.00%
05.02.04.02 ENCOFRADO Y DESENCOFRADO m2 35.18 90.00 3,166.20 35.18 3166.20 100.00% 0.00 0.00% 35.18 3166.20 100.00% 0.00 0.00 0.00%
05.02.04.03 ACERO fy=4,200 kg/cm2 kg 460.20 7.00 3,221.40 460.20 3221.40 100.00% 0.00 0.00% 460.20 3221.40 100.00% 0.00 0.00 0.00%
05.02.04.04 TAPAJUNTA METALICA EN PISOS m 9.80 300.00 2,940.00 4.90 1470.00 50.00% 4.90 1470.00 50.00% 9.80 2940.00 100.00% 0.00 0.00 0.00%
05.02.04.05 JUNTA DE DILATACION e=1" m 2.00 50.00 100.00 0.00 0.00 0.00% 2.00 100.00 100.00% 2.00 100.00 100.00% 0.00 0.00 0.00%
06 SUPER ESTRUCTURA
06.01 TABLERO VIGA - LOSA
06.01.01 CONCRETO f'c=280 kg/cm2 m3 14.04 440.00 6,177.60 0.00 0.00 0.00% 14.04 6177.60 100.00% 14.04 6177.60 100.00% 0.00 0.00 0.00%
06.01.02 ENCOFRADO Y DESENCOFRADO m2 59.13 90.00 5,321.70 0.00 0.00 0.00% 59.13 5321.70 100.00% 59.13 5321.70 100.00% 0.00 0.00 0.00%
06.01.03 ACERO fy=4,200 kg/cm2 kg 1,563.42 7.00 10,943.94 0.00 0.00 0.00% 1563.42 10943.94 100.00% 1,563.42 10943.94 100.00% 0.00 0.00 0.00%
06.01.04 JUNTA DE DILATACION e=1" m 8.00 50.00 400.00 0.00 0.00 0.00% 8.00 400.00 100.00% 8.00 400.00 100.00% 0.00 0.00 0.00%
06.02 VIGAS
06.02.01 CONCRETO f'c=280 kg/cm2 m3 12.79 440.00 5,627.60 0.00 0.00 0.00% 12.79 5627.60 100.00% 12.79 5627.60 100.00% 0.00 0.00 0.00%
06.02.02 ENCOFRADOS Y DESENCOFRADOS m2 79.02 100.00 7,902.00 0.00 0.00 0.00% 79.02 7902.00 100.00% 79.02 7902.00 100.00% 0.00 0.00 0.00%
06.02.03 ACERO fy=4,200 kg/cm2 kg 1,854.10 7.00 12,978.70 0.00 0.00 0.00% 1854.10 12978.70 100.00% 1,854.10 12978.70 100.00% 0.00 0.00 0.00%
06.03 DIAFRAGMAS
06.03.01 CONCRETO f'c=280 kg/cm2 m3 1.85 440.00 814.00 0.00 0.00 0.00% 1.85 814.00 100.00% 1.85 814.00 100.00% 0.00 0.00 0.00%
06.03.02 ENCOFRADO Y DESENCOFRADO m2 17.07 90.00 1,536.30 0.00 0.00 0.00% 17.07 1536.30 100.00% 17.07 1536.30 100.00% 0.00 0.00 0.00%
06.03.03 ACERO fy=4,200 kg/cm2 kg 411.46 7.00 2,880.22 0.00 0.00 0.00% 411.46 2880.22 100.00% 411.46 2880.22 100.00% 0.00 0.00 0.00%
07 ELEMENTOS COMPLEMENTARIOS
07.01 LOSA DE APROXIMACION
07.01.01 CONCRETO f'c=210 kg/cm2 m3 14.20 380.00 5,396.00 0.00 0.00 0.00% 14.20 5396.00 100.00% 14.20 5396.00 100.00% 0.00 0.00 0.00%
07.01.02 ENCOFRADOS Y DESENCOFRADOS m2 13.75 100.00 1,375.00 0.00 0.00 0.00% 13.75 1375.00 100.00% 13.75 1375.00 100.00% 0.00 0.00 0.00%
07.01.03 ACERO fy=4,200 kg/cm2 kg 990.55 7.00 6,933.85 0.00 0.00 0.00% 990.55 6933.85 100.00% 990.55 6933.85 100.00% 0.00 0.00 0.00%
07.02 BARANDAS
07.02.01 BARANDAS DE FºGº 4" m 31.20 300.00 9,360.00 0.00 0.00 0.00% 31.20 9360.00 100.00% 31.20 9360.00 100.00% 0.00 0.00 0.00%
07.02.02 PINTADO DE BARANDAS METALICAS m2 12.00 20.00 240.00 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 12.00 240.00 100.00%
07.03 NEOPRENO Y PAVIMENTOS
07.03.01 CARPETA ASFALTICA EN CALIENTE DE 2" m2 62.40 100.00 6,240.00 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 62.40 6240.00 100.00%
07.03.02 APOYO DE NEOPRENE DENSIDAD 60 und 4.00 1,000.00 4,000.00 0.00 0.00 0.00% 4.00 4000.00 100.00% 4.00 4000.00 100.00% 0.00 0.00 0.00%
07.04 VEREDAS
07.04.01 CONCRETO f'c=280 kg/cm2 m3 4.06 440.00 1,786.40 0.00 0.00 0.00% 4.06 1786.40 100.00% 4.06 1786.40 100.00% 0.00 0.00 0.00%
07.04.02 ENCOFRADO Y DESENCOFRADO m2 31.36 90.00 2,822.40 0.00 0.00 0.00% 31.36 2822.40 100.00% 31.36 2822.40 100.00% 0.00 0.00 0.00%
07.04.03 ACERO fy=4,200 kg/cm2 kg 542.78 7.00 3,799.46 0.00 0.00 0.00% 542.78 3799.46 100.00% 542.78 3799.46 100.00% 0.00 0.00 0.00%
08 OBRAS DE ENCAUSAMIENTO
RESUMEN DE VALORIZACION MENSUAL DE OBRA N° 03 OCTUBRE
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE MAZAMARI CONTRATO DE OBRA N° N° 001-2023-GM/MDM.
“RENOVACION DE PUENTE; EN EL(LA) CAMINO VECINAL R1206241 (PUENTE BALVIN) EN LA
OBRA TRAYECTORIA HACIA EL CENTRO POBLADO RIO DE ORO EN EL DISTRITO DE MAZAMARI, PROVINCIA PLAZO DE EJECUCION 90 DÍAS CALENDARIOS
SATIPO, DEPARTAMENTO JUNIN”
LUGAR CC.PP. RIO DE ORO MAZAMARI SATIPO JUNIN FECHA DE INICIO DE OBRA 8/10/2023
CONTRATISTA CEIA S.A.C FECHA DE TERMINO PROGRAMADO 11/8/2023
RESIDENTE DE OBRA ING. SEGUNDO JUAN LINGAN HERNANDEZ CIP N 68131 FECHA DE SUSPENSIÓN DE OBRA
SUPERVISOR DE OBRA ING . PONCE AVELLANEDA CESAR MANUEL CIP N 69236 FECHA DE REINICIO DE OBRA
08.01 ENCAUSAMIENTO EN ZONA DE PUENTE m3 418.30 15.00 6,274.50 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 418.30 6274.50 100.00%
08.02 TRANSPORTE Y ELIMINACION DE MATERIALES EXCEDENTES m3 501.96 15.00 7,529.40 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 501.96 7529.40 100.00%
09 SEÑALIZACION Y SEGURIDAD VIAL
09.01 SEÑALES INFORMATIVAS (1.25x2.50 m) und 2.00 2,000.00 4,000.00 0.00 0.00 0.00% 2.00 4000.00 100.00% 2.00 4000.00 100.00% 0.00 0.00 0.00%
10 VARIOS
10.01 CONCRETO f'c=140 kg/cm2 PARA FALSO PUENTE m3 47.50 350.00 16,625.00 0.00 0.00 0.00% 47.50 16625.00 100.00% 47.50 16625.00 100.00% 0.00 0.00 0.00%
10.02 CONSTRUCCION DE FALSO PUENTE m2 85.80 200.00 17,160.00 0.00 0.00 0.00% 85.80 17160.00 100.00% 85.80 17160.00 100.00% 0.00 0.00 0.00%
10.03 TUBERIA PVC SAL 3" m 82.04 15.00 1,230.60 0.00 0.00 0.00% 82.04 1230.60 100.00% 82.04 1230.60 100.00% 0.00 0.00 0.00%
10.04 ACABADO PULIDO EN VEREDAS CON MORTERO 1:2 x 1.5 CM m2 34.48 20.00 689.60 0.00 0.00 0.00% 34.48 689.60 100.00% 34.48 689.60 100.00% 0.00 0.00 0.00%
10.05 PINTURA PARA BORDES DE VEREDAS m 31.20 20.00 624.00 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 31.20 624.00 100.00%
10.06 LIMPIEZA FINAL DE OBRA m2 1,420.00 2.00 2,840.00 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1,420.00 2840.00 100.00%
10.07 PLACA RECORDATORIA DE BRONCE glb 1.00 900.00 900.00 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 900.00 100.00%
11 MITIGACION AMBIENTAL
11.01 MEDIDAS DE PREVENCION Y MITIGACION glb 1.00 1,500.00 1,500.00 1.00 1500.00 100.00% 0.00 0.00% 1.00 1500.00 100.00% 0.00 0.00 0.00%
11.02 SEÑALES INFORMETIVAS AMBIENTALES und 1.00 900.00 900.00 1.00 900.00 100.00% 0.00 0.00% 1.00 900.00 100.00% 0.00 0.00 0.00%
11.03 RESTAURACION DE AREAS AFECTADAS glb 1.00 2,000.00 2,000.00 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 2000.00 100.00%
11.04 PROGRAMA DE MANEJO DE RESIDUOS glb 1.00 2,000.00 2,000.00 1.00 2000.00 100.00% 0.00 0.00% 1.00 2000.00 100.00% 0.00 0.00 0.00%
11.05 PROGRAMA DE MONITOREO AMBIENTAL glb 1.00 9,000.00 9,000.00 0.00 0.00 0.00% 1.00 9000.00 100.00% 1.00 9000.00 100.00% 0.00 0.00 0.00%
11.06 PROGRAMA DE ASUNTOS SOCIALES glb 1.00 2,000.00 2,000.00 0.00 0.00 0.00% 1.00 2000.00 100.00% 1.00 2000.00 100.00% 0.00 0.00 0.00%
11.07 PLAN DE CONTINGENCIAS glb 1.00 1,000.00 1,000.00 1.00 1000.00 100.00% 0.00 0.00% 1.00 1000.00 100.00% 0.00 0.00 0.00%
12 SEGURIDAD Y SALUD OCUPACIONAL
12.01 SEGURIDAD Y SALUD glb 1.00 9,000.00 9,000.00 0.80 7200.00 80.00% 0.20 1800.00 20.00% 1.00 9000.00 100.00% 0.00 0.00 0.00%
12.02 VIGILANCIA, PREVENCION Y CONTROL DE COVID - 19 glb 1.00 13,127.69 13,127.69 1.00 13127.69 100.00% 0.00 0.00% 1.00 13127.69 100.00% 0.00 0.00 0.00%
13 FLETE TERRESTRE
13.01 FLETE TERRESTRE glb 1.00 9,526.00 9,526.00 1.00 9526.00 100.00% 0.00 0.00% 1.00 9526.00 100.00% 0.00 0.00 0.00%
27.74558%
SUB TOTAL 706,200.02 478,896.16 195,939.28 674,835.44 31,364.58
95.56%
4.44%
IGV 18.00% 0.00 0.00 0.00 0.00 0.00
SUPERVISOR DE OBRA ING . PONCE AVELLANEDA CESAR MANUEL CIP N 69236 FECHA DE REINICIO DE OBRA
01 OBRAS PROVISIONALES
01.01 CARTEL DE OBRA 3.60x2.40 und 1.00 1,280.00 1,280.00 1.00 1280.00 100.00% 0.00 0.00% 1.00 1280.00 100.00% 0.00 0.00 0.00%
01.02 HABILITACION DE ACCESO PROVISIONAL est 1.00 8,000.00 8,000.00 1.00 8000.00 100.00% 0.00 0.00% 1.00 8000.00 100.00% 0.00 0.00 0.00%
01.03 INSTALACION DE ACCESO PROVISIONAL est 1.00 4,000.00 4,000.00 1.00 4000.00 100.00% 0.00 0.00% 1.00 4000.00 100.00% 0.00 0.00 0.00%
02 TRABAJOS PRELIMINARES
02.01 MOVILIZACION Y DESMOVILIZACION DE EQUIPOS est 1.00 5,000.00 5,000.00 0.50 2500.00 50.00% 0.00 0.00 0.00% 0.50 2500.00 50.00% 0.50 2500.00 50.00%
02.02 DESBROCE Y LIMPIEZA DE TERRENO ha 0.16 1,000.00 160.00 0.16 160.00 100.00% 0.00 0.00% 0.16 160.00 100.00% 0.00 0.00 0.00%
02.03 TRAZO, NIVEL Y REPLANTEO PRELIMINAR m2 308.88 4.00 1,235.52 308.88 1235.52 100.00% 0.00 0.00% 308.88 1235.52 100.00% 0.00 0.00 0.00%
02.04 TRAZO, NIVEL Y REPLANTEO DURANTE LA EJECUCION DE OBRA mes 3.00 2,500.00 7,500.00 1.00 2500.00 33.33% 1.00 2500.00 33.33% 2.00 5000.00 66.67% 1.00 2500.00 33.33%
03 DEMOLICIONES Y DESMONTAJES
03.01 DEMOLICION DE ESTRUCTURAS DE CONCRETO m3 254.01 60.00 15,240.60 254.01 15240.60 100.00% 0.00 0.00% 254.01 15240.60 100.00% 0.00 0.00 0.00%
03.02 TRANSPORTE Y ELIMINACION DE MATERIAL DE DEMOLICIONES m3 381.02 20.00 7,620.40 381.02 7620.40 100.00% 0.00 0.00% 381.02 7620.40 100.00% 0.00 0.00 0.00%
04 MOVIMIENTO DE TIERRAS
04.01 SUB ESTRUCTURA
04.01.01 EXCAVACION PARA ESTRUCTURAS EN MATERIAL COMUN m3 374.66 20.00 7,493.20 374.66 7493.20 100.00% 0.00 0.00% 374.66 7493.20 100.00% 0.00 0.00 0.00%
04.01.02 EXCAVACION PARA ESTRUCTURAS BAJO EL AGUA m3 393.01 15.00 5,895.15 393.01 5895.15 100.00% 0.00 0.00% 393.01 5895.15 100.00% 0.00 0.00 0.00%
04.01.03 DESVIO DE CURSOS DE AGUA m3 226.58 13.00 2,945.54 226.58 2945.54 100.00% 0.00 0.00% 226.58 2945.54 100.00% 0.00 0.00 0.00%
04.01.04 RELLENO DE ESTRUCTURAS CON MATERIAL DE PRESTAMO m3 145.48 90.00 13,093.20 60.00 5400.00 41.24% 60.00 5400.00 41.24% 120.00 10800.00 82.49% 25.48 2293.20 17.51%
04.01.05 RELLENO DE ESTRUCTURAS CON MATERIAL PROPIO m3 256.58 50.00 12,829.00 128.29 6414.50 50.00% 90.00 4500.00 35.08% 218.29 10914.50 85.08% 38.29 1914.50 14.92%
04.01.06 TRANSPORTE Y ELIMINACION DE MATERIAL EXCEDENTE m3 656.77 20.00 13,135.40 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 656.77 13135.40 100.00%
04.02 CONFORMACION DE BASE PARA FALSO PUENTE
04.02.01 RELLENO DE ESTRUCTURAS CON MATERIAL PROPIO m3 40.84 50.00 2,042.00 0.00 0.00% 40.84 2042.00 100.00% 40.84 2042.00 100.00% 0.00 0.00 0.00%
05 SUB ESTRUCTURA
05.01 SOLADO
05.01.01 CONCRETO f'c=100 kg/cm2 SOLADO E=10 CM 1:12 C:H m2 163.46 30.00 4,903.80 163.46 4903.80 100.00% 0.00 0.00% 163.46 4903.80 100.00% 0.00 0.00 0.00%
05.01.02 ENCOFRADO Y DESENCOFRADO m2 7.67 90.00 690.30 7.67 690.30 100.00% 0.00 0.00% 7.67 690.30 100.00% 0.00 0.00 0.00%
05.02 ESTRIBOS
05.02.01 CIMENTACION
05.02.01.01 CONCRETO f'c=280 kg/cm2 m3 147.11 440.00 64,728.40 147.11 64728.40 100.00% 0.00 0.00% 147.11 64728.40 100.00% 0.00 0.00 0.00%
05.02.01.02 ENCOFRADO Y DESENCOFRADO m2 69.07 90.00 6,216.30 69.07 6216.30 100.00% 0.00 0.00% 69.07 6216.30 100.00% 0.00 0.00 0.00%
05.02.01.03 ACERO fy=4,200 kg/cm2 kg 10,439.50 7.00 73,076.50 10,439.50 73076.50 100.00% 0.00 0.00% 10,439.50 73076.50 100.00% 0.00 0.00 0.00%
05.02.02 PANTALLA
05.02.02.01 CONCRETO f'c=280 kg/cm2 m3 103.63 400.00 41,452.00 51.82 20728.00 50.00% 51.81 20724.00 50.00% 103.63 41452.00 100.00% 0.00 0.00 0.00%
05.02.02.02 ENCOFRADO Y DESENCOFRADO m2 300.89 90.00 27,080.10 150.45 13540.50 50.00% 150.44 13539.60 50.00% 300.89 27080.10 100.00% 0.00 0.00 0.00%
05.02.02.03 ACERO fy=4,200 kg/cm2 kg 7,420.67 7.00 51,944.69 5,936.54 41555.75 80.00% 1484.13 10388.94 20.00% 7,420.67 51944.69 100.00% 0.00000 0.00 0.00%
05.02.03 CABEZAL
RESUMEN DE VALORIZACION MENSUAL DE OBRA N° 02 SEPTIEMBRE
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE MAZAMARI CONTRATO DE OBRA N° N° 001-2023-GM/MDM.
“RENOVACION DE PUENTE; EN EL(LA) CAMINO VECINAL R1206241 (PUENTE BALVIN) EN LA
OBRA TRAYECTORIA HACIA EL CENTRO POBLADO RIO DE ORO EN EL DISTRITO DE MAZAMARI, PROVINCIA PLAZO DE EJECUCION 90 DÍAS CALENDARIOS
SATIPO, DEPARTAMENTO JUNIN”
LUGAR CC.PP. RIO DE ORO MAZAMARI SATIPO JUNIN FECHA DE INICIO DE OBRA 8/10/2023
CONTRATISTA CEIA S.A.C FECHA DE TERMINO PROGRAMADO 11/8/2023
RESIDENTE DE OBRA ING. SEGUNDO JUAN LINGAN HERNANDEZ CIP N 68131 FECHA DE SUSPENSIÓN DE OBRA
SUPERVISOR DE OBRA ING . PONCE AVELLANEDA CESAR MANUEL CIP N 69236 FECHA DE REINICIO DE OBRA
05.02.03.01 CONCRETO f'c=280 kg/cm2 m3 7.55 440.00 3,322.00 0.00 0.00% 7.55 3322.00 100.00% 7.55 3322.00 100.00% 0.00 0.00 0.00%
05.02.03.02 ENCOFRADO Y DESENCOFRADO m2 17.27 90.00 1,554.30 0.00 0.00% 17.27 1554.30 100.00% 17.27 1554.30 100.00% 0.00 0.00 0.00%
RESUMEN DE VALORIZACION MENSUAL DE OBRA N° 02 SEPTIEMBRE
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE MAZAMARI CONTRATO DE OBRA N° N° 001-2023-GM/MDM.
“RENOVACION DE PUENTE; EN EL(LA) CAMINO VECINAL R1206241 (PUENTE BALVIN) EN LA
OBRA TRAYECTORIA HACIA EL CENTRO POBLADO RIO DE ORO EN EL DISTRITO DE MAZAMARI, PROVINCIA PLAZO DE EJECUCION 90 DÍAS CALENDARIOS
SATIPO, DEPARTAMENTO JUNIN”
LUGAR CC.PP. RIO DE ORO MAZAMARI SATIPO JUNIN FECHA DE INICIO DE OBRA 8/10/2023
CONTRATISTA CEIA S.A.C FECHA DE TERMINO PROGRAMADO 11/8/2023
RESIDENTE DE OBRA ING. SEGUNDO JUAN LINGAN HERNANDEZ CIP N 68131 FECHA DE SUSPENSIÓN DE OBRA
SUPERVISOR DE OBRA ING . PONCE AVELLANEDA CESAR MANUEL CIP N 69236 FECHA DE REINICIO DE OBRA
05.02.03.03 ACERO fy=4,200 kg/cm2 kg 206.52 7.00 1,445.64 103.26 722.82 50.00% 103.26 722.82 50.00% 206.52 1445.64 100.00% 0.00 0.00 0.00%
05.02.04 PARAPETOS
05.02.04.01 CONCRETO f'c=280 kg/cm2 m3 5.06 440.00 2,226.40 0.00 0.00% 5.06 2226.40 100.00% 5.06 2226.40 100.00% 0.00 0.00 0.00%
05.02.04.02 ENCOFRADO Y DESENCOFRADO m2 35.18 90.00 3,166.20 0.00 0.00% 35.18 3166.20 100.00% 35.18 3166.20 100.00% 0.00 0.00 0.00%
05.02.04.03 ACERO fy=4,200 kg/cm2 kg 460.20 7.00 3,221.40 230.10 1610.70 50.00% 230.10 1610.70 50.00% 460.20 3221.40 100.00% 0.00 0.00 0.00%
05.02.04.04 TAPAJUNTA METALICA EN PISOS m 9.80 300.00 2,940.00 0.00 0.00% 4.90 1470.00 50.00% 4.90 1470.00 50.00% 4.90 1470.00 50.00%
05.02.04.05 JUNTA DE DILATACION e=1" m 2.00 50.00 100.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 2.00 100.00 100.00%
06 SUPER ESTRUCTURA
06.01 TABLERO VIGA - LOSA
06.01.01 CONCRETO f'c=280 kg/cm2 m3 14.04 440.00 6,177.60 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 14.04 6177.60 100.00%
06.01.02 ENCOFRADO Y DESENCOFRADO m2 59.13 90.00 5,321.70 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 59.13 5321.70 100.00%
06.01.03 ACERO fy=4,200 kg/cm2 kg 1,563.42 7.00 10,943.94 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1,563.42 10943.94 100.00%
06.01.04 JUNTA DE DILATACION e=1" m 8.00 50.00 400.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 8.00 400.00 100.00%
06.02 VIGAS
06.02.01 CONCRETO f'c=280 kg/cm2 m3 12.79 440.00 5,627.60 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 12.79 5627.60 100.00%
06.02.02 ENCOFRADOS Y DESENCOFRADOS m2 79.02 100.00 7,902.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 79.02 7902.00 100.00%
06.02.03 ACERO fy=4,200 kg/cm2 kg 1,854.10 7.00 12,978.70 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1,854.10 12978.70 100.00%
06.03 DIAFRAGMAS
06.03.01 CONCRETO f'c=280 kg/cm2 m3 1.85 440.00 814.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.85 814.00 100.00%
06.03.02 ENCOFRADO Y DESENCOFRADO m2 17.07 90.00 1,536.30 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 17.07 1536.30 100.00%
06.03.03 ACERO fy=4,200 kg/cm2 kg 411.46 7.00 2,880.22 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 411.46 2880.22 100.00%
07 ELEMENTOS COMPLEMENTARIOS
07.01 LOSA DE APROXIMACION
07.01.01 CONCRETO f'c=210 kg/cm2 m3 14.20 380.00 5,396.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 14.20 5396.00 100.00%
07.01.02 ENCOFRADOS Y DESENCOFRADOS m2 13.75 100.00 1,375.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 13.75 1375.00 100.00%
07.01.03 ACERO fy=4,200 kg/cm2 kg 990.55 7.00 6,933.85 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 990.55 6933.85 100.00%
07.02 BARANDAS
07.02.01 BARANDAS DE FºGº 4" m 31.20 300.00 9,360.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 31.20 9360.00 100.00%
07.02.02 PINTADO DE BARANDAS METALICAS m2 12.00 20.00 240.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 12.00 240.00 100.00%
07.03 NEOPRENO Y PAVIMENTOS
07.03.01 CARPETA ASFALTICA EN CALIENTE DE 2" m2 62.40 100.00 6,240.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 62.40 6240.00 100.00%
07.03.02 APOYO DE NEOPRENE DENSIDAD 60 und 4.00 1,000.00 4,000.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 4.00 4000.00 100.00%
07.04 VEREDAS
07.04.01 CONCRETO f'c=280 kg/cm2 m3 4.06 440.00 1,786.40 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 4.06 1786.40 100.00%
07.04.02 ENCOFRADO Y DESENCOFRADO m2 31.36 90.00 2,822.40 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 31.36 2822.40 100.00%
07.04.03 ACERO fy=4,200 kg/cm2 kg 542.78 7.00 3,799.46 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 542.78 3799.46 100.00%
08 OBRAS DE ENCAUSAMIENTO
RESUMEN DE VALORIZACION MENSUAL DE OBRA N° 02 SEPTIEMBRE
PROPIETARIO : MUNICIPALIDAD DISTRITAL DE MAZAMARI CONTRATO DE OBRA N° N° 001-2023-GM/MDM.
“RENOVACION DE PUENTE; EN EL(LA) CAMINO VECINAL R1206241 (PUENTE BALVIN) EN LA
OBRA TRAYECTORIA HACIA EL CENTRO POBLADO RIO DE ORO EN EL DISTRITO DE MAZAMARI, PROVINCIA PLAZO DE EJECUCION 90 DÍAS CALENDARIOS
SATIPO, DEPARTAMENTO JUNIN”
LUGAR CC.PP. RIO DE ORO MAZAMARI SATIPO JUNIN FECHA DE INICIO DE OBRA 8/10/2023
CONTRATISTA CEIA S.A.C FECHA DE TERMINO PROGRAMADO 11/8/2023
RESIDENTE DE OBRA ING. SEGUNDO JUAN LINGAN HERNANDEZ CIP N 68131 FECHA DE SUSPENSIÓN DE OBRA
SUPERVISOR DE OBRA ING . PONCE AVELLANEDA CESAR MANUEL CIP N 69236 FECHA DE REINICIO DE OBRA
08.01 ENCAUSAMIENTO EN ZONA DE PUENTE m3 418.30 15.00 6,274.50 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 418.30 6274.50 100.00%
08.02 TRANSPORTE Y ELIMINACION DE MATERIALES EXCEDENTES m3 501.96 15.00 7,529.40 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 501.96 7529.40 100.00%
09 SEÑALIZACION Y SEGURIDAD VIAL
09.01 SEÑALES INFORMATIVAS (1.25x2.50 m) und 2.00 2,000.00 4,000.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 2.00 4000.00 100.00%
10 VARIOS
10.01 CONCRETO f'c=140 kg/cm2 PARA FALSO PUENTE m3 47.50 350.00 16,625.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 47.50 16625.00 100.00%
10.02 CONSTRUCCION DE FALSO PUENTE m2 85.80 200.00 17,160.00 0.00 0.00% 0.00 0.00 0.00% 0.00 0.00 0.00% 85.80 17160.00 100.00%
10.03 TUBERIA PVC SAL 3" m 82.04 15.00 1,230.60 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 82.04 1230.60 100.00%
10.04 ACABADO PULIDO EN VEREDAS CON MORTERO 1:2 x 1.5 CM m2 34.48 20.00 689.60 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 34.48 689.60 100.00%
10.05 PINTURA PARA BORDES DE VEREDAS m 31.20 20.00 624.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 31.20 624.00 100.00%
10.06 LIMPIEZA FINAL DE OBRA m2 1,420.00 2.00 2,840.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1,420.00 2840.00 100.00%
10.07 PLACA RECORDATORIA DE BRONCE glb 1.00 900.00 900.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 900.00 100.00%
11 MITIGACION AMBIENTAL
11.01 MEDIDAS DE PREVENCION Y MITIGACION glb 1.00 1,500.00 1,500.00 1.00 1500.00 100.00% 0.00 0.00% 1.00 1500.00 100.00% 0.00 0.00 0.00%
11.02 SEÑALES INFORMETIVAS AMBIENTALES und 1.00 900.00 900.00 1.00 900.00 100.00% 0.00 0.00% 1.00 900.00 100.00% 0.00 0.00 0.00%
11.03 RESTAURACION DE AREAS AFECTADAS glb 1.00 2,000.00 2,000.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 2000.00 100.00%
11.04 PROGRAMA DE MANEJO DE RESIDUOS glb 1.00 2,000.00 2,000.00 1.00 2000.00 100.00% 0.00 0.00% 1.00 2000.00 100.00% 0.00 0.00 0.00%
11.05 PROGRAMA DE MONITOREO AMBIENTAL glb 1.00 9,000.00 9,000.00 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 9000.00 100.00%
11.06 PROGRAMA DE ASUNTOS SOCIALES glb 1.00 2,000.00 2,000.00 0.00 0.00 0.00% 0.00 0.00% 0.00 0.00 0.00% 1.00 2000.00 100.00%
11.07 PLAN DE CONTINGENCIAS glb 1.00 1,000.00 1,000.00 1.00 1000.00 100.00% 0.00 0.00% 1.00 1000.00 100.00% 0.00 0.00 0.00%
12 SEGURIDAD Y SALUD OCUPACIONAL
12.01 SEGURIDAD Y SALUD glb 1.00 9,000.00 9,000.00 0.50 4500.00 50.00% 0.30 2700.00 30.00% 0.80 7200.00 80.00% 0.20 1800.00 20.00%
12.02 VIGILANCIA, PREVENCION Y CONTROL DE COVID - 19 glb 1.00 13,127.69 13,127.69 0.50 6563.85 50.00% 0.50 6563.85 50.00% 1.00 13127.69 100.00% 0.00 0.00 0.00%
13 FLETE TERRESTRE
13.01 FLETE TERRESTRE glb 1.00 9,526.00 9,526.00 0.70 6668.20 70.00% 0.30 2857.80 30.00% 1.00 9526.00 100.00% 0.00 0.00 0.00%
14.21477%
SUB TOTAL 706,200.02 378,511.47 100,384.69 478,896.16 227,303.86
67.81%
32.19%
IGV 18.00% 0.00 0.00 0.00 0.00
01.01.01.01 TRAZO, NIVEL Y REPLANTEO m2 39.36 2.86 112.57 112.57 100.00% 0.00 0.00%
01.01.01.02 LIMPIEZA DE TERRENO EN GENERAL m2 39.36 3.44 135.40 135.40 100.00% 0.00 0.00%
01.01.02 BASE GRANULAR Y PAVIMENTO
01.01.02.01.01 SUB BASE GRANULAR E=0.15 M m2 19.06 15.59 297.15 297.15 100.00% 0.00 0.00%
01.01.02.02 BASE GRANULAR
01.01.02.02.01 BASE GRANULAR E=0.15 M m2 19.06 15.59 297.15 297.15 100.00% 0.00%
01.01.02.03 ENCOFRADO Y DESENCOFRADO
01.01.02.03.01 ENCOFRADO Y DESENCOFRADO DE PAVIMENTO m2 7.63 49.52 377.84 377.84 100.00% 0.00%
01.01.02.04 CONCRETO EN LOSAS
01.01.02.04.01 CONCRETO EN PAVIMENTO RIGIDO F'C= 210 KG/CM2 INCL. BARRIDO m3 3.81 447.63 1,705.47 1,705.47 100.00% 0.00%
01.01.02.04.02 CURADO DE PAVIMENTO RIGIDO m2 19.06 2.76 52.61 52.61 100.00% 0.00%
01.01.02.04.03 ACERO DOWELS DE 1/2" kg 7.47 9.66 72.16 72.16 100.00% 0.00%
01.01.02.05 JUNTAS DE DILATACION
01.01.02.05.01 JUNTAS ASFALTICAS EN PAVIMENTO RIGIDO ml 6.55 13.17 86.26 0.00 0.00% 86.26 100.00%
01.01.03 VEREDAS DE CONCRETO
01.01.03.01.01 TRAZO, NIVEL Y REPLANTEO m2 14.65 2.86 41.90 41.90 100.00% 0.00%
01.01.03.01.02 LIMPIEZA DE TERRENO EN GENERAL m2 14.65 3.44 50.40 50.40 100.00% 0.00%
01.01.03.01.03 DEMOLICION DE VEREDAS EXISTENTE m2 28.93 31.16 901.46 901.46 100.00% 0.00%
CRONOGRAMA REPROGRAMADO VALORIZADO DE ADICIONAL N° 01 DE OBRA
ADICIONAL DEDUCTIVO VINCULANTE N° 01 DE LA OBRA: “CONSTRUCCION DE PAVIMENTO, VEREDA Y CUNETA; EN EL(LA) CALLES PSJE. HUANTA, PSJE. DURANCITO, PSJE. RUBEN CALLEGARI Y PSJE 2
PROYECTO :
Y 3 DE J.V. PLAYA VERDE EN LA LOCALIDAD SATIPO, DISTRITO DE SATIPO, PROVINCIA SATIPO, DEPARTAMENTO JUNIN”.
CONTRATISTA CONSORCIO DURANCITO
RESIDENTE ING. SEGUNDO JUAN LINGAN HERNANDEZ CIP N 68131 FECHA DE INICIO 14 DE MAYO 2024
SUPERVISOR ING. TITO CIRO TRUJILLO MEZA CIP N° 151115 FECHA DE TERMINO 02 DE JUNIO 2024
PLAZO EJEC. 20 DIAS CALENDARIOS
PRESUPUESTO CRONOGRAMA VALORIZADA ADICIONAL DE OBRA
ITEM DESCRIPCION DE TAREAS UND MES % MES %
METRADO PRECIO PARCIAL 14-31 MAYO 01-02 JUNIO
01.01.03.01.04 DEMOLICION DE PAVIMENTO EXISTENTE m2 39.36 31.16 1,226.46 1,226.46 100.00% 0.00%
01.01.03.02 MOVIMIENTO DE TIERRAS
01.01.03.02.01 CORTE DE TERRENO MANUAL m3 2.93 51.09 149.69 149.69 100.00% 0.00%
01.01.03.02.02 PERFILADO Y COMPACTADO EN ZONA DE CORTE m2 14.65 10.76 157.63 157.63 100.00% 0.00%
01.01.03.02.03 ELIMINACION DE MATERIAL EXCEDENTE m3 3.52 13.27 46.71 46.71 100.00% 0.00%
01.01.03.02.04 AFIRMADO DE 4" PARA VEREDAS m2 14.65 14.85 217.55 217.55 100.00% 0.00%
01.01.03.03 ENCOFRADO Y DESENCOFRADO
01.01.03.04.01 CONCRETO EN MARTILLOS F'C=175 KG/CM2 m3 1.47 391.13 574.96 574.96 100.00% 0.00%
01.01.03.04.02 CONCRETO EN RAMPAS F'C=175 KG/CM2 m3 0.32 391.13 125.16 125.16 100.00% 0.00%
01.01.03.04.03 CURADO EN (VEREDAS, UÑAS EN VEREDAS, MARTILLOS Y RAMPAS) m2 23.05 2.95 68.00 0.00 0.00% 68.00 100.00%
01.01.03.05 JUNTAS DE DILATACION
01.01.03.05.01 JUNTAS ASFALTICAS ml 6.21 13.17 81.79 0.00 0.00% 81.79 100.00%
01.02 MEJORAMIENTO DE LA SUBRASANTE
01.02.01 MOVIMIENTO DE TIERRAS
01.02.01.01 CORTE DE MATERIAL SUELTO HASTA NIVEL DE SUB RASANTE C/MAQUINARIA m3 528.11 13.58 7,171.73 7,171.73 100.00% 0.00%
01.02.01.02 CONFORMACION DE LA SUB RASANTE m2 297.00 6.15 1,826.55 1,826.55 100.00% 0.00%
01.02.01.03 ELIMINACION DE MATERIAL EXCEDENTE CON VOLQ. 15 M3. m3 633.73 13.27 8,409.60 0.00% 8,409.60 100.00%
01.02.02 MEJORAMIENTO DE SUELOS
01.02.02.01. MEJORAMIENTO DE SUELO DE SUBRASANTE CON MATERIAL AFIRMADO E = 0.20 CM m2 594.00 14.75 8,761.50 8,761.50 100.00% 0.00%
01.02.02.02. GEOTEXTIL NO TEJIDO EN SUELO DE SUBRASANTE m2 297.00 5.18 1,538.46 1,538.46 100.00% 0.00%
CRONOGRAMA REPROGRAMADO VALORIZADO DE ADICIONAL N° 01 DE OBRA
ADICIONAL DEDUCTIVO VINCULANTE N° 01 DE LA OBRA: “CONSTRUCCION DE PAVIMENTO, VEREDA Y CUNETA; EN EL(LA) CALLES PSJE. HUANTA, PSJE. DURANCITO, PSJE. RUBEN CALLEGARI Y PSJE 2
PROYECTO :
Y 3 DE J.V. PLAYA VERDE EN LA LOCALIDAD SATIPO, DISTRITO DE SATIPO, PROVINCIA SATIPO, DEPARTAMENTO JUNIN”.
CONTRATISTA CONSORCIO DURANCITO
RESIDENTE ING. SEGUNDO JUAN LINGAN HERNANDEZ CIP N 68131 FECHA DE INICIO 14 DE MAYO 2024
SUPERVISOR ING. TITO CIRO TRUJILLO MEZA CIP N° 151115 FECHA DE TERMINO 02 DE JUNIO 2024
PLAZO EJEC. 20 DIAS CALENDARIOS
PRESUPUESTO CRONOGRAMA VALORIZADA ADICIONAL DE OBRA
ITEM DESCRIPCION DE TAREAS UND MES % MES %
METRADO PRECIO PARCIAL 14-31 MAYO 01-02 JUNIO
01.02.02.03. MEJORAMIENTO DE SUELOS DE SUBRASANTE (OVER DE 3/4" A 3") m3 118.80 130.05 15,449.94 15,449.94 100.00% 0.00%
01.02.02.04. MEJORAMIENTO DE SUELOS DE SUBRASANTE (OVER DE 6" A 8") m3 118.80 115.75 13,751.10 13,751.10 100.00% 0.00%
01.03 ALCANTARILLADO PLUVIAL
01.03.01 OBRAS PROVISIONALES
01.03.01.01 TRAZO, NIVEL Y REPLANTEO m2 43.61 2.86 124.72 124.72 100.00% 0.00%
01.03.01.02 LIMPIEZA DE TERRENO EN GENERAL m2 43.61 3.44 150.02 150.02 100.00% 0.00%
01.03.02 MOVIMIENTO DE TIERRAS
01.03.02.01 CORTE DE TERRENO MANUAL m3 35.92 10.38 372.85 372.85 100.00% 0.00%
01.03.02.02 PERFILADO Y COMPACTADO EN ZONA DE CORTE m2 43.61 10.76 469.24 469.24 100.00% 0.00%
01.03.02.03 ELIMINACION DE MATERIAL EXCEDENTE m3 43.10 13.27 571.94 0.00 0.00% 571.94 100.00%
01.03.03 ENCOFRADO Y DESENCOFRADO
01.03.03.01 ENCOFRADO DE ALCANTARILLADO PLUVIAL m2 195.87 49.52 9,699.48 9,699.48 100.00% 0.00%
01.03.04 CONCRETO ARMADO
01.03.04.01 CONCRETO F'C=210 KG/CM2 EN CANAL m3 14.86 447.63 6,651.78 6,651.78 100.00% 0.00%
01.03.04.02 ACERO FY 4200 KG/CM2 KG 939.30 7.53 7,072.93 7,072.93 100.00% 0.00%
TOTAL COSTO DIRECTO 89,166.40 79,948.81 9,217.59
TOTAL GASTO GENERALES 10.0178122% 8,932.52 8,009.12 923.40
UTILIDAD 9.00000000% 8,024.98 7,195.40 829.58
SUB TOTAL 106123.90 95,153.33 10,970.57
IGV 18% 0.00 - -
TOTAL PRESUESTO DE OBRA 106,123.90 95,153.33 10,970.57
PORCENTAJE PROGRAMADO MENSUAL 89.66% 10.34%
PORCENTAJE PROGRAMADO MENSUAL ACUMULADO 89.66% 100.00%
DATOS GENERALES
PROPIETARIO: : MUNICIPALIDAD DISTRITAL DE MAZAMARI